PLANTILLA AYUDA PARA LA PRESENTACION DE INFORMES

MENSUALES DEL ING. SUPERVISOR E INSPECTOR DE OBRA.

Carátula
I. Resumen del trabajo efectuado en el período cubierto por el informe y de las
principales incidencias ocurridas
II. Índice

III. Ficha técnica de obra

A N EX O N º 18

F IC HA T EC N IC A - A D M IN IST R A T IV A D E OB R A

OB R A :

SN IP:

LOC A LID A D D IST R IT O PR OV IN C IA U B IGEO M OD A LID A D D E EJEC U C ION EST A D O SIT U A C ION A L D E LA OB R A

D A T OS D E PR ESU PU EST O

PR ESU PU EST O C A D EN A F U N C ION A L


AÑO F T E.F T O. M N EM ON IC O PIA PIM M ET A PR ESU PU EST O 2 0 1……
SN IP PR OGR A M A T IC A

E.G. PIM

D A T OS D EL EX PED IEN T E T EC N IC O

PR ESU PU EST O Nº DE
F EC HA EN T ID A D C ON T R A T A N T E PR OY EC T IST A / EV A LU A D OR C OLEGIA T U R A T ELEF ON O D OM IC ILIO / EM A IL
A PR OB A D O R ESOL.
T o t al

D A T OS D EL EJEC U T OR

M ON T O D E PLA Z O N º D E C ON T R A T O F EC HA F IR M A EJEC U T OR / R ESID EN T E D E


C OLEGIA T U R A T ELEF ON O D OM IC ILIO / EM A IL PR ESU PU EST O 2 0 1……
C ON T R A T O SU PER V . D E OB R A C ON T R A T . OB R A

E.G. PIM

PLA Z O D E EJEC U C ION D E LA OB R A


F EC HA D E
F EC HA D E D ESIGN A C ION F EC HA D E A C T A F EC HA D E IN IC IO D E T o t al
EN T R EGA D E PLA Z O D E F EC HA D E T ER M IN O
D E SU PER V ISOR / EN T R EGA D E PLA Z O D E
EX PED IEN T E EJEC U C ION D E OB R A
IN SPEC T OR T ER R EN O EJEC U C ION
T EC N IC O

1 2 3 4 5 6
PLAZO DE OBRA
AMPLACION DE

RDS Nº RDS Nº RDS Nº RDS Nº RDS Nº

F echa F echa F echa F echa F echa

Est ad o Est ad o Est ad o Est ad o Est ad o

D ias D ias D ias D ias D ias

N U EV A F EC HA D E T ER M IN O
C ON T R A C T U A L D E OB R A

D A T OS D EL SU PER V ISOR O IN SPEC T OR D E OB R A

PA GOS SU PER V ISOR


F EC HA
F EC HA
PR OC ESO D E DE N º D E C ON T R A T O F EC HA F IR M A
SU PER V ISOR O IN SPEC T OR C OLEGIA T U R A T ELEF ON O D OM IC ILIO / EM A IL
SELEC C IÓN B U EN A D E SU PER V ISION C ON T R A T .
1
PR O
2

T OT A L

IV. Información general del Proyecto

4.1 Datos Generales de la Obra


Nombre de la Obra:
Código SNIP:
Función:
Programa:
Sub Programa:
Responsabilidad Funcional:
Unidad Ejecutora:
Fuente de Financiamiento:
Costo de Obra:
Modalidad de Ejecución:
Inspector o Supervisor:
Residente de Obra:
Plazo de Ejecución:
Fecha de Entrega de Terreno:
Fecha de Acta de Inicio:
Fecha de Inicio de Ejecución de Obra:
Fecha de Término de Ejecución Prevista:
Ampliaciones de Plazo:
Nueva Fecha de Término de Obra:
Fecha de Término real:
Adicionales de Obra:
Reducción de Obra:
Avance Físico Programado Mensual en Porcentaje:
Avance Físico Programado Acumulado en Porcentaje:
Avance Físico Ejecutado Mensual en Porcentaje:
Avance Físico Ejecutado Acumulado en Porcentaje:
Situación de la Obra:
Avance Financiero Ejecutado Mensual en Porcentaje:
Avance Financiero Ejecutado Acumulado en Porcentaje:
4.2 Antecedentes
4.3 Objetivos de la Obra
Señalar Objetivos Generales y Específicos
4.4 Ubicación Geográfica de la Obra
4.5 Fisiografía y Climatología
4.6 Recurso Agua y Suelo
4.7 Inventario de Infraestructura Hidráulica Existente
4.8 Organización de los Usuarios del Agua
4.9 Población Beneficiaria
4.10 Vías de Acceso a la Obra
4.11 Área a Irrigar con el Presente Proyecto
4.12 Metas Programadas para su Ejecución en el Expediente Técnico de la Obra

