Project Name: CONSTRUCTION OF THREE STOREY

AT SAN JOSE TALIBON, BO


Location: TALIBON,BOHOL
Appropriation: PHP 11,520,000.00

DETAILED ESTIMATES
ITEM NO. DESCRIPTION

PART A: FACILITIES FOR THE ENGINEER


PART B:
PART C: EARTHWORKS

1A Removal of Structures and Obstruction

a. Materials
None

b. Equipments
Minor Tools(10%of Labor)

c.Labor # of personnel
Engineer 1
Foreman 1
Laborer 6

1B Structure Excavation soil, Solid Rock

a. Materials
None
b. Equipments # of units
Air Compressor 130 HP 2
Jack Hammer 2
Excavator, (1.09 cu.m) 1
Excavator, (1.09 cu.m) *Rental 1
Repair and Maintenance
Fuel and Lubricants
Dumptruck(9.0 cu.m) 1
Dumptruck, (1.09 cu.m) *Rental 1
Repair and Maintenance
Fuel and Lubricants

c. Labor # of personnel
Engineer 1
Foreman 1
Laborer 6
Opperator(Excavator) 1
Opperator(Dumptruck) 1

PART C: TERMITE WORKS

Soil Poisoning

a. Materials
Soil Poisoning Solution

b. Equipments
Minor Tools(10%of Labor)

c.Labor # of personnel
Foreman 1
Laborer 1
PART D REINFORCED CONCRETE

Structural Concrete(Footing and Slab on Fill)


Class A 28 Days

a. Materials
Portland Cement - Approved Brand (Portland Tpe I)
Sand -
Gravel
Water

b. Equipments
Minor Tools(10%of Labor)

c.Labor
Engineer
Foreman
Laborer

PART MASONRY WORKS

CHB Non-Load Bearing(including reinforcing steel)150mm sq.m

a. Materials
6" concrete hollow block
Portland Cement - Apporved Brand (Portland Type 1)
Sand - Leyte Source
10mmØ x 6.00m def bar,grade 40
#16 GI Tie Wire
Hacksaw Blade
Water

b. Equipments
None

c.Labor # of personnel
Engineer 1
Foreman 1
Mason 2
Laborer 6
PART DOORS,WINDOWS AND HARDWARE

A.) Finishing hardware,knobs

a. Materials
Door Knob, Kwikset
b. Equipments
None

c.Labor # of personnel
Foreman 1
Carpenter 1

B) Finishing Hardware, hinges

a. Materials
3 1/2"x 31/2" butt hinges
#3 NAILS
#2NAILS
b. Equipments
None

c.Labor # of personnel
Foreman 1
Carpenter 1

C) DOORS

a. Materials
40mmthck,2.10X.90m SOLID PANEL DOOR
.70x2.10 FLUSH TYPE DOOR
2.10m X 1.5m ALUMINUM PATIO DOORS
b. Equipments
None
# of personnel
c.Labor 1
Foreman 2
Carpenter

D.) WINDOWS

a. Materials
40mmthck,2.10X.90m SOLID PANEL DOOR
.70x2.10 FLUSH TYPE DOOR
2.10m X 1.5m ALUMINUM PATIO DOORS
b. Equipments
None

c.Labor
Foreman
Carpenter
RUCTION OF THREE STOREY DORMITORY
AT SAN JOSE TALIBON, BOHOL
ALIBON,BOHOL
P 11,520,000.00

DETAILED ESTIMATES

ls 1

1577.60

# of personnel
hours 32.00 120.00 3,840.00
hours 32.00 85.00 2,720.00
hours 32.00 48.00 9,216.00
15,776.00

Material Cost -
Equipment Cost 1,577.60
Labor Cost 15,776.00
DIRECT COST 17,353.60
Profit 1,388.29
OCM 2,082.43
TAX 1,041.22
INDIRECT COST 4,511.94
SUB-TOTAL COST 21,865.54
Unit Cost 21,865.54
# of units RATE/HOUR
hours 48 35.00 3,360.00
hours 48 35.00 3,360.00
hours 48 2450.00 117,600.00
hours 48 1450.00 69,600.00
174.00 174.00
715.00 715.00
hours 48 1610.00 77,280.00
hours 48 785.00 37,680.00
94.20 94.20
660.00 660.00

# of personnel RATE/HOUR
hours 48 120.00 5,760.00
hours 48 85.00 4,080.00
hours 48 48.00 13,824.00
hours 48 75.00 3,600.00
hours 48 70.00 3,360.00
DIRECT COST 341,147.20
Profit 27,291.78
OCM 40,937.66
TAX 20,468.83
INDIRECT COST 88,698.27
SUB-TOTAL COST 429,845.47
Unit Cost 429,845.47

liter 170

liter 170 400.00 68000.00

# of personnel RATE/HOUR
hours 8 85.00 680.00
hours 8 48.00 384.00
DIRECT COST 69,064.00
Profit 5,525.12
OCM 8,287.68
TAX 4,143.84
INDIRECT COST 17,956.64
SUB-TOTAL COST 87,020.64
Unit Cost 87,020.64
bag
cu.m
cu.m
drum

pcs
bag
cu.m
kg
kg
pcs
drum

# of personnel
hour
hour
hour
hour
set 80

pcs 80 700 56,000.00

# of personnel
hour 4 85.00 340.00
hour 4 65.00 260.00
DIRECT COST 56,600.00
Profit 4,528.00
OCM 6,792.00
TAX 3,396.00
INDIRECT COST 14,716.00
SUB-TOTAL COST 71,316.00
Unit Cost 71,316.00

pcs 80.00 90.00 7,200.00


kgs 8 55.00 440.00
kgs 8 60.00 480.00

# of personnel
hour 4 85.00 340.00
hour 4 65.00 260.00
DIRECT COST 8,720.00
Profit 697.60
OCM 1,046.40
TAX 523.20
INDIRECT COST 2,267.20
SUB-TOTAL COST 10,987.20
Unit Cost 10,987.20

pcs 16 4,500.00 72000


pcs 21 3,000.00 63000
pcs 2 20,000.00 40000

# of personnel
hours 24 85.00 2040
hours 24 65.00 1560
DIRECT COST 178,600.00
Profit 14,288.00
OCM 21,432.00
TAX 10,716.00
INDIRECT COST 46,436.00
SUB-TOTAL COST 225,036.00
Unit Cost 225,036.00