ProposedwithSix
proposed expansion For
Story Building building project. Concern Society - Risk Registry
Community
Risk Identification Qualitative Risk Assessment Risk Response Plan Monitoring and Control
Risk Category
Probability
Objective
Primary
Impact
Interval, Status: Date
Response Responsible
No Risk Event Cause Effect Risk Matrix Response Actions Milestone or and Review
Strategy Entity
Stage Check Comments
VH
Probability
H X
Very High
Financial
Time
High
Budget Constraints- allocation in
1 Project not fully funded Project delay L Mitigate 2or 3 phases with options in Project Manager Monthly
doubt or subject to change
VL the contract
VL L M H VH
Impact
VH
Probability
H
Increased unit price
Financial
Medium
Medium
Engineers cost M X
Inaccurate cost Unit pricing effected by cost of considering the material Quantity At estimating
Cost
2 estimate L Mitigate
estimate material transportation transportation on narrow Surveyor sage
underestimated VL
VL L M H VH
accessible road
Impact
VH
Probability
H
Quality M Introducing a good
Design
High
Low
Inaccurate building Miscommunication between
3 design failure L x Mitigate communication protocol Architect At design stage
design design team
VL
(drop box)
VL L M H VH
Impact
VH x
Probability
H
Construction
Very High
Difficulty in M
High
H
Construction
Medium
High
Probability
H
Construction
Medium
Medium
Small constriction space with Threat for the M x Take safety precasions,
Cost
6 Health & safety surrounding building close to the workers and L Mitigate Implement health & safety Safety Engineer Monthly
proposed site outsiders VL policy
VL L M H VH
Impact
VH
Probability
H
External
Time
High
High
before
7 Approvals Delay of getting approvals Project delay L Avoid Authorities and get the Architect
tendering stage
VL permission bit early
VL L M H VH
Impact
VH
Probability
H X
Construction
Very High
M
High
Project cost Implement security Resident
Cost
8 Security lack of security L Mitigate Monthly
increases precautions Engineer
VL
VL L M H VH
Impact
VH
Probability
H
External
Medium
Medium
M x Make sure to avoid rainy
Time
9 Weather Rainy rainy weather conditions Project delay L Mitigate seasons in construction Project Manager At design stage
VL period.
VL L M H VH
Impact
VH
Probability
H
Cost/ time
Very High
Very low
External
Project cost M
Before
10 Natural disasters Unforeseen natural disasters increases & L Transfer Take insurance Contractor commencement
project delay VL X of work
VL L M H VH
VH
Probability
H
Construction