Sei sulla pagina 1di 1

METBUILD SDN. BHD. (formerly known as Metropolitan Estate Sdn. Bhd.

) (948986-K)

metbuild No. 9, Jln 51A/223, Section 52,46100 Petaling Jaya


T| +603-7960 3628
E| admin@metbuild.com.my
F| +603 -7960 7833

TOWER CRANE CHECKLIST


Crane Location Model Number Serial Number Date
/ / 20
Operator / Inspector Contractor / Project

Check all item indicated. Inspect as indicated and note condition.


S = Satisfactory U = Unsatisfactory N/A = Not Applicable
Preliminary S U N/A Upper / Machinery S U N/A
Foundation/Anchors (Visual) Unusual Noise
Tower Bolts (Random Check) Reeving
Ladders  Hoist
Landings  Trolley
Lacings  Luffing
Tie-ins Brakes
Gearbox Leaks  Hoist
Reeving  Trolley
Hook  Luffing
Hook Block Lubrication
Operational S U N/A  Ropes
Horn  Sheaves
E-stop  Slewing Gear
Wind Speed Indicator Drive attachments
Radius Indicator Lights
Load Indicator
Hoisting
 Up Slowdown Limit Remarks:
 Up Final Limit
 Down Final Limit
Trolley
 In Final Limit
 In Slowdown Limit
 Out Slowdown Limit
 Out Final Limit
Luffing Comments:
 Up Final Limit
 Up Slowdown Limit
 Down Slowdown Limit
 Down Final Limit
Slewing
 Left Limit
 Right Limit
Operator’s Signature Supervisor’s Signature

Any “unsatisfactory” condition should be reported to the supervisor and the servicing authority immediately. Crane operations
should cease until all “unsatisfactory” conditions have been resolved. Once any repairs have been made, all systems should be
checked for proper functionality.