Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
REPORT ASSIGNMENT 5
GROUP 14
GROUP PERSONNEL:
ii
LIST OF FIGURES
iii
additional cost that is needed is $ 2,948. The total capital investment of a biogas
plant is $ 3,752,215.
Operational cost is the total expense to run a production process. Operating
cost consist of the expense of manufacturing a product as well as the packaging
and shipping, selling and distribution, and general overhead expenses. Material
cost is very important because production process is depend on the material
supplier. The cost of raw material in the first year is $ 893,627 and annual cost of
raw material is $ 893,627. The cost of total indirect and direct labor is $ 440,750.
Utility costs are costs that used to finance the main necessities of the production
such as water and electricity. Each of water and electricity cost are $ 182,293 and
$ 479,092. Maintenance is required both for factories, offices, and supporting
equipment so it can be used continuously. The total cost of maintenance is $
221,944. The total cost of insurance is $ 56,900. After all of the cost breakdown
from operational cost calculated, the total operational cost per year could be
obtained.
To startup the plant, a large sum of money needed to meet the initial capital.
Thus, the calculation in this scenario is based on the assumption that the plant
would run based on subsidy from the government, and the rest is by investor. The
share capital for investor is 50%, while the rest would be owned by the
government. A profitability analysis is carried out to analyze the plant’s economic
feasibility. The factors to determined economic feasibility of the plant are
Payback Period (PP), Break-Even Point (BEP), Net Present Value (NPV), Return
on Investment (ROI), and Internal Rate of Return (IRR).
By the time, there will be instability that affects plant production, thus
affecting the economic feasibility. This instability happens because of the various
factors. Therefore, the sensitivity analysis needs to be done against some changes
to analyse what variables that can affect the stability of manufacturing process.
iv
LIST OF TABLES
v
CHAPTER 1
CAPITAL ESTIMATE
1.1 Calculation Assumption
In counting economic of Biogas Plant, calcualtion will be based on several
assumptions, such as :
USD currency that will be used in economic analysis is having exchange
rate 1USD= Rp 14,941,00
There are 330 work days and it is devided itu 2 days per batch.
The equipment is purchased in 2021
Duration estimated to complete the plant is 2 year
The production begin in 2022
The life time of this plant is 20 years, estimated to operate from 2022 to
2042
Depreciation will be calculated using declining balance method
All equipment has its salvage value
Plant total production is 5242 m3 biogas per year
1.2 Cost Index
The purchased cost of each piece of process equipment may now be
estimated from published cost data or from appropriate manufacturers’ bulletins.
Regardless of the source, the published purchased-cost data must always be
corrected to the current cost index. Most cost data which are available for
immediate use in a preliminary or predesign estimate are based on conditions at
some time in the past. Because prices may change considerably with time due to
changes in economic conditions, some method must be used for updating cost
data applicable at a past date to costs that are representative of conditions at a later
time. This can be done by the use of cost indexes. A cost index is merely an index
value for a given point in time showing the cost at that time relative to a certain
base time. In this economic analysis, Chemical Engineering Cost Index is used to
predicting plant equipment price in the year when the item bought in present time.
The available CEPCI data for 2017 can only be obtained for the range year between
2009-2017. The Table below shows the data for cost index from 2009-2017.
1 Universitas Indonesia
2
2017 634.8
CEPCI DATA
700
600
500 y = 11.912x - 23394
R² = 0.8305
400
300
200
100
0
2008 2010 2012 2014 2016 2018
Universitas Indonesia
3
Universitas Indonesia
4
Universitas Indonesia
5
vendor supplied list of standard sizes and often includes a driver, such as an electric
motor. A module contains not only the piece of equipment or machinery, but also all
other materials for installing it (setting it and connecting it to equipment in other
modules), including the piping to and from other modules; the concrete (or other)
foundation; ladders and other steel supporting structures; the instruments, controllers,
lighting. and electrical wiring; insulation; and painting. Also, depending on plant
location and size, some equipment may be housed in process buildings or shelters.
But, because of plant design class deal, piping cost and concrete module will not be
included and will be calculated manually.
To calculate the total bare module cost, FOB of equipment should be
multiplied with bare module factor. Bare- module factors vary among the various
types of fabricated equipment and process machinery, decreasing somewhat with
increasing size. The extent of this variation for ordinary materials of construction
and low to moderate pressures can be seen in table 1.3, which is taken from
Guthrie (1974), based on single units of smaller size, where the factors are as
much as 10% lower for multiple units of the same type.
