Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Report Assignment 5
GROUP 8
GROUP PERSONNEL:
Andrey Sapati Wirya (1306412161)
Clara Novia (1306370985)
Getta Austin (1306405364)
Luthfiyah Ainny (1306370852)
Ulina Ayu Pangesti (1306447726)
iv Universitas Indonesia
3.4.4 Sensitivity Graph.................................................................................. 44
3.4.5 Strategy ................................................................................................ 46
CHAPTER 4 CONCLUSION ............................................................................ 47
REFERENCES .................................................................................................... 48
v Universitas Indonesia
1 LIST OF FIGURES
vi Universitas Indonesia
1 LIST OF TABLES
Table 1.1 Marshall and Swift Chemical Equipment Cost Index (CEPCI) .............. 1
Table 1.2 List of equipment cost ............................................................................. 3
Table 1.3 Utility cost and waste water treatment Cost............................................ 7
Table 1.4 Supporting equipment cost ..................................................................... 9
Table 1.5 Piping and insulation cost ..................................................................... 10
Table 1.6 Elbow and junction cost ........................................................................ 10
Table 1.7 Fitting cost ............................................................................................ 10
Table 1.8 Controller cost ....................................................................................... 11
Table 1.9 Building volume area ............................................................................ 11
Table 1.10 Open area ............................................................................................ 12
Table 1.11 Civil work cost .................................................................................... 12
Table 1.12 Land cost ............................................................................................. 12
Table 1.13 Electricity installment cost .................................................................. 13
Table 1.14 Additional cost .................................................................................... 13
Table 1.15 CAPEX ............................................................................................... 15
Table 1.16 Benchmarking ..................................................................................... 17
Table 2.1 Raw material cost .................................................................................. 19
Table 2.2. Shipping cost ........................................................................................ 20
Table 2.3 Fixed direct labors salary ...................................................................... 22
Table 2.4 Total of direct worker costs .................................................................. 22
Table 2.5 Fixed indirect labor salary..................................................................... 22
Table 2.6 Total of indirect worker costs ............................................................... 24
Table 2.7 Main equipment electricity ................................................................... 24
Table 2.8 Supporting equipment electricity .......................................................... 26
Table 2.9 Water utility cost ................................................................................... 27
Table 2.10 Total fuel cost ..................................................................................... 27
Table 2.11 Total utility cost .................................................................................. 28
Table 2.12 Insurance Cost ..................................................................................... 29
Table 2.13 Other Cost ........................................................................................... 30
Table 2.14 Total OPEX ......................................................................................... 30
Table 3.1 Cumulative cash flow............................................................................ 33
Table 3.2 Weighted Average Cost of Capital (WACC) ........................................ 34
Table 3.3 Percentage of equity source .................................................................. 35
Table 3.4 BRI equity ............................................................................................. 35
Table 3.5 Investor equity....................................................................................... 36
Table 3.6 Total financial interest .......................................................................... 36
Table 3.7 Depreciation .......................................................................................... 37
Table 3.8 Break even point ................................................................................... 40
Table 3.9 Selling price fluctuations ...................................................................... 42
Table 3.10 Raw material cost fluctuations ............................................................ 43
Table 3.11 Distribution cost fluctuations .............................................................. 43
1 Universitas Indonesia
2
Universitas Indonesia
3
7 Heater and
Heat for Sterilization 500.00 392.42 415.24 531.51 1 577.22
Cooler
10 Vessel Tank Vaccine Liquid Storage 900.00 887.37 938.99 1,201.90 1 2,139.38
11 Storage YPD 200.00 57.71 61.07 78.17 1 156.34
12 Storage PBS 1,500.00 2,203.78 2,331.96 2,984.90 1 5,969.81
13 Storage Ammunium Sulfate 25% 50.00 50.00 52.91 67.72 1 135.44
Universitas Indonesia
4
Universitas Indonesia
5
Universitas Indonesia
6
1.2.2 Utility Cost and Waste Water Treatment Cost (Office Facilities)
Calculation for utility and WWT equipment, we used bare module cost
because capacity of our equipment is small. If using hystorical data, our
equipment cost cannot be calculated because our equipment capacity not in range.
