Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
- Onshore
Rivision History
TABLE OF CONTENTS
1. INTRODUCTION........................................................................................................................ 5
2. OBJECTIVE ............................................................................................................................... 5
3. AREA OF APPLICATION.......................................................................................................... 5
4. REFERENCES ........................................................................................................................... 5
6. RESPONSIBILITIES .................................................................................................................. 7
ATTACHMENTS................................................................................................................................ 27
1. INTRODUCTION
Mellitah Oil & Gas B.V. has the responsibility to secure the environment, health and safety of
its employees including seconded staff and contractors. Each year, scheduled shutdown
takes place in Mellitah Oil & Gas onshore Plants.
This document shall establish the HSE guideline for the yearly shutdown activities in order to
provide a reference for any similar shutdown and it does not override any mentioned
procedures such as: Permit to Work Procedure, Emergency Response Plans, etc.
Organizations and system preparedness can be benefit/ success for implementing the
relevant procedures prior or in the beginning of planned Shutdown activities, that shall gives
suitable period to measure/assess for achieving HSEQ objectives.
2. OBJECTIVE
The main objective of this document is to provide a simplified procedure to be used before,
during and after any shutdown operations. To determine the responsibility of persons from
different level (Manager, SPT, Coordinator, supervisor, individual, etc…) to successfully
achieve the SD planned activities with safety in mind, in order to meet the required
performance and compliance in accordance to the schedule target and implementation of
necessary measures to meet compliance with codes, standards, Company specification and
industrial safe practices.
3. AREA OF APPLICATION
These Corporate Guidelines for HSE Requirements during Yearly Scheduled Shutdown
areapplicable to all Mellitah Oil and Gas onshore facilities.
4. REFERENCES
MOG-HSEQ-SF-WI-
[Rif.A3] Confined Space Entry Mellitah Complex
058
MOG-HSEQ-SF-WI-
[Rif.A4] Confined Space Entry Wafa Field
062
MOG-HSEQ-SF-WI-
[Rif.A11] Work Instruction for Preparing Risk Assessment
057
BA Breathing Apparatus
SD Shut-Down
SPT Superintendent
6. RESPONSIBILITIES
Field/complex manager or his delegate will control the overall job with coordination with
HSEQ and Maintenance departments.
He is responsible for monitoring the issued PTW, implementing the required measure/s of
control to ensure safe system of work for various shutdown activities include:
Provide of expert technical safety advice to the operations and
maintenance/contractor, particularly when the risk is judged high or medium.
Provide resources and HSE personnel to control/monitor safety requirements and
permit compliance.
Approve, monitor and cancellation of Hot and Cold Permits to Work.
Ensuring that all safety measures/mitigation stated on the permit and its supported
document are implemented.
Attend Daily Shutdown Meeting
Production SPT
Maintenance SPT
To coordinate with the Production SPT or his delegate and HSE coordinator or his delegate
in order to ensure compliance with HSEQ Requirements and :
the provision of safety related documents, such as risk assessment, procedures, etc...
all members (supervisors, work force) have full knowledge of the restriction, and
associated hazards include their individual responsibility.
Applying PTW for planned activities.
Personnel competency to perform the work include their HSE training needed.
Attending Daily Shutdown Meeting.
Area Operators
Instruct the work forces under his authority of the safety measures, mitigation,
the associated hazards and permit requirements.
Reporting any changes in work content or environmental conditions to the Area
Authority and ensuring that safe conditions for work are re-established.
That housekeeping is maintained so that areas are orderly clean and tidy at all
the time.
Ensuring that the Permit is revalidated if work is to continue longer than for one
shift.
On completion of the work, the work site is left in a safe and tidy condition, all
tools and equipments are withdrawn, barriers and grating replaced.
Work forces are made fully aware of the hazards associated with the task for
which a "Permit to Work" is issued and of the Safety precautions to be taken.
Adequate PPE and appropriate safe equipment is provided.
Conduct Toolbox Talk as well review JRA.