Universitas Indonesia
Table 1. 3 Equipment Cost
Heat Exchanger
2 Heat Exchanger HE-100 1 2018 644.416 27,519 27,518.86 680.15 29,044.92 3.17 92,072.39
3 Heat Exchanger HE-101 1 2018 644.416 28,728 28,727.66 680.15 30,320.74 3.17 96,116.76
4 Heat Exchanger HE-102 1 2018 644.416 62,079 62,078.77 680.15 65,521.33 3.17 207,702.63
Reaktor
5 PBR 50 2018 644.416 50.00 2,500.00 680.15 2,638.64 3.05 8,047.84
6 Fermentor 2 2018 644.416 38,798 77,595.80 680.15 81,898.86 1.9 155,607.84
Centrifuge
disk stack
7 1 2018 644.416 101,276 101,275.79 680.15 106,892.02 2.03 216,990.80
centrifuge
Separator
6 Universitas Indonesia
7
Mixer
Seeding Tank
12 1 2018 644.416 4,000 4,000.00 680.15 4,221.82 1.8 7,599.28
Mixer
13 Make up MDEA 1 2018 644.416 4,000 4,000.00 680.15 4,221.82 1.8 7,599.28
Storage
Nutrient Storage
14 1 2011 585.7 12,500 12,500.00 680.15 14,515.79 1.7 24,676.85
Tank
Amonia Storage
15 1 2011 585.7 10,000 10,000.00 680.15 11,612.63 1.7 19,741.48
Tank
Water Storage
16 2 2018 644.416 502 1,003.08 680.15 1,058.71 2.8 2,964.38
Tank
Utility
17 Clarifier 2 2010 550.8 1,871 3,742.84 680.15 4,621.82 1 4,621.82
18 Filter Tank 1 2016 624.6 2,807 2,807.13 680.15 3,056.80 2.32 7,091.77
19 Ion Exchange 1 2016 634.8 2,807 2,807.13 680.15 3,007.68 2.32 6,977.82
20 Softener Tank 1 2018 644.416 600 600.00 680.15 633.27 2.32 1,469.19
21 Deaerator 1 2018 644.416 10,000 10,000.00 680.15 10,554.55 2.45 25,858.64
23 Boiler 1 2018 644.416 12,000 12,000.00 680.15 12,665.46 2.19 27,737.35
7 Universitas Indonesia
8
8 Universitas Indonesia
9
9 Universitas Indonesia
10
Universitas Indonesia
11
Controller
Total
Price Total Price
Type Qty Spare Price
(USD) (IDR)
(USD)
Level Indicator 5 2 35.00 245.00 3,660,545
Level
Level Transmitter 5 2 120.00 840.00 12,550,440
Flow Indicator 2 1 51.00 153.00 2,285,973
Flow
Flow Transmitter 2 1 120.00 360.00 5,378,760
Pressure Indicator 4 2 51.00 306.00 4,571,946
Pressure
Pressure Transmitter 4 2 101.00 606.00 9,054,246
Temperature
Indicator 10 5 220.00 3,300.00 49,305,300
Temperature
Temperature
Transmitter 10 5 90.00 1,350.00 20,170,350
Total 7,160.00 106,977,560.00
Universitas Indonesia
12
Price
Component 2 2
Area (m2) Cost (USD)
Price (IDR/m ) Price (USD/ m )
Building 3000000 201 1464 $ 293,956
Concrete 42750 2.9 10800 $ 30,902
Green Area 20000 1.3 360 $ 482
Asphalt 60000 4.0 7882 $ 31,652
Total $ 356,992
Universitas Indonesia
13
differs every year, its predicted that the price is Rp2,000,000/m2. So, the total cost
for land is shown in Table1.9.
Table 1. 9 Land Cost
Socket Outlet
50 3.5 $ 177
Manufacture
Socket Outlet Office 30 3.5 $ 105
Switch 250 1.3 $ 335
Electric Panel 8 6.7 $ 54
Total $ 749
Universitas Indonesia
14
Beside the market research cost, there are some additional cost that will be
included in CAPEX. The cost is based on the Indonesia Law of Industry No 14.
2001, with the additional of local services company such as Telkom for telephone
wire instalment and internet, water and hydrants installation, and licensing, shown
in the Table 1.12.
