51491

China : Liaoning Medium Cities Infrastructure Project (P 099992)


Procurement Plan (November 2009)

I. General

1. Project information:
Country: China
Borrower: People’s Republic of China
Project Name: Liaoning Medium Cities Infrastructure Project
Project ID: P 0099992
Project Implementing Agency (PIA):
Liaoning Urban Construction and Renewal Project Office (LUCRPO) will coordinate
and supervise all procurement activities. The PIAs for each project component are
described as follows:
No. Project Sub-component PIA
1 Jinzhou Sub-component Project Management Office (PMO) under
the Municipal Urban Construction
Committee (MUCC)
2 Liaoyang Sub-component PMO under the MUCC
3 Benxi Sub-component PMO under the MUCC
4 Fushun Sub-component PMO under the MUCC
5 Panjin Sub-component PMO under the Municipal Urban
Construction Bureau
6 Dengta Sub-component PMO under the Dengta Public Utility
Management Bureau

2. Bank’s approval Date of the procurement Plan: November, 2009


3. Date of General Procurement Notice: April 6, 2006
4. Period covered by this procurement plan: November 2009-December 2010

II. Goods and Works and non-consulting services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as
stated in Appendix 1 to the Guidelines for Procurement:
Prior Review Thresholds Proposed (USD)

Goods ≥ 0.5 million


Works ≥ 5 million

2. Prequalification: Not applied.


3. Any Other Special Procurement Arrangements: Not applied in 2009-2010.
4. Procurement Packages with Methods and Time Schedule
[List the Packages which require Bank’s prior review first and then the other packages]

1 2 3 4 5 6 7 8 9 10
Review Estimated
Estimated Cost Procure Prequalifi Domestic Expected
Contract by Bank Construction
Ref. No. ment Category cation Preference Bid-Opening
(Description) (Million (Million (Prior / Period
Method (yes/no) (yes/no) Date
RMB) USD) Post) (months)
Benxi
BPT21 Bus stop signs & Bus Shelters 10.81 1.58 ICB Goods (G) NO NO Prior March 1,2010 12
Traffic Signals Maintenance Car,
BTM21 3.64 0.53 ICB Goods (G) NO NO Prior Dec. 10,2009 6
Wireless communication system
ATC and signals, CCTV and cables,
BTM22 17.88 2.62 ICB G NO NO Prior Feb 1,2010 12
RLR system, TG system
BRM21-1 Milling Machine(2m) 1set 3.00 0.44 ICB G NO NO Prior Dec.20,2009 6
BRM21-2 9m Asphalt Paver 1set 3.00 0.44 ICB G NO NO Prior Dec.20 ,2009 6
Double Drum Vibrating Dec.20 , 2009
BRM21-3 Roller(12T)1 set, Roller(2T)1 set, 2.15 0.31 ICB G NO NO Prior 6
Single Drum Roller(18T)1 set
Sewer Scavenger Cleaning Machine Dec.20 ,2009
BRM21-4 1 set, Backhoe Loader 1 set, 3.27 0.48 ICB G NO NO Prior 6
Underground Piping Detector 1 set
Large Scale Transport Vehicle 4 sets, Dec.20 ,2009
Diesel/Liquid Transport Vehicle 1
