Sei sulla pagina 1di 10

Renewable Energy 117 (2018) 404e413

Contents lists available at ScienceDirect

Renewable Energy
journal homepage: www.elsevier.com/locate/renene

Optimal design of water supply networks using an energy recovery


approach
Gustavo Meirelles Lima*, Bruno Melo Brentan, Edevar Luvizotto Jr.
Laboratory of Computational Hydraulics, School of Civil Engineering, Architecture and Urban Planning, University of Campinas, Av. Albert Einstein, 951,
ria, Campinas, Brazil
Cidade Universita

a r t i c l e i n f o a b s t r a c t

Article history: Water Distribution Networks (WDNs) represent a major investment for water supply systems devel-
Received 13 May 2017 opment. The standard procedure for their design is to search for the minimum cost, which is produced by
Received in revised form the smaller diameters capable of maintaining the minimum required pressure. However, some District
10 October 2017
Metered Areas (DMAs) have a significant topographic elevation difference, and even if the minimum
Accepted 23 October 2017
Available online 27 October 2017
diameters are reached, the pressure remains high, and a Pressure Reducing Valve (PRV) is necessary.
However, if the pipe diameters of the network are increased, distributed headloss will be reduced, and
this additional energy will be locally dissipated in PRVs to maintain the pressure in the DMA below the
Keywords:
Water distribution networks
maximum allowed value. If a turbine is installed instead, the dissipated energy can be used, creating a
Pumps as turbines benefit that can justify the additional investment due to the diameter increment. Therefore, this paper
Energy recovery presents a method for the optimal design of a WDN considering energy recovery. The use of Pumps as
Energy efficiency Turbines (PATs) is considered for energy production. The optimal design is obtained using a two-level
Optimization optimization procedure: the first is used to obtain pipe diameters, and the second is used for PAT se-
lection. Particle Swarm Optimization is used, and two case studies are presented.
© 2017 Elsevier Ltd. All rights reserved.

1. Introduction estimation of the gradient direction, which in some problems, is not


simple and involves simplified numerical treatment. Therefore,
The pipes of water supply networks represent the largest in- meta-heuristic methods have been widely applied as an alternative
vestments for the deployment of these systems. Therefore, their for classical methods. Different techniques have been applied to the
design is made to achieve the minimum costs, which is obtained optimal design problem with good response [2e7]. Due to its un-
using the minimum diameters necessary to maintain the quality restricted characteristic, the restrictions are evaluated separately
standards of pressure and velocity. The calculation of these pa- using penalty functions and are added to the objective function to
rameters in looped networks is performed using a simultaneous be minimized. According to [8], the penalty function can be neither
solution of a system of equations, which are primarily non-linear. too hard, to avoid a wide search across the space, nor too soft,
The deterministic solution is difficult to obtain and usually re- which would lead to unfeasible solutions.
quires the linearization of hydraulic equations, which was virtually Pressure control is another hydraulic problem of water supply
impossible until recent computational advances [1]. Nevertheless, networks that uses optimization techniques to improve system
even with the development of software for hydraulic modeling, the efficiency [9,10]. developed methods for determining the optimal
design of water supply networks continued to depend on engi- location and operation of pressure reducing valves (PRVs). Inspired
neer's experience. To avoid this dependence and the uncertainties by the energy recovery obtained in reverse osmosis for seawater
involved in this design process, the hydraulic model was associated desalination [11,12], wastewater treatment [13] and industrial
with optimization techniques to obtain the network design with process [14], several studies showed that PRVs can be replaced for
minimum costs. However, classical techniques usually require the microturbines with this purpose [15e17]. Furthermore, due to the
low power potential observed in these valves, it is recommended to
use pumps as turbines (PATs), which has a low cost and good effi-
ciency [18e20]. The existing potential in water distribution net-
* Corresponding author.
works can contribute significantly to energy production with low
E-mail addresses: limameirelles@gmail.com (G. Meirelles Lima), brunocivil08@
gmail.com (B.M. Brentan), edevar@fec.unicamp.br (E. Luvizotto). environmental impact.

https://doi.org/10.1016/j.renene.2017.10.080
0960-1481/© 2017 Elsevier Ltd. All rights reserved.

