Datos

g c= 2.4 Tn-m
g s= 1.5 Tn-m
f'c= 280 kg/cm2
Fy = 4200 kg/cm2
Pd = 1.1 m
qa 36.9 TN/M2
COL 30 30
R 7 cm

M tot=
66.1975 90.32 0.00 28.03
P tot=
184.54

5.00 3.00
B1 B2 B3
8.30

1.- Excentricidad

M(R1-3)= 184.54 Tn
P1s = 66.1975 Tn

M(P1-3)=M(R1-3)
0.15 0.15
9,93 + 451,58 + 228,43 = 184,54 (X)
717.03 = 184.54 (X) 5
XCG = 3.885479833 m
e=x-l/2 = 0.26 m

por carga: 22.23 T/m2 + 22.23 T/m2


Pag. 131 Julio Cevallos Centeno
Ing. Civil - Mg. Sc. Estructuras
por momento: 0.00 T/m2 - 22.23 T/m2

2.-AREAS

𝑞�=𝑞𝑎−((𝛾 𝑐+�𝑠)/2)(Pd)-SC

qe = 34.755 Tn/m2 A=B X L

�=𝑃/𝑞� = 5.309761 m2 B= 0.63973 m Secciones


qa max<qa
B(m) qa max qa min A
0.6 44.0211882 30.091563 4.98 aumentar seccion
0.7 37.7324471 25.792768 5.81 aumentar seccion
𝑞𝑎 𝑚𝑎�=𝑃/�(1±(6 �)/�)
0.75 35.2169506 24.07325 6.225 OK
0.8 33.0158912 22.568672 6.64 OK
qa max = 41.28727 1.5 17.6084753 12.036625 12.45 OK
NO CUMPLE
qa min = 28.22273

67 cm

qa min = 1.50 m
qa max =

por metro lineal


qa max = 26.41 Tn/m W=qa max+qa min/2= 22.233825 Tn/m
qa min = 18.05 Tn/m

Por el metodo de las rigideces


22.234 Tn/m
0.2971430207
Mv = (𝑤 �^2)/2=(30,3� 〖 0,15 〗 ^2)/2 Mv = (𝑤 �^
0.15 5 3 0.15

Pag. 132 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
69.4813

16.6755
0

0
(+)M2-1

(+)M3-2
(-)M1-2

(-)M2-3
52.8058

0 M2 52.8058 0

-284.85448 109.00197 -5.241

0 52.8058 0 0
0 0 0 0
0 0 0 0
0 0 52.8058 0 0 0

0 -52.81 0

3.3351 55.585 55.585 33.351 33.351 3.3351

-10.56 -10.56 -17.6 -17.6

3.3351 66.145 45.025 15.751 50.951 3.3351

69.48 60.78 54.29

184.55

Pag. 133 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
armado de losa de cimiento:
Se asume diagrama de suelos rectangular para calcular el momento máximo en la zapata e
Mmax = W x Lcal x Lcal / 2 = 22,23 x 0,5 x 0,5 / 2 =
b h r d
100 cm 20 cm 7.0 cm 13.0 cm
Cuantía de calculo 0.0046 Cuantía final:
Area de acero: 5.98 cm2 Varilla de (mm)
12
Chequeo del cortante:
Vu resistente = 7.68 kg/cm2 Cortante (a cara de columna

armado de viga de cimentacion:


P2s = 90.32 Tn P1s = 28.03 Tn Para el diseno de la viga de cimentacion y facilidad de calculo utilizaremos la luz mayor y
Mmax = W x Lcal x Lcal / 10 = 22,23 x 5 x 5 / 10 =
b h r d
0.15 0.15 0.15 1.5 30 cm 50 cm 8.0 cm 42.0 cm
Cuantía de calculo Err:502 Cuantía final:
Area de acero: Err:502 cm2 Varilla de (mm)
3 14

Chequeo del cortante: vu res: 7.68 kg/cm2

8.30 Vuact = W x Lcal / 2 Vu act Vu act


55.58 Ton 55575
se coloca 1 estribo de 10 mm cada 15 cm
Se acepta el esfuerzo en el suelo por
ancho de zapata

Pag. 134 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
qa min<qa
OK
OK
OK
OK
OK