Note1: Enforce all HSE rules and regulations evenly and consistently whenever
and wherever violations or non-compliance are observed.
Note2: Compliance and execution are still in the hands of the Supervisors, work force
performing task and those individual roles/responsibilities to ensure the compliance and
implementation of all the requirements/safety measures.
The key objective in developing an adequate working plan and its relevant documentation is
to establish the necessary requirements of each sequential activity that will be undertaken
during initial or major shutdown within Mellitah Oil & Gas Onshore facilities. It’s helpful to
govern the various activities within geographical areas and time, by:
It is essential that the work plan be placed into operation without confusion, to fully utilise the
knowledge, skills, experience, include coordination, communication (including stakeholders)
and capabilities of the entire organization.
Adequate engineering and safety documentation is required to the success of achieving the
target and safety preparedness; depending on the various activities nature, type and
complexity, taking in consideration the relevant document adequacy and quality. This will
include but not limited to:
Note: Safety interface documents shall be produced where relevant to demonstrate how
these safety requirements are met, e.g. between:
Train 1 and Train 2 or between modification/construction activities and storage facility
8. WORKSITE PREPARATION
Depending on the nature, type or complexity of the job requires PTW. Once the hazards
associated with a particular job have been identified, it will be necessary to consider how
they can be captured, separated, isolated from the process lines, equipment or plant to be
worked on. Flammable, toxic, pressurised, high temperature, or low temperature fluids must
be removed, including the electrical sources.
An essential ingredient of any safe system of work is the integrity of the isolation procedure
and the required supported specific plan. Whilst the Work Permit identifies the isolation
requirement it does not provide the specific isolation details. These are to be
formal/documented and attached to the permit as per Mellitah Oil & Gas Isolation and re-
instatement work instruction or procedures. Ensure that appropriate precautions,
safeguards, and control measures are fully implemented so that work can proceed and
completed safely.
Documentation of Isolation
There must be a clear description of the isolation plan and marked-up P&ID, including a
detailed list tracking all items and method (e.g. Valves, spades, blinds, pipe/piece of pipe
disconnection, blank flanges, vent and drain opened, breakers rack out, etc) utilised in the
isolation. The isolation plan together with any other supported document such as P&ID and
register must be kept in the Permit Control Office (PCO).
Log register should be maintained and updated for all electrical isolation/de-isolation.
Any changes to the Isolation plan or isolation boundaries shall be approved/initialled by the
Maintenance and Production superintendents. This should be done before any physical
changes at site.
The effectiveness of the risk assessment process depends largely on competency, skills and
experience of the persons. Those persons that have the capability to utilise techniques and
required methods in order to identify, evaluate/analyse the risks of the overall
activities/operation will be undertaken prior, during and after shutdown. Depend on the
nature and the complexity of various activities, using as support the necessary study such as
HAZOP, QRA, etc, and that in early time of the scheduled shutdown to promote an adequate
Safety preparedness system and readiness in order to identify the necessary safeguards,
precautions, specific procedure , training needed and their implementation in the real time.
Refer to : MOG-HSEQ-IN-P-099.
The initial JRA should be undertaken before the origination of the Work Permit, and any
supporting permits or certificates. Whenever work has to be undertaken by Company, Third
party or contractors on Mellitah Oil & Gas facilities, it is necessary to perform a JRA.
Risk Assessment Matrix (RAM) is used as tool that provides a standard approach to the
qualitative assessment of risk. All activities, which fall in the High, Medium-High sector or
level, require documented evidence (MOG-HSEQ-F-115) in objective to:
It is essential that Production Supervisor take a lead roll in the risk assessment process, the
HSEQ team will assist in this event. This will ensure continuity over 24 hrs operation with the
risk assessment being discussed during each shift hand over.
Following preparation of the plant and equipment and prior to the task commencing, the
work site should be inspected by the relevant Production Supervision to ensure that all
aspects of the work have been considered and that the site, plant and equipment are in a fit
state for the work to proceed.
