Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Pre-installation Instructions
1 INTRODUCTION .....................................................................................................................................4
2 SYSTEM CONFIGURATION...................................................................................................................4
3.3 Acoustical...............................................................................................................................................13
3.6.1 Determination of the spot where grounding pole will be laid underground........................................18
3.8 RF Immunity...........................................................................................................................................20
6.2 Floor.......................................................................................................................................................25
6.2.1 Loading...............................................................................................................................................25
1 INTRODUCTION
The NeuViz 16 CT System is an advanced 16-slice detector continuous-rotation tomographic scanner
systems. NeuViz 16 configuration has similar pre-installation and site planning requirements as NeuViz Dual
systems. These systems are intended for an installation in smaller room areas as compared to other
scanners for simplified site planning.
2 SYSTEM CONFIGURATION
The NeuViz 16 System consists of the following system components:
(4) Power Protection Unit 80 kVA Hua Run Voltage Regulator for China only (non-IEC compliant) option.
Automatic Injectors, CCT are available options; refer to other section in this manual for the UPS and/or
Voltage Regulator options that are available with the NeuViz 16 CT Scanner System.
It is not allowed to place high voltage, UPS, VR or power conditioning equipment closer than 1.5 M (60
inches) from patient couch unless it is certified as a medical grade device. Neusoft strongly recommends that
these ancillary components be located in a Technical room (equipment closet) adjacent to the CT Exam
room or Control room. This provision may also protect the Neusoft Technician from radiation during
equipment installation and servicing.
REAR
FRONT
MIN.DOOR OPENING
REAR
FRONT
If planned to install the VR or Power Conditioning device in Control Room, the door width of the control room
is at least 800mm or as required of the power conditioning device.
2.4 Compatibility
Note: Neusoft design and manufacturing practices comply with IEC and other regulatory standards as
approved medical imaging devices. Refer to Section 2.10 for regulatory compliance listings and
agency approvals.
• The NeuViz 16 Workspace supports DICOM connectivity 3.0 compliant, PACS, scanners,
workstations and printers.
Each system is delivered with the options license according to the sales records.
3 ENVIRONMENTAL DATA
Heat emission
Scanner Gantry : 5.0 KW (17,075 BTU/hr)
1.5 kW (5,123 BTU/hr) – Standby
Heat emission
Teal Unit (option) : 0.65 KW (2,210 BTU/hr)
Hua Run V.R. (China option) : 1.20 KW (4,098 BTU/hr)
Heat emission
Operator Workstation & : 0.75 KW (2,561 BTU/hr)
Computer Rack
Console UPS (option) : 0.11 KW (375.00 BTU/hr)
Workstation (option) : 0.29 KW (1,000 BTU/hr)
• The gantry requires air-conditioning and good air flow. Additional capacity and circulation must be
considered when other equipment is located in this area including, but not limited to, other system
cabinets or power conditioning equipment.
• The ideal stable room temperature for the gantry during operation and including patient comfort is 22
degrees ℃ (72 ℉). Under no instances shall the temperature be allowed to drop below 18 ℃ (64 ℉)
or rise above 24 ℃ (75 ℉). Relative humidity 30% to 60% (non-condensing).
• The above conditions must be maintained at all times including overnight, weekends and holidays.
• Temperature change per hour must not exceed 4.1 ℃ (7.5 ℉) during operation.
• Location of room air-conditioning supply vents must not discharge directly over patient table and
treatment area causing discomfort to patient.
• See following figure for gantry air flow circulation directions, when it becomes available. Delta heat
rise temperature difference through the gantry is approximately 12 ℃ (21.6 ℉)
• The facility isolation transformer, Teal unit or Voltage Regulator cabinets require good air flow.
Additional capacity and circulation must be considered when other equipment is located in this area.
• Under no instances shall the temperature be allowed to drop below 18 C (64℉) or rise above 28 oC
(82℉). Relative humidity 20% to 80% (non-condensing). (Optional) A UPS Battery cabinet should not
be exposed to prolonged periods of temperature above 25℃
• The above conditions must be maintained at all times including overnight, weekends and holidays.
• The Operator Workstation/ Computer Rack require air-conditioning and good air flow. Additional
capacity and circulation must be considered when other equipment is located in this area including,
but not limited to, UPS, Workstation and Monitoring equipment.
