Sei sulla pagina 1di 6

Digitally signed by Anwesh Kumar

Anwesh DN: C=IN, OU=R&D, O=JEF TECHNO


SOLUTIONS P.LTD, CN=Anwesh
Kumar, E=anveshkmr150@ieee.org
Reason: I am the author of this

Kumar document
Location: Bangalore
Date: 2018-10-29 10:06:11

HEALTH ASSESSMENT OF AN EHV


EARTHING SYSTEM.
Anwesh Kumar Maddikunta MIEEE,

Deputy Manager R&D at JEF Techno Solutions Pvt.Ltd, Bangalore, India

Anveshkmr150@ieee.org

Abstract: Earthing is the important criteria in an EHV substation for the safety of personnel and equipment for the timely
operation of the protective devices without causing any fire or potential hazard to the personnel. It plays a vital role in limiting
the safe parameters like touch and step potentials. The aim of this paper is to discuss on how to verify the earthing system of a
live EHV substation for the integrity along with the safe parameters without actual shutting down of substation for the testing
and validating the same with software modelling.

Key Words: CDEGS (Current Distribution Electromagnetic Fields Grounding and Soil Structure Analysis) software, Grid
integrity, Off-grid frequency current injection kit, Riser integrity, Soil resistivity, Step potential, Touch potential, Tuned volt
meter.

I. INTRODUCTION earthing system for all the substation for every four years
and for the substations which have periodic verification and
The earthing is done at the time of construction of substation maintenance every year may go for earthing audit once in
with input parameters of soil resistivity and fault current of five years. It is also advisable that the earth grids laid in the
the design. In course of time, the system fault level increases low soil resistivity to be undergone for the audit every four
with the demand by addition of transformers and the years, as the condition of soil may lead to faster rate of
extension of bays but the earth grid will remain the same or corrosion. The switchyards which are older than 20 years are
sometimes extended with an addition of extra grid for the recommended for the audit of earthing system and in India,
bay. During the erection works of the new bays or any other the PGCIL(Power Grid Corporation Of India Limited) had
works by vendors the existing earth grid may get damaged passed the circular that all the substations which are older
and is left unseen for the rectification. This leads to the than 20 years are to be audited for the earthing system and
islanding of the earth grid and will not be known to the implement the audit recommendations to ensure the safety
engineer in-charge of the substation. Due to the fact that the parameters. The other state electricity boards have also
grid is laid below the finished ground level at a normal started implementation of the same to ensure the redundancy
depth of 600mm, it becomes a scenario “out of sight out of of the earthing system.
mind” and left unchecked periodically.
II. METHODOLOGY
Normally the earth grid design is done in accordance to
fulfil the requirements of at-least 25 years of life with a The process of the earthing audit involves different activities
tolerance for any additional fault level in the system. It is and are interrelated to verify the safety parameters in the
deemed that, the earth grid resistance is sufficient for the switchyard. The following are the activities carried during
safety and left unchecked to verify whether the earth grid is the health assessment of an earthing system [2]
sufficient for the safe parameters of touch and step
potentials. Audit of all the equipment will be done time to a) Soil Resistivity
time by specific testing instruments in order to ensure the b) Grid impedance
proper and timely operation of the devices. Whereas, the c) Riser integrity
audit of earthing system is done by measuring the earth d) Grid integrity
grid/pit resistance and check whether they are in limits of e) Measurement of touch and step potential
1ohm for the lower rating switchyards and 0.5ohm for the f) Effect of corrosion on the buried metal
high voltage switchyards. However, as per the IEEE 80
2013[1] by having low grid resistance will not be considered A) SOIL RESISTIVITY:
as safe and the earthing system needs to be checked for the Measurement of soil resistivity is important in evaluating the
safe touch & step potentials, Condition of pits, integrity of earthing system of a switchyard. Soil erosion takes place
risers connecting the equipment to grid and ground grid with course of time and the earthing resistance values
integrity from corner to corner. measured every year may not be in line with the existing soil
The soil erosion takes place normally for every four to five resistivity at that instant of time. Selection of the right
years and the same values of measured resistance may not location for measuring the soil resistivity is important while
be validated all through. As per the recommended practices evaluating for the grid impedance and safety parameters. It
adopted from the different standards of the different is recommended to do soil resistivity during the audit at
countries, it is advised to have checked the integrity of the different locations all through the periphery of the substation
1
for every 100 Mt and away from the substation such that
there is no interference of grid conductor in the measured
values. The distance for the measurement of soil resistivity
from the grid should be at-least half the distance between the
spikes. Please see below figure for the interference of the
grid conductor on the measured values when taken in
parallel to the grid conductor and the values taken in
perpendicular to the grid conductor. The variation in the
measured values vary up to 40 percent of the actual when
taken in parallel without proper separation distance from the
grid and leads to error in the calculations[6].