Note: For positive isolation such as spectacle blinds / blanks, the check includes ensuring
that correctly rated gaskets are in place and the flanged studs and bolts have been
tensioned correctly. Isolation integrity checks must also include a check on the use of
secondary isolation where appropriate by ensuring that they are properly engineered and
installed correctly.
The Gas testing and monitoring is a crucial element. Therefore, the following should be
considered:
Note: Initial gas testing of the internal atmosphere must be carried out from the outside of
the confined space at different level, If the gas tester is required to enter the confined space
to make further tests such as large vessel or storage tank, breathing apparatus, harness and
safety line must be worn. Further safety attendant must be present.
A suitable trained fire-watcher will be nominated for the task and fully briefed during the Tool
Box Talks (TBT) conducted by operations person in charge or by safety specialist, who will
address responsibilities, procedures and hazards associated with the work , especially in
case of Hot Work activities.
FIRE WATCHER
The trained fire watcher must be fully aware of his duties and responsibility assigned for:
Use the protection equipment on site (fire extinguishers, charged hoses, etc..
Raise the alarm in the event of fire or problem inside a vessel or tank.
Use the available means of communication.
12. EQUIPMENT
All equipment to be used for the work must be suitable and in a good condition. Welding
equipment must be sited securely, adjacent to the work area and safely positioned. Effective
earthing arrangements should be in place. Gas cylinders must be secured in position (up-
right) and have isolation keys in place with the associated hoses depressurised during work
stoppages.
It is essential that there is no conflicting work in adjacent areas. This is of course a prime
consideration in PTW preparation and issue. It is also important to consider the area or unit
above and below the work site. This is especially important on lower levels, where falling
sparks, slag or even hydrocarbon fluid could drop and accumulate. The effects of air
movement / wind direction within open units or outside decks / walkways should be
considered.
Suitable access to and egress from the work site must be available all times. Where
temporary access / egress is provided , such as scaffolding , it will be constructed , certified
and used in line with approved company procedures.
TBT or Work site briefing play a vital part in communicating responsibilities, procedures to
be followed and any hazards associated with the undertaking task. The work team leader
(foreman) will conduct a pre-job safety briefing prior to work commencing and to be
delivered to personnel involved with the work in hand.
Work permits can be prepared in advance but will not be issued to the site
performing Supervisor until the job site (where the task will be performed) has been
visited and assessed shortly before work is to start.
The site operating authority must be assured that the site performing Supervisor
understands the conditions / limitations laid down in the permit
It is important to make sure that one activity under a permit to work does not create
danger for another. Cross-referenced permits should be jointly authorized.
All personnel involved with the authorization of the permit or doing the work must be
alert to the possible changes in conditions and if they occur, shut down the operation.
Work will only be resumed when safe conditions have been re-established and the
original permit reactivated or possibly a new one issued.
When work is completed the site must be left in a safe and tidy condition. This needs
to beverified by the Operating authority.
Under No circumstances will the same person sign any PTW as Area Authority and
Task Supervisor (site performing authority).
Simultaneous work and PTW limitation must be consider
Conditions must becontinuouslymonitored
The Area or Equipment affected by the work is clearly defined and prominently
marked by advance visual displays and barriers as necessary to warn of associated
hazards and restrictions.
Personnel are fully notified of the controlled operations planned and the associated
restrictions resulting from such operations.
Personnel are fully apprised of their responsibility and authority when under the
control of a PTW.
During the execution of the shutdown, the following must be respected in order to carry out
the activities according to the prescribed local legislation as well as the current procedures:
Review shutdown documentation
Coordinate plant shutdown as per procedures (Shutdown philosophy procedure)
Track plant shutdown progress.
Coordinate execution of critical function test during shut down phase
Coordinate equipment preparation
Perrform safety audits during shutdown work
Record/report HSE non conformance
Communicate as and when required
Monitor shutdown work against critical path
Monitor resource usage and take appropriate action
Identify barriers to achieving shutdown critical path and negotiate solution.