BRM21-5 set, Silt-Clearing Vehicle with Grab 2.13 0.31 ICB G NO NO Prior 6
Bucket 1 set,
Road Profiler 1 set
Railway Station Bus Terminal,
BPT11 6.62 0.97 NCB CW NO NO Post Jan. 20, 2010 12
Jiefang Rd bus priority
BRI13 Beidi Bridge 130.00 19.03 NCB CW NO NO Prior Dec. 30,2009 18
Xihu Road Houhu Section, Jiefang 2
BRI14 35.13 5.14 NCB CW NO NO Prior May 1, 2010 12
Road, Xincheng road North Section
BRI15 Digong Road 24.30 3.56 NCB CW NO NO Post Dec 20,2009 12
BRM15 Binhe nan road 31.43 4.60 NCB CW NO NO Prior July 1, 2009 12
BRM16 Yuming Road, Caitun Road 72.58 10.63 NCB CW NO NO Prior Aug 18, 2009 12
Dengta
DRM21-1 Milling Machine 2.2 M 1Set 3.50 0.51 ICB G NO NO Prior Dec.20 ,2009 6
DRM21-2 9m Asphalt Paver 1set 2.50 0.37 ICB G NO NO Prior Dec.20 ,2009 6
Fushun
Traffic Signal Control System,
FTM21 14.66 2.15 ICB G NO NO Prior Mar. 30,2010 12
LED, 16 CCTV, RLR system
10 Traffic Patrol Vehicles,
6 Accident Investigation Vehicles,
Traffic Control Data System
FTM22-1 Vehicle, Road Safety Propaganda 5.65 0.83 ICB G NO NO Prior Dec.10,2009 6
Vehicle, 2 Signal Repair and
Maintenance Vehicles, 14 MV
Speed Monitor Devices
300 Wireless Electronic
FTM22-2 Communication Systems, Solar- 1.4 0.20 ICB G NO NO Prior Dec.10 ,2009 6
warning lights
FRM21 Mud-sucking truck 1.8 0.26 ICB G NO NO Prior Dec.20 ,2009 6
Traffic Management facilities
FTM11 32.04 4.69 NCB CW NO NO Post Jan. 30, 2010 12
(signs ,marking , signals)
Jinzhou
Traffic signals maintenance car,
JTM21 CCTV and cables, RLR system, 11.01 1.61 ICB G NO NO Prior May, 2010 12
GD System, Information Screen
JTM22 ATC and signals 15.43 2.26 ICB G NO NO Prior May, 2010 12
W1900 Milling Machine 2M,
JRM21-1 4.95 0.72 ICB G NO NO Prior
W35DC Milling Machine 0.5M
JRM21-2 Paver 9M 3.00 0.44 ICB G NO NO Prior
2 Double Drum Rollers (12.5-
JRM21-3 13T)DH120, 2 Rollers, Hand 2.52 0.37 ICB G NO NO Prior
Push Drum Roller
3 Single Drum Rollers (18T), 3
JRM21-4 Silt-Clearing Vehicle with Grab 4.58 0.67 ICB G NO NO Prior
Bucket, Road Profiler (180hp)
Wheeled Excavator 0.8M3, Dec.20 ,2009 6
5 Water Sprayer Vehicals,
3 Maintenance Vehicles,
5 Dump Trucks, 4 Wheel Loaders,
JRM21-5 6.22 0.91 ICB G NO NO Prior
Truck Crane 8T, Trailer-mounted
Falling Weight Deflectometer
(FWD),
3Lights Maintenance Vehicles
12 Lawn mowers, 15 Hedge
JRM21-6 machines, 15 Irrigators, 0.15 0.02 ICB G NO NO Prior
5 Chemical Sprayers
Fuzhou Street Bus Terminal,
Railway Station Bus Terminal,
Limin Street Bus Priority, Aimin
JPT11 6.57 0.96 NCB CW NO NO Post March, 2010 18
Street Bus Priority, Luoyang
Road Bus Priority, Shiying Road
Bus Priority
Shengli Bus Terminal, Xinzhi
JPT12 Street Bus Interchange, Nanshan 2.70 0.40 NCB CW NO NO Post March, 2010 10
Bus Interchange

