PRESUPUESTO AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO ACTUAL SALDO
Item Descripción
Und. Metrado Precio (S/.) Parcial (S/.) Metrado Monto % Metrado Monto % Metrado Monto % Metrado Monto
01 03 AULAS
1.01 TRABAJOS PRELIMINARES
01.01.01 LIMPIEZA GENERAL DE OBRA m2 478.80 0.55 263.34 0.00 0.00 0% 478.80 263.34 100% 478.80 263.34 100% 0.00 0.00 0%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. und 1.00 677.97 677.97 0.00 0.00 0% 1.00 677.97 100% 1.00 677.97 100% 0.00 0.00 0%
01.01.03 ALMACEN DE OBRA mes 3.00 1,243.00 3,729.00 0.00 0.00 0% 3.00 3,729.00 100% 3.00 3,729.00 100% 0.00 0.00 0%
01.01.04 CORTE DE TERRENO CON MAQUINARIA m3 263.10 3.75 986.63 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 263.10 986.63 100%
01.01.05 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE m3 328.88 8.73 2,871.12 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 328.88 2,871.12 100%
1.02 ESTRUCTURAS
01.02.01 MOVIMIENTO DE TIERRAS
01.02.01.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 MT m3 34.16 17.88 610.78 0.00 0.00 0% 34.16 610.78 100% 34.16 610.78 100% 0.00 0.00 0%
01.02.01.02 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 22.43 20.35 456.45 0.00 0.00 0% 22.43 456.45 100% 22.43 456.45 100% 0.00 0.00 0%
01.02.01.03 EXCAVACION MANUAL PARA ZAPATAS m3 42.60 13.30 566.58 0.00 0.00 0% 42.60 566.58 100% 42.60 566.58 100% 0.00 0.00 0%
01.02.01.04 RELLENO CON MATERIAL PROPIO m3 8.22 38.90 319.76 0.00 0.00 0% 8.22 319.76 100% 8.22 319.76 100% 0.00 0.00 0%
01.02.01.05 ACARREO DE MATERIAL EXCEDENTE HASTA D PROM=30M m3 85.67 23.34 1,999.54 0.00 0.00 0% 85.67 1,999.54 100% 85.67 1,999.54 100% 0.00 0.00 0%
01.02.01.06 REFINE NIVELACION Y COMPACTACION m2 49.76 0.62 30.85 0.00 0.00 0% 49.76 30.85 100% 49.76 30.85 100% 0.00 0.00 0%
01.02.01.07 AFIRMADO E=6" PARA PISOS INTERIORES Y EXTERIORES m2 154.19 15.57 2,400.74 0.00 0.00 0% 154.19 2,400.74 100% 154.19 2,400.74 100% 0.00 0.00 0%
01.02.01.08 ARENA BAJO AFIRMADO E=6" PARA PISOS INTERIORES Y EXTERIORES m2 110.30 24.04 2,651.61 0.00 0.00 0% 110.30 2,651.61 100% 110.30 2,651.61 100% 0.00 0.00 0%
01.02.01.09 ARENA BAJO AFIRMADO E=4" PARA PISOS INTERIORES Y EXTERIORES m2 85.67 17.04 1,459.82 0.00 0.00 0% 85.67 1,459.82 100% 85.67 1,459.82 100% 0.00 0.00 0%
01.02.01.10 ELIMINACION DE MATERIAL EXCEDENTE m3 85.67 40.71 3,487.63 0.00 0.00 0% 85.67 3,487.63 100% 85.67 3,487.63 100% 0.00 0.00 0%
01.02.02 CONCRETO SIMPLE
01.02.02.01 CIMIENTOS CORRIDOS F'C = 175 KG/CM2 + 25% P.M. m3 8.54 25.42 217.09 0.00 0.00 0% 8.54 217.09 100% 8.54 217.09 100% 0.00 0.00 0%
01.02.02.02 SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO HORMIGON m2 28.40 30.42 863.93 0.00 0.00 0% 28.40 863.93 100% 28.40 863.93 100% 0.00 0.00 0%