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413 405

Based on the information from the Piemonte region - Italy, and


using a geographic information system [21], estimated 1447 energy
potentials in water supply systems, which can produce 14e26 MW
[22]. highlighted Switzerland with 90 micro-hydropower plants of
this type and Morocco, where 8% of hydroelectric energy is ob-
tained in water supply systems. Operation under a dynamic sce-
nario of consumption, with daily and seasonal variations, is the
major challenge for the advancement of this technology, as the
variation of available power produces both electrical and hydraulic
issues [23e26]. highlight the long-term variation in demand, as
population and economic growth leads to an increase in con-
sumption. However, the development of more efficient equipment,
such as dishwashers or washing machines, reduces it. This variation
can affect the PAT operation, reducing the produced energy and
even causing water shortage.
As previously described, the traditional procedure used for
network design searches the minimum diameters possible. This
approach reduces the available energy in the system, as small di-
ameters produce higher headloss. In this scenario, the pressure
becomes more sensitive to consumption variations, which in-
creases the available power amplitude and makes the PAT opera-
Fig. 1. Karman-Knapp circle [32].
tion even more difficult [27,28]. studied the energy recovery in
water mains, where a small addition to the investment of pipes
with larger diameters was significantly surpassed by the increase in (2).
energy production [29]. highlighted that the traditional design,
despite the reduced investment, cannot be assumed to be the best q ¼ atan1 ðx  pÞ (1)
due to the dynamic behavior of a water supply operation during its
life cycle. Therefore [30,31], proposed a multiobjective design,  
taking into account energy consumption, demand variation and h ¼ WH$ q2 þ 1 (2)
pressure deficiency in addition to pipe costs to obtain more realistic
scenarios of network design. where q is the dimensionless flow coefficient, h is the dimension-
Considering the limitations of the traditional procedure for less head coefficient, x is the independent variable for the Suter
water network design and the energy potential that exists in PRVs, plan representation (varying from 0 to 2$p), and WH is the
this paper proposes the network design associated with the energy dimensionless head coefficient in the Suter plan. This procedure
recovery approach. Thus, the optimal design is obtained via the results in dimensionless curves, which are shown in Fig. 2-b. A
minimization of costs to install a micro-hydropower plant, which is power curve (Equation (3)) was adjusted for this new representa-
added to pipe costs while discounting the benefits obtained using tion. Since the specific speed of the machine is likely to be different
energy production during the plant life cycle. The costs of the micro for the 14 available curves, its characteristic curve can be obtained
hydropower plant are calculated according to the available power, via interpolation [35], polymorphism [36] or just adopting the
and the use of PATs is considered for energy recovery. Long-term curve with the nearest specific speed [37], as used in this paper.
forecasting is performed to predict both the demand and energy Therefore, using only the machine Best Efficiency Point (BEP), its
tariff variations through the plant life cycle. To solve the related characteristic curve in the turbine mode can be obtained.
optimization problem, the meta-heuristic technique Particle
Swarm Optimization (PSO) is used. Two case studies of Brazilian h ¼ a$qb (3)
District Metering Areas (DMAs) are presented, and the results ob-
tained using the energy recovery for optimal design are compared where a and b are the power curve adjustment coefficients.
with those obtained using the traditional approach of economical
design. 2. Optimal design

1.1. Pump as turbine modeling 2.1. Long-term forecasting

Hydraulic machines can operate under eight different operation Social, economic and climatic factors can significantly affect the
zones, characterized by head, flow, torque and speed direction. water demand [39]. Considering that the life cycle of a PAT is
Each zone is characterized by the direction of each parameter, as approximately 20 years [40], there is a great period for demand
presented by Ref. [32] in Fig. 1. changes, which can affect energy production, as described by
The mathematical representation of this circle is usually ach- Ref. [26]. To create this dynamic scenario, three demand patterns
ieved by using curves in the Suter plan [33]. To obtain these curves, are necessary: a daily pattern, which represents the demand vari-
as shown in Fig. 2-a, complex and expensive tests are necessary. ations in a 24-h period; a monthly pattern, to evaluate the seasonal
Therefore, in this paper, 14 curves obtained by Ref. [34] are used. behavior of the system; and an annual pattern, to estimate the
These curves are in the specific speed range from 0.46 to 4.94, and increase or decrease of demand on a long-term basis. Fig. 3 shows
according to affinity laws, they can be used for different machines the daily and monthly patterns used in case studies, which were
with the same specific speed. For each available curve, the opera- obtained from real water distribution systems of Brazil. The daily
tion as turbine zone (empty markers in Fig. 2-a) was identified, and pattern in Fig. 3-a shows the typical residential behavior, while the
considering nominal speed, new curves relating the dimensionless monthly pattern in Fig. 3-b presents a reduction in consumption
coefficients of flow, q, and head, h, were obtained via Eqs. (1) and during the winter.

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


406 G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413

Fig. 3. Demand curves: a) Daily pattern; b) Monthly pattern.