JRI18 Zhongyang Street, Zhongyang 63.63 9.32 NCB CW NO NO Prior March, 2010 12
North Street, Jinxing Road
JRI16 Guangzhou Street Railway Bridge 69.10 10.12 NCB CW NO NO Prior Jan.30, 2010 18
JRI17 Jiefang Road, Yunfei Street 81.92 11.99 NCB CW NO NO Prior Jan, 2010 18
JRM18 Shifu Road, Shifu West Road 6.01 0.88 NCB CW NO NO Post March, 2010 10
JRM19 Mingde Street 6.19 0.91 NCB CW NO NO Post March, 2010 10
Beian Road, Beizhen Road, Anda
Street, Taifeng Road, Hubei Road,
Jingdong Street, Weidong Street,
Fukang Road, Jinyuan Road,
JRM15 51.05 7.47 NCB CW NO NO Prior March, 2010 12
Hechun Road, Zhaodong Street,
Kuanggong Street, Jinxi Street,
Jiangxi Street, Zhonghuan south
Road
Liaoyang
CCTV and cables, Command Centre
LTM21 Upgrading, GD system, ATC and 15.00 2.20 ICB G NO NO Prior May, 2010 12
signals
LRM21-1 (9m) Paver, 3.00 0.44 ICB G NO NO Prior Dec.20 ,2009 6
LRM21-2 Roller(13T) 1.50 0.22 ICB G NO NO Prior Dec.20 ,2009 6
Unconfined Compression Strength
Testing System, Asphalt Concrete
Pavement Density Measuring
System, Hand Hold FWD,
LRM21-3 0.82 0.12 ICB G NO NO Prior Dec.20 ,2009 6
Dynamic Variable Energy Sounding
Instrument,
Gasoline Powered Coring Machine,
Soil Density Gauge
LRM21-4 Falling Weight Deflectometer 1.42 0.21 ICB G NO NO Prior Dec.20 ,2009 6
LPT11 Minzhu Road bus priority 17.10 2.50 NCB CW NO NO Post Nov, 2009 12
LPT12 Liaohua Bus parking lots 3.00 0.44 NCB CW NO NO Post March, 2010 12
Dongxing Road South Section,
LRI16 Sanli Street East Section, Sanli 29.30 4.29 NCB CW NO NO Post Nov, 2009 12
Street West Section, Nanchun Road
Zhongxin road, Beixin street,
LRI17 10.45 1.53 NCB CW NO NO Post March, 2010 12
Dongxing road
LRI19 Beigong Street, 10.50 1.55 NCB CW NO NO Post March, 2010 12
LRI20 Wudao Street, Liudao street 11.67 1.71 NCB CW NO NO Post March, 2010 12
LRM13 Xinyun Street, Wensheng Road 36.18 5.30 NCB CW NO NO Prior Nov, 2009 12
Panjin
PPT21 Bus IC card 10.36 1.52 ICB G NO NO Prior May, 2010 12
PPT22 112 Buses 60.0 8.82 ICB G NO NO Prior Dec.25 ,2009 6
ATC and signals, RLR system,
PTM21 45.81 6.71 ICB G NO NO Prior March, 2010 12
CCTV
Command Centre Integrated
Platform, Command Centre and
Computer Room, Wireless
Intercom Command System,
PTM22 Command Centre Upgrading, GD 35.22 5.16 ICB G NO NO Prior March, 2010 12
System, Urban entrance-exit
management system, 122 police
system, Traffic flow monitoring
system
4 Command Vehicles, 3 Traffic
PTM23 Trucks, GPS, 2 Rescue Vehicles, 10.56 1.55 ICB G NO NO Prior March, 2010 6
Mobile police system
PTM24 Guardrail 5.00 0.73 ICB G NO NO Prior March, 2010 6
PRM21-1 1 milling machine(2m) 3.40 0.50 ICB G NO NO Prior Jan.20, 2010 6
Asphalt pavers(9m), Jan.20, 2010
PRM21-2 7.20 1.05 ICB G NO NO Prior 6
2 Asphalt pavers(12m)
4 Vibrating Rollers(12t) Jan.20, 2010
PRM21-3 3.96 0.58 ICB G NO NO Prior 6
2 Rollers (2.5t)
Asphalt mixing station(model Jan.20, 2010
PRM21-4 9.50 1.39 ICB G NO NO Prior 6
3000)
2 sewer vacuum cleaning Jan.20, 2010
machines, 2 Backhoe Loaders, 1
multifunctional maintenance
vehicle, 1cherry picker truck(18t),
2 water spray trucks(20t),
PRM21-5 13.88 2.03 ICB G NO NO Prior 6
10dump trucks, 1 crane(25t),
2 wheeled bulldozers, 2 plate
rammers, 4 Small-size Cutting
Machine, 2 wheeled loaders,
2Non-contact equalizer bars
PRM22 1 cold recycling machine, 16 2.34 ICB G NO NO Prior May, 2010 6
1 Synchronization slurry seal
truck, 5 Snow-cleaning Vehicles,
3 Water Sprayers,2 Asphalt Oil
sprayers
III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated
in Appendix 1 to the Guidelines Selection and Employment of Consultants:
Prior Review Thresholds Proposed (USD)

Consulting Service ≥0.2 million for firm, ≥0.05 million for individuals, all SSS

2. Short list comprising entirely of national consultants: Short list of consultants for
services, estimated to cost less than US$ 300,000 or equivalent per contract, may
comprise entirely of national consultants in accordance with the provisions of paragraph
2.7 of the Consultant Guidelines.
3. Any Other Special Selection Arrangements: No.

4. Consultancy Assignments with Selection Methods and Time Schedule

1 2 3 4 5 6 7

Ref. No. Description of Estimated Selection Review Expected Comments


Assignment Cost (USD) Method by Bank Proposals
(Prior / Submission
Post) Date
LUCRPO
IDTS1 Enforcement of 300,000 QCBS Prior May 1, 2010
traffic
Management
training & study
tour
IDRI2 Transport 250,000 QCBS Prior May 1, 2010
Planning
IDRM1 Road 120,000 CQS Post May 1, 2010
maintenance
training & study
tour
IDPT1 Bus Priority 140,000 CQS Post May 1, 2010
training & study
tour