The calculation is summarized in table 1.3.
Universitas Indonesia
7
Utility Equipment
1 Vessel Tank Potable Water Storage 5,000.00 4,983.86 5,273.73 6,750.37 1 12,015.66
2 Purified Water Tank 1 1,000.00 428.55 453.48 580.45 1 1,033.20
3 Purified Water Tank 2 1,000.00 404.63 428.16 548.04 1 975.52
4 PDAM Water Storage 5,000.00 4,984.12 5,274.00 6,750.72 1 12,016.29
5 Lamp Ultraviolet Lamp 750.00 678.44 717.90 717.90 1 725.08
6 Membrane Reverse Osmosis 800,000.00 681,419.26 721,051.58 721,051.58 1 728,262.10
7 Ion Exchanger Ion Exchanger 30,000.00 29,751.66 31,482.06 31,482.06 1 31,796.88
8 Boiler Boiler for heat Sterilization 830.00 745.35 788.70 1,009.54 1 1,096.36
9 Boiler for Water Treatment 6,000.00 5,901.14 6,244.36 7,992.78 1 8,680.16
10 HE HE for Water Treatment 1 880.00 818.46 866.06 1,108.56 1 1,203.90
11 HE for Water Treatment 2 770.00 704.79 745.78 954.60 1 1,036.69
Heater for water bath seed
12 500.00 334.13 353.56 452.56 1 491.48
fermentor
Heater for water bath
13 700.00 685.69 725.57 928.73 1 1,008.60
fermentor
14 Cooling Tower Cooling Tower 12,200.00 12,200.00 12,909.57 12,909.57 1 14,019.79
15 Pump Centrifugal Pump 15.00 15.00 15.87 15.87 9 275.70
16 Compressor Compressor 1,000.00 1,000.00 1,058.16 1,058.16 1 1,327.99
Universitas Indonesia
8
Table 1.3 Utility cost and waste water treatment cost (Continued)
Correction FOB Price (2018)
Price Based Seller
Type of Cost Based FOB Price with Update
No Equipment Capacity (USD)=FOB Qty BM Cost (USD)
Equipment Cappacity (2018) (USD) Material Corection
Price (2016)(USD)
(USD) (USD)
WWT
1 Vessel Tank Collected Tank 200.00 116.33 123.10 123.10 1 246.20
2 Neutralization tank 200.00 116.33 123.10 123.10 1 246.20
3 Aeration tank 1 200.00 47.24 49.98 49.98 1 99.97
4 Aeration tank 2 200.00 47.24 49.98 49.98 1 99.97
5 Sedimentation tank 1,000.00 279.57 295.83 295.83 1 591.65
6 Chloration tank 1,600.00 840.84 889.74 889.74 1 1,779.49
7 Incinerator 10,000.00 9,309.16 9,850.59 9,850.59 1 19,701.18
TOTAL COST (USD) 838,730.07
Universitas Indonesia
9
15 TV 2 1,959.93 3,919.86
Universitas Indonesia
10
To determine the cost of piping we have to determine the type of the pipe
first. It’s determined by the P&ID. Determining the cost of pipe is based on its
length and the insulation based on the pipe outer surface area. The price for pipe
per ft is $ 1.05 and for insulation is $ 0.57 per m2. The piping and insulation cost
are listed in the following table.