0.203
Mv = (𝑤 �^2)/2=(30,3� 〖 0,15 〗 ^2)/2

Pag. 135 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
M

0.00 0 0.00 Θ1 0
A= 0.00 (+)M2-1 0X Θ2 = -52.81
0.00 0 (+)M3-2 Θ3 0

Vi

Vh

Vt

Pag. 136 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
0
0
0

Pag. 137 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
Esfuerzo por ml para zapata: 22,23 T/m
mento máximo en la zapata en su parte critica esto es al borde de la viga de cimentacion: L cal = 0.50 m
2.78 T-m (al borde de viga)
f'c fy B1 ro max ro mín.
210kg/cm2 4200kg/cm2 .85 cm .01063 cm .00330 cm
0.0046
# 5.29 Revision de separacion: 30.07 cm
4 varillas de 12 ml en cara inf en sentido de flexion
Sep = ( 95 - ( 1,2 x 4 ) ) / 3 esp = OK

Cortante (a cara de columna) = 11.12 Ton Vu actuante = 10.06 kg/cm2 aumentar espesor de zapata

Es. por ml viga para cimentacion: 22,23 T/m


o utilizaremos la luz mayor y el momento de W x L x L / 10 L cal = 5.00 m
55.58 T-m
f'c fy B1 ro max ro mín.
210kg/cm2 4200kg/cm2 .85 cm .01063 cm .00330 cm
Err:502
# Err:502 Revision de separacion: 2.72 cm
6 varillas de 14 ml en cara sup y en cara inf
Sep = ( 25 - ( 1,4 x 6 ) ) / 5 esp = OK

Vu res 9677.3 kg estribos 10 mm, Av = 1.57 cm2 S = Av x Fy x d / (Vact - Vres)

Vu act b d Vu act / 0.85 Vact/0.85 - Vres Sep en cm


kg 30.00 42.00 65382.35 55705.01 4.97

uerzo en el suelo por ser menor a 10T/m2


1.00 m

Pag. 138 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
Datos
γ c= 2.4 Tn-m
γ s= 1.5 Tn-m
f'c= 280 kg/cm2
Fy = 4200 kg/cm2
Pd = 1.1 m
qa 36.9 TN/M2
COL 30 30
R 7 cm

M tot=
66.1975 90.32 0.00 28.03
P tot=
184.54

5.00 3.00
B1 B2 B3
8.30

1.- Excentricidad

M(R1-3)= 184.54 Tn
P1s = 66.198 Tn P2s = 90.32

M(P1-3)=M(R1-3)
0.15 0.15 0.15
9,93 + 451,58 + 228,43 = 184,54 (X)
717.03 = 184.54 (X) 5
XCG = 3.885479833 m
e=x-l/2 = -0.26 m
8.30

Pag. 131 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
por carga: 22.23 T/m2 + 22.23 T/m2
por momento: 0.00 T/m2 - 22.23 T/m2

2.-AREAS
𝑞�=𝑞𝑎−((𝛾 𝑐+�𝑠)/2)(Pd)-SC

qe = 34.755 Tn/m2 A=B X L


�=𝑃/𝑞�
= 5.309761 m2 B= 0.63973 m Secciones
qa max<qa
B(m) qa max qa min A
0.6 30.0915628 44.021188 4.98 OK
𝑞𝑎 𝑚𝑎�=𝑃/�(1±(6 �)/�) 0.7 25.7927681 37.732447 5.81 OK
0.75 24.0732502 35.216951 6.225 OK
0.8 22.5686721 33.015891 6.64 OK
qa max = 28.22273 1.5 12.0366251 17.608475 12.45 OK
NO CUMPLE
qa min = 41.28727

Pag. 132 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
67 cm

qa min = 1.50 m
qa max =

por metro lineal


qa max = 18.05 Tn/m W=qa max+qa min/2= 22.233825 Tn/m
qa min = 26.41 Tn/m

Por el metodo de las rigideces

Mv = (𝑤 �^2)/2=(30,3� 〖 0,15 〗 0.203118


^2)/2
22.234 Tn/m

0.15 5

0.2 0.2 0.3333


0.1

0.2 0.5333

-0.2501 46.3208 -46.3208 16.676

0.20 0.1 0.00 Θ1 -46.0707 46.0707 -29.6453


A= 0.10 0.5333 0.1667 X Θ2 = 29.6453
0.00 0.1667 0.3333 Θ3 16.4254
-284.85448 109.00197

0.2501 -53.0058 52.133


10.9002 21.8004 -0.873
Pag. 133 Julio Cevallos Centeno
Ing. Civil - Mg. Sc. Estructuras
-56.970896 -28.48545 36.33
-0.2501 46.3208 -46.3208 16.676