• The ideal stable room temperature for the equipment during operation and including technician
comfort is 22 ℃ (72 ℉). Relative humidity 35% to 70% (non-condensing). Under no instances shall
the temperature be allowed to drop below 18 ℃ (64 ℉) or rise above 28 ℃ (82 ℉). Relative humidity
20% to 80% (non-condensing)
• The above conditions must be maintained at all times including overnight, weekends and holidays.
• Power conditioning equipment may be located outside of the control room, in order to help eliminate
heat concerns, and may be located in an equipment room within allowable cable length limitations
and temperature ranges specified above.
* Suggested that all south China customers prepare provide one dehumidifier unit for small room and two
units for larger room. For North China, according to local conditions, it is suggested to prepare one unit.
3.3 Acoustical
Audible noise
Scanner Gantry : 68 dB @ 1 meter typical
Note: If facility transformers or power conditioning equipment is placed in the exam room it should be
positioned as far away from the gantry (within limitations of the room and cable lengths) or located within a
dedicated closet enclosure, in order to prevent interference of its noise with the patient intercom.
Audible noise
Teal Unit (option) : 50 dB @ 1 meter typical
Hua Run V.R. (China option) : 50 dB @ 1 meter typical
Audible noise
Operator Workstation & : 55 dB @ 1 meter typical
Computer Rack
Console UPS (Option) 55 dB @ 1 meter typical
The external field strength at scanner and all other system components must be less than 1 gauss
( 0.1mT).
Room shielding requirements for CT scanners can be unique for any particular scanner installation. Scanner
placement within the scan room as well as specifics about the scan room and the spaces surrounding the
scan room should be considered in order to develop a proper scan room shielding design.
Scanner room shielding should therefore be designed and/or at least reviewed and approved by a qualified
radiological health physicist or the facility’s radiation safety officer. The completed shielding design should
also be inspected and verified to meet industry standards before clinical scanning begins. Other guidelines
must be followed as determined by local or country codes and regulations.
The primary and required input from manufacturers for determining the required shielding design is found in
the IEC Stray Radiation Dose Map(s) for a particular system. This map presents near worst-case room
scatter values in a horizontal plane containing the system’s axis of rotation. The map may also be rotated
about its symmetry axis (i.e. the scanner’s axis of rotation) to obtain room scatter values in the vertical
direction. From this scatter data and other detailed information about the scanner operation and the site, an
adequate and proper shielding design can be developed.
Additional information that could be useful in producing a successful radiation shielding design:
• Materials used in the construction of the existing walls, floors, doors and ceilings of the room and
surrounding spaces.
• Occupancy information (contents and usage) of the surrounding rooms and spaces.
• Anticipated operating workload for the scanner to be sited. Some busy modern scanners can
experience workloads approaching 1,000,000 mAs/week or more.
• Room scatter varies approximately linearly with collimated beam width if other factors remain
unchanged. For example, a 20 mm collimated beam width will produce approximately 50% of the
room scatter values as that of a 40 mm collimated beam width for a 140 kVp x-ray beam. Like
wise an 80 mm collimated beam will produce roughly twice the room scatter as a 40 mm beam
width.
• The scattered radiation falls off approximately as the square of the distance from the scattering
source. For example, the scattered dose at 2 meters is approximately 6.35 mm (¼ inch) the value
at 1 meter.
• Second and third order scatter from the air in the scanner room can result in a measurable and
significant dose behind adequate primary scatter barriers.
• Typical shielding requirements for modern multi-slice scanner rooms can vary from 1.58 mm (1/16
inch) to 3.17 mm (1/8 inch) lead equivalency, depending on the site specifics mentioned above.
The image below describes the radiation level in the process of scanning a 320 mm (Body Part) polyethylene
phantom in the scanning room.
If the walls of the scanning room are constructed with common solid bricks (density: 1600 kg / m3), their
thickness should not be less than 425mm. The wall 500mm thick is recommended.
In case the wall is constructed with cement (density: 2400kg / m3), the wall thickness should not be less than
240mm.
In case the wall is constructed with bricks mixed with cement (density: 2050 kg / m3), the wall thickness
should not be less than 275 mm.
The following suggestions are used for reinforcing the existing walls to increase their thickness (as an
example, take a wall that is constructed with solid bricks and whose thickness is 240 mm):
z Fasten inorganic composite protective boards to the wall with nails. A gap of 5-10mm between the
protective board and the wall should be reserved, and the gap will be filled and compacted with the
special protective painting two times;
z Remove the old wall coat, and spread the treated wall with the special protective painting. The painting
should be applied two times at an interval of 8-20 hours (when the wall surface dries to the extent of 70
percent), and the thickness of the coat built up each time should not be more than 6mm. The total
thickness of the resulted protective coat should be about 10mm.