V ASPECTO TECNICO
5.1 Valorización de obra

5.2 Hoja resumen de valorización

5.3 Verificación de la planilla de metrados con los respectivos gráficos, hoja de cálculo
y/o croquis explicativos que el caso requiera.

La verificación de la plantilla de metrados debe realizarse en base a gráficos como se


muestra en el siguiente ejemplo:
5.4 Gráfico del avance programado versus avance ejecutado, explicando las causas que
hayan motivado atrasos, si los hubiera, e informando las disposiciones tomadas para
superarlos
CURVA

AVANCE PROGRAMADO VS. AVANCE REAL

100% 98.55%

92.76%
90% 87.06%
83.82% 90.11%
88.93%
80%
AVANCE ACUMULADO PROYECTADO 75.99% 80.24%
AVANCE MENSUAL ACUMULADO (%)

70%
61.85%
AVANCE ACUMULADO REAL 68.28%
60%
50.46%
50% 55.68%
45.67%
41.79% 41.79%
38.30%
40%

34.92%
30%
20.52%
26.63%
20% 21.99%
21.99%
19.61%
5.12%
10%
0.00% 10.16%
0.58%

0% 0.00% 0.10% 3.07%


INICIO nov-2014 dic-2014 ene-2015 feb-2015 mar- abr-2015 may- jun-2015 jul-2015 ago-2015 sep-2015 oct-2015 nov-2015 dic-2015
2015 2015

PLAZO DE EJECUCION

CUADRO RESUMEN DEL DE AVANCE PROGRAMADO Y EJECUTADO

AVANCES PROGRAMADOS PARCIALES Y ACUMULADOS AVANCES PARCIALES Y ACUMULADOS VALORIZADOS

MONTOS PROGRAMADOS S/. PORCENTAJES MONTOS VALORIZADOS S/. PORCENTAJES


MES MES
PARCIAL S/. ACUMULADO S/. PARCIAL % ACUMULADO % PARCIAL S/. ACUMULADO S/. PARCIAL % ACUMULADO %

INICIO - 0.00 0.00% 0.00% INICIO 0.00 0.00 0.00% 0.00%


nov-2014 10560.35 10,560.35 0.10% 0.10% nov-2014 62,159.03 62,159.03 0.58% 0.58%
dic-2014 316680.40 327,240.75 2.97% 3.07% dic-2014 483,395.89 545,554.91 4.54% 5.12%
ene-2015 754875.70 1,082,116.46 7.09% 10.16% ene-2015 1,639,382.17 2,184,937.08 15.39% 20.52%
feb-2015 1006611.84 2,088,728.30 9.45% 19.61% feb-2015 1,893,830.84 4,078,767.91 17.78% 38.30%
mar-2015 253427.46 2,342,155.75 2.38% 21.99% mar-2015 371,533.28 4,450,301.20 3.49% 41.79%
abr-2015 2,342,155.75 0.00% 21.99% abr-2015 0.00 4,450,301.20 0.00% 41.79%
may-2015 493975.98 2,836,131.73 4.64% 26.63% may-2015 413,977.21 4,864,278.40 3.89% 45.67%
jun-2015 882980.00 3,719,111.74 8.29% 34.92% jun-2015 510,137.18 5,374,415.58 4.79% 50.46%
jul-2015 2211168.33 5,930,280.07 20.76% 55.68% jul-2015 1,212,607.25 6,587,022.83 11.39% 61.85%
ago-2015 1341100.87 7,271,380.94 12.59% 68.28% ago-2015 1,506,251.21 8,093,274.04 14.14% 75.99%
sep-2015 1274230.29 8545611.23 11.96% 80.24% sep-2015 833,516.87 8,926,790.91 7.83% 83.82%
oct-2015 726514.59 9272125.83 6.82% 87.06% oct-2015 543,840.51 9,470,631.42 5.11% 88.93%
nov-2015 324825.70 9596951.53 3.05% 90.11% nov-2015 408,665.03 9,879,296.46 3.84% 92.76%
dic-2015 1052983.74 10649935.23 9.89% 100.00% dic-2015 616,175.18 10,495,471.64 5.79% 98.55%
TOTAL 10,649,935.23 100.00% TOTAL 9,879,296.46 98.55%