01.02.02.03 FALSO PISO DE 4" DE CONCRETO 1:10 m2 36.77 45.01 1,655.02 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 36.77 1,655.02 100%
01.02.03 CONCRETO ARMADO
01.02.03.01 ZAPATAS
01.02.03.01.01 CONCRETO F'C= 210 KG/CM2. EN ZAPATAS m3 14.20 359.74 5,108.31 0.00 0.00 0% 14.20 5,108.31 100% 14.20 5,108.31 100% 0.00 0.00 0%
01.02.03.01.02 ACERO FY=4200 KG/CM2, GRADO 60 kg 397.06 3.81 1,512.80 0.00 0.00 0% 397.06 1,512.80 100% 397.06 1,512.80 100% 0.00 0.00 0%
01.02.03.02 VIGA DE CIMENTACION
01.02.03.02.01 CONCRETO F'C= 210 KG/CM2. P/VIGAS DE CIMENTACION m3 5.69 393.83 2,240.89 0.00 0.00 0% 5.69 2,240.89 100% 5.69 2,240.89 100% 0.00 0.00 0%
01.02.03.02.02 ENCOFRADO Y DESENCOFRADO P/VIGAS DE CIMENTACION m2 56.90 34.48 1,961.91 0.00 0.00 0% 56.90 1,961.91 100% 56.90 1,961.91 100% 0.00 0.00 0%
01.02.03.02.03 ACERO FY=4200 KG/CM2, GRADO 60 kg 781.58 3.81 2,977.82 0.00 0.00 0% 781.58 2,977.82 100% 781.58 2,977.82 100% 0.00 0.00 0%
01.02.03.03 SOBRECIMIENTO
01.02.03.03.01 CONCRETO F'C=210 KG/CM2. PARA SOBRECIMIENTOS m3 6.43 359.74 2,313.13 0.00 0.00 0% 6.43 2,313.13 100% 6.43 2,313.13 100% 0.00 0.00 0%
01.02.03.03.02 ENCOFRADO Y DESENCOFRADO (PARA SOBRECIMIENTOS Y MUROS) m2 68.88 59.52 4,099.74 0.00 0.00 0% 68.88 4,099.74 100% 68.88 4,099.74 100% 0.00 0.00 0%
01.02.03.03.03 ACERO FY=4200 KG/CM2 EN VIGAS kg 279.89 3.54 990.81 0.00 0.00 0% 279.89 990.81 100% 279.89 990.81 100% 0.00 0.00 0%
01.02.03.04 COLUMNAS
01.02.03.04.01 CONCRETO F'C= 210 KG/CM2. P/COLUMNAS m3 11.72 359.74 4,216.15 0.00 0.00 0% 11.72 4,216.15 100% 11.72 4,216.15 100% 0.00 0.00 0%
01.02.03.04.02 ENCOFRADO Y DESENCOFRADO P/COLUMNAS m2 133.20 39.37 5,244.08 0.00 0.00 0% 133.20 5,244.08 100% 133.20 5,244.08 100% 0.00 0.00 0%
01.02.03.04.03 ACERO FY=4200 KG/CM2, GRADO 60 kg 1,884.15 3.81 7,178.61 0.00 0.00 0% 1,884.15 7,178.61 100% 1,884.15 7,178.61 100% 0.00 0.00 0%
01.02.03.05 VIGAS
01.02.03.05.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 11.72 409.09 4,794.53 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 11.72 4,794.53 100%
01.02.03.05.02 ENCOFRADO Y DESENCOFRADO P/VIGAS m2 86.42 55.51 4,797.17 0.00 0.00 0% 23.56 1,307.82 27% 23.56 1,307.82 27% 62.86 3,489.36 73%
01.02.03.05.03 ACERO FY=4200 KG/CM2 EN VIGAS kg 1,341.15 3.54 4,747.67 0.00 0.00 0% 412.00 1,458.48 31% 412.00 1,458.48 31% 929.15 3,289.19 69%
01.02.03.06 COLUMNETAS
01.02.03.06.01 CONCRETO F'C=175 KG/CM2. PARA COLUMNETAS m3 0.79 372.39 294.19 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 0.79 294.19 100%
01.02.03.06.02 ENCOFRADO Y DESENCOFRADO P/COLUMNETAS m2 13.65 39.37 537.40 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 13.65 537.40 100%
01.02.03.06.03 ACERO FY=4200 KG/CM2 EN VIGAS kg 154.60 3.54 547.28 0.00 0.00 0% 154.60 547.28 100% 154.60 547.28 100% 0.00 0.00 0%
01.02.03.07 VIGETAS