Note: On-the-spot guidance given by professionals is preferable while adopting this method to guarantee a
proper mixed painting and a right technology, and to avoid cracking of the wall coat.
z Fasten wooden board to the wall with nails, then fasten lead sheet 1mm thick to the wooden board with
nails, and then adhere a layer of decorating board to the lead sheet.
Note: Persons who work in the lead room for long time may be vulnerable to the adverse effect.
Note: The above-mentioned methods are applied to the walls facing the front and the back of gantry.
These two walls are the main protected objectives. As to the lateral walls, ceiling and floor, their
protective thickness may be decreased to a lead equivalent of 1.5-2mm.
Lead glass is used for the watching windows, and their lead equivalent should not be less than 2mmPb.
The protection of the ventilator may be taken into consideration depending on the local reality.
The following points should be paid attention to in case there are windows:
z Window blind should be used to avoid the influence of the sunlight on watching screen of display.
z The measurement for preventing dust from entering the room should be taken if there are profuse dusts
outdoors.
z Keep proper room temperature and humidity. The influence of the outdoor environment on the indoor
temperature and humidity should be diminished to the minimum in rainy season or in the seasons when
temperature fluctuation is great.
The window installation in the scanning room should comply with the local
regulation. Regular ventilation of the scanning room should be guaranteed
because X-ray in the room makes the air not healthy. If windows are
Fix Active
shade shade
necessary, their size should be as small as possible, and single direction
ventilator should be installed as is shown in the right figure. Fixed shade is
made of wood and covered with 2mm Pb.
The form of the protective door may be sliding door, double doors, and single door.
In case of the sliding door, its lower side should be placed in the groove 10-15 mm deep beneath the ground,
its upper side should be 100mm higher than that of the entrance, and its width should be 200mm wider than
that of the entrance, so that the door would cover the entrance entirely with an excess of 100mm on either of
two lateral sides when it is closed;
In case of the door fixed on hinge, it should cover the entrance entirely with an excess of over 10mm on each
of the four sides of the door when it is closes.
For the door protection, lead equivalent should not be less than 2mm.
Please take the followings factors into account while fixing the ground wire:
3.6.1 Determination of the spot where grounding pole will be laid underground
The spot where grounding pole will be laid underground should be over 3 meters distant from the nearest
building, and be near by control room where exists a cabinet containing three phase Stabilized Power supply
Unit (RPU).
Grounding pole of CT scanner system should be over 10 meters distant form the grounding pole of lightning
conductor, and no water resource, drainage system, stones and architectural wastes exist in its vicinity.
As a grounding pole, an electrolyzed copper plate 3 mm thick with 1000mm*1000 mm area is preferable.
The connection between copper plate and copper wire could not be made by tin-soldering, and it could be
made only by electrical welding and gas welding, and the welded area should not be less than 10 cm2.
Copper plate should be buried in the moist soil under the layer of frozen soil of the land (in Frigid Zone). In
general, the laying depth should be more than 2 meters. The procedures for laying are described as follow:
a) Dig a pit whose area should be about 1.5 m2 and whose depth should be 2 meters;
c) Spread a layer of common salt (powder) 5mm thick on the layer of charcoal;
e) Spread a layer of common salt 5mm thick and a layer of charcoal 10mm thick above the plate;
f) Fill the pit with the soil excavated while watering till the pit is filled completely.
The upper end of the red copper wire from the underground copper plate should emerge above the ground for
10cm~20cm, and should be connected tightly with the ground wire from the control room by electrical welding,
gas welding, or by bolting and clamping, but should not by tin-soldering. The naked part should be wrapped
with rubberized tape, and then be led to the control room.
The ground wire leading to the control room should be a copper cable whose cross section should not be less
than 6mm2.
Note: in the region with special geologic conditions, users should invite local power department or
qualified professionals for guidance of laying grounding pole underground
Note: for ground with sand structure, the quality of backfill soil should be taken care of. It is not
allowed to use excavated soil to backfill; it is advised to use soil from other places (only wet
soil).
Airborne contaminants must be minimized once the Neusoft medical equipment is placed in the clinic/ hospital
facility staging area or CT suite. All major room constructions must be completed eliminating concrete and
drywall dust. Refer to appropriate Room Ready Checklists for more details and level of acceptance.
