This document provides a schedule for engineering activities related to Modules MM1 and MM2 for an FPSO development project in Ghana. It lists key engineering milestones and deliverables from March 2015 through April 2016, including commencement of basic and detailed engineering, HAZID and HAZOP reviews, 3D modeling reviews at 30%, 60%, and 90% completion, and fabrication and load-out of Module MM1. The schedule outlines engineering tasks for areas like general project management, detailed engineering plans and procedures, and process and systems work from March 2015 through June 2015 to support fabrication and installation of the modules.
This document provides a schedule for engineering activities related to Modules MM1 and MM2 for an FPSO development project in Ghana. It lists key engineering milestones and deliverables from March 2015 through April 2016, including commencement of basic and detailed engineering, HAZID and HAZOP reviews, 3D modeling reviews at 30%, 60%, and 90% completion, and fabrication and load-out of Module MM1. The schedule outlines engineering tasks for areas like general project management, detailed engineering plans and procedures, and process and systems work from March 2015 through June 2015 to support fabrication and installation of the modules.
This document provides a schedule for engineering activities related to Modules MM1 and MM2 for an FPSO development project in Ghana. It lists key engineering milestones and deliverables from March 2015 through April 2016, including commencement of basic and detailed engineering, HAZID and HAZOP reviews, 3D modeling reviews at 30%, 60%, and 90% completion, and fabrication and load-out of Module MM1. The schedule outlines engineering tasks for areas like general project management, detailed engineering plans and procedures, and process and systems work from March 2015 through June 2015 to support fabrication and installation of the modules.
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3 Actual Work Milestone Remaining Work Summary Page 66 of 72 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Activity ID Activity Name Original Start Finish 2015 2016 Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun MM2-1305-PT-00-R-CA-00005-1 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IDC 25 20-Mar-15* 17-Apr-15 MM2-1305-PT-00-R-CA-00005-2 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFR 7 18-Apr-15 25-Apr-15 MM2-1305-PT-00-R-CA-00005-3 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFD 0 27-Apr-15 27-Apr-15 MM2-1305-PT-00-R-CA-00005-4 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFC 27 27-Apr-15 30-May-15 MM2-1305-PT-00-R-CA-00006 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL00759 20-Mar-15 30-May-15 MM2-1305-PT-00-R-CA-00006-1 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IDC 25 20-Mar-15* 17-Apr-15 MM2-1305-PT-00-R-CA-00006-2 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFR 7 18-Apr-15 25-Apr-15 MM2-1305-PT-00-R-CA-00006-3 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFD 0 27-Apr-15 27-Apr-15 MM2-1305-PT-00-R-CA-00006-4 MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFC 27 27-Apr-15 30-May-15 MM2-14440 TR/MTO for Pig Receivers (Q.O.C) 1 07-May-15 07-May-15 MM2-14460 Prepare / Submit/ Approve Mechanical Shop Drawings 84 09-Oct-15 15-Jan-16 0.D.26.0000.MM2.C Procurement 314 08-Apr-15 15-Feb-16 0.D.26.0000.MM2.C.N Structural 293 08-Apr-15 25-Jan-16 0.D.26.0000.MM2.C.N.92 PTSC 293 08-Apr-15 25-Jan-16 MM2-11180 RFQ/TBE/CBE/PO for Primary & Secondary Steel 39 08-Apr-15 16-May-15 MM2-11440 Delivery for Primary & Secondary Steel 119 17-May-15 12-Sep-15 MM2-11720 RFQ/TBE/CBE/PO for Tertiary Steel 35 10-Jun-15 14-Jul-15 MM2-11960 Delivery for Tertiary Steel 91 15-Jul-15 13-Oct-15 MM2-12180 RFQ/TBE/CBE/PO for Structural Miscellaneous 37 29-Jul-15 03-Sep-15 MM2-12400 Delivery for Structural Miscellaneous 77 04-Sep-15 19-Nov-15 MM2-12540 RFQ/TBE/CBE/PO for Gratings 37 10-Aug-15 15-Sep-15 MM2-12640 Delivery for Gratings 91 16-Sep-15 15-Dec-15 MM2-12720 RFQ/TBE/CBE/PO for SF and Grillage Material 37 11-Oct-15 16-Nov-15 MM2-12800 Delivery for SF and Grillage Material 70 17-Nov-15 25-Jan-16 0.D.26.0000.MM2.C.L Piping 311 11-Apr-15 15-Feb-16 0.D.26.0000.MM2.C.L.92 PTSC 311 11-Apr-15 15-Feb-16 MM2-10700 RFQ/TBE/CBE/PO for Piping Bulk 46 11-Apr-15 26-May-15 MM2-10940 Delivery for Piping Bulk 127 27-May-15 30-Sep-15 MM2-11200 RFQ/TBE/CBE/PO for Manual valves 58 30-Apr-15 26-Jun-15 MM2-11460 Delivery for Manual valves 182 27-Jun-15 25-Dec-15 MM2-11740 RFQ/TBE/CBE/PO for Barred Tee 47 29-Apr-15 14-Jun-15 MM2-11980 Delivery for Barred Tee 176 15-Jun-15 07-Dec-15 MM2-12200 RFQ/TBE/CBE/PO for Cuni fittings 53 09-May-15 30-Jun-15 MM2-12420 Delivery for Cuni fittings 108 01-Jul-15 16-Oct-15 MM2-12560 RFQ/TBE/CBE/PO for Corrosion, sand probe, sample connection, chemical connection… 41 19-May-15I 28-Jun-15 MM2-12660 Delivery for Corrosion, sand probe, sample connection, chemical connection131 29-Jun-15 06-Nov-15 MM2-12740 RFQ/TBE/CBE/PO for 3D Bend (free bare pipe to bending contractor) 48 31-May-15 17-Jul-15 MM2-12820 Delivery for 3D Bend (free bare pipe to bending contractor) 213 18-Jul-15 15-Feb-16 MM2-12860 RFQ/TBE/CBE/PO for Pipe Supports 39 07-Jun-15 15-Jul-15 MM2-12920 Delivery for Pipe Supports 85 16-Jul-15 08-Oct-15 MM2-12960 RFQ/TBE/CBE/PO for Quick Coupling 52 10-Jul-15 30-Aug-15 MM2-12980 Delivery for Quick Coupling 98 31-Aug-15 06-Dec-15 MM2-13040 RFQ/TBE/CBE/PO for Piping insulation 55 05-Jul-15 28-Aug-15 Date Revision Checked Approved Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3 Actual Work Milestone Remaining Work Summary Page 67 of 72 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Activity ID Activity Name Original Start Finish 2015 2016 Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun MM2-13080 Delivery for Piping insulation 99 29-Aug-15 05-Dec-15 MM2-13100 RFQ/TBE/CBE/PO for Bolt nut, gasket and other 53 07-Jul-15 28-Aug-15 MM2-13160 Delivery for Bolt nut, gasket and other 71 29-Aug-15 07-Nov-15 MM2-13200 RFQ/TBE/CBE/PO for Valve Inter-locks 56 17-Sep-15 11-Nov-15 MM2-13240 Delivery for Valve Inter-locks 70 12-Nov-15 20-Jan-16 0.D.26.0000.MM2.C.R Mechanical/ Material Handling 251 08-May-15 13-Jan-16 0.D.26.0000.MM2.C.R.91 Yinson 5 08-Jan-16 13-Jan-16 MM2-11780 ROS for Material Handling Equipment 0 08-Jan-16 ROS for Material Handling Equipment MM2-12020 ROS for Safety equipment 0 13-Jan-16 ROS for Safety equipment 0.D.26.0000.MM2.C.R.92 PTSC 197 08-May-15 20-Nov-15 MM2-11000 RFQ/TBE/CBE/PO for Pig Receivers (Q.O.C) 48 08-May-15 24-Jun-15 MM2-11240 Delivery Pig Receivers (Q.O.C) 149 25-Jun-15 20-Nov-15 0.D.26.0000.MM2.C.1 E&I 296 08-Apr-15 28-Jan-16 0.D.26.0000.MM2.C.1.91 Yinson 0 04-Jan-16 04-Jan-16 MM2-10980 ROS for ICSS RIO panels 0 04-Jan-16 ROS for ICSS RIO panels MM2-11220 ROS for F&G detectors 0 04-Jan-16 ROS for F&G detectors MM2-11500 ROS for PA Systems 0 04-Jan-16 ROS for PA Systems 0.D.26.0000.MM2.C.1.92 PTSC 296 08-Apr-15 28-Jan-16 MM2-10960 RFQ/TBE/CBE/PO for Motor Operated Valve 58 08-Apr-15 04-Jun-15 MM2-11480 Delivery for Motor Operated Valve 238 05-Jun-15 28-Jan-16 MM2-11760 RFQ/TBE/CBE/PO for ON-OFF Valve 61 12-Apr-15 11-Jun-15 MM2-12000 Delivery for ON-OFF Valve 231 12-Jun-15 28-Jan-16 MM2-12220 RFQ/TBE/CBE/PO for H2S analyzer 52 30-Apr-15 20-Jun-15 MM2-12440 Delivery for H2S analyzer 189 21-Jun-15 26-Dec-15 MM2-13220 RFQ/TBE/CBE/PO for Lighting Fixtures 48 20-Jun-15 06-Aug-15 MM2-13260 Delivery for Lighting Fixtures 133 07-Aug-15 17-Dec-15 MM2-13320 RFQ/TBE/CBE/PO for Pressure Safety valves 59 28-Apr-15 25-Jun-15 MM2-13360 Delivery for Pressure Safety valves 217 26-Jun-15 28-Jan-16 MM2-13400 RFQ/TBE/CBE/PO for E&I Cable Tray & Ladder 48 11-Jun-15 28-Jul-15 MM2-13440 Delivery for E&I Cable Tray & Ladder 106 29-Jul-15 11-Nov-15 MM2-13480 RFQ/TBE/CBE/PO for Choke Valve 58 17-Apr-15 13-Jun-15 MM2-13520 Delivery for Choke Valve 229 14-Jun-15 28-Jan-16 MM2-13560 RFQ/TBE/CBE/PO for Junction Box 59 22-Jun-15 19-Aug-15 MM2-13600 Delivery for Junction Box 105 20-Aug-15 02-Dec-15 MM2-13620 RFQ/TBE/CBE/PO for Pig Signaller 53 19-May-15 10-Jul-15 MM2-13680 Delivery for Pig Signaller 167 11-Jul-15 24-Dec-15 MM2-13700 RFQ/TBE/CBE/PO for E&I Steel Support 35 11-Jun-15 15-Jul-15 MM2-13720 Delivery for E&I Steel Support 77 16-Jul-15 30-Sep-15 MM2-13740 RFQ/TBE/CBE/PO for ElectronicTransmitter (PT/TT/LT/FT) 48 17-Jun-15 03-Aug-15 MM2-13760 Delivery for ElectronicTransmitter (PT/TT/LT/FT) 147 04-Aug-15 28-Dec-15 MM2-13780 RFQ/TBE/CBE/PO for E&I Cable 62 13-Jun-15 13-Aug-15 MM2-13800 Delivery for E&I Cable 111 14-Aug-15 02-Dec-15 MM2-13820 RFQ/TBE/CBE/PO for Gauges (PG/TG/LG) 41 06-Jun-15 16-Jul-15 Date Revision Checked Approved Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3 Actual Work Milestone Remaining Work Summary Page 68 of 72 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Activity ID Activity Name Original Start Finish 2015 2016 Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun MM2-13840 Delivery for Gauges (PG/TG/LG) 161 17-Jul-15 24-Dec-15 MM2-13860 RFQ/TBE/CBE/PO for E&I Cable Gland 48 03-Jul-15 19-Aug-15 MM2-13880 Delivery for E&I Cable Gland 105 20-Aug-15 02-Dec-15 MM2-13900 RFQ/TBE/CBE/PO for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.) 