Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Index Terms—34 node test feeder, quasi-static time-series Section II describes the development and implementation of
analysis, power flow, voltage regulator operation simulation, PV the proposed quasi-static time-series test feeder. Example
integration, distribution system impacts. analyses for 1MW single-site utility scale PV system
integration, based on the simulation of the quasi-static time-
I. INTRODUCTION series test feeder, are presented in Sec. III. Section IV
The increasing number and size of photovoltaic (PV) systems concludes the paper.
either being interconnected or requesting interconnection at
the distribution system level has resulted in an increased II. THE QUASI-STATIC TIME-SERIES TEST FEEDER BASED ON
interest in distribution system modeling for use in determining THE IEEE 34 NODE TEST FEEDER
the impacts of such PV integrations. Accordingly, many
distribution system modeling professionals have begun to A. General requirements for quasi-static time series power
develop the appropriate modeling tools to evaluate and flow simulations
quantify these impacts. One of the tools of most interest Quasi-static time-series analysis is essentially a sequential
currently is the ability to investigate the operational series of discrete power flow solutions. “Quasi-static” refers
characteristics of a modeled distribution system and an to the concept that a static steady-state power flow solution is
interconnected PV system over a set time period (typically a being used to evaluate an inherently dynamic, i.e. non-steady-
day or a year in simulation length). This type of analysis, state, system. Typically, if the system is changing slowly
called quasi-static time-series analysis as defined in [1], is compared to the discrete time interval between quasi-static
typically used to evaluate the low frequency dynamics of a power flow solutions the low frequency dynamics of the
distribution system. In terms of PV interconnection studies a system are well represented in the quasi-static time-series
analysis. For distribution system modeling this means that the
accuracy of a quasi-static time-series analysis will depend on
Barry A. Mather is with the Distributed Energy Systems Integration the time period between steady-state power flow solutions and
(DESI) Group at the National Renewable Energy Laboratory (NREL), the settling time of the system after a dynamic event that is
Golden, CO 80401 USA (e-mail: barry.mather@nrel.gov).
desired to be evaluated in the analysis. “Time-series” refers to
the causal time dependence of the next steady-state power The voltage regulators specified in the 34 node test feeder
flow solution to the system state determined by the last have well defined regulator control set points provided. These
steady-state power flow solution. include the voltage regulation bandwidth, regulating voltage
level, and line compensation values R and X. The PT ratio and
For the development of a quasi-static time-series PV primary CT rating are also given for completeness. It was not
integration test feeder the operational characteristics that were indicated whether the voltage regulators were reversible. For
of interest were the operation of the voltage regulation PV integration analysis the reversibility of the voltage
devices. In distribution systems such devices are typically regulators will be one of the many important factors to
controlled using low bandwidth controllers that often have consider when using the quasi-static time-series feeder.
time delay lockouts to disable device operation for a fixed
C. Load profiles and feeder load allocation
period of time following a change in device state. These time
delays are often in the range of 30s to 2 min. A simulation Since the goal of a quasi-static time-series analysis is to
time period of 1 min was chosen for the development of this investigate or evaluate the operation of the distribution system
quasi-static time-series test feeder based on the compromise over a period of time it is important that the distribution
between the time delay operational characteristics of typical system loading be as realistic as possible. Unfortunately, the
voltage regulation devices and the available load and solar 34 node test feeder has only static loading specified. This
resource data discussed in Secs. II.C and II.D. Both datasets loading data was assumed to be the peak load for each load
are developed for the year 2010. point on the system as would typically be used in basic
B. IEEE 34 Node Test Feeder Characteristics planning power flow studies.
Figure 1 shows a single line diagram of the 34 node test
Four hourly load profiles based on load research statistics
feeder as described in [2]. Individual nodes are denoted by
containing 8,760 data points per year were utilized for the
number starting with 800 at the substation bus bar connection.
development of the quasi-static time-series test feeder. They
This 24kV test feeder is very long, with a maximum line
length to the substation from node 848 of nearly 36 miles, and are available online from Southern California Edison [8]. The
is lightly-loaded. The circuit includes two voltage line four load profiles used include domestic (DOM), commercial
regulators connected between nodes 814-850 and 852-832 (COM), industrial (IND) and street lighting (SL). Table I
respectively. To static capacitors are also connected to the shows the 2010 static load profiles used for the four load
feeder at nodes 844 and 848 with ratings of 100kVAr/phase classes integrated into the quasi-static time-series test feeder.