Table 1.5 Piping and insulation cost
Requirement Outer
Length Total Price Insulation
Nominal ID Area
Material Schedule (ft) (USD) (USD)
Pipe (in) (m2)
0.5 40 0.52 55.71 0.06 58.66 0.03
Carbon
1.25 40 1.38 8,075.62 20.47 8,503.63 11.67
Steel
2.5 40 2.47 6,605.74 33.49 6,955.85 19.09
Total 15,518.14 30.79
The elbow and junction cost are calculated in pieces. The price varies with
its diameter. The elbow and junction cost are listed in the following table
Table 1.6 Elbow and junction cost
Requirement
Quantity Price (USD)
Material Nominal Pipe Schedule ID (in)
1.25 40 1.38 10 1,356.64
Elbow 90
2.5 40 2.47 17 3,316.768
1.25 40 1.38 4 890.928
T Junction
2.5 40 2.47 5 2,136.41
Total 7,700.746
The valve used within the piping system are comprised with only one type,
that is diaphragm globe valve with pneumatic actuator. The air to open (AO) and
air to close (AC) type are of the same price. The valve cost are listed in the
following table
Table 1.7 Fitting cost
b. Controller Cost
Another component form this sub chapter is controller. Controller is very
important for the process so we need the spare in case of emergency. Our
Universitas Indonesia
11
controller is based on the uses in P&ID.The controller cost are listed in the
following table
Table 1.8 Controller cost
Price Total Price
Type Quantity Spare
(USD) (USD)
Level Controller 3 1 985.07 3,832.75
Flow Controller 8 4 895.52 10,452.96
Pressure Controller 1 1 2,238.81 4,355.40
Temperature
6 3 1,343.28 11,759.58
Controller
Timer Controller 3 1 895.52 3,484.33
Analysis Controller 6 3 895.52 7,839.72
Total 41,724.74
Universitas Indonesia
12
Size (m)
No Area Area (m2)
Length Wide
1 Building - - 3793.92
2 Open Area (road) 115 78.23 4,626.205
3 Green Area (44 Trees) 1.447266 1.45 92.16147
4 Waste Treatment Pond 3 3.09 9.27
5 Waste Treatment Open Area 13.5 8.59 115.965
6 Parking Area 1 1 30.11 30.113
7 Parking Area 2 4 28.03 112.12
8 Parking Area 3 6 20.10 120.6
9 Parking Area 4 4 24.00 96
TOTAL 8,996.355
Based on Table 1.9 and 1.10 we can determine the cost of civil work by
based on the basic cost or assumption from the contractor we hired, which shown
below:
Table 1.11 Civil work cost
Price/Unit Total Price
No. Type Area Total Price (IDR)
(USD/m2) (USD)
1 Site (m2) 125.235 25.96 3,251.65 44,794,738.58
Green Area
2 92.161 5.56 512.77 7,063,889.56
(m2)
1st Floor 418390.
3 74.18 31,037,844.69 427,577,348,433.96
Building (m3) 146
2nd Floor 30692.5
4 50.07 1,536,904.35 21,172,394,334.61
Building (m3) 49
4985.03
5 Asphalt (m2) 9.27 46,226.24 636,812,711.18
8
TOTAL 32,624,739.70 449,438,414,107.89
Universitas Indonesia
13
Universitas Indonesia
14
Universitas Indonesia
15
Universitas Indonesia
16
Main Equipment
Offsite
Supporting Equipment
Control
Insulation
Figure 1.1 explain about cot breakdown in CAPEX cost. The main cost is
for Civil Work 88% and than main equipment cost is 5%.
1.3 Benchmarking
The purpose of doing a benchmarking is to ensure the validity of cost &
investment of this plant, and to provide further visualization of the economic
capability of the plant. In Indonesia, Hepatitis B vaccine is produced by Biofarma,
and thus we compare some data with Biofarma. Below is the result of our
benchmarking:
Universitas Indonesia
17
Benchmarking
Benchmark Production Capacity
CAPEX OPEX ROI ROA
Plants (vial/year)
Biofarma 8,935,905,480,000,000.00 22,018,932,960,000,000.00 439,448,000,000.00 11,775,000 254,502,400,000.00
Universitas Indonesia
2 CHAPTER 2
2 OPERATING COST
18 Universitas Indonesia
19
Universitas Indonesia
20
Universitas Indonesia
21
From the tables above, the total cost for the raw material to production of
vaccine hepatitis B is $ 86,850,713 per year. This cost is already including the
shipping the materials to the our plant. The shipping is done by the supplier, so we
ony need to facilitate a warehouse and storage tank
Universitas Indonesia
22
Total 143,728.40
For the direct labors annually the salary will be $143,728.40 for 48 labors.