52 20-Jul-15 09-Sep-15 MM2-13920 Delivery for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.) 84 10-Sep-15 02-Dec-15 MM2-13940 RFQ/TBE/CBE/PO for MOV & Lighting distribution panel 48 20-Jun-15 06-Aug-15 MM2-13960 Delivery for MOV & Lighting distribution panel 126 07-Aug-15 10-Dec-15 MM2-13980 RFQ/TBE/CBE/PO for Orifice Plate/Restriction Orifice 47 21-Jun-15 06-Aug-15 MM2-14000 Delivery for Orifice Plate/Restriction Orifice 140 07-Aug-15 24-Dec-15 MM2-14020 RFQ/TBE/CBE/PO for Tubing & Fitting 39 11-Jun-15 19-Jul-15 MM2-14040 Delivery for Tubing & Fitting 140 20-Jul-15 06-Dec-15 MM2-14060 RFQ/TBE/CBE/PO for Heat Tracing system 48 20-Jun-15 06-Aug-15 MM2-14080 Delivery for Heat Tracing system 126 07-Aug-15 10-Dec-15 0.D.26.0000.MM2.D Construction 194 18-Aug-15 01-Apr-16 0.D.26.0000.MM2.D.N Structural 182 18-Aug-15 24-Mar-16 0.D.26.0000.MM2.D.N.20 Blasting & Painting 154 21-Sep-15 24-Mar-16 MM2-10880 Blast, primer, tie coat for primary beam of Main Deck 10 21-Sep-15 01-Oct-15 MM2-12880 Blast, primer, tie coat for primary beam of Mezz deck 10 26-Sep-15 07-Oct-15 MM2-12900 Blast, primer, tie coat for secondary beam of main deck 10 08-Oct-15 19-Oct-15 MM2-12940 Blast, primer, tie coat for primary beam of upper deck 10 10-Oct-15 21-Oct-15 MM2-13000 Blast, primer, tie coat for secondary beam of Mezz deck 10 13-Oct-15 23-Oct-15 MM2-13020 Blast, primer, tie coat for deck plate of main deck 10 17-Oct-15 28-Oct-15 MM2-13060 Blast, primer, tie coat for secondary beam of upper deck 10 17-Oct-15 28-Oct-15 MM2-13120 Blast, primer, tie coat for deck plate of Mezz deck 10 22-Oct-15 02-Nov-15 MM2-13140 Blast, primer, tie coat for Legs and Braces for MD & Mezz Deck 14 26-Oct-15 10-Nov-15 MM2-13180 Blast, primer, tie coat for deck plate of upper deck 10 04-Nov-15 14-Nov-15 MM2-13280 Third coat for Mezz deck 10 20-Nov-15 01-Dec-15 MM2-13300 Third coat for main deck 10 21-Nov-15 02-Dec-15 MM2-13340 Third coat for upper deck 10 09-Dec-15 19-Dec-15 MM2-13380 Sweep blast and painting for handrail 10 16-Dec-15 26-Dec-15 MM2-13420 Blast to galvanizing hand rail 14 28-Dec-15 13-Jan-16 MM2-13460 Touch up for column and bracing 14 18-Jan-16 02-Feb-16 MM2-13500 Touch up for deck plate 14 03-Feb-16 24-Feb-16 MM2-13540 Final and touch up for main deck 14 02-Mar-16 17-Mar-16 MM2-13580 Final and touch up painting for upper deck 14 02-Mar-16 17-Mar-16 MM2-13640 Final and touch up painting for Mezz deck 14 02-Mar-16 17-Mar-16 MM2-13660 Cleaning and hand over MM2 14 09-Mar-16 24-Mar-16 0.D.26.0000.MM2.D.N.05 Pre-Fabrication 30 18-Aug-15 22-Sep-15 MM2-10820 Pre-fab & Assembly for LOSF 30 18-Aug-15 22-Sep-15 0.D.26.0000.MM2.D.N.10 Fabrication 134 17-Sep-15 26-Feb-16 0.D.26.0000.MM2.D.N.10.1 Main Deck 122 17-Sep-15 12-Feb-16 MM2-10840 Cut & prep Main Deck Primary Beams 10 17-Sep-15 28-Sep-15 MM2-11120 Fab Main Deck nodes & Joints 10 17-Sep-15 28-Sep-15 Date Revision Checked Approved Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3 Actual Work Milestone Remaining Work Summary Page 69 of 72 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Activity ID Activity Name Original Start Finish 2015 2016 Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun MM2-11360 Cut & prep Main Deck Secondary Beams & Stiffeners 10 05-Oct-15 15-Oct-15 MM2-11640 Fab Main Deck Plates 10 14-Oct-15 24-Oct-15 MM2-11900 Fab column and bracing 14 17-Oct-15 02-Nov-15 MM2-12160 Fab Handrail, landing & Sockets... 