01.02.03.07.01 CONCRETO F'C=175 KG/CM2. PARA VIGAS Y DINTELES m3 0.61 353.52 215.65 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 0.61 215.65 100%
01.02.03.07.02 ENCOFRADO Y DESENCOFRADO P/VIGAS m2 8.12 55.51 450.74 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 8.12 450.74 100%
01.02.03.07.03 ACERO FY=4200 KG/CM2 EN VIGAS kg 346.04 3.54 1,224.98 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 346.04 1,224.98 100%
01.02.03.08 LOSAS ALIGERADAS
01.02.03.08.01 CONCRETO F'C= 210 KG/CM2. P/LOSAS ALIGERADAS m3 16.58 380.46 6,308.03 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 16.58 6,308.03 100%
01.02.03.08.02 ENCOFRADO Y DESENCOFRADO P/LOSAS ALIGERADAS m2 189.57 47.56 9,015.95 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 189.57 9,015.95 100%
01.02.03.08.03 ACERO FY=4200 KG/CM2, GRADO 60 kg 598.67 3.81 2,280.93 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 598.67 2,280.93 100%
01.02.03.08.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO und 1,580.00 2.57 4,060.60 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 1,580.00 4,060.60 100%
1.03 ARQUITECTURA
01.03.01 ALBAÑILERIA
01.03.01.01 MURO DE LADRILLO KK DE ARCILLA DE CABEZA, MEZCLA 1:4 m2 43.20 93.75 4,050.00 0.00 0.00 0% 43.20 4,050.00 100% 43.20 4,050.00 100% 0.00 0.00 0%
01.03.01.02 MURO DE LADRILLO KK DE ARCILLA DE SOGA, MEZCLA 1:4 m2 18.90 61.33 1,159.14 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 18.90 1,159.14 100%
01.03.01.03 ACERO FY=4200 KG/CM2, GRADO 60 kg 52.29 3.81 199.22 0.00 0.00 0% 52.29 199.22 100% 52.29 199.22 100% 0.00 0.00 0%
01.03.02 REVOQUES ENLUCIDOS Y MOLDURAS
01.03.02.01 TARRAJEO EN COLUMNAS m2 146.85 26.87 3,945.86 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 146.85 3,945.86 100%
01.03.02.02 TARRAJEO EN VIGAS m2 94.55 26.87 2,540.56 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 94.55 2,540.56 100%
01.03.02.03 TARRAJEO EN MUROS m2 190.98 26.87 5,131.63 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 190.98 5,131.63 100%
01.03.02.04 CIELO RASO CON MEZCLA DE CEMENTO ARENA 1:4 m2 189.57 17.46 3,309.89 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 189.57 3,309.89 100%
01.03.03 BRUÑAS
01.03.03.01 BRUÑA e=1cm EXTERIOR MTS 173.79 4.16 722.97 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 173.79 722.97 100%
01.03.03.02 BRUÑA e=1cm INTERIOR MTS 72.90 4.16 303.26 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 72.90 303.26 100%
01.03.03.03 VESTIDURAS DE DERRAMES CON BORDES BOLDEADOS M : 1 : 5 m 27.08 1.73 46.85 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 27.08 46.85 100%
01.03.04 PISOS Y PAVIMENTOS
01.03.04.01 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 110.30 15.73 1,735.02 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 110.30 1,735.02 100%
