Revision Index
Revision Issue date Issue description Pages Origin
0 Feb. 2017 For approval
Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 1 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
TABLE OF CONTENTS
A. Scope…………………………………………………………………………………………………...
B. Energization Prerequisites……………………………………………………………………….......
C. Switching Program…………………………………………………………………………………….
Anexure-1: Name and contact number of Engineers executing the programs……………
A. Scope:
1.0 Step-01: Energization of 11 kV cable from SHB-A-PU1/K08 to SB 0054/K04 & Energization of SB 0054.
2.0 Step-02: Energization of 11/0.415 kV Transformer-1&2 at SB 0054 and respective LVAC.
3.0 Step-03: Energization of 11 kV cable from SB 0054/K01 to SB 0052/K01 & Energization of SB 0052.
4.0 Step-04: Energization of 11/0.415 kV Transformer-1&2 at SB 0052 and respective LVAC.
5.0 Step-05: Energization of 11 kV cable from SHB-A-PU2/K07 to SB 0052/K04.
Notes:
HSE rules will be strictly followed during execution of complete program.
Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 2 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
B. Energization Prerequisite.
S. No. Action By Checked
1.1 Copy of SLD delivered to AMD, C.E, DMS and T&P Contractor/Consultant
1.2 Pre-commissioning test results delivered to T&P. Contractor/Consultant
1.3 Clearance to energize certificate for SB 0054 and SB
0052 is issued by Contractor and signed by all Contractor/Consultant
concerned.
1.4 Confirm that no earthing applied in the circuit to be
Contractor/Consultant
energized.
1.5 Energization program approved. Contractor/Consultant /AADC
1.6 All Power Cables are tested and connected. Contractor/Consultant
1.7 All protections are in service, healthy and approved
Contractor/Consultant /AADC
setting has been adapted and tested.
1.8 All permits are returned Contractor/Consultant /AADC
1.9 All engineers executing the programs are available
Contractor/Consultant /AADC
and ready to start.
1.10 Confirm all LVAC panels incoming Isolator and O/G
Fuses are open. No power supply connected and no
Contractor/Consultant
earthing applied to LVAC related to SB 0054 and
SB 0052
1.11 All earthing removed for the circuit/equipment to
Contractor/Consultant /AADC
be energized at SB 0054 and SB 0052
Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 3 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
C. SWITCHING PROGRAMS.
Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 4 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
Step-02: Energization of 11/0.415 kV Transformer-1&2 at SB 0054 and respective LVAC.
Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 6 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
Anexure-1: Name and contact number of the engineers executing the program.
Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 7 of 7.
Rev. 0