STATEMENT
SMC MANUFACTURING (VIETNAM) 2ND
FACTORY – PHASE 2
1
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Precast Erection
SMC2.2/PVC/MS/05.06/PCW/001_REV.01
Revision History
Revision Date of issue Purpose of issue
(approved/revision)
2
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
CONTENTS
1.INTRODUCTION ..................................................................................................4
2.BUILDING DESCRIPTION ..................................................................................5
3.OGANIZATION CHART FOR THIS PROJECT .................................................8
4.FLOW CHART AND DIRECTION OF WORK ...................................................9
5.SCHEDULE ..........................................................................................................12
6.SPECIFIC STANDARD .......................................................................................13
7.TOOLS & EQUIPMENT .....................................................................................13
8.MATERIALS ........................................................................................................17
9.MATERIAL HANDING,STORAGE AND DELIVERY ....................................20
10.PREPARATION WORKS..................................................................................25
11.CONSTRUCTION METHOD ...........................................................................26
12.QUALITY CONTROL .......................................................................................50
13.HEALTH & SAFETY AND ENVIRONMENT ................................................51
14.APPENDIX .........................................................................................................56
Appendix 1: Risk Assessment .................................................................................56
Appendix 2: Inspection and Test plan .....................................................................67
Appendix 3: Inspection Checklist ............................................................................72
Appendix 4: Inspection and Test Request ...............................................................84
Appendix 5: Caculation Sheet .................................................................................86
Appendix 6: Scaffolding Certificate ......................................................................111
Appendix 7: Erection Drawing A3 size .................................................................154
3
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
1. INTRODUCTION
1.1 PURPOSE:
- Archive highest quality of project that cast in place structure cannot do.
- Saving Labor
Site Address : Lot A1,D2 street, Long Duc IP, Long Duc Ward, Long Thanh District, Dong
Nai Province Vietnam
4
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
2. BUILDING DESCRIPTION
2 Beam PC
3 Slab PC
5
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
6
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
7
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
3. OGANIZATION CHART
8
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
9
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
10
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
11
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
5. SCHEDULE (A3)
12
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
6. SPECIFIC STANDARD
- TCVN 9115 - 2012: Assembled concrete and reinforced concrete structures – Practice for
erection and acceptance.
- TCVN 5757- 2009: Steel wire ropes for general purposes − Minimum requirements
- TCVN 5873-1995: Welds in steel.
- KVN Project Specification and ITP sheets for inspection.
I FACTORY 5 37
Engineer 2
Safety 1
Surveyor 2
ERECTING Foreman 2
1
PRECAST TEAM
Welder 4
Workers 10
Crane Operator 2
Signaler 2
Engineer 1
2 GROUTING TEAM Foreman 1
Workers 10
II FACTORY 6 37
Engineer 2
Safety 1
ERECTING Surveyor 2
1
PRECAST TEAM
Foreman 2
Welder 4
Workers 10
13
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Crane Operator 2
Signaler 2
Engineer 1
2 GROUTING TEAM Foreman 1
Workers 10
Total 54
Equipment
No Equipment Quantity Capacity Remarks
I Factory 5 & Factory 6
14
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
5 Generator Welding 4
Machine
15
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
12 PAL-scaffold many
16
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
13 QUICKSTAGE-scaffold many
8. MATERIALS
No Item Description
1
Sika grout Sika Viet 25kg/bag PVC supply
214-11 Nam
2
Steel plate 6mm-12mm PVC supply
3
Welding rod Kim Tinh E 42 PVC supply
17
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- Sika grout 214-11 is a cement mortar, self-leveling, non-shrinkage with time allowed for
construction is extended to adapt to the local temperature.
- Sika grout 214-11 HS is a grout of self-leveling, high strength early, free of iron, shrinkage
compensation, use immediately, products have selected and pre-mixed aggregates to create
Make a homogeneous mixture.