Once the CT system has been fully installed and turned-over to the customer, air quality must be maintained
throughout the life of the system. Design of the facility HV/AC system must consider common dust and dirt
problems affecting internal equipment sub-components, air flow and system reliability. Air vents (supply,
return, positive, negative, pressurized, or otherwise) should be fully ducted and must never be distributed
through open interstitial ceiling spaces exposed to dust, asbestos and other contaminants.
Chemical contamination must also be considered, in order to avoid corrosion to internal and external
equipment parts and connections.
3.8 RF Immunity
The NeuViz 16 system complies with the following regulatory standards and agencies:
• UL 60601-1
• EN/IEC 60601-1
The following list itemizes the total NeuViz 16 CT system by material and weight content. Contact the Neusoft
for additional information and documentation on this topic when required.
4 SITE SURVEY
See Pre-installation Check List for the Site Inspection/ Pre-installation Checklist.
Floor loading and clearances must be determined as acceptable along the entire delivery path with, but not
limited to, doorways, corridors, ramps, elevators and the CT exam room. Neusoft Supervision (or by a
trained and approved Neusoft representative) is required during the entire delivery and handling process
for all CT system equipment or heavy power conditioning equipment. Use of elevator lifts to move CT
equipment to another floor level within building must be first approved by the customer’s facility engineer or
elevator service provider prior to equipment delivery. Allowable load limits will vary depending on elevator
classification for passenger and freight use
All delivery trucks used to transport the CT system must have shock absorbers as the minimum requirements.
Air-ride suspension is preferred. The CT system components must remain in its original packaging from the
factory to the warehouse or (in some instances) the customers’ delivery door.
Forklift Specifications:
• 4500 kg minimum capacity capable of balancing load that is 2.4 M long with center of gravity at
midpoint when lowering gantry and wooden crate from delivery truck.
Note: Wooden pallet must remain attached to bottom of gantry for forklift operations.
Refer to the following gantry delivery weight combinations to determine a specific configuration:
• 2035 kg = Configuration for crated delivery: Gantry inside full wooden shipping crate with pallet.
• 1930 kg = Configuration for moving through hospital building: Gantry (no side covers) with dolly
wheels attached.
Refer to the following list for a breakdown on individual components to itemize from:
Note: For elevator lifts, it may be possible to reduce gantry weight by temporarily removing the dolly
wheels. Contact the HelpDesk for more information and direction as needed.
Once the wooden shipping crate is dismantled, the pallet (or steel shipping tubes) under the gantry can be
removed by using the dolly wheels as jacks to raise the gantry. Never attempt to move or push the gantry
without the dolly wheels, wooden shipping pallet or steel shipping tubes attached. Dolly wheels P/N
4541 100 50251 must be ordered from Neusoft.
5.2 Rigging & Lifting
Neusoft supervision is required during the entire delivery and handling process of the CT system. For
overhead lifting with a crane, the wooden shipping crate must remain attached to the gantry. Nylon straps will
wrap around the bottom of the crate’s lower pallet. Minimum roof hatch opening shall be xxx cm L by xxx cm
W for the entire crate to fit through. Never tip the gantry or attempt to lay it flat to compensate for low
overhead clearances.
Humidity in % (non-condensing) 10 / 90
Note: These temperatures do not apply to phantoms which contain water, which will freeze at
temperatures from 0 C (32 F) or lower.
6 MECHANICAL / STRUCTURAL
See following figures for overall dimensions, center of gravity displacement and weights for NeuViz 16 system
equipment components and accessory or options.
Notice: Refer to Installation and Service Manuals for this product on equipment handling and safety
considerations.
Packed Patient
Table Couch (in 2570(101.2) 970(38.2) 1230(48.5) 475(1047)
wooden crate)
Packed
1500(59.1) 800(31.5) 100(3.9) 60(132)
Console Table
Transport
N/A 35(77)
Console Table
Installed
1400
Console Table w/ 700(27.6) 740(29.3) 46.3(102)
(55.2)
Monitor & Acc.
Packed LCD
Located on accessories pallet
19” Monitors (ea.)
Transport LCD in
own box 483(19) 280(11) 584(23) 10(22)
19” Monitors (ea.)
Installed LCD
488(19.2) 221(8.7) 495(19.5) 8(18)
19” Monitors (ea.)