and 150kVAr/phase respectively. As the targeted quasi-static time-series simulation step time
822 was 1 min (525,600 data points/solutions per year) the load
profiles were resampled at 1 min intervals with simple linear
820
interpolation applied between the hourly data points. The use
818 826 of load profiles based on hourly load research statistics is not
800 Reg #1
802 806 808 812 814 850
optimal as the resulting circuit is not as variable as would be
816
824 expected from actual circuit measurements. Additional
810 828
random variation on top of the resulting load profiles was
considered but as the load profiles solely represent the
864
830 averaged load profile of a statistically significant number of
Reg #2
840 836 860 834 832 852 customers from the same rate class (as they are derived from
854
858 load research statistic data) it is difficult to justify such
862 842 888 856 variation without assuming some number of customers behind
each load point. Alternatively, the approach was taken that
838 844 890 assumed each load point in the 34 node test feeder served a
statistically significant number of customers and that these
846
customers were all of the same rate class. Such assumptions
848 were required since no additional information on the actual
loading characteristics of the 34 node test feeder is publically
Fig. 1. Single line diagram of the IEEE 34 node test feeder showing the available. As better load models become publically available
location of the two voltage regulators and two shunt capacitors. they should be incorporated into the proposed quasi-static
time-series test feeder for a more realistic simulation of the
The bus voltage at node 800 is 1.05pu for all three phases modeled distribution circuit. As currently implemented and
possibly suggesting that the substation contains a load tap proposed test feeder does allow the relative evaluation of the
changer (LTC) for regulating substation bus voltage. Such an
primary impacts of PV integration but does under represent
LTC is not defined in the original 34 node test feeder and has
the effects of higher frequency load variations.
not been added to the proposed quasi-static time-series test
feeder.
3
TABLE II
LOAD PROFILE DATA SOURCES AND DESCRIPTIONS
Spot Loads
Node Balanced kVA Load Allocation
860 Y 108 IND
840 Y 48 IND
844 Y 720 IND
848 Y 108 IND
890 Y 675 IND
830 N 65 DOM
Distributed Loads
Nodes Balanced kVA Load Allocation
802-806 N 84 DOM
808-810 N 24 DOM
818-820 N 51 DOM
820-822 N 205 COM
Fig. 2. Flow chart showing the load allocation algorithm used for each spot
816-824 N 7 SL
and distributed load in the 34 node test feeder in order to associate loads with 824-826 N 60 DOM
load profiles. 824-828 N 6 SL
828-830 N 10 SL
The resulting load allocation for the quasi-static time-series 854-856 N 6 SL
test feeder is shown in Table II. It is important to note that the 832-858 N 22 DOM
858-864 N 3 SL
load model (Δ or Y and Z, I, or PQ) associated with each spot
858-834 N 49 DOM
and distributed load was not modified from the 34 node test 834-860 N 219 COM
feeder and was not considered as part of the load allocation 860-836 N 125 DOM
algorithm. It should be noted that the IEEE 34 node test 836-840 N 60 DOM
feeder does not model distribution transformers or the 862-838 N 42 DOM
secondary distribution circuit connecting customers to the test 842-844 N 14 DOM
feeder. All loads are lumped by phase and referred to the 844-846 N 68 DOM
primary circuit voltage. The potential impacts on the 846-848 N 34 DOM
secondary circuit due to the integration of PV onto the
4
and this voltage is present at node 814 otherwise identified as base case. The maximum voltage, again discounting the
the primary side of voltage regulator #1. The maximum yearly voltages seen near the substation, for the day is 1.0489 pu and
voltage, again ignoring nodes near the substation, is 1.0496 is located at the point of interconnection of the modeled 1MW
pu. This maximum voltage is seen at the output of voltage PV system. Inspecting the yearly dataset the minimum
regulator #2. voltages seen on the feeder are 0.9728 pu and 0.9764 pu for
the primary input nodes for voltage regulators #1 and #2
respectively. The maximum voltages seen are 1.0748 pu and
1.15 1.0517 pu again for the primary input to voltage regulators #1
Vpu,max
and #2 respectively.
Vpu,avg
1.1 Vpu,min The results of this example feeder voltage profile analysis
mirror the common expectations and concerns of PV
integrations at a considerable distance from a substation.