- Compressive strength 27 ° C
18
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
+ Concrete surfaces must be clean, solid, none grease, dust and other impurities. Metal
surfaces (iron, steel) must be free of scale, grease or oil. Surfaces Water absorption must be
completely saturated, but not to stagnate.
+ When mixing grout, it should be slowly added to the pre-dosed water to achieve the desired
consistency. Mix with a low speed mixer with a mixing disc...
+ When pouring the mortar into the substrate must keep the flow of mortar without
interruption
- CT38 steel (or SS400) capable of bearing large, high load, difficult to deformation during
use, resilient.
19
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
C Si Mn P(Max) S(Max)
All materials delivery plan and storage location have to follow daily plan approved by KVN
engineers that needed to coordinate every day in site daily meeting.
20
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
THE SITE PLAN (add bản vẽ bằng cách dùng phần mềm better WMF cho rõ)
21
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- Transportation PC components after finished factory inspection by PHAN VU, KVN and
other relevant contractors engineers.
- Components are arranged on vehicles of appropriate size and load and are tightly
constrained to prevent shocks and impacts.
22
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
PRECAST
Height of TRANSPORT
DESCRIPTION Unit Dimension Weight of 1
Quantity segment CACULATION
(mm) segment(ton)
(m)
I. COLUMN
11.75(m
Gridline E1 pc 13 500x500 8.07
)
Gridline E pc 15 500x500 7.00 (m) 4.81
12.35(m
Gridline D pc 15 500x500 8.49
) Using
13.40 VEHICLE
Gridline C Pc 15 500x500 9.21
(m) Type 2 for
12.35 delivery.
Gridline B pc 15 500x500 8.49
(m) 6 nos /day
Gridline A Pc 15 500x500 7.00 (m) 4.81
11.75
Gridline A1 pc 13 500x500 8.07
(m)
Total pc 101
II. Slab Length Width Weight Using
VEHICLE
Thickness Type 1 for
Pc 1176 3.093 2.086 1.13 Tons
70mm delivery. 42
nos/day
Total pc 1176
9.3 Site Stock Plan (A3) (sử dụng bản vẽ đính kèm cho cả e nhà)
23
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
24
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- All components have to marking center lines every face of them before installation.
- Cast-in-situ structure need to marking center line and inspection level and location.
25
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
+ Check type of components make sure get the right structure by: Name, tag, number.
+ If steel cables are used, cushions should be placed to avoid damaging the concrete, and
protect the cable.
+ When lifting, the middle clamping mechanism must be used to ensure the distribution of
load on the structure.
+ Cable must comply with standards and have a special structure to remove the hook.
26
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
+ The use of installed structures for linking to other lifting devices must following
approved design.
+ Remove the crane hook after: fixed temporary bracing system or temporary connection
that approved by engineers and surveyors.
+ Care should be taken in the assembly process to prevent damage. Damaged components
must be replaced or repaired following KVN instruction.
+ Engineers and surveyors have to monitor workers to minimize the tolerance of location
as well as level at connection.
+ The assembly of the secondary components shall be carried out after the joints of the
lower load-bearing structures reached strength or finished temporary connection.
27
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
28
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
29
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
c. Detailed sequence
30
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
31
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-Install cang type 2 at two locations on pc column and install cable + turnbuckle
-Setting up lifting system and hook up column
-Using the 80T crane to raise the column slowly upward and move the column to position.
- Column braced by 8 cables following design, local load is 5 tons in 4 directions. After pc
column is installed, connect bracing cables into counterweight, tight turnbuckle to adjust pc
column verticality.
32
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-After bracing cables fixed and location inspected, remove crane’s hook.
33
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- Construction of joints between the neck columns and columns by Non-shrink grout.
34
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- When the grout reaches strength checked by sample test, bracing cable can be removed.