As well as direct labor costs, indirect labor costs consist of fixed and variable
costs. Indirect workers consists of corporate leadership, production department,
professional engineer, and research and development. The cost of indirect workes
can be seen in the table below:
Table 2.5 Fixed indirect labor salary
Salary/month/ Amount
Department Position Total (USD)
person (USD) (person)
President
2,540.65 1 30,487.80
Director
Secretary of
President 508.13 1 6,097.56
Stakeholder
Director
Vice
President 1,814.75 1 21,777.00
Director
Finance
Accounting 907.38 1 10,888.50
Finance Manager
Department Assistant
Finance 617.02 1 7,404.18
Manager
General
Support and SCM 907.38 10,888.50
1
Service Manager
Department
Universitas Indonesia
23
Universitas Indonesia
24
Total 306,167.25
For the indirect labors annually the salary will be $303,136.00. So the total
salary for direct and indirect labor will be $306,167.25 or Rp4,217,760.00. The
salary hasn’t included insurance costs which will be added every month to the
salary.
2.1.3 Utility
Utility costs are costs that used to finance the main necessities of the
production such as water, electricity, and plant infrastructure. Variable utility
costs are costs for utilities that used for production processes. Those utilities are
such as electricity and fuel for the generator when there is no electricity supply
from PLN or when it is black out. We have also the utility for water.
To calculate the cost of electricity on production process, we will use data
of power needed by equipments to operate. Calculation of energy balance is done
based on the assumption that power needed by each equipment to be operated in
one hour in one day.
a. Electricity Utility
Table 2.7 Main equipment electricity
Energy Energy
Total Requirement Supplied Energy
Equipment Power
operation for Process by PLN Losses
Name (kW)
time (hours) per year per year (15%)
(kW) (kW)
Process Equipment
Media Blending
0.75 2.41 235.0 270.2 35.2
Tank
Heat
Sterilization E- 0.5 0.39 25.4 29.2 3.8
28
Cooling
Sterilization E- 7.2 0.39 365.0 419.8 54.8
29
Seed Fermentor 0.75 5.7 555.8 639.1 83.4
Universitas Indonesia
25
Universitas Indonesia
26
Universitas Indonesia
27
b. Water Utility
We have counted our water utility in previous assignment 3. Now we are
going to calculate the water utility cost. For the water requirement, we are going
to use water that obtained directly from the PDAM. The price for water in
industry is Rp. 2,500/m3. So we can calculate our water utility cost.
Table 2.9 Water utility cost
c. Fuel Utility
In case of a power outage, Hepatitis Vaccine Plant uses a generator to keep
the continuity of the production. For diesel motor generators, we assumed used a
diesel not every time but at one month just used a diesel one time. The
specification of the generator is about 750kW. Based on those assumption, diesel
needed for Butanol Factory generator is equal to:
Table 2.10 Total fuel cost
Cost Type Quantities Price (USD) Total Price
Solar for genset 30 0.38 11.22
Total/month 11.22
Total/year (USD) 1 134.58
Total/year (IDR) 1,854,000.00
Universitas Indonesia
28
Water 4,623.98
Fuel 134.58
2.2 Maintenance
Maintenance can be defined as an activity to maintain condition of the
facilities or plant equipment and made repairs or replacement that necessary in
order to obtain a satisfactory state of production operations, as well as planned
before. Maintenance is required both for factories, offices, and supporting
equipment so it can be used continuously and optimal production quality can be
assured.