Voltage
Voltage
1
No PV 1MW PV at 840
Node φA φB φC φA φB φC
test feeder. The simulated voltage regulator tap positions may line compensation disabled. A small improvement in the
vary depending on initial circuit conditions and the number of tap operations was observed but the feeder voltage
distribution system analysis software used for the regulation may have been adversely affected. The number of
implementation of the quasi-static time-series test feeder. In voltage regulator tap operations shown in Table V can be used
order to better compare circuit simulation solutions the tap to compare alternate implementations of the proposed quasi-
positions that result in the voltage profiles presented in Table static time-series test feeder using various distribution system
III are given in Table IV. analysis software packages.
TABLE IV
VOLTAGE REGULATOR TAP POSITIONS ON JUNE, 16TH, 2010 AT 12:15PM FOR
500
0
0 6 12 18 24
Time of Day (hour)
TABLE V Figure 6 shows the daily PV system power output and the
TOTAL NUMBER OF VOLTAGE REGULATOR TAP CHANGE OPERATIONS FOR 2010 voltage regulator #1 and #2 tap positions for Wednesday, June
FOR VARIOUS PV DEPLOYMENT AND VOLTAGE REGULATION COMPENSATION
CASES
16th, 2010. The position of the voltage regulator taps are
shown for all three phases. The PV system power output
profile shows a day that is mostly clear during the morning
hours with thick intermittent clouds appearing in the
afternoon. The voltage regulator tap positions and movements
show the efforts expended by the voltage regulators to
accommodate for the variability of the interconnected 1MW
PV system that is interconnected at node 840.
Figure 7 shows the same data as Figure 6 but for only for the
hours of 10:00 a.m.—1:00 p.m. for a closer look at the voltage
regulator tap positions and movements during periods of high
solar resource variability. Plots like those shown in Figures 7
and 8 can be used to determine voltage regulator operations
7
500 N
op,A
1500 N
16 0
φ
A
8 φ 0 10 20 30
B
φ
Distance from Substation (mi)
0 C
Fig. 8. Percent tap operation increase for regulator #1 for the interconnection
-8 of a 1MW PV system along the length of the main 3-phase trunk of the 34
node test feeder (from 800 to 840) with standard regulator R+jX
-16 compensation.
10 11 12 13
Time of Day (hour)
Regulator #2 Tap Pos. (N)
16
φ
A
500 N
8 φ op,A
B
N
Percent Reg. Op. Increase
φ op,B
0 C
400 N
op,C
-8
300
-16
10 11 12 13
Time of Day (hour) 200
Fig. 7. Top: Modeled PV system power output for 10:00 a.m.—1:00 p.m.,
Wednesday, June 16th, 2010 for a 1MW system whose PV inverter(s) saturate 100
at an array irradiance of 1200W/m2. Middle: Voltage regulator # 1 tap position
and movement for the case when a 1MW PV system modeled in the top figure
is interconnected at node 840 (end of the line). Bottom: Voltage regulator #2
0
tap position and movement for the case described above.
0 10 20 30
Distance from Substation (mi)
The results of additional PV integration analysis using the Fig. 9. Percent tap operation increase for regulator #2 for the interconnection
quasi-static time-series test feeder are presented in Figs. 8 and of a 1MW PV system along the length of the main 3-phase trunk of the 34
9. These figures show the percent increase of the voltage node test feeder (from 800 to 840) with standard regulator R+jX
compensation.
regulator tap operations for the possible integration of a 1MW
PV system at any node along the main 3-phase feeder line cost of reduced voltage regulation capability along the feeder.
from node 800 to node 840. The modeled 1MW PV system’s Still, the example analysis shows the kinds of analyses that
inverter(s) saturate at a GHI of 1200W/m2. Figure 8 shows the can be investigated using the proposed quasi-static time-series
effect of integrating the 1MW PV system along the line for test feeder.
voltage regulator #1 and Fig. 9 shows the same for voltage
regulator #2. IV. CONCLUSIONS
This example analysis shows some interesting results as to the This paper presents a quasi-static time-series test feeder based
effect of PV system placement on the test feeder. Not only is it on the well-known 34 node test feeder. This test feeder has
apparent that locating the PV system near the substation specifically been developed to evaluate and quantify the
results in fewer voltage regulator operations but also that distribution system impacts of distributed PV integrations.
locating the PV system on the primary side of the voltage The load profiles and solar resource profiles used are both
regulator, as opposed to the secondary, if connection near the publically available. The quasi-static time-series test feeder
voltage regulator is required may also reduce voltage regulator has been developed using 2010 data and has a discrete solving
operations. Further analysis of this finding is required as such time period of 1 min between power flow solutions. This
a reduction in voltage regulator tap operations my come at the results in a total of 525,600 power flow solutions per year. A
8