Fig. 2. a) Head (WH) and torque (WB) curves in the Suter plan; b) Dimensionless sensitive to climatic changes and can have major variations in short
curves in the turbine mode for different specific speeds [38].
periods, as shown in Fig. 4-b. Between 2010 and 2015, in addition to
the dry season, economic and political issues also affected the
For the annual forecasting, a correlation between water and tariffs [46,47]. examined this dubious scenario, highlighting that
energy consumption was made using the available data for S~ ao the available forecasting methods are used only for a few years
Paulo, from 1995 to 2014, which were obtained from Refs. [41,42]. ahead. Therefore, due to its high volatility, the forecasting of energy
Fig. 4-a shows a moderate correlation between water and energy tariffs is as complex as water demand forecasting. In this way, the
consumption for the period, with a Pearson coefficient of 0.454. average inflation observed in the last 10 years, of 6.92% per year
Considering the high uncertainties in long-term demand fore- [48], was used to readjust energy tariffs in simulations, which is a
casting [43,44] and the fact that for residential sectors, there is a conservative assumption because it is the base value for the annual
good correlation between water and energy consumption [45], the readjustment practiced by the companies.
growth rate expected for energy, projected in Ref. [42], of 2.2% per
year is also applied for water demand. Even so, since dry seasons 2.2. Problem formulation
are likely to have a drop in consumption due to rationing and
governmental policies, the probability of this event was also The optimal design problem combined with the energy recovery
considered, and a reduction rate of 1.5% per year (average observed approach can be solved using the minimization of an objective
between 1997 and 2005) was used in this case. These dry seasons function, defined as the sum of pipe and micro-hydropower plant
created an initial discontinuity in the projected consumption and costs discounted by the benefits obtained via energy production, as
four additional cases of reduction. Fig. 4-a shows the long-term shown in Equation (4).
forecasting obtained using this approach.
Energy tariff is also an important parameter to be considered OF ¼ minðPC þ MC  EBÞ (4)
when the benefits of energy recovery are calculated. Considering
the application in Brazil, where the electrical system is primarily where OF is the objective function, PC is the pipe costs, MC is the
composed of hydropower plants, the readjustment of tariffs is very micro-hydropower plant cost, and EB is the energy recovery

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413 407

Fig. 4. Long term forecasting: a) Energy and water consumption correlation and their long-term forecasting; b) Historical energy tariff readjustments [42].

benefits. plant power were valid for the 5e224 kW range, allowing the
Pipe costs are a function of their diameter and length and can be calculation of its costs through Equation (6).
calculated using Equation (5).
MC ¼ 2:246$P 2 þ 338:23$P þ 8218:79 (6)

X
NP
where P is the available power.
PC ¼ DCi $Li (5)
Finally, the benefits obtained with the energy recovery through
i¼1
the PAT life cycle should be adjusted to present values. Therefore,
where NP is the number of pipes in the network, DCi is the unitary the Net Present Value (NPV) is used, per Equation (7).
cost of pipe i, and Li is the length of pipe i. P 
i¼1 r$g$Qi;t $Hi;t $hi;t
8760
The micro-hydropower plant costs can be divided into three X
n $TEt
categories: project, civil construction and electromechanical EB ¼ NPV ¼ t
(7)
t¼1 ð1 þ iÞ
equipment costs. In this work, the costs obtained by Ref. [49],
adjusted by the period inflation, are used. The costs related to the

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


408 G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413

Fig. 5. Flowchart for network design using the energy recovery approach.

where n is the PAT life cycle, r is the water specific mass, g is the problem are as important as the optimization technique used.
gravitational acceleration, Qi,t is the PAT flow at hour i of year t, Hi,t Nevertheless, PSO has been widely used to solve different problems
is the PAT head at hour i of year t, hi,t is the PAT efficiency at hour i of of water supply systems with good results [38,53,54]. This tech-
year t, TEt is the energy tariff in year t, and i is the annual interest nique is based on the behavior of birds searching for food. Each
rate. particle of the method represents a possible solution, with an initial
To solve this optimization problem, the meta-heuristic tech- position (solution), X, and velocity, V, randomly defined. Over it-
nique PSO, developed by Ref. [50], is used [51]. studied four erations, the velocity and position of each particle are updated
different meta-heuristic techniques for the optimal design prob- using Equations (8) and (9), taking into account its best position
lem, and similar results were obtained. In addition [52], showed ever found, P, the best position ever found by the swarm, G, and its
that the penalty functions used to create the boundaries of the inertia, u. The coefficients c1 and c2, cognitive and social

Fig. 6. Laudissi DMA layout and the PAT location.