Packed Host
Located on accessories pallet #1
Computer
Transport Host
Located on accessories pallet #1
Computer Rack
Installed Host
660(26) 620(24.4) 720(28.3) 150(331)
Computer Rack
Accessories
1540(60.7) 1220(48.1) 1030(40.1) 235(518)
Pallet
Teal Isolation Transformer Option (50/60 Hz)
Input: 200 to 480 VAC
Output: 380/220VAC
(this option is required for all non-380 and 400 VAC sites)
Packed 37 kVA
Teal Isolation
1320(52) 770(30.4) 830(32.7) 300(662)
Transformer (IEC
compliant)
Installed 37 kVA
Teal Isolation
516(20.3) 552(21.7) 712 (28) 274
Transformer (IEC
compliant)
Apply the following space distances mm (inches) around CT equipment as described. Local codes may
exceed these requirements:
Gantry Couch:
• Front and rear distances are usually dictated by table travel and patient access
• Ceiling height: Recommended 2.43M (8’-0”); Minimum for air flow 2.3M (7’-6”)
6.2 Floor
6.2.1 Loading
Gantry
Patient Couch
See following drawing for equipment floor loading displacement and dimensions in relationship to floor
contact locations.
6.2.2 Vibration\
Operation Operation
Gantry & Couch Rest of System
Vibrations / Shock range in Hz 10 – 150 10 – 150
Vibrations / Shock amplitude in mm 0 – 0.15 0 – 0.15
Vibrations / Shock acceleration in grms 0–2 0–2
Shock acceleration in g 0–2 0–2
Shock pulse duration in msec 6 – 10 6 – 10
Air pressure in Hecto-pascal 500 / 1060 500 / 1060
Note 1: Max. Grms allowable = 0.00001 x (Hz) ^1.7 over the range of 1 to 150 Hz. Maximum allowable
vibration of the x-ray focal spot with respect to the patient couch support top. Higher vibrations at
certain frequencies could lead to image degradation. Vibration velocity = 5500 x (Hz) ^0.7 uin/sec.
Note 2: Max. Allowable steady state vibration transmitted through floor not to exceed 10-3 m/s2 rms
maximum single frequency above baseline from 1 to 80 Hz under gantry and patient couch.
6.2.3 Leveling
See following drawing for equipment floor levelness and waviness tolerances within given equipment
perimeters.
When shim stock is applied exceeding 4mm in thickness to compensate for un-level floor surfaces, improper
anchor engagement may occur using the standard mounting hardware supplied with the CT system. Local
Neusoft Service representative to determine alternative solutions with customer, such as: deeper anchors,
longer studs, through bolting, grout pad, etc.
6.2.4 Anchoring
Gantry
• Sleeve anchor with 4000 psi (27.6 MPa) normal weight concrete:
• 150 mm (5.9”) long by 1/2” (12 mm) diameter with 95 mm (3.7”) embedment
Patient Couch
• Sleeve anchor with 4000 psi (27.6 MPa) normal weight concrete:
• 150 mm (5.9”) long by 1/2” (12 mm) diameter with 108 mm (4.3”) embedment
6.2.4.1 Seismic
Seismic calculations are to be provided through a third-party licensed engineering firm in compliance with
state or country regulations. See following drawing for equipment center of gravity weight and locations where
available.
6.3 Ceiling
Finished ceiling height must not restrict service access, air flow and user’s appliances with the CT equipment.
6.4 Wall
N/A
7 ELECTRICAL DATA
Mains branch power capacity : 80 kVA Nominal size recommended for dedicated supply circuit
Maximum/ momentary power : 65 kVA @ 5 sec. Maximum 50 kW X-ray exposure
required
Steady state/ long time/ processing : 12 kVA
Standby/ idle : 2 kVA
Line voltage variation : + 10% - 10% total (absolute) limits
Line frequency range : 50/60 + /- 1 Hz
Phase to phase imbalance : 5%
Load voltage regulation : +/- 5% not to exceed absolute limits
Voltage drop allowed in feeders : 2% when supply source and other line impedance contributors do
(copper) not exceed an additional 3%, which equates to 5% total regulation
limit.
Conductor impedance : Ohms/ 1000 ft. (305M), .85 PF, copper wires in steel conduit
Power factor : 0.85 min. PF
Mains resistance (for all source : 100 mOhm line to line, max at 380 VAC
impedance measured at the CT
:
Gantry)
Measured current 480 VAC : Standby 2.4 Amps, 3 phase average
(standby, steady state, maximum, Steady state 15 Amps
inrush)
Maximum 78 Amps (50 kW scan @ 480 VAC, 0.85 PF) 5 sec.