5.5 Condiciones meteorológicas en el área del proyecto y otros factores que puedan
afectar el desarrollo normal de la obra
La justificación de las condiciones meteorológicas en contra de las actividades en obra
debe ser justificada con asientos en cuaderno de obra, fotografías y otros documentos
válidos (registro de estaciones meteorológicas) si fuera necesario.

5.6 Aspectos críticos, problemas encontrados, acciones correctivas propuestas para


incrementar el ritmo de la obra si fuera necesario, comentarios relevantes
El Supervisor debe informar respecto a los siguientes aspectos:
 Desabastecimiento de materiales
 Desabastecimiento de mano de obra no calificada en obra
 Interrupción de vías de accesos a la obra
 "caso fortuito" a lo que acontece inesperadamente, o sea a lo "imprevisible";
la fuerza mayor alude a lo irresistible, es decir lo "inevitable".
 Ausencia del Residente en Obra
 Rendimiento muy bajo de los trabajadores
 Oposición de Beneficiarios a la ejecución de la obra
 Mala calidad de materiales de construcción
 Mala calidad de obra
 Etc, Etc

5.7 Resultados de la inspección y control de calidad del trabajo realizado por el ejecutor,
presentando la documentación por el cual se certifique que los materiales utilizados
en la obra cumplen con las especificaciones técnicas del proyecto.

La inspección y control de calidad de trabajo realizado por el supervisor e


inspector de obra debe ser en los siguientes aspectos:

CALIDAD DE OBRA
- Verificar el trazo de la obra, control de niveles, secciones, etc, etc.
- Que se ejecute los trabajos de acuerdo a las indicaciones de las
Especificaciones Técnicas.
- Verificar los rendimientos de mano de obra y de equipos
- Que se respeten la dosificación en la preparación de los concretos de
acuerdo a lo indicado en el Expediente Técnico de la Obra.
- En relación a los encofrados, verificar: calidad de la madera, espesor de la
madera, diseño de encofrado, tolerancias, etc.
- En lo que respecto a las instalaciones en general verificar que los diseños,
los diámetros materiales utilizados, sean los indicados en los planos
constructivos y en las especificaciones técnicas del expediente tecnico.
- Cuando en el expediente ni en los planos se indique la calidad de los
materiales, el Supervisor o Residente deberá solicitar que estos sean de
primera y de marca reconocida.
- La realización de pruebas (protocolos de prueba hidráulica, ensayos de
rotura de briquetas de concreto, etc, etc) solicitadas en el expediente
técnico para constatar que se han cumplido los requerimientos y exigencias
de los trabajos.
- En general todas las actividades técnicas necesarias para que las partidas
se ejecuten de acuerdo a las especificaciones y normas de la buena
ingeniería.

CALIDAD DE LOS MATERIALES

- Que los materiales utilizados en la obra cumplan con los requerimientos de


las especificaciones técnicas.
- La realización de ensayos solicitados en el expediente técnico para
constatar la calidad de los materiales.
- El correcto almacenamiento y traslado, de acuerdo con las especificaciones
del material.

CONTROL DE EJECUCION DE PARTIDAS


EJEMPLO:
ACERO DE REFUERZO
- Verificar que los tipos de armaduras estén de acuerdo a los diagramas y
cantidades del expediente técnico.
- Recabar los certificados de calidad del acero y accesorios a emplearse de
sus fabricantes.
- Controlar la colocación y amarre de las armaduras cuidando que los
empalmes estén de acuerdo a los diseños.