Below is the execution of the activities following the pre-work site preparation and checks,
the documentation is completed and signed, an initial gas testing is carried out, then the
planned activity can proceed (for example hot work (HW) / CSE):
Whenever hot works are to be carried out, it is necessary to follow strict procedures.
Arc and acetylene welding or cutting equipment must be inspected for
any defect before transferring to operation site.
Work can not proceed before the on site safety specialist accomplish
his inspection, gas testing and PTW final on site review.
All welding equipment must be equipped with 9 kg powder type fire
extinguishers , more fire extinguishers and fire watchers will posted
around operation location by the on site safety specialist.
Shielding will be used to prevent welding sparks and heat from igniting
flammable / combustible materials.
When welding or cutting near flammable / combustible materials, be
sure to check for smoldering fire after the work is completed. Always
use water to wet the material before and after the work, a water circle of
3 to 5 meter will be made under the targeted part of plant / equipment,
to prevent any event had the potential to cause a fire / explosion.
Remove all rubbish and scrap from the site at the end of each worked
operation, empty rubbish and trash bins at the end of each work day.
Before beginning crane operations, the following instructions must be taken into
consideration:
LIFTING:
The working radius of each crane will be roped off and warning signs erected on
all four sides.
The crane operator will not leave the crane until the lift is completed or returned
to ground.
When the crane is not in operation, the operator will secure the hook and switch
off the engine.
A load chart and radius of lift chart will be displayed in the operator cab.
Each crane will display a valid inspection and load test sticker on the operator
cab.
Before each crane operation, pre lift planning and safety meeting will be held on
location.
Before commencing any lifting operation, all the necessary valid certifications for
both the machine and the operator should be inspected by onsite operations
person in charge and company safety specialist for more detialis, refer to
document MOG-HSEQ-Q-P-248 Corporate safe lifiting Operations.
Following the initial pre-start gas tests, the HW / CSE site will be subjected to continuous
gas monitoring and only qualified person (safety specialist) should conduct this task.
Monitoring of the work site will be conducted by using a suitable automatic multi gas
detector.
RIGGING
The following safety instructions are to be taken into consideration when carrying out rigging
activities:
All rigging work should be done by qualified riggers.
Standard crane hand signs will be used, only signal man will give signals to the
operator.
Wire ropes, slings and web slings will be checked before work starting for frayed
ropes and slings, excessive rust or rot, kinks or bleeding from over stressing.
Ropes and slings with defects will be removed from service. Ropes and slings
will be tagged or colour coded to show inspection date.
Crane lift loads will not exceed 80 % of the crane and rigging rated load capacity.
All loads must be rigged properly; a minimum of two slings will be used. Sling
angles will never exceed than 60 degrees.
A minimum of two guide lines will be used for each lift.
Standard hand signals will be used for crane operations, our mega-phone unit may also be
used .Only vertical lifts will be made, loads will not be dragged or pulled.
The yearly shutdown is containing some risky jobs which have potential harm to persons,
asset, and environment. It requires the use of Competency, skill and experience in capturing
those risks and to set method/techniques in providing the necessary elements and special
measures/mitigation and control to complete the job safely.
Before entering confined space, the following arrangements should be taken into
consideration:
When working at heights, safety belt / harness must be checked for defects or
damage and must be used.
Life line is to be used if secured place to attach safety belt or harness can not be
found. (Remember… safety belt/harness is only as strong as the point where it is
attached).
The top of an erected ladder will extend at least 60 cm above the landing. The
ladder will be properly secured to the landing to prevent falling or slipping.
Where erected handrails, toe boards, safety nets, platforms or scaffolds are to be
removed immediately after performing the work.
Personal Protective Equipment (PPE) must be worn as required for each type of jobs within
shutdown activities as per the conducted JRA where a potential exposure to hazardous
conditions is. Hard hats, safety goggles and safety foot wear as a minimum is mandatory
when working on the site. Other PPE such as eye, face, hand, and body and ear protection
are necessary when required.