Table 1. 12 Additional Cost
Universitas Indonesia
Table 1. 13 Total Capital Investment
Investment Group Component Description Parameter Cost (USD) Total Cost (USD)
Main Equipment Production Process Equipment Calculated
1,357,390
Equipment Offsite Equipments for Utility and Waste Treatment Calculated
Supporting Equipment Office Facilities and Additional Hardwares Calculated 36,130
Control Process Controller and Indicators Calculated 7,160
Materials
Direct Cost Building and Civil Work Concrete, Asphalt and Building Calculated 356,992 2,129,483
Electricity Electricity Installment Calculated 749
Licensing Patent Registration and Performance Testing Calculated 605
Additional Cost
Land Land Cost for Plant Development Calculated 368,115
Installation Installation Cost Calculated 2,343
Contractor Fee Contractor Fee Calculated 28,559
Contingency - 15% TBM 203,609
Indirect Cost 637,637
Market Research Survey and Consultant Service Calculated 3,681
Engineering Expense EPC Fee 29.6% TBM 401,788
TOTAL PERMANENT INVESTMENT ( CTPI) 2,767,120
15 Universitas Indonesia
1.4 Benchmarking
The purpose of doing a benchmarking is to ensure the validity of cost &
investment of this plant, and to provide further visualization of the economic
capability of the plant. In the world, there are still only few and mostly considered
new biogas plants that does production in a significant and accountable quantity.
Universitas Indonesia
CHAPTER 2
OPERATING COST
2.1 Direct Production Cost
Operational cost is the total expense to run a production process. Operating
cost consist of the expense of manufacturing a product as well as the packaging
and shipping, selling and distribution, and general overhead expenses. The
manufacturing expense will be interpreted to mean those expenses required to
make a product and to ready it for shipment. Unit cost is the cost of an item based
upon either a mass or volume unit. Raw materials, by-products and utility costs
are quoted on these bases. Operational is categorized into fixed operation cost and
variable cost. Fixed operation cost is all the costs that we spent other than
manufacturing cost, such as administrative cost, distribution cost, marketing cost,
etc. Variable expenses vary approximately in direct proportion to the production
rate.
2.1.1 Raw Material Cost
Material cost is very important because production process is depend on the
material supplier. Biogas production plant with production capacity 1721.916 m3
gas methane per year and require large amount of raw material. There are
microalgae, carbon dioxide, water, microorganism and nutrient.
List of raw materials and prices as well as the suppliers required in the
production of bio-asphalt are summarized in the Table 2.1. All of the raw material
required are shipped every week, so the calculation used the amount of material
needed for a week-worth production.
17 Universitas Indonesia
18
Universitas Indonesia
19
Amount/
Salary/month/ Total Total Salary
Position shift
person ($) Workers /year ($)
(person)
Operator and 303 10 30 109,256
Technician
Production 359 3 9 38,736
Supervisor
Utility 303 2 6 21,851
Operator
Utility 359 1 3 12,912
Supervisor
Total 48 182,756
Total per year
182,756
The total direct workers salary is $ per month and $ per year. There are
three components of remuneration that the company should give to employees:
1. Basic wages (basic income), is the base remuneration (base salary).
2. Fixed allowance, ie payments to workers who carried out regularly and is not
associated with the presence of workers or certain of achievement.
3. Allowances are not fixed, is a payment that is directly or indirectly associated
with the workers be given on an intermittent basis and are paid according to the
time unit that is not the same as the time of payment of basic wages, such as
transport.
Universitas Indonesia
20
The estimate number of operators is for per shift and to account for three
shifts daily. For this plant, since the process operation is continuous, the operators
should cover the full 24 hours, 7 weeks, 12 month a year. For the basis, it is
decided to make 3 shift operations in direct labor. The cost of indirect works can
be seen in Table 2.3.
Table 2. 3 Indirect Labor Salary
Universitas Indonesia
21
2.1.3 Utility
Utility costs are costs that used to finance the main necessities of the
production such as water, electricity, and plant infrastructure. Variable utility
costs are costs for utilities that used for production processes. Those utilities are
such as electricity and fuel for the generator when there is no electricity supply
from PLN or when it is black out. This biogas production plant also has the utility
for water. To calculate the cost of electricity on production process, data of power
needed by each equipment to operate are used. Calculation of energy balance is
done based on the assumption that power needed by each equipment to be
operated in one year.
2.1.3.1 Electricity
Table 2.5 shows the electricity required to operate each equipment in main
process.