60 28-Nov-15 12-Feb-16 0.D.26.0000.MM2.D.N.10.2 Mezz Deck 126 21-Sep-15 20-Feb-16 MM2-11040 Cut & prep Mezz Deck Primary Beams 10 21-Sep-15 01-Oct-15 MM2-11280 Fab Mezz Deck nodes & Joints 10 21-Sep-15 01-Oct-15 MM2-11540 Cut & prep Mezz Deck Secondary Beams & Stiffeners 10 05-Oct-15 15-Oct-15 MM2-11820 Fab column and bracing 14 17-Oct-15 02-Nov-15 MM2-12060 Fab Mezz Deck Plates 10 19-Oct-15 29-Oct-15 MM2-12280 Fab Handrail, landing & Sockets... 60 07-Dec-15 20-Feb-16 0.D.26.0000.MM2.D.N.10.3 Upper Deck 120 03-Oct-15 26-Feb-16 MM2-10860 Cut & prep Upper Deck Primary Beams 10 03-Oct-15 14-Oct-15 MM2-11380 Fab Upper Deck nodes & Joints 10 03-Oct-15 14-Oct-15 MM2-11660 Cut & prep Upper Deck Secondary Beams & Stiffeners 10 09-Oct-15 20-Oct-15 MM2-11920 Fab Upper Deck Plates 14 26-Oct-15 10-Nov-15 MM2-12320 Fab Handrail, landing & Sockets... 60 12-Dec-15 26-Feb-16 0.D.26.0000.MM2.D.N.25 Installation 137 24-Sep-15 08-Mar-16 0.D.26.0000.MM2.D.N.25.1 Main Deck 133 24-Sep-15 03-Mar-16 MM2-10920 Assembly Main Deck Primary Beams & Deck nodes above LOSF 30 24-Sep-15 28-Oct-15 MM2-11160 Assembly Main Deck Secondary Beams & Stiffemers above LOSF 14 17-Oct-15 02-Nov-15 MM2-11420 Installation Main Deck Plate 16 03-Nov-15 20-Nov-15 MM2-11700 Installation Columns onto Main Deck (for Mezz Deck) 10 10-Nov-15 20-Nov-15 MM2-11940 Installation Bracings onto Main Deck 24 11-Dec-15 08-Jan-16 MM2-12480 Installation Remaining Legs onto Main Deck 8 12-Dec-15 21-Dec-15 MM2-12520 Installation Handrail, landing & Sockets, Gratings... 50 30-Dec-15 03-Mar-16 MM2-12620 Weighting for MM2 1 24-Feb-16 24-Feb-16 0.D.26.0000.MM2.D.N.25.2 Mezz Deck 127 01-Oct-15 03-Mar-16 MM2-11060 Assembly Mezz Deck Primary Beams & Deck nodes 21 01-Oct-15 24-Oct-15 MM2-11300 Assembly Mezz Deck Secondary Beams & Stiffemers 14 21-Oct-15 05-Nov-15 MM2-11560 Installation Mezz Deck Plate 12 06-Nov-15 19-Nov-15 MM2-11840 Install Mezz Deck onto Main Deck 6 03-Dec-15 09-Dec-15 MM2-12080 Installation Columns onto Mezz Deck 8 12-Dec-15 21-Dec-15 MM2-12300 Installation Bracings onto Mezz Deck 10 31-Dec-15 12-Jan-16 MM2-12460 Installation Handrail, landing & Sockets, Gratings... 45 06-Jan-16 03-Mar-16 0.D.26.0000.MM2.D.N.25.3 Upper Deck 117 17-Oct-15 08-Mar-16 MM2-10900 Assembly Upper Deck Primary Beams & Deck nodes 30 17-Oct-15 20-Nov-15 MM2-11140 Assembly Upper Deck Secondary Beams & Stiffemers 14 04-Nov-15 19-Nov-15 MM2-11400 Installation Upper Deck Plate 16 20-Nov-15 08-Dec-15 MM2-11680 Install Upper Deck onto Main Deck & Mezz Deck 6 22-Dec-15 28-Dec-15 MM2-12340 Installation Handrail, landing & Sockets, Gratings... 