01.03.04.02 VEREDA DE CONCRETO f'c=140 kg/cm2, e=0.15 m. + Sardinel m2 48.70 65.45 3,187.42 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 48.70 3,187.42 100%
01.03.04.03 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 9.78 7.31 71.49 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 9.78 71.49 100%
01.03.04.04 CONTRAPISO DE 48 MM. m2 110.30 15.70 1,731.71 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 110.30 1,731.71 100%
01.03.05 CONTRAZOCALOS
01.03.05.01 CONTRAZOCALO DE CEMENTO S/COLOREAR h = 0.20 m. m 52.70 1.05 55.34 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 52.70 55.34 100%
01.03.05.02 CONTRAZOCALO CEMENTO S/COLOREAR H = 10 CM m 72.90 0.45 32.81 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 72.90 32.81 100%
01.03.06 CUBIERTA Y TECHO
01.03.06.01 MORTERO CEMENTO ARENA 1:10 m3 3.61 290.27 1,047.87 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 3.61 1,047.87 100%
01.03.07 CARPINTERIA DE MADERA
01.03.07.01 PUERTA DE MADERA APANELADA m2 7.20 244.00 1,756.80 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 7.20 1,756.80 100%
01.03.07.02 VENTANA DE MADERA CEDRO C/PROTECCION VAR. DE FIERRO LISO 1/2" m2 36.30 125.60 4,559.28 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 36.30 4,559.28 100%
01.03.08 CERRAJERIA
01.03.08.01 BISAGRA ALUMINIZADA DE 4" X 4" PESADA PARA PUERTA pza 9.00 17.59 158.31 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 9.00 158.31 100%
01.03.08.02 CERRADURA P/PUERTA EXTERIOR TIPO PARCHE 3 GOLPES pza 3.00 81.18 243.54 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 3.00 243.54 100%
01.03.08.03 CERROJOS PARA VENTANAS DE BRONCE pza 42.00 3.50 147.00 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 42.00 147.00 100%
01.03.09 VIDRIOS, CRISTALES Y SIMILARES
01.03.09.01 VIDRIOS SEMIDOBLES p2 390.73 4.46 1,742.66 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 390.73 1,742.66 100%
01.03.10 PINTURA
01.03.10.01 PINTURA SATINADA 2 MANOS EN CIELORRASO m2 189.57 8.42 1,596.18 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 189.57 1,596.18 100%
01.03.10.02 PINTURA SATINADA 2 MANOS EN MUROS INTERIORES Y EXTERIORES m2 190.98 8.42 1,608.05 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 190.98 1,608.05 100%
01.03.10.03 PINTURA SATINADA 2 MANOS EN VIGAS m2 94.55 8.42 796.11 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 94.55 796.11 100%
01.03.10.04 PINTURA SATINADA 2 MANOS EN COLUMNETAS m2 13.65 8.42 114.93 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 13.65 114.93 100%
01.03.10.05 PINTURA SATINADA 2 MANOS EN COLUMNAS m2 133.20 8.42 1,121.54 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 133.20 1,121.54 100%
01.03.10.06 PINTURA BARNIZ EN VENTANA DE MADERA m2 72.60 4.13 299.84 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 72.60 299.84 100%