Figure.2

B) GRID IMPEDANCE:

Measurement of grid resistance/impedance can be done by


fall of potential using three point method. There is a
limitation for using three point method for measuring grid
resistance as the distance required to drive the current spike
should be at least 5 times the length of the diagonal of the
grid and away from the grid. The same can be measured
with the current spike at a distance of three times the length
of the diagonal accounting to some error of 8 to 15 percent.
The potential spike to be driven at different locations
starting from the location of current spike to 20 percent of
the current spike length from the grid and the values of the
resistance to be noted. Now the noted values to be plotted on
the graph with respect to the potential spike distance and the
Figure.1 curve in the graph where saturated/linear is deemed to be the
grid resistance of the switchyard. The above method of
Soil Resistivity should be carried as prescribed in IEEE 81 measurement is called Taggslope method [2] and is
2012 [2]by using ‘Four Point Wenner’ method as shown in
applicable where the soil is uniform in nature. If the soil is
the below figure with equal spacing of the spikes for the non uniform in nature then the above is invalid and the
depths of 0.5Mt, 1Mt, 2Mt, 5Mt, 10Mt, 20Mt, 30Mt, 50Mt impedance can be drawn from the software simulation. The
etc., subject to the available space. The meter used for below Figure 3 shows the Taggs slope fall of potential
measuring the resistance should be capable of injecting the method and software evaluation for grid impedance.
current at off-grid frequency to filter out the interference and
nuisance signals from the vicinity of the measurement and
for the error free calculations. So the selection of meter for
testing is also an important criteria to avoid any short-comes
in the design and recommended for off grid frequency
meters for taking measurements. The measured resistance
values shall be used in calculating resistivity by using the
formula prescribed in the standards as

Depth of driving the rod is insignificant when compared to


spacing between the spikes and in the calculations ‘b’ can be
neglected and the simplified formula for measuring the earth
pit resistance is Fall of potential graph