Maintenance process is performed with the three parts, i.e major
equipments maintenance, plant and office building maintenance, and supporting
equipment maintenance. Maintenance cost consists of cost for maintaining and
repairing equipment. It is usually takes 10% of total investment cost production
(Ir. Yuriadi Kusuma, M.Sc "Effective Maintenance Management"). This can be
calculated by:
𝑇𝐶𝐼
𝑀𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑐𝑜𝑠𝑡 = 10% 𝑥 (3)
𝑙𝑖𝑓𝑒𝑡𝑖𝑚𝑒
49,797,915
𝑀𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑐𝑜𝑠𝑡 = 0.1 𝑥 ( )
10
Universitas Indonesia
29
2.4 Insurance
For our plant, we use two types of insurance, there are insurance for
workers and insurance for plant. Based on the working safety insurance PP No 84
Year 2010, the amount of insurance given must be 1% from the worker salary. On
the other hand, the amount of building / plant insurance must be 5% from the
plant cost. The calculation of insurance cost can be seen from table below:
Table 2.12 Insurance Cost
Assurance
Percentag Price of Source
Insurance Source Total Price (USD)
e (USD)
Raw
2% Raw material 86,850,713.11 1,737,014.26
Material
Building and
Plant 1% 43,302,535.73 433,025.35
Equipment
Worker 4% Salary for worker 449,895.47 15,746.34
TOTAL of Insurance (USD) 2,185,785.95
TOTAL of Insurance (IDR) 30,111,387,236.86
Universitas Indonesia
30
Operational Cost
Type
Price (USD)
Raw Material 86,850,713
Direct Labor 143,728
Indirect Employee 306,167
Utilities 24,207
Maintenance 4,330,253
Assurance 2,185,786
Other Cost 497,979
Total Operational Cost
94,338,834
(USD)
Universitas Indonesia
31
OPEX
1.34%
0.28% 1.34%
2.77%
3.31%
1.30%
91.00%
Universitas Indonesia
3 CHAPTER 3
3 ECONOMIC EVALUATION
Where:
D : Presentage of loan in bank
E : Presentage of loan from investor
V : Total presentage
Kd : Value of loan interest from bank
Ke : Value of loan interest from Investor
Tm : Value of goverment interest
32 Universitas Indonesia
33
Net Profit
Cash All Gross Net Profit Cummulative
Sold Product OPEX Maintenance Depreciation Revenue Before Cash Flow
Year Expenses expenses Profit After Tax Cash Flow
Volume Price (USD) Cost (USD) (USD) (USD) Tax (USD)
(USD) (USD) (USD) (USD) (USD)
(USD)
Universitas Indonesia
34
Universitas Indonesia
35
Based on calculation, our WACC is 8.622%. For our capital cost we rent
from bank 60% with interest rent 12% and 40% from investor with interest rate
20%.
3.2.1 Equity
For our operational of cash flow, we don’t have any capital, so we rent
capital cost. we rent from bank 60% with interest rent 12% and 40% from investor
with interest rate 20%. We need USD 49,797,914.73. for our first capital. In
building factory, the most important factor that will be reviewed is whether the
plant is profitable or not. Owners can only invest a whole, but it would be very
risky if something happens when the factory is still in the active period. We
choosing Bank Rakyat Indonesia (BRI) for 10 years with interest 12% per year.
Table 3.3 Percentage of equity source
LOAN
Capital Source Interest Rate Capital Share (USD)
Bank 0.60 0.12 29,878,748.84
Investor 0.40 0.20 19,919,165.89
Universitas Indonesia
36
3.2.2 Depreciation
Depreciation is the reduction in value of an asset. The method used to
depreciation an asset is a way to account for the decreasing value of the asset to
the owner and to represent the diminishing value of capital funds invested in it.
Salvage value is the estimated trade-in or market value at the end of the asset’s
useful life. The salvage value, S expressed as an estimated dollar amount or as a
percentage of the first cost, may be positive, zero, or negative due to dismantling
and carry-away costs.
Universitas Indonesia
37
Now, we can make a list of our assets from late section. We have
equipment and building as our assets. The equation used in this declining balance
method of depreciation is: (Blank & Tarquin: 5th edition. Ch.16 Authored by Dr.
Don Smith, Texas A&M University):
𝑑𝑚𝑎𝑥 = 0,2
𝑑𝑡 = 𝑑𝑚𝑎𝑥 (1 − 𝑑𝑚𝑎𝑥 )𝑡 (5)
𝐵𝑉𝑡 = 𝐵𝑉𝑡−1 (1 − 𝑑𝑡 )𝑡−1 (6)
Where:
dmax = maximum depreciation rate
dt = depreciation rate for t-year
BVt = book value for t-year
t = year of depreciation
The depreciation rate is for main equipment, supporting and also building.