- Some details to be noted during construction:
+ Stump column connect to column detail
+ Cable and the cang connecting detail
+ Detail of cang for column type 1,type 2
+ Details anchor column type 1, type 2
35
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
36
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
37
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
250x550
L= 10(m),
400x950 W=3.43(t)
L= 10 (m), ,12pcs
W= 9.5(t)
400x950
L= 10(m),
W=9.5(t),
400x950 14pcs
L= 10 (m),
W= 9.5(t)
400x950
L= 10 (m),
W= 9.5(t)
400x950
L= 10(m),
250x550 W=9.5(t),
L= 10(m), 14pcs
W=3.43(t)
38
v
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
300x520
L= 4.5(m)
W=1.76(t)
300x950
13pcs
L= 15(m)
W=10.69(t)
43pcs
300x950
L= 15(m)
W=10.69(t)
43pcs
300x950
L= 15(m)
W=10.69(t)
43pcs
300x950
L= 15(m),
W=10.69(t)
300x520
43pcs
L= 4.5(m)
W=1.76(t)
13pcs
39
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
c. Detailed sequence
- Welding wedge steel plate connect to embed steel plate of corbel (weld 1a, weld 1b)
40
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- Place steel plate under scaffolding. Install scaffolding (using Pal scaffolding) to designed position. Welding scaffolding in to steel
plate. Use I200 bars to support under beam, adjust the height of the bar I200 to bottom beam level.
41
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
42
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- Crane is lifting and erecting beam into position, in-process erecting use two ropes to
adjusting beam. When adjusting beam into corbel, use wooden shim (~3cm) to keep the gap
between the column–beam.
43
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
44
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- Grouting team will conduct cleaning, form fitting and grouting structure’s joints.
45
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
46
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
70MM 70MM
W=1.55(t) W=1.55(t)
294pcs 294pcs
70MM
W=1.55(t)
294pcs
70MM
W=1.55(t)
294pcs
47
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
c. .Detailed sequence
- The height of the scaffold is equal to the height of the bottom of the floor.
48
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
49
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
By KVN Checklist
50
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
51
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
52
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
53
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
54
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
55
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
14. APPENDIX
Appendix 1
Risk Assessment
56
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
KV/FORM/SA/14.01
JHA
JOB HAZARD ANALYSIS FORM - PHÂN TÍCH MỐI NGUY TRONG CÔNG VIỆC
57
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
No. Activity Hazard Severity Likelihood Risk Actions to Reduce Risk – Action by, Severity Likelihood Risk
Stt Hoạt động Mối nguy Mức độ Khả năng Level Reducing Severity and/or Designation Mức độ Khả năng Level
nghiêm nghiêm
trọng xảy ra (Follow up trọng xảy ra
Mức độ rủi Likelihood Date) Mức độ
ro
Hành động, rủi ro
Các hành động để giảm nguy cơ-giảm tên gọi (theo
(a) (b) (a)x(b) mức độ nghiêm trọng và/hoặc khả năng dõi ngày) (c) (d) (c)x(d)
01 Delivery Traffic accident 4 2 8 Provide appropriate platform & access HSE officer 4 1 4
Drop material 3 2 6 Provide signal man Site engineer 3 1 3
Ensure hand brake is engaged when the
truck ins in stationary
Site speed limit
Unloading the Crane failure 4 3 12 Crane inspection prior to using HSE officer 4 1 4
steel frame
Hit to worker 4 3 12 Don't allow people stay underneath the Site engineer 4 1 4
hoist during its operation
Cut, scratch hand 3 3 9 2 2 4
Barricade the lifting area and provide
Hit to structure 4 2 8 4 1 4
sufficient warning signs
People injuries 3 3 9 2 1 2
Wearing sufficient PPE
Tiny material should be placed in
containers or buckets
No material is placed at stacked along the
access or at the edges of the platform or
openings
Workers must carry loads within the safe
human lifting capacity
03 Assembling Crane failure 4 3 12 Crane inspection prior to using Barricade HSE officer 4 1 4
the working area
Hit to worker 4 3 12 Site engineer 4 1 4
Provide the signal man to control Provide
Cut, scratch hand 3 3 9 2 2 4
hand gloves
58
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
04 Sequencing of Conflict with other 3 3 9 Plan for safe, practical and economic HSE officer 2 2 4
erection work. parts of the project working, not just for time. Avoid return
Site engineer
construction visits for crane if possible.
creating unsafe
One bay must be properly braced and the
working
erection can continue from this braced bay.
conditions.
