Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
618
Synopsis
As per IRC: 112, the time dependent losses have to be calculated in a detailed manner. The procedure is not familiar to Design Engineers. This article lays
down, the detailed method of calculation for arriving at the losses using IRC: 112. In addition the losses have also been calculated using IRC: 18. At the
end comparison has been made between the codes for losses and also for the total time dependent losses and proved both the codes lead to same result for
50% RH only. This article will familiarize the Engineers with the procedure for the calculation of time dependent losses using IRC: 112.
1. INTRODUCTION
Stressed on 28 days Girder placed on bearing Loss between 45 days and 70 days = (2.65 – 2.45) = 0.20%.
35 days Deck slab cast on 45 days Crash
Barrier erection by 70 days Wearing coat to be Loss on 90 days Effective hours = 1992 hrs.
completed by 90 days
d) Bending Moments:
Due to self-weight = 62 tm
Loss between 70 days to 90 days = 2.76 – 2.65 = 0.11 %
Due to deck slab = 62.4 tm
Due to crash barrier = 24.8 tm Loss between 90 days to α Refer clause 6.3.6.
Due to wearing coat = 19.55 tm
Long term loss is 3 times of 2.5 = 7.5%.
e) Prestressing Details:
Loss between 90 days to
Jacking force for cable 1 and 2 = 175t Jacking
force for cable 3 = 146t Prestressing force at Table 2 Relaxation Loss on 1st Stage Cable
center after friction and slip loss in cable 1
and 2 is 157t Prestressing force at center after Loss between 7 days and 28 days = 2.25%
Loss between 28 days and 45 days = 0.20%
friction and slip in cable 3 is 131t
Loss between 45 days and 70 day = 0.20%
3 Loss of Prestress due to Loss between 70 days and 90 days = 0.11%
Relaxation Loss between 90 days and ∝
= 4.74%
Referring to clause 7.9.2 (1) and figure 6.3 of IRC: 112 Total Loss (Check) = 7.50%
the maximum Jacking force shall be 0.87 x 0.9 = 0.78
fp. Taking average stress to be 95% of above value and This check step shall be carried out to see whether it
taking 5% loss due to elastic shortening, the average works out to be 3 times of 1000 hr value or not.
stress in the cables after anchorage will be 0.78 x 0.95 x
0.95 = 0.70 fp. As per table 6.2 of IRC: 112, the relaxation b) Relaxation Loss on stage 2 cable.
loss for 0.7 fp for low relaxation steel is 2.5%.
Similarly proceeding for 2nd stage cables.
a) Relaxation loss on stage 1 cable Stressed on 7 Second stage cables are stressed on 28 days.
days On 28 days: Loss between 7 days and 28 Loss between 45 days and 28th day. Effective
days shall be accounted. Effective days after hours 408.= 87% loss takes place. Loss will be
prestress applied is 28-7=21 days. Total no. of 0.87 x 2.5 = 2.18% Loss on 70 days. Hours
hours: (28-7) x 24 = 504 hrs. As per Table 6 between 70 days and 28 days = 1008 hrs. Taking
for 500 hrs loss will be 90 % of 1000 hrs loss. it as 1000 hrs, loss will be 2.5%. Loss between
Loss up to this stage is = 0.9 x 2.5 = 2.25% 70 days and 45 days will be 2.5 – 2.18 = 0.32%.
Loss between 7 days and 45 days, Total no. Loss on 90 days. Effective hours = 1488.
of effectivehrs = 912% of loss = 98%. Hence
loss will 0.98 x 2.5 = 2.45%. Loss between 28 Loss =
days to 45 days = (2.45-2.25) = 0.20%. Loss
on 70 days. Effective hours = 1512 hrs. As Loss between = 70 days and 90 days 2.65-2.50
it has exceeded 1000 hrs. Refer clause A2.11 = 0.15% Loss up to α = 7.5% Loss between 90
equation A2-38. days and α = 7.5 – 2.65 = 4.85%
1512 0.143
P 1512=2.5 1000 P =2.65% Summarization the losses on 2nd Stage cable.
kh works out to 0.7375 or 0.74. Consider it as 0.75 for Table 6 Total Shrinkage Strain
easy calculation.
Between Autogenous Drying Total Strain as
The unrestrained drying shrinkage value as given days Strain Shrinkage Strain per IRC:18
in table No. 6.8 relates to Relative Humidity (RH)
percentage. IRC: 18 did not relate it to RH. Assuming
RH as 50% and instead of M45 considering it as M50
the value of strain = 420 x 106 . For M45 strain = 443 x
106. Slight change and can be disregarded.
For loading on 7 days . From loading on 7 days the coefficient will work out between
3.1 (corrected) and 2.6 (corrected). Similarly for other
the table . More or
ages of loading. Hence Designers are advised to go
less the values are same. For any grade higher than
by the Annexure rather than using the tabular values.
M45 using the tabulation value will be conservative
and lead to higher losses.