50 05-Jan-16 08-Mar-16 0.D.26.0000.MM2.D.R Mechanical/ Material Handling 112 26-Oct-15 10-Mar-16 0.D.26.0000.MM2.D.R.20 Blasting & Painting Equipment support 93 17-Nov-15 10-Mar-16 Date Revision Checked Approved Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3 Actual Work Milestone Remaining Work Summary Page 70 of 72 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Activity ID Activity Name Original Start Finish 2015 2016 Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun MM2-10800 Blast, primer for equipment support 21 17-Nov-15 10-Dec-15 MM2-11620 Touch up for equipment support and final coat 14 24-Feb-16 10-Mar-16 0.D.26.0000.MM2.D.R.25 Installation 40 26-Oct-15 10-Dec-15 MM2-10780 Fabrication and installation euipment support 40 26-Oct-15 10-Dec-15 0.D.26.0000.MM2.D.R.80 Equipment Securing 74 07-Dec-15 08-Mar-16 MM2-10120 Installation ROP1 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15 MM2-10420 Installation ROP2 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15 MM2-10540 Installation safty sign and safety equipment 25 03-Feb-16 08-Mar-16 0.D.26.0000.MM2.D.L Piping 135 05-Oct-15 16-Mar-16 0.D.26.0000.MM2.D.L.20 Blasting & Painting 126 15-Oct-15 16-Mar-16 MM2-12100 Blast & Paint for piping spool, SS 60 19-Oct-15 26-Dec-15 MM2-12360 Blast & Paint for piping spool, Duplex SS & Cladding 60 15-Oct-15 23-Dec-15 MM2-12500 Blast & Paint for Pipe support 55 24-Oct-15 26-Dec-15 MM2-12580 Blast & Paint for piping spool CS 90 30-Oct-15 18-Feb-16 MM2-12680 Touch up painting for piping 50 13-Jan-16 16-Mar-16 MM2-12760 Touch up for piping support 14 12-Feb-16 27-Feb-16 MM2-12840 Touch up painting for valve 14 16-Feb-16 02-Mar-16 0.D.26.0000.MM2.D.L.10 Fabrication 107 05-Oct-15 12-Feb-16 MM2-10720 Fabrication Carbon steel piping spool work 107 05-Oct-15 12-Feb-16 MM2-11100 Fabrication Stainless steel piping spool work 60 13-Oct-15 21-Dec-15 MM2-11320 Fabrication Duplex SS & Cladding piping spool work 60 07-Oct-15 15-Dec-15 MM2-11580 Fabrication Pipe support 60 14-Oct-15 22-Dec-15 MM2-11860 Fabrication CUNI piping spool work 35 26-Oct-15 04-Dec-15 0.D.26.0000.MM2.D.L.25 Installation 84 11-Nov-15 23-Feb-16 MM2-10740 Pipe support installation 60 11-Nov-15 20-Jan-16 MM2-11340 Installation Carbon steel piping spool work 56 25-Nov-15 29-Jan-16 MM2-11600 Installation Stainless steel piping spool work 55 26-Nov-15 29-Jan-16 MM2-11880 Installation Duplex SS & Cladding piping spool work 55 26-Nov-15 29-Jan-16 MM2-12120 Installation Manual valve 30 02-Jan-16 05-Feb-16 MM2-12380 Installation CUNI piping spool work 22 05-Jan-16 29-Jan-16 MM2-12600 Installation MOV valve 15 30-Jan-16 22-Feb-16 MM2-12700 Installation Choke valve 15 30-Jan-16 22-Feb-16 MM2-12780 Installation On-off valve 15 01-Feb-16 23-Feb-16 0.D.26.0000.MM2.D.L.40 Testing 42 31-Dec-15 24-Feb-16 MM2-10220 Flushing and hydro test 30 31-Dec-15 04-Feb-16 MM2-10300 Flangemanagement & reinstatement 37 07-Jan-16 24-Feb-16 0.D.26.0000.MM2.D.1 E&I 101 13-Nov-15 16-Mar-16 0.D.26.0000.MM2.D.1.20 Blasting & Painting 88 28-Nov-15 16-Mar-16 MM2-10760 Blast & Paint E&I support 40 28-Nov-15 14-Jan-16 MM2-12140 Touch up for E&I support 14 01-Mar-16 16-Mar-16 0.D.26.0000.MM2.D.1.10 Fabrication 50 13-Nov-15 11-Jan-16 MM2-10100 Fabrication Electrical Support 50 13-Nov-15 11-Jan-16 MM2-10280 Fabrication Instrument Support 50 13-Nov-15 11-Jan-16