4 3 12 The first component erected must be
Wrong sequence
braced or tied-up properly – free standing
can lead to collapse 4 1 4
column is not allowed.
of the crane
overturning
59
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
08 Crane move Crane toppled 3 3 9 Crane toppled injuring workers involved HSE officer 3 1 3
and setting injuring workers addressing hazards associateds, best
Site engineer
practices, and control measure.
Select appropriate crane for the
job.Stabilize ground when moving the
crane..Matting the ground with steel plates
if it is so soft.
Solid road must be made to facilitate
movement of cranes and set up.
60
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
10 Welding work Electrical shock to 4 3 12 Proper use of electricity with double HSE officer 2 1 2
worker. Fire due to
insulated equipment, cables or/and Site engineer
fuel in contact with
welding slags grounding and ELCB installed.
Personal injury Fire extinguishers available; wet the
ground surface; flammable materials to
be removed from impact areas.. To use
proper PPE for the job.
11 Inadequate Personal injury 3 3 9 Ensure safe access - provide safe means of HSE officer 2 2 4
access for trips and slips.
access and egress. Site engineer
integrity
testing.
61
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
No. Activity Hazard Severit Likelihood Risk Actions to Reduce Risk – Action by, Severity Likelihood Risk
y
Stt Hoạt động Mối nguy Khả năng Level Reducing Severity and/or Designation Mức độ Khả năng Level
Mức độ nghiêm
nghiêm xảy ra (Follow up xảy ra
Mức độ rủi Likelihood trọng Mức độ
trọng Date)
ro
rủi ro
Các hành động để giảm nguy cơ-giảm mức Hành động,
độ nghiêm trọng và/hoặc khả năng tên gọi (theo
(a) (b) (a)x(b) dõi ngày) (c) (d) (c)x(d)
01 Delivery the Traffic accident 3 3 9 Licensed operator, speed limit HSE officer 3 1 3
scaffold
Trip, slip, fall 3 3 9 Remove all the obstruction on access way Site engineer 2 1 3
components to
site Cut, scratch the hand 2 3 6 Wear the proper hand gloves 2 2 4
03 Erection the Cut, scratch the hand 2 3 6 Wear proper hand gloves HSE officer 1 2 2
scaffolding
Collapse the scaffold 4 3 12 Check base condition before work Site engineer 4 1 4
system due to erection
on the soft ground
Collapse the scaffold
due to using bad quality 4 3 12 Check the quality of scaffold components 3 1 3
of scaffold components before erection
Worker falls down
4 2 8 4 1 4
during erection
Only competent person can carry out the
work
62
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
04 Working on Scaffolding collapse 4 3 12 Using safe scaffold by notice to 'safe to work' HSE officer 4 1 4
scaffolding tag
Fall of person 4 3 12 Site engineer 2 1 2
Not using scaffold overload
Fall of material & tools 4 3 12 3 1 3
05 Dismantling Cut, scratch the hand 2 3 6 Wear proper hand gloves HSE officer 2 2 4
the Strictly follow the dismantling procedure
4 3 12 Site engineer 4 2 8
scaffold Barricade the working area
Scaffold collapse due to
Stock the dismantled material
improper dismantling
procedure
4 2 8 4 1 4
Fall scaffold
components and hit to
worker below
63
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
66
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Appendix 2
Inspection and Test plan
67
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
68
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
69
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
70
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
71
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Appendix 3
Inspection Checklist
72
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
73
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
74
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
75
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
76
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
77
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
78
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
79
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
80
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
81
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
82
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
83
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Appendix 4
Inspection and Test Request
84
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
85
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Appendix 5
Calculation sheet
86
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
N Components Weight Safety Erection Crawler Boom Working Boom lifting capacity Evaluate
o (ton) factor crane length radius
loading ( check catalogue Grane)(tấn)
(tấn)
(tấn) (m) (m)
(2) (2) >(1)
(1)
87
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
88
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
89
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
90
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
91
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
92
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
93
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
94
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
95
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
96
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
97
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
98
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
99
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
100
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
101
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
102
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
103
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-Input data:
Method to anchor:
Load:
104
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-Check.
