Quench Tower/absorber Tower - Student - Cheresources.com Community https://www.cheresources.com/invision/topic/10325-quench-towerabsorb...

Cheresources.com Community → General Chemical Engineering Forum → Student

Featured
Articles
Check out the
latest featured
articles.

File Library
Check out the
latest downloads
available in the
File Library.

New Article
Product
Viscosity vs.
Shear

Featured File
Vertical Tank
Selection

New Blog
Entry
Production of
Triple

Superphosphate- posted in
Ankur's blog

Quench Tower/absorber Tower


Started by CRF, Apr 20 2010 10:53 AM

Share this topic:


| More

Posted 20 April 2010 - 10:53 AM


CRF

Hello there,

I am having some trouble designing a quench tower... actually, i am not sure how to start it. Should I consider it like an
absorber tower? Can I simulate it in ASPEN PLUS like Radfrac, to predict the amount of water? what about NUT and HUT?

the goal is to exchange heat with a stream gas coming from a reactor, from 230 C to 90 C, at 19 bar... then, the water vapor in
the stream will condensate and also some co2 will be scrubbed, even tough its not the objective.

1 of 3 1/12/2019, 12:48 PM
Quench Tower/absorber Tower - Student - Cheresources.com Community https://www.cheresources.com/invision/topic/10325-quench-towerabsorb...

ah, just one more thing... can i use metal packing ( steel carbon), in a absorber tower with gasoline and glp, at 50 C? I thinks
theres no problem right, since gasoline is not corrosive and metal is the cheapest option

thanks folks

Posted 20 April 2010 - 05:41 PM


abhi_agrawa

Carlinha,

I think that you have a hot stream coming out of a reactor at 230 deg C and you intend to cool it to 90 deg C, by contacting
with water. So your tower will have the hot gas feed at the bottom, water will be fed at the top. The vapor from the top of the
tower is to be at 90 deg C, the bottom product will be circulating water + condensed water. You also mentioned about
condensed gasoline components. These should also be taken out from the bottom of the tower.

Now if my understanding is correct, this tower has the following functions:


- Cool the reactor effluent
- Condense gasoline components from reactor effluent
- Absorb some CO in water (incidental)

You can simulate this tower in ASPEN PLUS as a Radfrac column. Please be sure to check the Absorber option "ON" for
easier convergence. In this tower, you have no reboiler or condenser, so the degrees of freedom is "0".

I do not know what you mean by "NUT" and "HUT". If you implied "Number of transfer Units" and "Height of transfer unit",
then for number of transfer unit (NTU), you will have to do a rigorous heat transfer calculation. The height of transfer unit
(HTU) will depend on:
- The type of packing
- Size of packing

Please search literature for HTU. Once you have the HTU, assume some heat transfer coefficient and do a heat balance across
each simulation stage. The temperature of vapor/liquid in and from each stage is known, hence the total heat transfer is
known. This will give you the duty that can be extracted from that stage. From this duty you can estimate the water
condensation in that stage.

I have seen and deigned several such towers, and invariably the material of packing is Carbon Steel. Usually there is no
corrosion problem (unless the reactor effluent can form corrosive compound after dissolving in water), also carbon steel
packing will have much better strength than plastic or ceramic packing.

Hope this helps,


Abhishek

Posted 21 April 2010 - 06:39 AM


CRF

Abhishek,

Thanks for the help!


Actually, I know how a quench works, but I was not sure how to design it... the diameter is a function of liquid and vapor
flows, but I was wondering how to calculate HTU and NTU, since the main objective is heat transfer, not mass transfer.
The objectives are:

-Coolling the gas stream - reactor efluent;


-Condensating the water of the gas stream;
-Scrubbing part of co2 of the gas stream.

I was thinking about using a packed tower, but I ve been reading and I think that´s not the best option... I will use a spray
tower. In this case, I can design it as a flash tank with some spray nozzles(atomizers)...I am not sure how to calculate the
diameter of the atomizers and how many ...it sure will be function of water flow, but i ve got no references about atomizers

2 of 3 1/12/2019, 12:48 PM
Quench Tower/absorber Tower - Student - Cheresources.com Community https://www.cheresources.com/invision/topic/10325-quench-towerabsorb...

The gasoline will be absorbed in other tower.

Thanks again

Posted 21 April 2010 - 04:28 PM


abhi_agrawa

Carlinha,

For this service I have never designed a spray tower, and can not help you in that.

I have designed several such tower that used packing. Please note that the contacting efficiency in a spray tower will be
significantly less than that of a packed tower.

Abhishek

Posted 05 May 2010 - 05:10 PM


siretb

Hello.

You have the two options, as stated.


For a packed column (metal or ceramic packing) the HTU will be reasonably well calculated by ASPEN, RATEFRAC.
You will have the risk of a dry/wet transition zone, if the gas is moving upwardsa and if the wetting rate is low.
I see you operate at 19 bars. At what temperature do you have the so called adiabatic temperature?
As for the amount of water necessary, you may use , if you want to go for the ASPEN option, a simple flash coupled with a
design spec. You increase the water flow until some liquid phase apperas in the liquids of a Flash2. You also get the
temperature.

Many a time a conditioning tower thta will spray water to cool gas down, from temperatures of some 300-400°C down to
150°C will be high (some 15m to give a flavor). For 19 bars and 90°C, this will change a bit.

You do have a third option, depending where the dewpoint is, and if the 90°C you mention is critical: That would be to spray
a large amount of liquid, (quench like design) where you would spray 6 to 10 times the flow that will be evaporated (and
already calculated (ASPEN, FLASH2). And you recirculate to the quench the water that is left. Such unit should be much
smaller in size.
At any rate, be extremely cautious of areas where you may have dry/wet transitions (corrosion, fouling).

Back to Student · Next Unread Topic →

Tray Clogging In Absorber In Mdea Cycle 3 replies 22 Dec 2018


Started by Guest_siamak_* , 12 Nov 2018 283 views

Calculations Of Cooling Tower 1 reply 22 Nov 2018


Started by Guest_Sajad9teen_* , 22 Nov 2018 247 views

Cooling Tower Performance 2 replies 14 Nov 2018


Started by Guest_Bruno Credidio_* , 09 Nov 2018 511 views

Design A Closed Circuit Cooling Tower 0 replies 03 Oct 2018


Started by Guest_katolbashi_* , 03 Oct 2018 361 views

Zero Blowdown Cooling Tower HOT 10 replies 09 Aug 2018


Started by Guest_prashamjain_* , 07 Aug 2018 532 views

Cheresources.com Community → General Chemical Engineering Forum → Student

3 of 3 1/12/2019, 12:48 PM

Potrebbero piacerti anche