Sei sulla pagina 1di 4

METHOD STATEMENT FOR FORMWORK

Contents
Resources Used ....................................................................................................................................... 1
Safety Points ........................................................................................................................................... 1
Work Procedures .................................................................................................................................... 2
Material for Formwork........................................................................................................................ 2
Centering/Staging ............................................................................................................................... 2
Shuttering ........................................................................................................................................... 2
Camber ................................................................................................................................................ 3
Surface Treatment .............................................................................................................................. 3
Erection of Form Work (Centering and shuttering) ............................................................................ 3
Inspection of Form Work .................................................................................................................... 4
Removal of Formwork......................................................................................................................... 4
Precautions ............................................................................................................................................. 4

Resources Used
A. Manpower
- Skilled Labour
- Unskilled Labour

B. Machinery
- Measurement tape
- Hacksaw
- Blade
- Ties and braces
- Hammer
- Crane (for shifting)

Safety Points
 When erecting, altering and/or dismantling formwork there should be inadequate free fall
distance underneath the working area.
 Stripping of formwork for structural elements like cantilever, beams/slabs shall be done only
after mobilization of full restraining forces.
 Adequate fire-fighting facilities/fire extinguishers to be fixed in around work space.
 Appropriate PPE to be worn at all times.

Work Procedures
Material for Formwork
Propping and Centering: All propping and centering should be either of steel square tubes with
extension pieces.

Centering/Staging
 Staging should be as designed with required extension pieces as approved by Engineer-in-
Charge to ensure proper slopes, as design for slabs/beams etc. and as per levels as shown in
drawing. All the staging to be either of Tubular steel structure with adequate bracings.
 Centering and shuttering of any upper floor being cast shall be suitably supported on one
floor below the top most floors already cast.

Shuttering
 Shuttering used shall be of sufficient stiffness to avoid excessive deflection and joints shall
be tightly buttled to avoid leakage of slurry. If required, rubberized lining/ tape of material
as approved by the Engineer-in-Charge shall be provided in the joints.
 The shuttering should also be properly repaired before use and properly cleaned to avoid
stains, honey combing, seepage of slurry through joints etc.
 Runner Joists: MS Channel or any other suitable section of the required size shall be used as
runners.
 Assembly of beam head over props. Beam head is an adopter that fits snugly on the head
plates of props to provide wider support under beam bottoms.
 Form work shall be properly designed for self-weight, weight of reinforcement, weight of
fresh concrete, and in addition, the various live loads likely to be imposed during the
construction process (such as workmen, materials and equipment). In case the height of
centering exceeds 3.50 meters, the prop may be provided in multi-stages.
Camber
 Suitable camber shall be provided in horizontal members of structure, especially in
Cantilever spans to counteract the effect of deflection. The form work shall be so assembled
as to provide for camber. The camber for beams and slabs shall be 4 mm per metre (1 to
250) or as directed by the Engineer-in-Charge, so as to offset the subsequent deflection, for
cantilevers the camber at free end shall be 1/50th of the projected length or as directed by
the Engineer-in-Charge.

Surface Treatment
 Oiling the Surface: surfaces are coated with suitable mould oil which acts both as a parting
agent and also gives surface protections.

Erection of Form Work (Centering and shuttering)


 Any member which is to remain in position after the general dismantling is done should be
clearly marked.
 Material used should be checked to ensure that, wrong items/ rejects are not used.
 Bracing, struts and ties shall be installed along with the progress of form work to ensure
strength and stability of form work at intermediate stage. Steel sections (especially deep
sections) shall be adequately restrained against tilting; overturning and form work should be
restrained against horizontal loads. All the securing devices and bracing shall be tightened.
 When adjustable steel props are used. They should:
 Be undamaged and not visibly bent.
 Have the steel pins provided by the manufacturers for use.
 Be restrained laterally near each end.
 Have means for centralizing beams placed in the foreheads.
 Screw adjustment of adjustable props shall not be over extended.
 Double wedges shall be provided for adjustment of the form to the required position
wherever any settlement/ elastic shorting of props occur. Wedges should be used only at
the bottom end of single prop. Wedges should not be too steep and one of the pair should
be tightened/ clamped down after adjustment to prevent shifting.
 No member shall be eccentric upon vertical member.
 The number of nuts and bolts shall be adequate.
 All provisions of the design and/or drawings shall be complied with Cantilever supports shall
be adequate.
 Props shall be directly under one another in multistage constructions as far as possible.
 Required camber shall be provided over long spans.
 Supports shall be adequate, and in plumb within the specified tolerances.

Inspection of Form Work


The completed form work shall be inspected and approved by the Engineer-in-Charge before the
reinforcement bars are placed in position. Proper form work should be adopted for concreting so as
to avoid honey combing, blow holes, grout loss, stains or discoloration of concrete etc.
 Proper and accurate alignment and profile of finished concrete surface will be ensured by
proper designing and erection of form work which will be approved by Engineer-in-Charge.
 Shuttering surface before concreting should be free from any defect/ deposits and full
cleaned so as to give perfectly straight smooth concrete surface. Shuttering surface should
be therefore checked for any damage to its surface and excessive roughness before use.

Removal of Formwork
The formwork shall be so removed as not to cause any damage to concrete. Centering shall be
gradually uniformly lowered in such a manner as to permit the concrete to take stresses due to its
own weight uniformly and gradually to avoid any shock or vibration.

Precautions
 Where necessary, formwork shall be so arranged that the soffit form, properly supported on
props only can be retained in position for such period as may be required by maturing
conditions.
 Close watch shall be maintained to check for settlement of formwork during concreting. Any
settlement of formwork during concreting shall be promptly rectified.

Potrebbero piacerti anche