Table 9 Creep Coefficients from IRC: 112 for 70 years he residual strain between intervals are much higher
T
when 50% RH is encountered. However when time
50% RH 80% RH
Age at dependent losses are increased, by 20% as per IRC:18
Loading it will cover for the nominal thickness of members
50 mm 150 mm 600 mm 50 mm 150 mm 600 mm
7 3.9 3.1 2.6 2.6 2.3 2.0 both 150 mm, and 600 mm for 80% RH. The 50 mm
28 3.0 2.5 2.0 1.9 1.7 1.5 thickness may not be a practical case. Coefficients for
90 2.4 1.9 1.6 1.5 1.4 1.20 50% RH they will still be deficient in creep and 20%
enhancement will not cover the creep strains indicated
he values given in the table are corrected values for
T in IRC: 112.
50% RH as printing errors have been noticed.
6 alculation of Losses for Mid-
C
Table 10 Computation of Creep Strain as Per Span Section
IRC: 112 for 50% RH and Strain as Per IRC: 18
Cable stressed on 7th day having a prestressing force of
50% RH Strain as 131t located at 0.113 m from bottom of girder.
Days per IRC: Prestressing effect
18
50 mm 150 mm 600 mm
7
Tensile stress due to self-weight of girder
28
90
Compressive stress around cable = 577.41-373.49
Table 11 Computation of Creep Strain as Per =203.92 t /m2 Modular Ratio = 5.73 E of cable 1.95 x
IRC: 112 for 80% RH and Strain as Per IRC: 18 1.95 x 106 kg/cm2 Area of one strand = 98.7 mm2
= 131 – 4.66 = 126.34t Stress in concrete due to stage cable) Refer table = 0.6 x 1343 x 5.73
1st stage cable stressing and self-weight of girder = x 9.87 x 10-4 = 4.56t Total Losses on Stage 1
577.41 (1-.0356) – 373.49 = 183.36 t/m2 cable from 28 days to 45 days = 13.0t
B. Losses between 28 days and 45 days before
casting of the deck slab Net force at the end of 45 days 126.34 - 13.0 = 113.34t
Stress in concrete due to 1st stage cable and self-
ffect of 2nd stage cable stressing Total Force 314t,
E weight
Stress at 1st stage cable
c) Creep loss due to 1st stage cable stressing (1) Losses on stage 1 cable.
effect=
a) Loss due to relaxation =
nd
d) Creep loss due to 2 stage cable stressing effect
= b) Loss due to Shrinkage
Assuming losses taking place on precast section for d) Gain in prestress due to deck slab casting
this period. Thiswill not make much of change.
(0.73 - 0.62) x 375.90 x 5.73 x 9.87 x 10-4 =(-)0.23t
st
Stress in concrete due to 1 stage cable and self-weight
e) Gain in prestress due to crash barrier casting.
Concrete stress around cable due to 2nd stage oss due to creep (0.87-0.78) x 1252 x 5.73 x
c) L
11.84 x10-4 x 2 = 1.53t
cable stressing d) G
ain in prestress due to casting of deck slab
(0.73-0.62) x 375.90 x 5.73 x 11.84 x 10-4 x
D. Losses between 70 days and 90 days.
2 = (-) 0.56t
Assume full load of crash barrier on 70th day e) Gain in prestress due to crash barrier casting
Stress in concrete
Total losses on 1st stage cable between 90 days Creep loss on 1st stage cable due to 1st stage prestress:
Total Losses = 14.1t (Not match of change) (A) Losses between 7 days and 28 days for cable
of 1st stage:
=
(1) Losses on 1st stage cable
At the end of days prestressing force
Creep loss 2nd stage cable: will be 6.8 x 2.4= 16.32t c. Creep Loss =
Total losses =34.34 (-17.28-16.32)= 33.38t
After accounting for self-weight stress in concrete otal stress due to first and second stage and cables
T
and self-weight
= 512.44 - 373.49 =
Effect of casting deck slab = 375.90
(1) Losses in 1st stage cable:
Net stress = 1437.7-375.90 = 1061.8
a. Elastic shorteningless due to stressing of 2nd stage
cable 1343 x 5.73 x 9.87 x 10-4 = 7.60t Total prestressing force at the end of 45 days
Stress in concrete
c. Creep loss
a. Elastic shortening loss = otal Loss on 1st stage cable between 45 and 70 days
T
= 0.77t
% Loss =
b. Relaxation loss
Stress in concrete =
Crash barrier effect = 100.40 t/m2 Wearing coat effect = 79.14 t/m2
Total force = 114.50 + 293.29 = 407.79t Concrete stress at the end of 90 days = 12.897 +
1285.68 - 375.90-100.40 - 79.14 = 859 t/m2
tress in concrete = 131.66 + 1292.70 -100.40-375.