Cables:
105
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
𝑁 26.3 kN
= 9.0 kN
106
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Amitosis:
107
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Amitosis:
Amitosis :
angle α (degree) 0 30 45 60
108
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
7 10.29 acceptance
8 11.76 acceptance
9 13.23 acceptance
10 14.7 acceptance
11 16.17 acceptance
12 17.64 acceptance
According to the standard TCVN 5757-2009 and Steel specifications, choose d = 10mm
Turn Buckle
Type Weight (kN) Cable Dimension (mm) Rope cap (kN) Remark
M6 2.25 refuse
M8 4.1 refuse
M22 32 acceptance
109
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Components Dimension Height (m) Weight Rope cap TCVN 5757- 2009
(mm) (ton) min P selected steel cable
diameter (mm)
(ton)
110
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Appendix 6
Scaffolding certificate
111
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
112
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
113
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
(Ø76 x 3mm)
Height External Inner Gross Net Moment Operating Slenderness Convention Bucklin Proposed Remark
of the diamete diameter area area of height Slenderness g factor load
frame D (cm) d (cm) A Ath inertia Lo (cm)
H (cm) (cm2) (cm J (cm2) P1 (kg)
2)
150 7.5 6.9 44.16 6.78 44.03 75.00 29.44 0.94 1.15 16,887.51
Coefficie
300 7.5 6.9 44.16 6.78 44.03 150.00 58.87 1.88 0.89 13,001.20
nt of
working
450 7.5 6.9 44.16 6.78 44.03 225.00 88.31 2.83 0.66 9,686.10
condition
s is 0.8
600 7.5 6.9 44.16 6.78 44.03 300.00 117.75 3.77 0.47 6,942.20
Steel
tensile
750 7.5 6.9 44.16 6.78 44.03 375.00 147.19 4.71 0.33 4,769.50
strength
of 2,700
900 7.5 6.9 44.16 6.78 44.03 450.00 176.62 5.65 0.22 3,168.00
kg / cm2
1000 7.5 6.9 44.16 6.78 44.03 500.00 196.25 6.28 0.17 2,417.68
114
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- Combination 1 frame consists of four buttress against single linked together by the
horizontal bracing.
- Combination of a single pillars including: foot size +3 frame 1.5m 1 frame 0.75m + U.