Fall restraining / arresting devices; the two commonly used ones are the full body harness
and the safety belt; harness is used for above ground work, where restraining and arresting
protection is required, safety belts are used to restrain the wearer at his place of work on
horizontal surfaces. Full body harnesses are required when working in areas with no guard
rails at heights above 1.8 meter. Fall restraining devices must be stored in clean and dry
conditions away from sun radiation and must be thoroughly inspected both on issue and at
the start of each shift.
Supervisors shall ensure that the workforces under their direct authority understand what to
do if an emergency situation arise, that will be briefed in Tool Box Talk, e.g. determine
escape route of working place area taking in consideration the wind direction and
safest/nearest assembly point.
It is essential that 'active monitoring' of work site is undertaken by the appropriate level of
supervision, namely:
Work leader
Nominated area supervisor
Production shift supervisor
The on site safety specialist.
Such monitoring is conducted to ensure that: the work is being carried out safely, the
appropriate personnel are involved, the work place circumstances have not changed and
that the stipulated conditions on the PTW are being adhered to.
Spillages may occur during the shutdown at the waste water treatment (WWT) during
dealing with knock out drums and no oil spillage is expected during working on gas trains. It
is accepted policy that whenever such a spill occurs, immediate action should be taken to
prevent further spillage, to prevent fire and to implement cleans-up operations.
Spills on land are the simplest to handle. They normally require collection and transfer of the
oil by means of removing the oil spillage that accumulated on ground by applying dry soil
/sand to absorb the oil and then transfer the oily sand to approved dumping area.
The oil that accumulated on the oily water surface in the evaporation pond needs to be
collected by a special tool, like a fishing net made from wire mesh material) and then the
collected oil will be put into open empty container of appropriate size to be recycled again in
the system.
“Where there is a need to empty and refill the molecular sieves, an appropriate container will
be put on truck under the knock out drums at gas trains to collect all the used molecular
sieves and then transferred and stored on cement slabs available for some time for drying
these materials”.
The following table shows the HSE team needed for the yearly shutdown on day and night
shifts:
The following table contains the materials needed for the shutdown:
1 Ambulance Stand-by
5 MSA gas detectors Multi gas detectors to test / monitor
gas condition before, during and after
hot works/CSE activities.
5 Intrinsically safe To be used during inspecting confined
torches spaces
20- to 40 pcs its Pad-locks To lock-out the identified isolated
depend on each site valves
20 pcs to 40 pcs Small size metal chain To lock-out the identified isolated
(1 meter each depend valves
on each site )
20 to 40 pcs Tag-out labels For valves not to be open
3 – 5 rolls Safety tapes To isolate work sites
1 roll Nylon rope (life line) To be used for rescue purposes
of 1.5 inches diameter
size
2 Megaphone with siren For rescue purposes
10 Full body harnesses For inspector , maintenance crew and
stand-by rescue team
4 sets Breathing apparatus For stand-by rescue team
sets BA
From 10 to 20 pcs Disposable coveralls For inspecting / cleaning inside
confined spaces
30 – 50 pcs Scaffolding green tags To confirm safety inspection
30-50 pcs Scaffolding red tags For stop working
25-50 pcs Gas mask (MSA- For rescue purposes
smoke hood)
4 Clear safety glasses For shutdown personnel during
(for day shift) inspecting confined space inspection
20-50 pcs Dark safety glasses For shutdown staff
It is important to realize that all activities in a complete and accurate way to make sure all
issues have been resolved and closed out with no significant errors or consequences. The
following have to be verified:
Confirm that all scheduled work on equipment is complete before hand back is
accepted
Ensure equipment hand back documentation complete per site protocol
Coordinate pre-start equipment integrity checks
Coordinate and validate plant de-isolation and preparation for service
Ensure appropriate plant start up authority is obtained
Coordinate start up critical function tests as required
Coordinate and record plant start up progress
Ensure that all generated waste is removed and disposed as per MOG procedures
for contractors and suppliers/Waste Management Procedure/Site handling and
disposal of waste procedure.
ATTACHMENTS