S
90 =948 t/m2 Net prestressing force at the end of 90 days
b. Shrinkage loss =
b. Loss due to shrinkage
Creep loss =
c. Creep loss = Total loss on 1st stage cable between 90 days and
µ
st
otal Loss on 1 stage cable between 70 and 90 days
T
= 0.675t et prestressing force at the end of µ: =113.82 -
N
14.0 = 99.82t
Loss %
Stress in concrete =
et prestressing force at the end of 90 days = 114.50
N
– 0.68 = 113.82t =
Stress = 131.666 - 0.718 - 1.97 = 128.97t/m2 (2) Losses in 2nd stage cable:
b. Shrinkage loss = 2.4 x .025 = 0.60t c. Creep loss = 5.68 x 2.4 = 13.63t
c. Creep loss = 2.4 x .0.3= 0.72t Total loss in 2nd stage cable between 90 days and
µ= 34.67t
Total loss = 1.76t
= 249.22t
Concrete Stress =
% of force remaining =
Revised Total loss = 13.95 - 5.68 + 5.03 = 13.30t Table 12 Summary of Losses 1st Stage Cable
7 Conclusi ons worked out based on 50% RH the shrinkage loss has
remained same. For higher RH the shrinkage strain has
The calculation of time dependent losses is a complicated to be lower.
process but once if it is practiced it will become easier.
Now each time dependent loss will be commented in As IRC: 18 had not differentiated between RH’s. The
detail. coefficients, shown appears to be based on 50% RH and
the loss will work out more in case of 80% RH as 50%
a) Relaxation Loss: RH coefficient is being followed.
The 1000 hr loss values given in IRC: 18 and IRC: 112 c) Creep Loss:
are same and also 3 times of 1000 hr value to be taken
at is also same. However if one is interested to get The creep coefficients given in IRC: 112 takes in to
relaxation value beyond 1000 hr, the formula given in account the RH, member thickness and age of loading.
the annexure can be used and estimated, keeping the To find out the creep coefficients, preparation of table as
value as 3 times of 1000 hr value. Both codes will lead to indicated in the article is a must. Detailed procedure is
the same result as far as Relaxation loss is concerned. required, to prepare the table as indicated in this article.
Further use of this table and arrive at creep loss requires
b) Shrinkage Loss: skill. In order to familiarize the Engineers the worked
out example gives, the procedure to arrive at the creep
IRC: 112 is more scientific. It relates to member
losses. If creep factors are arrived using annexure A2
thickness relative humidity and grade of concrete. At
there will be reduction in creep coefficients.
higher RH the shrinkage loss will be less and lower RH
shrinkage loss will be high. More over the code covers The strain given in IRC: 18, does not take into account
two types of shrinkages viz Autogenous shrinkage and the RH, the notational thickness. As proved earlier Creep
Drying shrinkage. strain given by IRC: 18 will generally be lower and
with 20% enhancement of time dependent losses will
Whereas IRC: 18 gives only one value for all RH.
cover 80% RH both for 150 mm and 600 mm notional
Moreover as per IRC: 18 strain at initial stage is higher
thickness of members which are practical ranges of
and residual strain islower as shown in the worked
notional thickness, whereas for 50% RH, the creep loss
out example. The strain as per IRC: 112 is opposite.
gets under estimated when IRC: 18 is used for the same
However the total strain appears to be same for 50%
range of thickness.
RH, when 20% higher losses are considered. This will
be explained in detail. Let us assume the curing is d) Total Loss:
stopped after 3 days. The shrinkage strain left is 4.3 x
10-4 as per IRC: 18, when multiplied by 1.20 the ultimate In the worked out example it can be seen after enhancing
shrinkage will be 4.3 x 10-4 x 1.2 = 5.16 x 10-4. the time dependent losses by 20%, the time dependent
losses worked out by IRC: 18 match with the loses
Prestressed concrete uses generally M50 grade. As per worked out by IRC: 112. Though it cannot be concluded
IRC: 112, Autogenous shrinkage strain is 75 x 10-6. by taking one example, further examples may reveal
Drying shrinkage strain for M50 grade concrete and for the closeness of results. IRC: 18 cover estimates the
50% RH is 420 X 10-6 and for 80% RH is 240 x 10-6. shrinkage loss and under stimates the creep loss which
Thus the total shrinkage strain for 50% RH is 4.95 X leads to sort of balancing act with the result both the
10-4 and for 80% RH is 3.15 x 10-4 . Thus it can be codes give same value for 50% RH. For 80% RH; IRC:
seen that as per IRC: 18 (when enhanced by 20%) and 112 should give lesser losses when compared with IRC:
as per IRC: 112 shrinkage strain from both codes will 18 as shrinkage strain and creep strain bothare lower for
match for 50% RH. For 80% RH, IRC: 18 would over 600 mm notional thickness and more or less same for
estimate the shrinkage strains. As the problem has been 150 mm thickness.
8 Recommendation References
Designers can follow the above out lined procedure and 1. Code of Practice for Concrete Bridges –
are advised to use the equations in given Annexure A2 IRC: 112: 2011.
for arriving at the creep coefficients for getting greater 2. Design Criteria for Prestressed Concrete Road
accuracy and saving, instead of using the table in order Bridges – IRC: 18 : 2000.
to reduce the time dependent creep loss. Appears both
codes may lead to same result. However IRC: 112 takes 3. Fib Modal Code: 2010.
into account lot of parameters for prescribing the strain
4. CEB-FIP Model code : 1990
coefficients.
The views expressed in the paper are personal views of the Authors. For any query, the author may be contacted at: E-mail: tvish123@hotmail.com