Table 2. 5 Electrcity Cost for Main Process
Duration
Power Power
No Equipment Qty process
(kW) (kWh)
(h)
1 Lamp for Photobioreactor 1 12 0.10 1.2000
2 P-100 1 24 1.10 26.4000
3 P-101 1 24 0.50 12.0000
4 C-100 1 24 0.40 9.6000
5 P-102 1 24 2.00 48.0000
6 CEN-100 1 24 2.56 61.4400
7 Fermentor R-101 1 24 0.32 7.5984
8 P-103 1 24 0.10 2.4000
9 P-104 1 24 0.25 6.0000
10 P-105 1 24 0.47 11.2800
11 P-106 1 24 0.50 12.0000
12 Fermentor R-102 1 24 1.50 36.0000
13 P-107 1 24 0.50 12.0000
14 C-101 1 24 10.00 240.0000
Universitas Indonesia
22
Duration
Power Power
No Equipment Qty process
(kW) (kWh)
(h)
15 P-108 1 24 0.02 0.4800
16 P-109 1 24 0.50 12.0000
17 P-111 1 24 0.09 2.1600
18 P-112 1 24 0.50 12.0000
19 P-113 1 24 1.50 36.0000
20 P-114 1 24 0.02 0.4800
21 P-115 1 24 0.02 0.4800
22 P-116 1 24 0.02 0.4800
23 P-117 1 24 0.02 0.4800
TOTAL 550.48
TOTAL electicity requirement a year 181,657.87
Table 2.6 shows the electricity required to operate each equipment in supporting
equipment.
Table 2. 6 Electricity Cost for Supporting Equipment
Power Operation Total Power Per
Supporting Equipment Qty
(kW) time (h) Day (kWh)
Air Conditioner 5 0.2 24 24
CCTV 15 0.04 24 14.4
Dispenser 1 0.08 24 1.92
Faximiles 2 0.0005 10 0.01
Neon lamp 30 0.4 10 120
Photocopy, scanner, and
2 0.1 10 2
printer machine
Televisions 2 0.4 5 4
UV lamps 4 0.015 10 0.6
Total per day 167
Total per year 55,087
2.1.3.2 Water
Water is needed to produce steam which provide heat for the process.
Table 2.8 shows the cost needed for water. Water cost for industry based on price
list from PDAM Cilegon is Rp. 9,500.00 or $ 0.65/m3.
Table 2. 8 Water for Utility Cost
2.2 Maintenance
Maintenance can be defined as an activity to maintain condition of the
facilities or plant equipment and made repairs or replacement that necessary in
order to obtain a satisfactory state of production operations, as well as planned
before. Maintenance is required both for factories, offices, and supporting
equipment so it can be used continuously, and optimal production quality can be
assured.
Maintenance process is performed with the three parts, i.e major equipments
maintenance, plant and office building maintenance, and supporting equipment
maintenance. Maintenance cost consists of cost for maintaining and repairing
equipment. It is usually takes 10% of total investment cost production (Ir. Yuriadi
Universitas Indonesia
24
2.3 Insurance
This plant calculates the insurance for building and plant, raw materials and
the workers (labors), as shown in Table 2.10.
Table 2. 10 Insurance Cost
Insurance Percentage Source Price of Price of
Type (%) Source Insurance ($)
Worker 3.70% salary for worker 440,750 16,308
Plant 2.27% cost of equipment 1,357,390 30,840
Raw 2% raw material cost
485,952 9,719
Material
Total of Insurance 56,900
Universitas Indonesia
25
Universitas Indonesia
26
CHAPTER 3
ECONOMIC EVALUATION
Universitas Indonesia
27
3.3.2 Depreciation
3.3.3 Before and After-Tax Cash Flow
3.4 Profitability Analysis
A profitability analysis is carried out to analyze the plant’s economic
feasibility. The factors to determined economic feasibility of the plant are
Payback Period (PP), Break-Even Point (BEP), Net Present Value (NPV), Return
on Investment (ROI), and Internal Rate of Return (IRR).
3.4.1 Payback Periode
Payback period is the time needed for cash inflow to be equivalent with cash
outflow. Payback period mainly indicates project’s liquidity rather than
profitability (Sullivan, et al. 2015). Payback period can be calculated from the
cumulative cash flow. The payback period of this project is X years
Universitas Indonesia
28
A project can be counted as feasible if the NPV > 0, which means the
project is profitable or provide benefits if implemented. If NPV < 0, the project is
not eligible to run because it does not generate profit.
Where r is the value of IRR and TCI is Total Capital Investment. The
calculation of IRR is done by using Microsoft Excel where it already has the
function to calculate the IRR in economic analysis. If Microsoft Excel cannot
calculate the negative IRR value, modified IRR formula is used. Excel's MIRR
function has this form:=MIRR (values, finance_rate, reinvest_rate).
The values argument is the same as the values argument for the IRR. It is an array
or cell reference to the cash flows for which the MIRR is to be calculated.
The finance_rate argument is the annual interest rate that would be paid to cover
any negative cash flows incurred during the life of the investment.
The reinvest_rate argument is the interest rate that would be earned on cash that
the investment generates during its life.
Universitas Indonesia
29
Universitas Indonesia
30
CHAPTER 4
CONCLUSION
Universitas Indonesia
31
REFERENCES
Universitas Indonesia