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413 409

   
Pik  Xik G  Xik
Vikþ1 ¼ u$Vik þ c1 $rand1 $ þ c2 $rand2 $ (8)
Dt Dt

Xikþ1 ¼ Xik þ Vikþ1 $Dt (9)

For the described design problem, two optimization stages are


performed: In the first, PSO particles are randomly initialized with
pipe diameters, and the first hydraulic simulation is carried out
without the micro-hydropower plant. Thus, knowing previously
the local for its installation, flow and pressure data obtained from
this first simulation are used to select an adequate PAT. In the
second stage, a frequency curve of power is created, and a second
optimization is performed to identify the PAT BEP, which maxi-
mizes the energy produced through its life cycle. The boundary of
this optimization is the minimum flow necessary for PAT operation.
In this study, a minimum of 50% of BEP is considered to avoid low
efficiency and the appearance of vibration problems [55]. After the
BEP is defined, the first stage continues, using the result to deter-
Fig. 7. Energy recovery feasibility for the Laudissi DMA design.
mine the characteristic curve of the PAT (Equation (3)). A new hy-
draulic simulation, now with the micro-hydropower plant already
parameters, respectively, are adjusted through iterations to installed, is performed, allowing the evaluation of the benefits
perform a better global search for the initial iterations (higher value obtained with energy recovery and the violation of boundary
of c1), and a refined local search at the end of the process (higher conditions, represented by the minimum pressure allowed in the
value of c2). network, which will be added to the objective function as a penalty.
Finally, the costs are calculated, and the objective function is

Fig. 8. Optimization results for the standard scenario in Laudissi DMA: a) Objective function evolution; b) Pipe diameters; c) Pressure on the critical node.

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


410 G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413

evaluated. Fig. 5 shows a flowchart that summarizes the procedure hydropower plant is surpassed by the benefit obtained using en-
for network design using the energy recovery approach. The ergy recovery, while on the right, for minimum pressures above
routine was developed in MatLab, using the Optimization Toolbox 37 m, the traditional design approach presents better results.
to perform the PSO. It is important to highlight that leakage was not Considering a standard scenario, with the minimum pressure of
considered in this work, which would make the optimization 10 m and an initial energy tariff of 0.30 $/kWh, the additional in-
problem even more complex due to the extra benefit/cost evalua- vestment necessary for the energy recovery is $42,480 (23.5%), but
tion of a reduction/increase in leakage volume. the benefit obtained with the average power of 3.72 kW is
$297,804, seven times the additional value. Observing the differ-
ence between the average power produced and the nominal power
3. Case study of the PAT, approximately 35 kW, it can be assumed that only for the
final years of the project is there an effective operation of the PAT.
3.1. Laudissi DMA Therefore, a second machine can be used for the initial years and for
the low consumption periods of the final years to increase the en-
This case study presents a real DMA of the city of Santa Ba rbara ergy produced. If this new scenario is considered, with a smaller
do Oeste - SP, Brazil. This DMA has 25 nodes and 31 pipes, and a PRV PAT installed for the initial demand, with the addition of a second
is already installed for pressure control. The average consumption machine after 10 years, the average power increases to 6 kW and
for the initial period of operation is 67.5 l/s. Fig. 6 shows the DMA the benefit obtained increases to $480,156, with an additional cost
layout and the location of the PAT. of only $51,899 (28.7%), which increases the energy recovery
To evaluate the influence of the minimum pressure allowed and feasibility even more. Due to the uncertainties in water demand
energy tariff, which are the most sensitive to energy recovery and energy tariff forecasting, a scenario with constant values for
feasibility, different values were adopted for these parameters. For these parameters was simulated, considering a minimum pressure
minimum pressure, the range was defined between 10 m, which is of 10 m. In this case, the net benefit obtained was significantly
the minimum value defined for Brazilian systems [56], and 40 m. improved to $534,280. This occurs because the PAT can operate on
For the initial energy tariff, a range of 0.15e0.60 $/kWh was its BEP during the entire life cycle, increasing the energy produced
defined, as it encompasses the different energy charging systems and surpassing the drawback of a reduced energy tariff. considering
available in Brazil. A total of 110 scenarios were evaluated this result, the worst scenario possible occurs when the water de-
combining different values for minimum pressure (10, 13, 16, 19, 22, mand increase and the energy tariff remains constant. In this case,
25, 28, 31, 34, 37 and 40 m) with the initial energy tariff (0.15, 0.20, the energy recovery still produces a better result, but the net
0.25, 0.30, 0.35, 0.40, 0.45, 0.50, 0.55 and 0.60 $/kWh). The PSO was benefit is reduced to only $17,080.
set using 50 particles, 1000 iterations and a tolerance for objective Observing the evolution of the objective function for the stan-
function variation of 1012. Using the results obtained in all sce- dard scenario (Fig. 8-a), it can be noted that at the beginning, the
narios, Fig. 7 was created. On the left is a zone where the additional pipe costs are high due to the increase of their diameter to reduce
investment to increase pipe diameters and install the micro- the headloss of the system and improve the available power for

Fig. 9. Campos do Conde II layout and DMA configuration for the PATs location.