We have the assumption of 10% for main equipment and than 3% for supporting
and building this is according to main depreciation for national assets.
Table 3.7 Depreciation
No. of Year Depreciation (USD)
0 -
1 1,156,825.80
2 1,109,746.39
3 1,065,316.83
4 1,023,333.87
5 983,612.75
6 945,985.37
7 910,298.71
8 876,413.36
9 844,202.21
10 813,549.27
11 784,348.60
12 756,503.38
13 729,924.98
14 704,532.27
15 680,250.84
16 657,012.39
17 634,754.19
18 613,418.52
19 592,952.23
20 573,306.29
TOTAL 16,456,288.23
Universitas Indonesia
38
This depreciation each year leads to the salvage value. Salvage value is the
estimated resale value of an asset at the end of its useful life. After we end our
production we can get back the money from our assets which are called salvage
value. The salvage value counted in the table at Appendix for Depreciation cost.
From the calculation in Appendix Table, we can, at least, have salvage value
around USD 16,456,288.23 at the end of the plant life time.
90,000,000
80,000,000
70,000,000
60,000,000
50,000,000
NPBT
40,000,000
NPAT
30,000,000
20,000,000
10,000,000
-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
(10,000,000)
Figure 3.1 Net Profit Before Tax (NPBT) and Net Profit After Tax (NPAT) cash flow
From figure 3.1 we can se that out profit can be seen in 3rd year. For after
tax cash flow, this cash flow is calculated with tax. The income tax we assume is
25% after depreciation according to Direktorat Jenderal Pajak, 2013.Because it is
after tax, the cash flow will have the lower cumulative income; this after tax cash
flow is used for calculating the profitability analysis such as ROI, IRR, BEP, and
Payback Period. The calculations of after tax and before tax cash flow are shown
in the appendix.
Universitas Indonesia
39
Payback Period can also be seen from the plot the graph between the net
profit by the time (years), so we can obtain the payback period for this plant is
3.74 years.
Universitas Indonesia
40
The total fixed cost is the fixed cost values tend to be stable and not
influenced by the amount of production and the variable cost is the variable cost
of the value depends on the amount of goods produced. value depends on the
amount of goods produced.
In this case the BEP can be previously seen from the graph, Payback
Period occurs on 3.74 years when total production reached 5,040,240.61 unit sale
or 80% production sale. The BEP we get is $10,080,481.22. We can see table
below:
Table 3.8 Break even point
Year %production sale Unit sale
1 0.5 5,040,241
2 0.5 5,040,241
3.00 0.8 8,064,384.98
3.74 0.8 8,064,384.98
BEP 26,209,251.18
Universitas Indonesia
41
The IRR is the interest rate, also called the discount rate, which is required
to bring the net present value (NPV) to zero. That is, the interest rate that would
result in the present value of the capital investment, or cash outflow, being equal
to the value of the total returns over time, or cash inflow:
𝐶𝑡
𝑁𝑃𝑉 = ∑𝑇𝑡=1 (1+𝑟)𝑡 − 𝑇𝐶𝐼 = 0 (8)
By using Microsoft Excel, then we can obtain for the IRR of 40.21%
Hepatitis Vaccine Plant. Those facts give us a good impact, so that our plant and
product may be compared with other plant and also visible to be built.
Universitas Indonesia
42
As we can see from the table above, the selling price of Hepatitis B
Vaccine is very sensitive. The fluctuation by 5% higher or lower really impact the
IRR, payback period, and NPV.
Universitas Indonesia
43
From the table above, we can see the sensitivity of raw material. If the raw
material cost is increase about 5%, can effect are IRR will become lower, NPV
lower and PP longer.
Universitas Indonesia
44
The deviations of civil work cost not affect so much with the IRR, NPV,
and Payback Period. This is because the civil work is a cost in total capital
investment which is paid only once in a project of this plant, so the changes are
not too significant on existing cash flow.
60.00
50.00
40.00
IRR
0.00
-20% -10% 0% 10% 20%
Deviation
From the chart above that greatly affects the IRR is the selling product
price. It can be seen that the increase in the value of the product price causes a
Universitas Indonesia
45
very significant increase in the IRR. And if raw materials and civil work cost will
lead to increased salary decreases IRR.