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3 Actual Work Milestone Remaining Work Summary Page 71 of 72 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Activity ID Activity Name Original Start Finish 2015 2016 Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 0.D.26.0000.MM2.D.1.25 Installation 70 10-Dec-15 07-Mar-16 MM2-10060 Installation Electrical Support 48 10-Dec-15 04-Feb-16 MM2-10400 Installation of Instrument Support 41 18-Dec-15 04-Feb-16 MM2-10520 Installation Electrical cable Ladder/Tray 35 26-Dec-15 05-Feb-16 MM2-10580 Installation Instrument cable and Tubing Ladder/Tray 35 29-Dec-15 13-Feb-16 MM2-10620 Installation Instrument equipments 30 27-Jan-16 07-Mar-16 MM2-10660 Installation Electrical Equipments 30 26-Jan-16 05-Mar-16 MM2-10680 Installation Tubing 28 29-Jan-16 07-Mar-16 MM2-11080 Install Heat tracing 25 25-Jan-16 27-Feb-16 0.D.26.0000.MM2.D.1.40 Testing 48 11-Dec-15 05-Feb-16 MM2-10080 Testing Electrical Cable 40 11-Dec-15 27-Jan-16 MM2-10260 Testing Instrument Cable 40 11-Dec-15 27-Jan-16 MM2-10320 Calibration of instrument equipments 25 28-Dec-15 26-Jan-16 MM2-10480 Function test/ Leak test (Choke Valve, On-off Valve) 7 29-Jan-16 05-Feb-16 0.D.26.0000.MM2.D.1.30 Cabling & Termination 55 06-Jan-16 15-Mar-16 MM2-10040 Pulling Electrical Cable 35 06-Jan-16 20-Feb-16 MM2-10240 Pulling Instrument Cable 30 13-Jan-16 22-Feb-16 MM2-10380 Glanding and Termination Electrical 35 28-Jan-16 14-Mar-16 MM2-10500 Glanding and Termination Instrument 32 02-Feb-16 15-Mar-16 0.D.26.0000.MM2.D.4 Insulation 35 01-Feb-16 17-Mar-16 0.D.26.0000.MM2.D.4.25 Installation 35 01-Feb-16 17-Mar-16 MM2-10160 Insulation for Mechanical equipment & Piping 35 01-Feb-16 17-Mar-16 0.D.26.0000.MM2.D.5 Mechanical Completion ("A" Scope) 48 23-Jan-16 24-Mar-16 0.D.26.0000.MM2.D.5.60 Finishing 43 23-Jan-16 18-Mar-16 MM2-10140 ITR checksheet for Piping 40 23-Jan-16 15-Mar-16 MM2-10340 ITR checksheet for Instrument 30 13-Feb-16 18-Mar-16 MM2-10440 ITR checksheet for Electrical 30 12-Feb-16 17-Mar-16 0.D.26.0000.MM2.D.5.70 Pre-commissioning 33 16-Feb-16 24-Mar-16 MM2-10360 Pre-com for Modules MM1 ( Leak Test, Heatracing...) 33 16-Feb-16 24-Mar-16 MM2-10460 Disciplines Acceptance Certificate (DAC) 20 27-Feb-16 21-Mar-16 MM2-10560 Loop Test from Instrument devices to RIO panels 16 04-Mar-16 22-Mar-16 MM2-10600 Full power up of the module lighting 4 24-Feb-16 27-Feb-16 MM2-10640 Mechanical & Pre-com Completion date for MM2 0 24-Mar-16 Mechanical & Pre-com Com 0.D.26.0000.MM2.D.6 Finishing/ Load-Out 33 24-Feb-16 01-Apr-16 0.D.26.0000.MM2.D.6.1 Load-Out 33 24-Feb-16 01-Apr-16 MM2-10000 Fab Seafastening & Install Grillage on Barge for MM2 20 24-Feb-16 17-Mar-16 MM2-10200 Load-Out for Modules MM2 7 26-Mar-16 01-Apr-16 0.D.26.0000.MM2.T Transportation (Optional) 7 02-Apr-16 08-Apr-16 0.D.26.0000.MM2.T.7 Delivery 7 02-Apr-16 08-Apr-16 0.D.26.0000.MM2.T.7.70 Delivery 7 02-Apr-16 08-Apr-16 MM2-10180 Transportation Modules MM2 to Singapore Yard 7 02-Apr-16 08-Apr-16
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3 Actual Work Milestone Remaining Work Summary Page 72 of 72