2
Software simulation for grid impedance

Figure.3 Figure.4
C) RISER INTEGRITY: If the division of current is draining to less than 20 percent
Integrity is verified to ensure the electrical connectivity then it indicates immediate action is required for
between bonding connections/joints. If the two metals are rectification and if the current is less than 5 percent of the
bonded by nut bolt connections / welding / riveted / brazing/ injected current then it is considered to be openness to the
soldering the same cannot be considered as integral unless grid connection or the equipment towards the direction of
verified for the electrical continuity by the current injection. lesser current flow.
The risers are the conductors which raises from the grid and Before the test had been conducted, the test risers were
either connects to the earth pit or to the equipment and are presumed to be in good and healthy condition for above and
physically seen above the ground. The integrity of the below ground connections and when the actual test was
connection can be verified by current injection of low carried by current injection. The anomalies were observed
amplitude of upto 30 A at low voltages and at off-grid and verified by excavation wherever required and found that
frequency in the live substation [2] [5]. If the current is the integrity of risers were missing. Thus it is important to
injected at the grid frequency for the low amplitudes then perform the riser integrity test to ensure that each equipment
the same cannot be identified whether it is the one injected is integral with the earth grid to avoid the development of
or leakage current due to the fact that there is always hazard potentials during the fault scenario and to safely
presence of the leakage currents in the grid. To differentiate discharge the currents to grid offering the least resistance
the current injected at grid frequency, the amplitude should path, otherwise leading to the fatal of the personnel coming
be as high as 100 A or more which may cause potential in contact with the equipment.
hazard to the personnel working in the environment and may
lead to the nuisance tripping in a live substation and such D) GRID INTEGRITY:
high amplitudes of currents are advisable for a substation in
The earth grid is laid beneath the finished ground level at a
the shutdown stage. In order to avoid the above short back in
depth of 600mm and deemed to be integral without
the testing of a live substation, the current at off-grid
verification as it is below ground. In the course of time due
frequency is injected closest to the grid frequency as an
to the activities of vendors like excavation and erection of
example for a 50Hz grid, the off-grid frequency should be
any new installations, the grid may be damaged and as the
60Hz and vice versa.
grid is laid below ground will not be known forever. With
A reference riser to be identified from the grid, example any the presence of moisture content in soil, the grid may be
earth pit in the bay and should be verified for its integrity by corroded and the joints may be eroded and the same can be
trial and error method. One probe from the secondary of the verified only when checked for the integrity of the grid by
current injection kit to be connected to the reference riser current injection method.
and the other to be connected to the riser under test in the
A reference point in the grid to be considered for the
bay and a constant current of up to 10 A to be injected in the
verification of the grid integrity and the resistance is
loop formed by bridging the reference riser and riser under
measured at various points from the reference point to the
test. Ideally each equipment will have two riser connections
diagonal corner of the grid by using Earth Continuity Tester
to the grid for redundancy and when verified for the
which is capable of measuring in the order of micro ohms.
integrity of each riser under test, the split of current should
The measurements are carried by kelvins bridge method for
be divided in equal proportionate. The difference in the ratio
minimizing the errors by considering the voltage drop across
will indicate the condition of the bonding towards
the reference riser and riser under test only. The measured
equipment/grid.
resistance for the risers at a similar distances from the
3
reference riser should be in close proximity and if any order to simulate the fault scenario. The current injected
abnormalities in the values are observed, same can be should be at off-grid frequency so as to avoid interference
verified by voltage drop for the current injected across the with the grid frequency and leakage currents. The GPR will
bridging risers [4] [5] [7]. The measured values can also be raise due to the current injected, the touch and step
verified by comparing with the theoretical values by potentials should be measured at different locations in the
considering the length of conductor, area of cross section of vicinity of the probe connected in the grid by using a tuned
the conductor, resistivity of the material. As per the volt meter which can filter out the other frequencies. The
international standards the resistance of the grid from corner above procedure should be repeated at different location of
to corner should be in the order of 10milli ohms and the the grid or at-least four corners and centre of the grid. The
bonding resistance across the joints should be in the order of measured values are extrapolated to the station fault current
100micro ohms. The limits are mentioned in BS 7430[3] and the safety parameters of design for touch and step
table 14 for the different joints in the substation. potentials can be verified whether in the safe limits or not.

The integrity of the grid will be checked by measuring the


resistance across the various points and by changing the
reference point where ever required. Thus by the above
method the islanding points in the grid can be identified and
the same can be verified by excavation to locate and rectify
the anomalies to avoid the development of any potential
hazards in the grid.

Figure.6

F) EFFECT OF CORROSION:

The grid conductor should be excavated randomly at few


locations and the surface should be scrubbed to remove the
mud and corrosion layer if any and the effective area of
cross section to be measured using a standard vernier
callipers. By having the measured effective area of the
conductor it can be ascertained whether the left out material
is sufficient enough to carry the fault current as per the
design.

III. SOFTWARE MODELLING

INTERPRETATION WITHOUT THE AUDIT OF


EARTHING SYSTEM
Figure.5
If the audit is not carried and the grid is simulated to
E) MEASUREMENT OF TOUCH AND STEP evaluate the safety parameters by considering only the soil
POTENTIAL: resistivity, grid dimensions and inputs of the design then it
may show the result that the gird is safe.
The safety in a substation is achieved by limiting the Ground
Potential Rise, Touch and Step Potentials. The measurement The myths are that there is no change in the soil resistivity
of touch and step potential is difficult for the actual fault as the soil is not changed or uniform in nature, construction
scenario but the same can be determined from the of grid as per the design, riser connection/ grid conductor
extrapolation of values measured with the remote fault for a are the same as there was no disturbance and were lying
low currents by using an off-grid frequency current injection beneath the ground, and in its place. The facts are that in the
kit in conjunction with the tuned voltmeter. The kit should course of time, soil erosion takes place due to wind and
be capable for injecting the off-grid frequency currents from floods and there may be change in the resistivity and soil
the remote location (approximately 5 to 7 times the diagonal may not be uniform in nature, the grid construction may not
length of the grid) to simulate the real time fault at the be in line to the design due to site feasibility constraints,
remote location. Standard equipment are available which external agencies may do some erection works which may
can operate at different frequency ranges for the current damage the earth grid below the ground, corrosion would
injection with variable option from 45 Hz to 70 Hz [1] [2]. have happened and poor workmanship would lead to the
missing of integrity for the risers and grid conductors. But,
One end of the secondary terminals of the kit to be
in the software simulation the inputs taken are dimensions of
connected to the grid and the other to the remote electrode.
the grid, soil resistivity, area of cross section of the grid
A current of low magnitude up to 10 A to be injected in the
conductor and thus grid shows safe as in below Figure 7
loop through the soil from the remote location to the grid in
even after several years of the grid had been laid.
4
in the grid design for the software simulation and the results
will give the actual parameters pertaining to the grid like
touch and step potentials whether in the safe limits.

