Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
the Operation of
the Grid System
Agenda Friday, 14.08.09
1) Brief introduction of the particular dispute on which expert opinion is required and both
parties’ positions on the dispute.
2) Expert’s presentation on the operation of the Grid System in Malaysia;
a) Governance of the Grid System;
b) Operational Envelope of the Grid System in Malaysia;
c) Operation of the Grid System in Malaysia;
• Operational Planning Process;
• Real Time Operation;
• Any distinction between TNB and IPP plants
d) Management of system demand and generation balancing process;
e) Instances where demand shedding will be undertaken by the GSO;
f) Situations in which brownouts, blackouts and supply interruptions can occur;
g) Comparison of operation of the Grid System in Malaysia by the GSO and NLDC vis‐à‐vis
international utility practices (comparison with other island Grid Systems);
h) Application of GSO and NLDC processes and standards to generation plant (TNB or IPP owned).
i) Extent of impact on the Grid System by a generating plant’s failure to comply with a dispatch
instruction;
3) Discussion on the draft outline of the Expert Report
a) The substantive issues to be dealt with in the Expert Report
b) Approach as regards experts’ comments on witness statements and how this is dealt with in the
Expert Report;
4) Administrative Matters
a) Current Progress of work done by expert to date.
b) Duration of presence in Malaysia for preparation of Expert Report.
c) Timelines for drafts submitted for discussion.
d) Expert costs estimates.
e) Briefing on arbitration procedure and procedure during hearing in November.
f) Duration of presence in Malaysia and personnel;
Operational Planning Process
Power System Operation
Grid System
Power Operational
Real Time
System Control &
Planning
Operation Operation
1) Generation dispatch;
2) Implement scheduled outages and issuing PTW;
3) Perform switching actions as required, e.g.,
breaker operations, load transfer, load-shedding
etc.
4) Network monitoring;
5) Real Time Contingency Assessments (RTCA);
6) Redispatching;
7) Restoration;
Daily Operational Planning Process
INPUTS Production
cost studies, Coordination
OUTPUTS
System Of System
Operation Commissioning
Daily studies Output Documents:
Generating 1. Generation
Units Outage Schedule &
Schedule Outage
PROCESSES
2. Transmission
Outage &
Demand A day ahead Unit Commissioning
Forecast and Daily Security 3. System Security
Commitment
Availability Assessment Assessment
schedule
Declarations
For distribution to
Control centre,
Generators,
EGAT Daily Interconnection
Availability (EGAT)
Declaration
Daily Daily
Docket Transmission
meeting Outage
INPUTS
Generation Dispatch Process
NOT OK
OK GSO CHECK REDISPATCH (ANOTHER
DELIVERY TIME/DISPATCH GENERATOR)
PARAMETERS
RECORD
INFORMATION
RECORD
REDISPATCH
INFORMATION
SETTLEMENT
INFORMATION FOR
SINGLE BUYER
SETTLEMENT
INFORMATION FOR
SINGLE BUYER
Fundamental Dynamic
Responses
Power Transfer in AC System
4) Increase in power 300MW
transfer will increase Impedance X
the angles;
5) There is limit to the
increase in angle Vg g
such that the system Vr r
will become
unstable;
6) The dynamic g r
analysis looking at
movement of the
rotor angle is also Reference Reference
called ‘rotor angle
stability’; Power transfer, P =
Vg x Vr x sin(r - g)
X
Power Transfer in AC System
1) In DC system, 400MW
power transfer is Impedance X
determined by the
difference in voltage
magnitude between
Vg g
two points; Vr r
2) In AC system, power
transfer is
determined mainly g r
by the voltage angle
differences between
two points; Reference Reference
3) At generation bus,
the voltage angle is Vg x Vr x sin(r - g)
Power transfer, P =
controlled by the X
rotor angle of the
alternator
Generators
Dynamic Perspective
Step-up Transformer
Fluid in
Auxiliary
Equipment
Pref Unit Tx
Pe
Measurement Alternator,
Valves Governor f Devices Vt
e.g. rated
It at 375MVA
& reactive
Stator/Armature capability
Rotor
Turbine
Pmech Vref
P M = PE
d2
P M – PE = J EF
Air gap
dt2 D
Fluid-out
Generator Dynamics
Turbine Power
scheduled to dispatch
at 250MW; 0.95 pf
• Generators with
headroom (spinning
reserve) will open
its fuel valve to
produce more
mechanical power Turbine power
to exert forces to increases to
bring speed to
bring all generators normal
to the same
speed/frequency;
Dynamic Behaviour
System Fault – Generator responses
1) A short-circuit in the
system will
instantaneously
Active
result in terminal Power
voltage drop and a
sudden reduction of
active power output Terminal
Voltage
and increase of
reactive power and
the excitation Field
controller reacts Voltage
quickly to increase
Reactive
field voltage; Power
06 10 14 18 22 02 06
Dynamic Behaviour
Insufficient Spinning Reserve
• Frequency will
decline beyond
With Underfrequency
Load-shedding
generator limits
unless load-
shedding is
applied
Without
Underfrequency
Load-shedding
Dynamic Behaviour
Frequency – Loss of 140MW Generation, Adequate Spinning Reserve
Frequency, Hz
140MW
Generation
Trip
Dynamic Behaviour
Frequency – Loss of 250MW Generation , Adequate Spinning Reserve
Frequency, Hz
250MW
Generation
Trip
Dynamic Behaviour
Frequency – Loss of 320MW Generation , Adequate Spinning Reserve
Frequency, Hz
320MW
Generation
Trip
Dynamic Behaviour
Frequency – Loss of 650MW Generation , Adequate Spinning Reserve
Frequency, Hz
650MW
Generation
Trip
49.3Hz
Dynamic Behaviour
Frequency – Loss of 1250MW Generation , Adequate Spinning Reserve
• Underfrequency
load shedding
Frequency, Hz
(UFLS) disabled
1200MW
Generation
Trip
Frequency
dive
Dynamic Behaviour
Frequency – Loss of 650MW Generation , Adequate Spinning Reserve
• With
underfrequency
Frequency, Hz
load shedding
(UFLS) applied
49.3Hz
UFLS not required
Dynamic Behaviour
Frequency – Loss of 650MW Generation ,
Inadequate Spinning Reserve
• With
underfrequency
Frequency, Hz
load shedding
(UFLS) applied
49.3Hz
5% load
shed
Dynamic Behaviour
Frequency – Loss of 1250MW Generation , Adequate Spinning Reserve
• With
underfrequency
Frequency, Hz
load shedding
(UFLS) applied
49.3Hz
First 5%
Load shed
Frequency recovery
Second 8%
Load shed