Quotation for Geotechnical Investigation & Topography, Sardar Mohammad Dawood Khan hospital,

Kabul

Submitted By: Omran Geotechnical Company (OGC).

Submitted To: Denzay Architecture & Engineering

Unit Cost Total Cost


No. Description of Task Unit QYT
(USD) (USD)

1 General Items

1-1 All Mob-Demob charges for Trucks, Drilling Rigs, Equipment, field staff and soil samples L.S 650 1 $650

1-2 Accommodation Facility and Food, Internet for field people in Site by OGC Responsibility L.S 300 1 $300

2 Topography Study

Total Survey Area : 15.000sqm(including site utilities etc.) L.S 2500 1 $2,500

2 Field Geotechnical Investigation

Drilling of Three (03) Boreholes by 18 m Depth by Rotary Drilling Rigs (BH#01, BH#02 &
2.1 Meter $40 54 $2,160
BH#03 (Total Drilling 54 m) )

2.4 Standard Penetration Test (SPT), (ASTM D 1586) Test $20 19 $380

2.5 Field Density of soil by sand cone method (FDT) (ASTM D-1556) Test $25 3 $75

Contractor has responsibility for all official procedure with Clinet & Afghan Government to prepare permission letter for start
Note
of Geotechnical Investigation.

3 Laboratory Testing - Representative Soil Samples

3.1 Sieve Analysis for soil particle size distribution (ASTM D-421) Test $10 16 $160

3.2 Plastisity Index (PI) determination (ASTM D-4318) Test $15 8 $120

3.3 Soil Engineering Classification by AASHTO & UNIFIED systems Test $5 16 $80

3.4 Hydrometer test (ASTM D 422) Test $20 7 $140

3.5 Moisture Content determination (ASTM D-2216) Test $15 6 $90

3.6 Specific Gravity by Pyknometer (ASTM D-854) Test $10 4 $40

3.7 Direct shear test on cohesive soils (ASTM D-3080) Test $30 3 $90

3.8 UCS test (unconfined Compressive Strength of cohesive soil) (ASTM D-2166) Test $30 4 $120

3.9 Soluble Sulfate content of soil (ASTM C-1580) Test $30 2 $60

3.10 Collapse Potential Test (ASTM D-5333) on samples depth of 1.5 and 2.25 meters Test $30 4 $120

3.11 Unconsolidated-Undrained Triaxial Compression Test on Cohesive Soils (ASTM D 2850) Test $45 3 $135

4 Lab Data Analyzing and Water Well Reporting

Preparing comprehensive Report consist of sub soil description, Lab test results, field test
4.1 results, BH & TP logs, subsoil profile, water table reporting, Geotechnical Reccomendations, L.S $450 1 $450
bearing capacity, sattlement and Limitations for foundation and design

TOTAL PRICE (USD) $7,670

mosavi@greentech.af
Samad Heidari omran.geotechnic@yahoo.com
Technical V.P s.heidari@ogc.af
Omran Geotechnical Co.
Date: December 06, 2018

Time Schedule Day


1 Mob and Demob of Field Staff & Soil Samples 2
2 Field work 8
3 Laboratory Tests 9
4 Data Processing & Final Geotechnical Reporting 3
Total Time (Day) 22