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413 411

energy recovery. After some iterations, the pipe diameters remains 3.2. Campos do Conde II DMA
practically constant, and the PAT operation point is adjusted to
maximize energy production, which increases the NPV value. At The second case study is also a real DMA, from Piracicaba - SP,
final iterations, pipe diameters are reduced without major energy Brazil. This DMA is larger, with 121 nodes, 153 pipes and an initial
losses since a small reduction cannot create a significant headloss, demand of 315 l/s. Observing the DMA layout and its elevation
while the PAT operation point is finally set to an optimal value. The distribution, four minor DMAs can be defined. Therefore, in this
micro-hydropower plant costs remained insignificant compared case, four PATs are considered for the design optimization, one at
with others costs for all optimization procedure. Fig. 8-b shows the each new DMA entrance, as shown in Fig. 9.
increase of the first pipe, as it carries the total flow and is thus more For this case, only the standard scenario, with an initial energy
susceptible to headloss, which would significantly reduce the en- tariff of 0.30 $/kWh and a minimum pressure of 10 m, was evalu-
ergy production. The other pipes show similar diameters, with the ated. Due to the higher number of variables in this problem, the PSO
exception of pipe 32, which is significantly larger using the tradi- was set with 200 particles and the maximum iterations to 5,000,
tional approach. Since it has one of the minor lengths in the while the tolerance for the objective function variation was set to
network, its diameter is increased to compensate the headloss of 1012. Different from the Laudissi DMA, objective function mini-
other pipes with a low cost for the project. On average, the energy mization did not occur due to an increase in energy production over
recovery approach designed a network with 22.9% larger di- iterations, as observed in Fig. 10-a. Instead, the energy production
ameters. Finally, Fig. 8-c shows the pressure on the critical node remained practically constant, while the pipe costs were reduced.
(node with the minimum pressure) for the project life cycle. Due to This behavior occurs due to a greater relevance of pipe costs in the
diameter differences, the critical node for the traditional procedure objective function. Therefore, economically, it is more interesting to
is node 13, while with the energy recovery approach, node 23 reduce pipe costs than to increase energy production. Even so, the
presents minimum pressures. As expected, the pressure decays additional costs to increase the available power ($305,331) were
over the years due to the increase in demand, and only in the final surpassed by the energy benefits ($1,961,972) obtained with an
year of operation is the minimum pressure allowed in the network average power of 24.5 kW (sum of the average power of all four
achieved. However, during the operation period, the energy re- PATs), indicating the feasibility of the energy recovery approach.
covery approach produced better pressure control. Therefore, even Observing the frequency of pipe diameters for each method
using the traditional procedure, a pressure control device is (Fig. 10-b), it is noticeable that an increase resulted from the energy
necessary, as during most of the time, the network operates at high recovery approach. On average, pipe diameters increased by 58.3%,
pressures. which surprisingly is higher than the increase observed for the

Fig. 10. Optimization results for the standard scenario in Campos do Conde II DMA: a) Objective function evolution; b) Pipe diameters; c) Pressure at the critical node.