01.03.10.07 PINTURA BARNIZ EN PUERTAS m2 14.40 4.13 59.47 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 14.40 59.47 100%
01.03.10.08 PINTURA EN CONTRAZOCALO C/ESMALTE m2 125.60 16.23 2,038.49 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 125.60 2,038.49 100%
1.04 INSTALACIONES SANITARIAS
01.04.01 AGUA PLUVIAL
01.04.01.01 GARGOLAS und 3.00 13.42 40.26 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 3.00 40.26 100%
1.05 INSTALACIONES ELECTRICAS
01.05.01 SALIDAS ELECTRICAS
01.05.01.01 SALIDA DE TECHO C/CABLE AWG TW 2.5MM(14)+D PVC SAP 19MM(3/4) pto 12.00 72.42 869.04 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 12.00 869.04 100%
01.05.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC pto 24.00 46.67 1,120.08 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 24.00 1,120.08 100%
01.05.01.03 SALIDA PARA INTERRUPTOR SIMPLE pto 1.00 18.09 18.09 0.00 0.00 0% 1.00 18.09 100% 1.00 18.09 100% 0.00 0.00 0%
01.05.01.04 SALIDA PARA INTERRUPTOR DOBLE pto 3.00 25.59 76.77 0.00 0.00 0% 3.00 76.77 100% 3.00 76.77 100% 0.00 0.00 0%
01.05.02 CAJAS
01.05.02.01 CAJA DE PASE 150 x 150 x 100 MM und 3.00 21.72 65.16 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 3.00 65.16 100%
01.05.03 CABLE Y CONDUCTORES
01.05.03.01 CABLE ELECTRICO NYY 1 X 2.5 MM2. m 240.00 3.05 732.00 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 240.00 732.00 100%
01.05.03.02 CABLE ELECTRICO NYY 2 X 4 MM2. m 360.00 2.94 1,058.40 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 360.00 1,058.40 100%
01.05.04 TABLEROS
01.05.04.01 TABLERO GENERAL 2X15A, 2X20A, 2X30A und 1.00 145.00 145.00 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 1.00 145.00 100%
01.05.04.02 TABLERO DISTRIBUCION CAJA METALICA CON 12 POLOS pza 1.00 183.81 183.81 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 1.00 183.81 100%
01.05.05 LUMINARIAS
01.05.05.01 FLUORESCENTE RECTO ISPE 2 X 40 W INCLUYENDO EQUIPO Y PANTALL und 12.00 98.09 1,177.08 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 12.00 1,177.08 100%
01.05.05.02 FLUORESCENTE RECTO ISPE 2 X 36 W INCLUYENDO EQUIPO Y PANTALL und 3.00 88.09 264.27 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 3.00 264.27 100%
01.05.06 POZOS A TIERRA
01.05.06.01 POZO-CONEXION A TIERRA EN SISTEMA C/EQ.BOMBEO,ALUMB,TOMACORR und 1.00 1,069.11 1,069.11 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 1.00 1,069.11 100%
01.05.06.02 EXCAVACION DE ESTRUCTURAS m3 1.80 15.56 28.01 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 1.80 28.01 100%
01.05.06.03 RELLENO CON MATERIAL PROPIO m3 1.80 38.90 70.02 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 1.80 70.02 100%
01.05.07 PRUEBA DE INST. ELECTRICAS
01.05.07.01 PRUEBA DE INSTALACIONES ELECTRICAS GLB 1.00 562.02 562.02 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 1.00 562.02 100%