0.25 53.01

3.34 55.585 55.585 33.351

10.55 10.55 17.58

3.34 45.035 66.135 50.931

48.38 117.07

-66.13
-62.79

3.34 2.03

2.97

41.712

45.04

50.94

45.97
Pag. 134 Julio Cevallos Centeno
Ing. Civil - Mg. Sc. Estructuras
-6.631308

0.2505

-43.062 -44.84

-52.23
3.-Calculo de Ru

para el Mu en la cara de la columna


𝑅�=𝑀�/(∅ 𝑏 𝑑^2 )= los y en la cara de la columna

y1= 41.712
𝜌𝑏=0,85 𝛽 𝒇�/𝐹𝑦 (6300/(6300+𝐹𝑦))
= 0.029 y2= -62.79

y3= 47.603
𝜌𝑚𝑎�= 0.0145

Pag. 135 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
Tn P1s = 28.03 Tn

0.15 0.15 1.5

Pag. 136 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
qa min<qa
aumentar seccion
aumentar seccion
OK
OK
OK

Pag. 137 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
Mv = (𝑤 �^2)/2=(30,3� 〖 0,15 〗 ^2)/2
0.297

3 0.15

0.3333 K
0.167

0.3333 ∑K

-16.6755 0.25 Mv,f

-16.4254 ∑MV,F

-5.241 Θ

-0.2571
-1.7468
Pag. 138 Julio Cevallos Centeno
Ing. Civil - Mg. Sc. Estructuras
18.1652
-16.6755 0.25

0.26

Vi
33.351 3.335

17.58 Vh

15.771 3.335 Vt

19.11

-15.8
-12.432
2.29
0V

0.71 3.348

47.6

Pag. 139 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
6.1

0.25

0.5

Pag. 140 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
armado de losa de cimiento: Esfuerzo por ml para zapata: 22,23 T/m
Se asume diagrama de suelos rectangular para calcular el momento máximo en la zapata en su parte critica esto es al borde de la viga de cimentacion:
Mmax = W x Lcal x Lcal / 2 = 22,23 x 0,5 x 0,5 / 2 = 2.78 T-m
b h r d f'c fy B1 ro max
100 cm 20 cm 7.0 cm 13.0 cm 210kg/cm2 4200kg/cm2 .85 cm .01063 cm
Cuantía de calculo 0.0046 Cuantía final: 0.0046
Area de acero: 5.98 cm2 Varilla de (mm) # 5.29
4 varillas de 12 ml en cara inf en sentido de flexion
12
Chequeo del cortante:
Vu resistente = 7.68 kg/cm2 Cortante (a cara de columna) = 11.12 Ton Vu actuante =

armado de viga de cimentacion: Es. por ml viga para cimentacion: 22,23


Para el diseno de la viga de cimentacion y facilidad de calculo utilizaremos la luz mayor y el momento de W x L x L / 10
Mmax = W x Lcal x Lcal / 10 = 22,23 x 5 x 5 / 10 = 55.58 T-m
b h r d f'c fy B1 ro max
30 cm 50 cm 8.0 cm 42.0 cm 210kg/cm2 4200kg/cm2 .85 cm .01063 cm
Cuantía de calculo Err:502 Cuantía final: Err:502
Area de acero: Err:502 cm2 Varilla de (mm) # Err:502
6 varillas de 14 ml en cara sup y en cara inf
14

Chequeo del cortante: vu res: 7.68 kg/cm2 Vu res 9677.3 kg estribos 10 mm, Av =

Vuact = W x Lcal / 2 Vu act Vu act b d Vu act / 0.85 Vact/0.85 - Vres


55.58 Ton 55575 kg 30.00 42.00 65382.35 55705.01
se coloca 1 estribo de 10 mm cada 15 cm
Se acepta el esfuerzo en el suelo por ser menor a 10T/m2
ancho de zapata 1.00 m
Pag. 141 Julio Cevallos Centeno
Ing. Civil - Mg. Sc. Estructuras
Pag. 142 Julio Cevallos Centeno
Ing. Civil - Mg. Sc. Estructuras
〖 0,15 〗 ^2)/2

Pag. 143 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
0
0
0

Pag. 144 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras
L cal = 0.50 m
(al borde de viga)
ro max ro mín.
.01063 cm .00330 cm

Revision de separacion: 30.07 cm


Sep = ( 95 - ( 1,2 x 4 ) ) / 3 esp = OK

10.06 kg/cm2 aumentar espesor de zapata

T/m
L cal = 5.00 m

ro max ro mín.
.01063 cm .00330 cm

Revision de separacion: 2.72 cm


Sep = ( 25 - ( 1,4 x 6 ) ) / 5 esp = OK

estribos 10 mm, Av = 1.57 cm2 S = Av x Fy x d / (Vact - Vres)

Vact/0.85 - Vres Sep en cm


55705.01 4.97

Pag. 145 Julio Cevallos Centeno


Ing. Civil - Mg. Sc. Estructuras