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


412 G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413

Laudissi DMA, even with the pipe costs being more relevant in this Swarm Evol. Comput. 17 (2014) 14e24, https://doi.org/10.1016/
j.swevo.2014.02.002.
case. This can be explained by the interaction of DMAs. Since the rez-García, M. Herrera, M, Water distribution
[7] I. Montalvo, J. Izquierdo, R. Pe
pressure of all DMAs is connected with DMA 1, the pressure drop system computer-aided design by agent swarm optimization, Computer-
caused by PAT 1 reduces the available power of the other three sites. Aided Civ. Infrastructure Eng. 29 (6) (2014) 433e448, https://doi.org/10.1111/
Therefore, the pipe diameters have to increase to maintain high mice.12062.
[8] Z.Y. Wu, A.R. Simpson, A self-adaptive boundary search genetic algorithm and
available power at these sites. The pressure behavior of the critical its application to water distribution systems, J. Hydraulic Res. 40 (2) (2002)
nodes of each DMA was similar to that observed for Laudissi DMA, 191e203, https://doi.org/10.1080/00221680209499862.
as shown in Fig. 10-c, where a decay over the years is observed due [9] L.F.R. Reis, R.M. Porto, F.H. Chaudhry, Optimal location of control valves in pipe
networks by genetic algorithm, J. Water Resour. Plan. Manag. 123 (6) (1997)
to the increase in demand, reaching the minimum value at the final 317e326, https://doi.org/10.1061/(ASCE)0733-9496(1997)123:6(317).
year, and the need for a pressure control device during the network [10] J. Saldarriaga, C.A. Salcedo, Determination of optimal location and settings of
life cycle is once again highlighted. pressure reducing valves in water distribution networks for minimizing water
losses, in: 13th Computer Control for Water Industry Conference - CCWI,
Procedia Engineering, vol. 119, 2015, pp. 973e983, https://doi.org/10.1016/
4. Conclusions j.proeng.2015.08.986.
[11] C.F. Wan, T.S. Chuang, Energy recovery by pressure retarded osmosis (PRO) in
SWROePRO, Appl. Energy 162 (2016) 687e698, https://doi.org/10.1016/
The paper presented a new approach for WDN design, consid- j.apenergy.2015.10.067.
ering energy recovery. The procedure is based on the minimization [12] A. Altaee, P. Palenzuela, G. Zaragoza, A.A. Al-Anezi, Single and dual stage
of global costs, represented by the pipes and micro-hydropower closed-loop pressure retarded osmosis for power generation: feasibility and
performance, Appl. Energy 191 (2017) 328e345, https://doi.org/10.1016/
plant, discounted by the benefit obtained using energy produc- j.apenergy.2017.01.073.
tion. The results showed that the additional costs to increase pipe [13] Y. Gu, Y. Li, X. Li, P. Luo, H. Wang, Z.P. Robinson, X. Wang, J. Wu, F. Li, The
diameters are surpassed by the energy recovery benefit. The feasibility and challenges of energy self-sufficient wastewater treatment
plants, Appl. Energy (2017), https://doi.org/10.1016/j.apenergy.2017.02.069.
sensitivity analysis of the energy tariff and minimum pressure [14] Q. Zhang, X. Zhao, H. Lu, T. Ni, Y. Li, Waste energy recovery and energy effi-
required performed for Laudissi DMA showed that even with un- ciency improvement in China's iron and steel industry, Appl. Energy 191
favorable conditions, i.e., low energy tariff and high minimum (2017) 502e520, https://doi.org/10.1016/j.apenergy.2017.01.072.
[15] M.R. Vilanova, J.A.P. Balestieri, Hydropower recovery in water supply systems:
pressure in the network, the energy recovery is feasible. In addition, models and case study, Energy Convers. Manag. 84 (2014) 414e426, https://
when two PATs are selected, one to operate with the initial con- doi.org/10.1016/j.enconman.2014.04.057.
ditions of consumption and the second to be installed after 10 years [16] I. Samora, V. Hasmatuchi, C. Münch-Allign, M.J. Franca, A.J. Schleiss,
H.M. Ramos, Experimental characterization of a five blade tubular propeller
of operation, the observed benefits significantly increased. Finally,
turbine for pipe inline installation, Renew. Energy 95 (2016) 356e366,
it could be observed that for cases with low water demand varia- https://doi.org/10.1016/j.renene.2016.04.023.
tion during the PAT life cycle, the benefit is increased, since the PAT [17] D. Jiyun, Y. Hongxing, S. Zhizheng, C. Jian, Micro hydro power generation from
water supply system in high rise buildings using pump as turbines, Energy
can operate for longer periods close to its BEP. For the worst case
(2017), https://doi.org/10.1016/j.energy.2017.03.023.
possible, with a constant energy tariff and a high variation in water [18] H.M. Ramos, A. Borga, M. Sima ~o, New design solutions for low-power energy
demand, the energy recovery approach remained feasible, but the production in water pipe systems, Water Sci. Eng. 2 (4) (2009) 69e84, https://
net benefit was significantly reduced. The study of Campos do doi.org/10.3882/j.issn.1674-2370.2009.04.007.