115
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
* Checking for Pal supporting (D76x3mm)/ Tính toán khả năng chịu tải một
chân giáo pal
116
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-Compressive capacity base on the stable condition: Khả năng chịu nén do mất ổn
định
Strength check
+ Moment checking M= PL/4 =26.25 kNm
Deflection check
+ Deflection = 1.4 mm OK
+ Limitation = 4.8 mm
117
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Calculation of supporting system for Main beam 400x950mm/Tính toán giàn giáo
chống đỡ dầm 400x950:
Loading application :
-Span of beam: L= 9.2 m
-Height of beam: h= 1.1 m
-Width of beam: b= 0.5 m
-Thicking of slabs hs= 0.15 m
-Span of sub-beam Lsb= 14.70 m
-Height of Precast beam hp= 0.95 m
Load on sub-beam:
Dead Load of sub- beam: gb2=19.63kN/m
Live load of slabs on beam when casting: pb1=5.00 kN/m
Live load of slabs on beam when using: pb1=33.33 kN/m
Load on main- beam:
Distribute load
Dead load of beam: gb1=13.75 kN/m
space of two support is: 3.30 m
Load to corbel of subbeam: 65.98 kN
Load to support system: 177.34 kN
118
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
119
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Loading for one prop/ Tải trọng tính toán 1 chân giàn giáo: P = 44.3 (kN)
Apply support system for main beam/ Bố trí chống đứng cho dầm chính là:
[P] = 117 (kN) > P = 44.3(kN)
> the capacity of system enough to support for beam/ Hệ chống pal đủ khả
năng chịu lực với Hệ số an toàn : n = [P] / P = 2.6
Calculation of supporting system for Sub beam 300x950mm/Tính toán giàn giáo
chống đỡ dầm 300x950:
Dimension:
Load on slabs:
120
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Combination load:
ultimate limited stage
Phase 1: crane and Erection P=1.4*1.1*gb1= 10.97 kN/m2
Phase 2: before weld end of beam P=1.1*gb1=7.84kN/m2
Phase 3: cast on place p=1.1gb1+1.1gb2+1.2qb2=27.59 kN/m2
Phase 4: finish and operate p=1.1g1+1.1g2+1.2q1= 61.59 kN/m2
Service limited stage
Phase 1: crane and Erection p=1.4*gb1= 9.98 kN/m2
Phase 2: before weld end of beam p=gb1= 7.1 kN/m2
Phase 3: cast on place p=gb1+gb2+qb2= 24.63 kN/m2
121
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
122
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-Loading for one prop/ Tải trọng tính toán 1 chân giàn giáo: P = 33.2 (kN)
-Apply support system for main beam/ Bố trí chống đứng cho dầm chính là:
-Loading for one jack base / Tải trọng tính toán 1 chân đế: P = 177.34 /4 = 44.3 (kN)
-The support of jacke base/ khả năng chịu tải của chân đế:
123
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
124
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
125
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
126
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
127
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
128
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
129
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
130
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
131
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
132
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
133
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
- One single brace: base jack +2 pier 3.0m 1+ 1 pier 0.5m + U-jack
134
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
*Checking for supporting base (D49x2mm)/ Tính toán khả năng chịu tải một
chân giáo nêm
-Horizontal distance /Khoảng cách giằng ngang: h = 990(mm)
135
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Loading application :
Dimension:
Span of slab: L= 3.03 m
Thickness of slab: h= 0.15 m
Thickness of Precast slab: hp= 0.07 m
Load:
Dead Load of Precast slabs g1= 1.75 kN/m2
Dead Load of concrete cast on place g2= 2.00 kN/m2
Live load of cast on place q1= 1.50 kN/m2
Live load q2= 10.00 kN/m2
Conbination load:
ultimate limited stage
Phase 1: crane and Erection p=1.4*1.1*g1= 2.70 kN/m2
Phase 2: cast on place p=1.1g1+1.1g2+1.2q2= 5.93 kN/m2
Phase 3: finish and operate p=1.1g1+1.1g2+1.2q1= 16.13 kN/m2
Service limited stage
136
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
137
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-Loading for one prop/ Tải trọng tính toán 1 chân giàn giáo: P = 21.54 /4 = 5.39 (kN)
(We use Etabs program to calculate this structure)
138
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
-Apply support system for slab / Bố trí chống đứng cho sàn là:
[P] = 38 (kN) > P = 5.83 (kN)
>the capacity of system enough to support for beam/ Hệ chống pal đủ khả năng
chịu lực với Hệ số an toàn : n = [P] / P = 6.5
Loading for one jack base / Tải trọng tính toán 1 chân đế: P = 5.83 (kN)
The support of jacke base/ khả năng chịu tải của chân đế:
139
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
140
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
141
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
142
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
143
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
144
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
145
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
146
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
147
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
148
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
149
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
150
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
151
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
152
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
153
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
Appendix 7
Erection drawing A3
154
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
155
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
156
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
157
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
158
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
159
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
160
PROJECT: SMC MANUFACTURING (VIETNAM) 2NDFACTORY- PHASE 2
161