For the above grid in Figure 7, the audit had been carried out
and the findings were incorporated in the software
simulation and the results of safety will be represented as
below Figure 8 in which the grid was found to be islanding
at many locations and the touch voltage was found to be
unsafe (coloured area representing the different potentials)
and the step potential was found to be safe.

Representation of grid as per design

Actual representation of the earth grid on post audit findings

Software simulation showing the touch voltages are safe

Software simulation showing the touch voltages are unsafe

Software simulation showing the step voltages are safe

Figure.7

INTERPRETATION AFTER THE ACTUAL AUDIT OF


EARTHING SYSTEM.

To have the correct assessment of the earthing system at a


particular period, the audit has to be carried as per the
methodology mentioned in section-II and the corresponding
measured values like soil resistivity at the time of audit,
resistance values obtained in the riser integrity, islanding Software simulation showing the step voltages are safe
locations obtained in the grid integrity are to be incorporated
Figure.8
5
IV. TABLES OF INPUT DATA TO BE f) The person near the remote electrode should be
COLLECTED IN THE AUDIT communicated and kept away from the electrode
while testing

VI. CONCLUSION

Comprehensive earthing adequacy audit of an EHV earthing


system is required for all the substations (mainly older
substations) to ascertain the safety parameters. By
conducting the audit of earthing system, we will be able to
bring down the potential hazards to the equipment failures
and to the human life by identifying the anomalies like exact
location of missing of integrity of the existing earth
connections to the equipment or to the grid, islanding
locations of the grid, condition of the existing earth grid
conductor for the design fault current rating, measured touch
Table.1 Soil Resistivity and step potentials whether in the safe limits. The anomalies
observed in the audit will be proposed for rectification and
the same can be verified by the test methods mentioned in
the section-II.

Now the grid after rectification of audit findings should be


evaluated with the software simulation for the safety
parameters as mentioned in section-III and if required any
modifications to bring the grid to safe, the same should be
implemented. The audit of earthing system not only
beneficial for the old EHV substation but can be
implemented for the new substations before commissioning
to ensure the safety parameters as per the design and to
ascertain the quality of workmanship.

Table.2 Riser integrity


VII. REFERENCES

[1] IEEE 80 Guide for safety in AC substation Grounding

[2] IEEE 81 Guide for measuring earth resistivity, ground


impedance, and earth surface potentials of grounding
system.

[3] BS 7430-Code of practice for protective earthing of


electrical installations

[4] Ground Grid integrity testing by Riley E Moore Virginia


power
Table.3 Grid integrity (values in milli ohms) [5] Effective use of continuity testing to assess grounding
system integrity by Dr.Darren Woodhouse, Mr. Ian
V. PRECAUTIONS TO BE TAKEN:
McLagan and Mr.Stephen palmer
The tests mentioned in the Section II are to be carried in the
[6] IEEE Transaction on New method and instrument for
live substation and the following cares must be taken while
touch and step voltage measurements.
doing
[7] Grounding system testing and assessment by Moritz
a) Engaging the trained engineers to carry out the
Pikisch, Sirko Bohme.
audit
b) All the persons working in the environment should
be equipped with PPE (Personal Protective
Equipment)
c) All the test equipment should be provided with the
earth leakage circuit breaker/Protective device for
the safety of personnel.
d) All the test instruments should be of calibrated
e) Tests should not be carried on a monsoon day.
6

Potrebbero piacerti anche