6.00
5.00
4.00
PBP
0.00
-20% -15% -10% -5% 0% 5% 10% 15% 20%
Deviation
From the chart above to obtain a rapid payback period greatly affects the
product is the increase in the price of products. The higher a value of the product
price will accelerate the payback period. And other factors such as raw materials
and civil work cost to improve the salary if it will add value payback time period.
600,000,000.00
500,000,000.00
400,000,000.00
NPV
0.00
-20% -10% 0% 10% 20%
Deviation
Universitas Indonesia
46
From the graph above the product price is an important factor, because the
increasing value of the product price will change into a higher NPV while other
factors are raw materials and civil work cost.
3.4.5 Strategy
With the sensitivity analysis above we can conclude is the most sensitive
and can make IRR, Payback Period, and NPV change is selling price of Hepatitis
Vaccine. The raw material less sensitive than selling price of product because the
portion of our operating cost and TCI that is civil work cost is almost the same for
each component and not significant give differences of IRR, PP, and NPV. Selling
price of Hepatitis Vaccine is very sensitive because it can affect the IRR below
the MARR so that can affect how many investor that will invest their money in
our plant. Therefore we have some strategy to the sensitivity of selling price. The
strategies are we maintain the selling price 10% higher than it’s original price due
to the sensitivity. It is very possible to do because vaccine plant in Indonesia is
very limited and many are not recognized by BPOM, as well as the needs of
hepatitis B vaccine in Indonesia and foreign is very high. If we have to decrease
our selling price because of unpredicted things happens maybe inflation. We can
reduce our production capacity so our plant is still profitable
Universitas Indonesia
4 CHAPTER 4
5 CONCLUSION
In this section we will conclude all of the report for economic analysis of
our plant. The result of that analysis is listed below:
1. The total capital investment (CAPEX) for our plant is $49,797,914.73.
2. Operational cost of our company is $94,338,834.44.
3. The price of Hepatitis B vaccine is $18.00 per vial.
4. To fulfil the need of starting capital, we are given loan by BRI and
investor with the ratio of 6:4, with period of instalment payment 10 years.
5. We calculate every cost needed and predicting the profitability to make
cash flow before tax and cash flow after tax.
6. ROI for our company is 183.10%.
7. The payback period of our company is 3.74 year, which is considered as a
very fast payback period.
8. The BEP of our company is 80% production sale, in another word we have
to sell 26,209,254.18 unit sale until we start to gain profit.
9. IRR of our company is 40.21%, which is considered high and highly
appealing for investors.
10. The calculation of NPV, or Net Present value of our product with MARR
of 8.622% results with $547,794,059.22.
11. The sensitivity analysis shows that Hepatitis B vaccine product is most
sensitive for the value of selling price.
12. From the economic research, we can conclude our company worth it to be
implemented.
47 Universitas Indonesia
6 REFERENCES
Blank & Tarquin. 5th edition. Ch.16 Authored by Dr. Don Smith, Texas A&M
University
Branan, Carl. 2002. Rules of Thumb For Chemical Engineers. Houston : ElSevier.
Brownell, Lloyd E and Edwin H. Young. 1959. Process Equipment Design. John
Wiley & Sons, inc.
Cheremisinoff , Nicholas P. 2000. Handbook of Chemical Processing Equipment.
Butterworth-Heinemann.
Coulson & Richardson. 1983. Chemical Engineering Design. Oxford : El-Sevier.
Chemical And Process Design Handbook. New York : McGraw-Hill.
Perry, Robert H. 1999. Perry’s Chemical Engineers’ Handbook. McGraw-Hill
Companies, Inc.
Seider, W. D., Seader, J. D. & Lewin, D. R. 2003. Product and Process Design
Principles, John Wiley and Sons, Inc.
Sinnott, R. K. 2005. Chemical Engineering Design 4th edition. Elsevier.
Wallas, Stanley M. 1988. Chemical Process Equipment Selection and Design.
Butterworth-Heinemann
48 Universitas Indonesia