1.06 VARIOS
01.06.01 JUNTA SISIMICA DE 2" m 21.15 24.34 514.79 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 21.15 514.79 100%
01.06.02 JUNTA DE DILATACION DE 1" EN PISO INTERIOR m 109.35 4.77 521.60 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 109.35 521.60 100%
01.06.03 JUNTA DE DILATACION DE 1" EN VEREDA m 69.70 4.77 332.47 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 69.70 332.47 100%
01.06.04 PIZARRA ACRILICA 4.00 x 1.20 M, INCLUYE PORTA PULMON und 3.00 455.00 1,365.00 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 3.00 1,365.00 100%
01.06.05 FLETE TERRESTE GLB 1.00 24,561.94 24,561.94 0.00 0.00 0% 0.36349976 8,928.26 36% 0.36 8,928.26 36% 0.64 15,633.68 64%
02 GRADAS DE ACCESO
02.01 TRAZO Y REPLANTEO m2 8.00 1.10 8.80 0.00 0.00 0% 8.00 8.80 100% 8.00 8.80 100% 0.00 0.00 0%
02.02 CORTE SUPERFICIAL MANUAL E=0.40 m m3 2.80 18.31 51.27 0.00 0.00 0% 2.80 51.27 100% 2.80 51.27 100% 0.00 0.00 0%
02.03 REFINE NIVELACION Y COMPACTACION m2 8.00 0.62 4.96 0.00 0.00 0% 8.00 4.96 100% 8.00 4.96 100% 0.00 0.00 0%
02.04 AFIRMADO E=6" PARA PISOS INTERIORES Y EXTERIORES m2 8.00 15.57 124.56 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 8.00 124.56 100%
02.05 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.91 43.16 168.76 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 3.91 168.76 100%
02.06 CONCRETO F'C=175 KG/CM2. P/GRADA Y/O PISO SIMPLE m3 2.26 381.45 862.08 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 2.26 862.08 100%
02.07 PASAMANO METALICO TUBO ø 2" m 8.00 50.45 403.60 0.00 0.00 0% 0.00 0.00 0% 0.00 0.00 0% 8.00 403.60 100%
03 PLATAFORMA MULTIUSOS
03.01 TRAZO Y REPLANTEO m2 300.00 1.10 330.00 0.00 0.00 0% 300.00 330.00 100% 300.00 330.00 100% 0.00 0.00 0%
03.02 CORTE SUPERFICIAL MANUAL E=0.30 m m2 90.00 17.45 1,570.50 0.00 0.00 0% 90.00 1,570.50 100% 90.00 1,570.50 100% 0.00 0.00 0%
03.03 REFINE NIVELACION Y COMPACTACION m2 300.00 0.62 186.00 0.00 0.00 0% 300.00 186.00 100% 300.00 186.00 100% 0.00 0.00 0%
03.04 AFIRMADO E=6" PARA PISOS INTERIORES Y EXTERIORES m2 43.44 15.57 676.36 0.00 0.00 0% 32.58 507.27 75% 32.58 507.27 75% 10.86 169.09 25%
03.05 ARENA BAJO AFIRMADO E=6" PARA PISOS INTERIORES Y EXTERIORES m2 45.00 24.04 1,081.80 0.00 0.00 0% 33.75 811.35 75% 33.75 811.35 75% 11.25 270.45 25%
03.06 ELIMINACION DE MATERIAL EXCEDENTE m3 112.50 40.71 4,579.88 0.00 0.00 0% 112.50 4,579.88 100% 112.50 4,579.88 100% 0.00 0.00 0%
03.07 ENCOFRADO Y DESENCOFRADO PARA LOSA DEPORTIVA m2 66.50 16.50 1,097.25 0.00 0.00 0% 49.88 822.94 75% 49.88 822.94 75% 16.63 274.31 25%
03.08 CONCRETO F'C=175 KG/CM2 PARA PLATAFORMAS MULTIUSOS m3 47.45 373.41 17,718.30 0.00 0.00 0% 35.59 13,289.66 75% 35.59 13,289.66 75% 11.86 4,428.64 25%
