EXCEL INDUSTRIES LTD -EBS

Go-Live Downtime Schedule EXCEL INDUSTRIES LTD

S.No Areas
1 DBA
2 DBA

3 DBA
5 DBA

6 DBA
7 DBA

8 DBA
9 OPM

10 DBA
11 DBA
12 DBA
13 DBA
14 DBA
15 DBA
16 DBA
EXCEL INDUSTRIES LTD -EBS UPGRADE 12.1.3 FROM 11.5.
e EXCEL INDUSTRIES LTD

Major Milestones Start Date


Clone
Cloning of 11.5.10.2 Production database to identified HP 3-Mar-13
Pre-Upgrade Process
Application of AD.I.7 3-Mar-13
Applying Sub Ledger Patch and pre-req 3-Mar-13
Run Gather Scheme Statistics 3-Mar-13
System for Pre-Upgrade Checkups 3-Mar-13
Application Services Shutdown 3-Mar-13
Take a Backup(APPS & DB) 3-Mar-13
OPM Pre-Migration Process
Applying Pre-Install Patches for OPM 3-Mar-13
Checking OPM Migration Error Log 3-Mar-13
Resolving OPM Migration Log Errors 3-Mar-13
Take a Backup(APPS & DB) 3-Mar-13
Upgrade Process For Application
Upgrading Application from 11.5.10.2 to R12.1.1
R12 Stage move and Install 3-Mar-13
Applying Pre-Install Patches 3-Mar-13
Appling Opatches 4-Mar-13
Apply Main Patch 4-Mar-13
Apps Tech_st and Apps Setup (First Run) 5-Mar-13
System preparation for Autoconfig 6-Mar-13
Enabling Autoconfig on DB Tier 6-Mar-13
Enabling Autoconfig on R12.1.1 6-Mar-13
Take a Backup(APPS & DB) 6-Mar-13
OPM Post-Migration Proces
Applying Post-Migration Patches
Checking OPM Migration Error Log
Resolving OPM Migration Log Errors
Upgrade Process For Database
Upgrading Database from 10.2.0.4 to 11.2.0.3 with Companion
Applying Additional Patches 4-Mar-13
Upgrade Steps 4-Mar-13
Take a Backup(APPS & DB) 4-Mar-13
Upgrade Process For Application
Upgrading Application from R12.1.1 to R12.1.3
Pre-Upgrade Process 5-Mar-13
Apply Maintaince Patch 5-Mar-13
Apply Help Patch 5-Mar-13
Post-Upgrade Process
Post Upgrade -Database 5-Mar-13
Post Upgrade Patches 5-Mar-13
Post Upgrade Functional and Technical activites are below 6-Mar-13
Post Upgrade Technical 6-Mar-13
Post Upgrade Functional
Release 12.1.3
12.1.3 FROM 11.5.10.2

Complete Date Person Time Status

3-Mar-13 Mr.Hemal Shah 4Hours

3-Mar-13 Mr.Adithya/Tajmal 1Hour


3-Mar-13 Mr.Adithya/Tajmal 3Hours
3-Mar-13 Mr.Adithya/Tajmal 4Hours
3-Mar-13 Mr.Adithya/Tajmal 1Hour
3-Mar-13 Mr.Adithya/Tajmal 10mins
3-Mar-13 Mr.Adithya/Tajmal 4Hours

3-Mar-13 Mr.Adithya/Tajmal 3Hours


3-Mar-13 Mr.Vijay/Raman/Senthil 2Hours
3-Mar-13 Mr.Vijay/Raman/Senthil 1Hour
3-Mar-13 Mr.Adithya/Tajmal 4Hours
Total=17Hours

3-Mar-13 Mr.Adithya/Tajmal 1Hour


4-Mar-13 Mr.Adithya/Tajmal 1Hour
4-Mar-13 Mr.Adithya/Tajmal 1Hour
5-Mar-13 Mr.Adithya/Tajmal 25Hours
5-Mar-13 Mr.Adithya/Tajmal 1Hour
6-Mar-13 Mr.Adithya/Tajmal 1Hour
6-Mar-13 Mr.Adithya/Tajmal 30mins
6-Mar-13 Mr.Adithya/Tajmal 30mins
6-Mar-13 Mr.Adithya/Tajmal 4Hours

4Hours
1Hour
2Hour
Total=41Hours

4-Mar-13 Mr.Adithya/Tajmal 5Hours


4-Mar-13 Mr.Adithya/Tajmal 18Hours
5-Mar-13 Mr.Adithya/Tajmal 4Hours
Total=27Hours
Mr.Adithya/Tajmal
5-Mar-13 Mr.Adithya/Tajmal 1Hours
5-Mar-13 Mr.Adithya/Tajmal 18Hours
5-Mar-13 Mr.Adithya/Tajmal 1Hours
Total=24Hours
5-Mar-13 Mr.Adithya/Tajmal 1Hours
6-Mar-13 Mr.Adithya/Tajmal 4Hours
6-Mar-13 Mr.Vijay/Raman/Venkat/Shree Pr 1Hour
6-Mar-13 Mr.Shree Prasanth/Sethu 1Hour
Mr.Vijay/Raman/Ram/Senthil/Ven7Hour
Ready for Business User end Total Hours Taken:120