Measured current 380 VAC : Standby 3 Amps, 3 phase average
(standby, steady state, maximum, Steady state 18 Amps
inrush)
Maximum 98 Amps (50 kW scan @ 380 VAC, 0.85 PF) 5 sec.
Equipment Isolation
The CT system equipment components shall be insulated from building steel, such as; raceways, trough
ducts, junction boxes, floor rebar, etc. Apply NeuViz Isolation Template P/N 4541 101 35021 under
Gantry and Couch (see following drawing). Only isolated ground wires from the facility power source or
power conditioner shall provide proper grounding to the CT system, assuring safety and ground quality
in compliance with country and local codes. See Protective Earth Ground paragraph below.
Supply Device
Facility power supply needed to feed the following approved CT system power protection units:
a) Teal 37 kVA Isolation Transformer: delta input from source with newly derived wye output
supply to gantry. This unit is IEC compliant.
b) Hua Run 80 kVA Voltage Regulator (China option): wye input from source with newly derived
wye output supply to gantry. Non-IEC compliant.
c) Controlled Power Company 75kVA Voltage Regulator : delta input from source with newly
derived wye output supply to gantry. This unit is IEC compliant.
Apply a dedicated 75 kVA branch isolation transformer (3% regulation rating or better, 2% is preferred),
or purchase a approved power conditioning device, to create a separately derived source whenever:
a. The isolated earth (PE) and neutral (N) conductors are not available from the main
power supply source at the Neutral / Ground reference point.
b. The run length of feeders exceeds 61 meters (200 ft).
c. It is necessary to improve power factors and reduce fault current.
Nominal input voltage to the Hua Run voltage regulator (China option only) requires 380 VAC, 50 Hz.
Nominal input voltage to the Controlled Power Company voltage regulator (ROW) requires 380 Vac/ 400Vac,
50/ 60 Hz. Use of Teal isolation transformer has input range of 200-480 VAC, 50/60 Hz.
Other commercial brands may not be compatible. Neusoft must approve substituting or adding other power
protection equipment, contact Helpdesk if additional information is required.
Run distances and cable/ conductor sizes from Facility Supply to Room Safety Disconnect or input of Teal
Unit based on 380 VAC input:
Run distances and cable/ conductor sizes from Room Safety Disconnect or Teal Unit output to CT Gantry
based on 380 VAC input:
0 – 52 Ft. (16 M) : 16 MM2 power and earth power, neutral and earth
0 – 69 Ft. (25 M) : 21 MM2 power and earth power, neutral and earth
Note 1: A neutral wire is required to input of CT Gantry, from facility supply or from output of Teal unit. Size
(MM2) of neutral wire to be determined by national or local building codes. Neusoft recommends same size
as power feeders and isolated ground wires.
Note 2: Nominal protection ratings of circuit breakers suggested by Neusoft must not exceed amp ratings of
the feeder wires, as specified by local or national codes.
Note 3: Neusoft supplied power cable is available up to 30 M. Contact Neusoft for availability. Provide input
voltage information for obtaining correct cable set.
Note 4: Licensed electrical contractor shall supply and install all copper cable/ conductor wiring described
above and is responsible for connecting to supplied voltage regulator, isolation transformer or power filter
equipment. FSE will make final connections to scanner gantry and consoles, as required.
See following figure for Mains Connection Wiring required of the customer’s facility.
See following figure for cable chart defining specific lengths, routings, diameters and connector sizes.
See following figure for cable duct/trough and raceway sizes, routings and details.
N/A
7.6 Lighting
• A minimum of one socket within close proximity to gantry is required for servicing.
• A minimum of one socket within close proximity to equipment is required for servicing.
• Quantity of wall sockets is customer and code dependent. Specific requirements will depend on Hard
Copy units, other options and customer’s own equipment.
• A minimum of one socket within close proximity to CT Console is required for servicing.
8 NETWORK DATA
The following specifies the minimum network requirements for NeuViz 16 System installation:
• The local system administrator must assign IP address, subnet masks and gateways.
• It is strongly advised to connect the CT system to the hospital network through a router of an
intelligent switch.
Pre-installation
Delivered : N/A
To be ordered : N/A