[19] A. Carravetta, G. Del Giudice, O. Fecarotta, H.M. Ramos, Energy production in
Conde II DMA confirmed the reliability of the proposed design water distribution networks: a PAT design strategy, Water Resour. Manag. 26
method, as the energy recovery was limited due to a higher econ- (13) (2012) 3947e3959, https://doi.org/10.1007/s11269-012-0114-1.
omy obtained when the pipe diameters were reduced, maintaining [20] J. Gallagher, I.M. Harris, A.J. Packwood, A. McNabola, A.P. Williams, A strategic
assessment of micro-hydropower in the UK and Irish water industry: iden-
the commitment to global economic attractiveness. As expected, tifying technical and economic constraints, Renew. Energy 81 (2015)
due to the higher number of variables, the second case study pre- 808e815, https://doi.org/10.1016/j.renene.2015.03.078.
sented a higher computational effort, requiring more than three [21] C. Soffia, F. Miotto, D. Poggi, P. Claps, Hydropower potential from the drinking
water systems of the Piemonte region (Italy), in: In: 4th Sustainable Energy
times the iterations of the first. Even so, the time spent to perform and Environmental Protection Conference, 2010. Bari, Ita lia.
the design using the energy recovery lasted no more than 10 h on a [22] N. Byns, K. Leunis, K. Peeters, L. Tonnet, K.U. Leuven, The use of hydropower in
regular computer, which is not relevant compared to the benefits water supply, in: European Water and Sanitation Services Vs Sustainable
Development, 2011.
obtained. It is also important to highlight that for both case studies,
[23] N. Fontana, M. Giugni, D. Portolano, Losses reduction and energy production
water losses were not considered, which can be a significant barrier in water-distribution networks, J. Water Resour. Plan. Manag. 138 (3) (2012)
to the use of energy recovery. This is mainly due to the poor ca- 237e244, https://doi.org/10.1061/(ASCE)WR.1943-5452.0000179.
[24] M. Marchis, G. Freni, Pump as turbine implementation in a dynamic numerical
pacity of PATs to operate with a reasonable performance under
model: cost analysis for energy recovery in water distribution network,
dynamic conditions, being ineffective for leakage control during J. Hydroinformatics 16 (1) (2015) 1e14, https://doi.org/10.2166/
low consumption periods. hydro.2015.018.
[25] R. Sitzenfrei, J. von Leon, Long-time simulation of water distribution systems
for the design of small hydropower systems, Renew. Energy 72 (2014)
References 182e187, https://doi.org/10.1016/j.renene.2014.07.013.
[26] L. Corcoran, A. McNabola, P. Coughlan, Predicting and quantifying the effect of
[1] T.M. Walski, A history of water distribution, J. Am. Water Works Assoc. 98 (3) variations in long-term water demand on micro-hydropower energy recovery
(2006) 110e121. in water supply networks, Urban Water 14 (7) (2017) 1e9, https://doi.org/
[2] A.R. Simpson, L.J. Murphy, G.C. Dandy, Pipe network optimization using Ge- 10.1080/1573062X.2016.1236136.
netic Algorithms, in: Proceedings of Specialty Conference of Water Resources [27] A. Afshar, F.B. Jemaa, M.A. Marino, Optimization of hydropower plant inte-
Planning and Management Division, American Society of Civil Engineers, gration in water supply system, J. Water Resour. Plan. Manag. 116 (5) (1990)
Seattle, Washington, USA, May 1993, pp. 392e395. 665e675, https://doi.org/10.1061/(ASCE)0733-9496(1990)116:5(665).
[3] Z.W. Geem, J.H. Kim, G.V. Loganathan, A new heuristic optimization algo- [28] G. Meirelles, A.N.C. Viana, R.S. Dias Jr., Optimal design of water mains
rithm: harmony search, Simulation 76 (2) (2001) 60e68, https://doi.org/ considering microgeneration” (in Portuguese), in: 25 Congresso Nacional de
10.1177/003754970107600201. Saneamento e Meio Ambiente, 2014. S~ ao Paulo.
[4] H.R. Maier, A.R. Simpson, A.C. Zecchin, W.K. Foong, K.Y. Phang, H.Y. Seah, H.Y., [29] B. Coelho, A.A. Campos, Efficiency achievement in water supply systems-A
C.L. Tan, Ant colony optimization for design of water distribution systems, review, Renew. Sustain. Energy Rev. 30 (2014) 59e84, https://doi.org/
J. Water Resour. Plan. Manag. 139 (3) (2003) 200e209, https://doi.org/ 10.1016/j.rser.2013.09.010.
10.1061/(ASCE)0733-9496(2003)129:3(200). [30] I. Basupi, Z. Kapelan, Flexible water distribution system design under future
[5] C.R. Suribabu, T.R. Neelakantan, Design of water distribution networks using demand uncertainty, J. Water Resour. Plan. Manag. 141 (4) (2015), 04014067,
particle swarm optimization, Urban Water J. 3 (2) (2006) 111e120, https:// https://doi.org/10.1061/(ASCE)WR.1943-5452.0000416.
doi.org/10.1080/15730620600855928. [31] J. Marques, M. Cunha, D. Savic, O. Giustolisi, Water network design using a
[6] N. Moosavian, B.K. Roodsari, Soccer league competition algorithm: a novel multiobjective real options framework, J. Optim. (2017) 1e13, https://doi.org/
meta-heuristic algorithm for optimal design of water distribution networks, 10.1155/2017/4373952.