03.09 JUNTAS ASFALTICAS m 120.00 4.91 589.20 0.00 0.00 0% 60.00 294.60 50% 60.00 294.60 50% 60.00 294.60 50%
04 GRADERIA
04.01 TRAZO Y REPLANTEO m2 45.00 1.10 49.50 0.00 0.00 0% 45.00 49.50 100% 45.00 49.50 100% 0.00 0.00 0%
04.02 CORTE SUPERFICIAL MANUAL E=0.40 m m3 22.50 18.31 411.98 0.00 0.00 0% 22.50 411.98 100% 22.50 411.98 100% 0.00 0.00 0%
04.03 REFINE NIVELACION Y COMPACTACION m2 45.00 0.62 27.90 0.00 0.00 0% 45.00 27.90 100% 45.00 27.90 100% 0.00 0.00 0%
04.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 37.50 43.16 1,618.50 0.00 0.00 0% 30.00 1,294.80 80% 30.00 1,294.80 80% 7.50 323.70 20%
04.05 CONCRETO F'C=175 KG/CM2. P/GRADA m3 49.50 366.57 18,145.22 0.00 0.00 0% 31.50 11,546.96 64% 31.50 11,546.96 64% 18.00 6,598.26 36%
COSTO DIRECTO 232,361.81 0.00 109,953.61 109,953.61 122,408.17
GASTOS GENERALES 33,901.59 0.00 16,042.23 16,042.23 17,859.35
UTILIDAD 23,236.18 0.00 10,995.36 10,995.36 12,240.82
SUB TOTAL 289,499.58 0.00 136,991.20 136,991.20 152,508.34
FACTOR DE RELACION 0.98999999 0.98999999 0.98999999 0.98999999 0.98999999
MONTO BRUTO VALORIZADO 286,604.58 0.00 135,621.29 135,621.29 150,983.26
IGV 51,588.82 0.00 24,411.83 24,411.83 27,176.99
PRESUPUESTO DE OBRA 338,193.40 0.00 0.00% 160,033.12 47.32% 160,033.12 47.32% 178,160.25 52.68%
VALORIZACIÓN
MONTO
DESCRIPCION CONTRATADO ANTERIOR
SIN IGV ACTUAL
% %
S/.
S/.
TOTAL VALORIZACION CONTRACTUAL (V) S/. 286,604.58 S/. 0.00 0.00% S/. 135,621.29 47.32%
REAJUSTES
REAJUSTE DEL MES 0.00 0.00
AMORTIZACIONES
AMORTIZACIÓN POR FIEL CUMPLIMIENTO 0.00 0.00 0.00
MONTO TOTAL A PAGAR AL CONTRATISTA S/. 338,193.40 S/. 0.00 S/. 160,033.12
BRERO 2018
18
TIVA N 10652 – EL MOLINO, DISTRITO DE CHANCAY BAÑOS –
VALORIZACIÓN
ACUMULADO SALDO
% %
S/. S/.
0.00
0.00
0.00
0.00
S/. 135,621.29
0.00 0.00
135,621.29 150,983.29
24,411.83 27,176.99
S/. 160,033.12 S/. 178,160.28
90 %
4
91.45
80 %
3
68.47
70 %
VANCE
60 %
100 %
90 %
4
91.45
80 %
3
68.47
PORCENTAJE DE AVANCE 70 %
60 %
50 % 2
47.32
40 %
30 % 2
33.92 AVANCE
PROGRAMADO
20 % AVANCE EJECUTADO
Li nea r (AVANCE
10 % EJECUTADO)
1
0
0%
0 di as 1 10 di as 20 di as 30 di a s 40 di a s 50 di as 60 di as 70 di as 80 di a s 90
0
DIAS CALENDARIO
PORCENTAJES VALORIZADOS EJECUTADOS
DIAS PROGRAMADO EJECUTADO
MENSUAL ACUM. MENSUAL ACUM.
0 0 0.00 0 0
21 33.92 33.92 47.32 47.32
52 34.55 68.47
82 22.98 91.45
90 8.55 100.00
(Curva S)
5
100
4
91.45
5
100
4
91.45
AVANCE
PROGRAMADO
AVANCE EJECUTADO
Li nea r (AVANCE
EJECUTADO)
70 di as 80 di a s 90 di as
CRONOGRAMA DE AVANCE DE OBRA EJECUTADO
“MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA
OBRA: INSTITUCION EDUCATIVA N 10652 – EL MOLINO, DISTRITO DE CHANCAY BAÑOS
REGION: – SANTA CRUZ – CAJAMARCA”
CAJAMARCA
PROVINCIA: SANTA CRUZ
DISTRITO: CHANCAY BAÑOS
LOCALIDAD: EL MOLINO
PERIODO: DEL 08/02/2018 AL 28/02/2018