PROPOSED DELIVERY SCHEDULE FOR ENGINEERING, FABRICATION, SUPPLY, DELIVERY, INSTALLATION & COMMISSIONING OF FOUR UNITS OF STEAM CONDENSERS AT GAS PROCESSING PLANT SANTONG, PGB

ID Task Task Name Duration Start Finish August September October November December
Mode 7/31 8/7 8/14 8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 10/16 10/23 10/30 11/6 11/13 11/20 11/27 12/4 12/11 12/18 12/25 1/1
1 Overall delivery schedule for 4 units of Air  145 days Mon 8/8/16 Fri 12/30/16
Finned Fan Coolers for PGB (GPP5 & GPP6)
2 Confirmation of order 0 days Mon 8/8/16 Mon 8/8/16 8/8
3 Kick off meeting 2 days Mon 8/8/16 Tue 8/9/16
4 Establishment of engineering drawings  25 days Wed 8/10/16 Sat 9/3/16
and design calculation
5 Send to Third Pary for verification and  5 days Sun 9/4/16 Thu 9/8/16
endorsement
6 Send to PGB for review and comment 7 days Fri 9/9/16 Thu 9/15/16
7 Send to DOSH for design approval 60 days Fri 9/16/16 Mon 11/14/16
8 Materials procurement (Oversea) 90 days Wed 8/10/16 Mon 11/7/16
9 Finned tube materials 90 days Wed 8/10/16 Mon 11/7/16
10 Header plugs and soft iron gaskets 60 days Sun 9/4/16 Wed 11/2/16
11 Flanges and swaged reducers 55 days Sun 9/4/16 Fri 10/28/16
12 Materials procurement (Local) 45 days Wed 8/10/16 Fri 9/23/16
13 Carbon steel plates SA516‐70 20 days Wed 8/10/16 Mon 8/29/16
14 Side plates materials 20 days Sun 9/4/16 Fri 9/23/16
15 Fabrication at shop 84 days Fri 9/16/16 Thu 12/8/16
16 Material inspection (Plates) 1 day Fri 9/16/16 Fri 9/16/16
17 Tube sheets/plug sheets fabrication 25 days Sat 9/17/16 Tue 10/11/16
18 Header boxes welding  28 days Wed 10/12/16 Tue 11/8/16
19 Nozzle fit up and welding 7 days Wed 11/9/16 Tue 11/15/16
20 NDT inspection 4 days Wed 11/16/16 Sat 11/19/16
21 PWHT of header's boxes 4 days Sun 11/20/16 Wed 11/23/16
22 Side plates /structures fabrication  12 days Sat 9/24/16 Wed 10/5/16
23 Galvanizing of shell plates 10 days Thu 10/6/16 Sat 10/15/16
24 Painting of shell plates / structures 10 days Sun 10/16/16 Tue 10/25/16
25 Shell plates & header's boxes assembly 3 days Thu 11/24/16 Sat 11/26/16
26 Tube inspection 1 day Sun 11/27/16 Sun 11/27/16
27 Tube insertion and expand 5 days Mon 11/28/16 Fri 12/2/16
28 Pre‐HT of tube bundle 2 days Sat 12/3/16 Sun 12/4/16
29 Official HT of tube bundle witness by PGB,  2 days Mon 12/5/16 Tue 12/6/16
Third Party & DOSH
30 Packing and preservation 2 days Wed 12/7/16 Thu 12/8/16
31 Delivery to site 0 days Thu 12/8/16 Thu 12/8/16 12/8
32 Site installation / PTR 22 days Fri 12/9/16 Fri 12/30/16
33 Mobilization to site 1 day Fri 12/9/16 Fri 12/9/16
34 Taking possesion of site GPP 5 0 days Fri 12/9/16 Fri 12/9/16 12/9
35 Scaffolding works 0.5 days Sat 12/10/16 Sat 12/10/16
36 Removal of existing E5‐1101 G/H 1.5 days Sat 12/10/16 Sun 12/11/16
37 Install new E5‐1101 G/H 1.5 days Mon 12/12/16 Tue 12/13/16
38 Commissioning of E5‐1101 G/H 7 days Tue 12/13/16 Tue 12/20/16
39 Taking possesion of site GPP 6 0 days Tue 12/20/16 Tue 12/20/16 12/20
40 Scaffolding works 0.5 days Tue 12/20/16 Tue 12/20/16
41 Removal of existing E6‐1101 I/J 1.5 days Wed 12/21/16 Thu 12/22/16
42 Install new E6‐1101 I/J  1.5 days Thu 12/22/16 Fri 12/23/16
43 Commissioning of E6‐1101 I/J 7 days Sat 12/24/16 Fri 12/30/16
44 Handing over of works 0 days Fri 12/30/16 Fri 12/30/16 12/30

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: AFC E‐1101 Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 7/22/16 Milestone External Milestone Manual Task Start‐only
Summary Inactive Task Duration‐only Finish‐only

PREPARED BY: TENAGA TIUB Page 1