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬


G. Meirelles Lima et al. / Renewable Energy 117 (2018) 404e413 413

[32] T.R. Knapp, Complete characteristics of centrifugal pumps and their use in the Hydrogen Energy 41 (35) (2016) 15919e15929, https://doi.org/10.1016/
prediction of transient behavior, Trans. ASME (1937) 683e689. j.ijhydene.2016.04.181.
[33] E.B. Wylie, V.L. Streeter, Fluid Transients, EUA (1983) Thomson-Shore, Mich- [46] H.T. Pao, Forecasting electricity market pricing using artificial neural net-
igan, 1983. works, Energy Convers. Manag. 48 (3) (2007) 907e912, https://doi.org/
[34] A.R.D. Thorley, M.H. Chaudry, Pump characteristics for transient flow analysis, 10.1016/j.enconman.2006.08.016.
in: BHR Group Conference Series Publication vol. 19, Mechanical Engineering [47] R. Weron, Electricity price forecasting: a review of the state-of-the-art with a
Publications Limited, Bedford, 1996, pp. 461e476. look into the future, Int. J. Forecast. 30 (4) (2014) 1030e1081, https://doi.org/
[35] J. Izquierdo, P.L. Iglesias, Mathematical modelling of hydraulic transients in 10.1016/j.ijforecast.2014.08.008.
simple systems, Math. Comput. Model. 35 (2001) 801e812, https://doi.org/ [48] Instituto Brasileiro De Geografia E Estatística - IBGE, http://www.ibge.gov.br/
10.1016/S0895-7177(02)00051-1. home/estatistica/indicadores/precos/inpc_ipca/defaultseriesHist.shtm,
[36] G. Meirelles, E. Luvizotto Jr., Method to estimate complete curves of hydraulic accessed in 01/2017.
pumps through the polymorphism of existing curves, J. Hydraulic Eng. 143 (8) [49] M.R. Vilanova, Study of Pumps as Turbines and Motors as Generators for Micro
(2017), 04017017, https://doi.org/10.1061/(ASCE)HY.1943-7900.0001301. Hydropower Plants, Master Thesis (in portuguese), Universidade Federal de
[37] W. Wan, W. Huang, Investigation on complete characteristics and hydraulic Itajuba, Itajub
a, Brazil, 2007.
transient of centrifugal pump, J. Mech. Sci. Technol. 25 (10) (2011) [50] R.C. Eberhart, J. Kennedy, A new optimizer using particle swarm theory, in:
2583e2590, https://doi.org/10.1007/s12206-011-0729-9. Proceedings of the Sixth International Symposium on Micro Machine and
[38] G. Meirelles, E. Luvizotto Jr., B.M. Brentan, Selection and location of pumps as Human Science, vol. 1, 1995, pp. 39e43.
turbines substituting pressure reducing valves, Renew. Energy 109 (2017) [51] D. Mora-Melia, P.L. Iglesias-Rey, F.J. Martinez-Solano, P. Ballesteros-Pe rez,
392e405, https://doi.org/10.1016/j.renene.2017.03.056. Efficiency of evolutionary algorithms in water network pipe sizing, Water
[39] M.A. Al-Zahrani, A. Abo-Monasar, Urban residential water demand prediction Resour. Manag. 29 (13) (2015) 4817e4831, https://doi.org/10.1007/s11269-
based on artificial neural networks and time series models, Water Resour. 015-1092-x.
Manag. 29 (10) (2015) 3651e3662, https://doi.org/10.1007/s11269-015- [52] I.N. Marchiori, G. Meirelles, B.M. Brentan, E. Luvizotto Jr., J. Izquierdo, Penalty
1021-z. functions in the optimal design of new water distribution networks” (in
[40] Europump, Hydraulic Institute and U.S. Department of Energy, Pump Life Portuguese), in: Congreso de Me todos Nume ricos en Ingeniería, 2017.
Cycle Costs: a Guide to LCC Analysis for Pumping Systems, Hydraulic Institute, Valencia, Espanha.
Parsippany, NJ, 2001. [53] D. Kang, K. Lansey, Real-time demand estimation and confidence limit anal-
[41] National System of Sanitation Information - SNIS, Diagnosis of Water and ysis for water distribution systems, J. Hydraulic Eng. 135 (10) (2009) 825e837,
Sewage Services e 2014, 2014. Technical Report (in Portuguese). https://doi.org/10.1061/(ASCE)HY.1943-7900.0000086.
[42] Empresa De Pesquisa Energe tica - EPE, Brazilian Energy Balance (In Portu- [54] B.M. Brentan, E. Campbell, G. Meirelles, E. Luvizotto, J. Izquierdo, Social
guese), Ministerio de Minas e Energia, 2015, p. 294. network community detection for DMA creation: criteria analysis through
[43] C.T. Osborn, J.E. Schefter, L. Shabman, The accuracy of water use forecasts: multilevel optimization, Math. Problems Eng. (2017), https://doi.org/10.1155/
evaluation and implications, JAWRA J. Am. Water Resour. Assoc. 22 (1) (1986) 2017/9053238.
101e109, https://doi.org/10.1111/j.1752-1688.1986.tb01865.x. [55] A. Williams, Pumps as Turbines Users Guide, International Technology Pub-
[44] T.M. Fullerton, A.L. Molina, Municipal water consumption forecast accuracy, lications, London, 1995, p. 59. ISBN l-85339-285-5.
Water Resour. Res. 46 (6) (2010), https://doi.org/10.1029/2009WR008450. [56] Brazilian Association of Technical Standards - ABNT, NBR 12218-Project of
[45] S. Jiang, J. Wang, Y. Zhao, S. Lu, H. Shi, H.F. He, Residential water and energy Water Distribution Network for Public Supply, 1994. Technical report (in
nexus for conservation and management: a case study of Tianjin, Int. J. Portuguese).

https://freepaper.me/t/511303 : ‫خودت ترجمه کن‬

Potrebbero piacerti anche