CRONOGRAMA DE AVANCE DE OBRA

FECHA DE INICIO DE OBRA


OBRA: PLAZO DE EJECUCION dias
“AMPLIACION DEL SISTEMA DE AGUA POTABLE Y DESAGUE EN HUANTALLON, DISTRITO DE JANGAS – HUARAZ - ANCASH”
FECHA DE TERMINO
FECHA : Abril 2012

SEMANA PERIODO
ITEM PARTIDAS MES ABRIL MES MAYO MES JUNIO
MONTO 9-15 16-22 23-30 1-6 7-13 14-20 21-31 1-10 11-17 18-24 25-30
CONSTRUCCION DEL SISTEMA DE AGUA POTABLE 156,750.58
S/. 3,244.86
1.01 OBRAS PROVISONALES P 3,244.86
E 3,244.86
S/. 296.00 296.00 296.00 296.00 296.00 296.00 296.54
1.02 OBRAS PRELIMINARES P 2,072.54
E 413.00 413.00 414.94
S/. 3,831.00 3,831.15
MOVIMIENTO DE TIERRAS

2.00 EXCAVACIONES ( ZAPATAZ.CIMIENTOS CORRIDOS,CISTERNA) P 7,662.15


E
S/. 4,191.00 4,191.00 4,193.54
1.04 LINEA DE CONDUCCION P 12,575.54
E 2,191.00 3,191.00 7,193.54
S/. 2,547.00 2,547.67
1.05 CRUCE AEREO LC (L=16M) P 5,094.67
E 2,147.00 2,947.67
S/. 4,790.00 4,790.00 4,790.00 4,793.15
1.06 CAMARA ROMPE PRESION TIPO CRP-06 (08 UND) P 19,163.15
E 4,764.00 4,764.00 4,766.75
S/. 6,663.00 6,663.00 6,663.49
1.07 RESERVORIO 10 M3 P 19,989.49
E
S/. 2,137.78
1.08 CASETA DE VALVULAS (01 UND) P 2,137.78
E
S/. 14,758.00 14,758.00 14,758.00 14,759.55
1.09 LINEA DE ADUCCION Y RED DE DISTRIBUCION P 59,033.55
E 19,677.00 19,677.00 19,679.55
S/. 2,561.36
1.10 CAMARA ROMPE PRESION TIPO CRP-07 (01 UND) P 2,561.36
E
S/. 1,446.35 1,446.35
1.11 VALVULAS DE CONTROL EN RED (06 UND) P 2,892.70
E
S/. 1,151.00 1,152.37
1.12 VALVULAS DE PURGA EN RED (05 UND) P 2,303.37
E
S/. 8,641.12 8,641.12
1.13 CONEXIONES DOMICILIARIAS (80 UND) P 17,282.24
E
S/. 184.00 184.00 184.00 185.18
1.14 ENSAYOS Y PRUEBAS DE CONCRETO EN AGUA POTABLE P 737.18
E 252.10 252.10
CONSTRUCCION DEL SISTEMA DE DESAGUE 99,775.78
S/. 11,463.00 11,463.00 11,463.76
2.01 REDES COLECTORAS P 34,389.76
E
S/. 8,413.00 8,413.87
2.02 BUZONES Y BUZONETAS P 16,826.87
E
S/. 3,874.69
2.03 CONEXIONES DOMICILIARIAS EN DESAGUE P 3,874.69
E
S/. 2,884.50 2,884.53
2.04 POZO DE ABSORCION (01 UND) P 5,769.03
E
S/. 1,210.23
2.05 MANTENIMIENTO DE UNIDADES P 1,210.23
E
S/. 10,329.28 10,329.28
2.06 DISPOSICION INDIVIDUAL DE DESAGUE P 20,658.56
E
S/. 975.50
2.07 RECUPERACION DE AREAS P 975.50
E
S/. 4,234.48 4,234.49
2.08 CERCO PERIMETRICO PARA PLANTA DE TRATAMIENTO P 8,468.97
E
S/. 169.44 169.44
2.09 ENSAYOS Y PRUEBAS DE CONCRETO DE DESAGUE P 338.88
E
S/.
2.10 OPER. Y MANT. EN OBRAS DE AGUA POTABLE Y DESAGUE P 735.00
E
S/.
2.11 MEDIDAS DE MITIGACION AMBIENTAL P 975.00
E
S/. 462.00 462.00 462.00 462.00 462.00 462.00 462.00 462.00 462.00 462.00 462.00
10 FLETE (INC. AGUA Y DESAGUE) P 5,553.29
E 925.50 925.50 925.67
COSTO DIRECTO 256,526.36

PROGRAMADO 103,189.22 40.23% 68,258.36 26.61% 82,897.49 32.32%


AVANCE MENSUAL(%)
EJECUTADO 0.00% 0.00 0.00% 0.00 0.00%
PROGRAMADO 103,188.22 40.23% 171,446.58 66.84% 254,344.07 99.16%
AVANCE ACUMULADO(%)
EJECUTADO 0.00% 0.00 0.00% 0.00 0.00%