Sei sulla pagina 1di 144

HIRING AGENCY FOR SCADA

IMPLEMENTATION AT CNG
STATIONS (INCLUDING DTC &
RETAIL OUTLET ) & PNG
SEGMENT
Project No. P.011489
Document No. P.011489 R11050 001
IGL Tender No. IGL/ND/C&P/EC14876

INDRAPRASTHA GAS LIMITED (IGL), NEW DELHI


NEW DELHI | INDIA

PUBLIC

19 June 2018

TECHNICAL DOCUMENTATION
Technical, Vol II of II, Rev. 0
MAIN TABLE OF CONTENTS
SCADA IMPLEMENTATION AT CNG STATION
P.011489
(INCLUDING DTC & RETAIL OUTLET) & PNG
SEGMENT

S.No. Description Document / Drawing No. Rev. No. Pages Page Nos.

A VOLUME I OF II (COMMERCIAL)

B VOLUME II OF II

B.1 Material Requisition P.011489-I-11071-01 0 6

B.2 Special Instruction to Contractor P.011489-I-11078-01 0 5

B.3 Scope of Work P.011489-I-11075-01 0 9

B.4 SCADA operation Philosophy P.011489-I-11075-01 0 3

B.5 PTS- SCADA and RTU System with Annexures P.011489-I-11097-01 0 34

Annexure -I- Source of Supply (SOS) P.011489-I-11097-01 22

Annexure -II -Power Consumption Requirement


P.011489-I-11097-01 2
(PCR)
Annexure-III- Typical I/O Counts details for RU
P.011489-I-11097-01 5
system

Annexure-IV- List of Equipment at CNG station P.011489-I-11097-01 2

Annexure-V- Total Phase station P.011489-I-11097-01 29

Annexure-VI -Existing PLC detail P.011489-I-11097-01 1

B.6 PTS- Instrument Cables P.011489-I-11097-02 0 6

B.7 Recommended Vendor List P.011489-I-11073-01 0 3

B.8 RTU interface Drawing P.011489-I-21003 0 1

B.9 SCADA System Architecture P.011489-I-21009 0 2

Page
Page11 of
of1 142
Page 2 of 142
P.011489
MATERIAL REQUISITION I-11071
01

A. DESCRIPTION OF GOODS AND/OR SERVICES

Item Description Quantity/ Unit Rate Total


Unit
A SUPPLY
Supply of SCADA system as per PTS- SCADA and RTU
1.
system and Annexure-1 at Master station

SCADA system with servers, all the required hardware,


a clients, application software, all required software, OPC (UA) 2 Nos.
server with 4 clients.

Archiving server with 3-year storage capacity all required


software and hardware. (Note: server size given in tender
b. specification is tentative. Bidder shall ascertain the size as per 1 Nos.
the requirement of storage capacity and functionality. Bidder
shall consider given size as minimum requirement)

Web server with 21” monitor, keyboard and mouse, unlimited


c. license with 30 concurrence users with auto refresh along with 1 Nos
all the required Software (SMS, Email, Mobile Apps)

d. 21” Monitor with key board and mouse. 1 Nos.

e. KVM switch min 8 port 1 Nos.

Server cabinet with complete internal wiring for mounting


f. servers, KVM switch, LAN switch, Router and server monitor 1 Nos.
with mouse and keypad etc.
g. Wall Mounter Power distribution box 1 No

h. Engineering work station with 21” monitor, key board, mouse 1 Nos
and all license software and hardware
i. Operator work station with 21” monitor, key board, mouse and 2 Nos
all license software and hardware
j. Min 24 Port LAN switch 2 Nos

k. Min 10 Ports Router 1 Nos

l. GPS with digital clock , cable and antenna 1 Nos

m. LAN /Ethernet cables LS

n. PDT(Laptop) loaded with OS, Microsoft office, Application 1 Nos


software, Antivirus etc
o. A4 size Printer 1Nos

p. Fire wall security system with dedicated ports for SCADA 1 Nos
server, web server, achieve server etc

2 RTU along with cabinet, internal wiring as per PTS-


SCADA and RTU & Annexure-1

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 1 of 6


Page 3 of 142
P.011489
MATERIAL REQUISITION I-11071
01

Item Description Quantity/ Unit Rate Total


Unit
a Cat 1 – RTU, Dual SIM 3G/4G & Ethernet port (for MPLS 293 Nos
connectivity) Router/modem and LAN switch (min 8 port)
b Cat 2 - – RTU, Dual SIM 3G/4G & Ethernet port (for MPLS 78 Nos
connectivity) Router/modem and LAN switch (min 8 port)
c Cat 3 - – RTU, Dual SIM 3G/4G & Ethernet port (for MPLS 18 Nos
connectivity) Router/modem and LAN switch (min 8 port)
All above given quantities are tentative and may vary as per site & functionality requirement. Bidder is
Note also required to ascertain the equipment & quantity those are not mentioned herein but require according
to functionality and their standard practices/ system. No extra claim will be entertained after award.

B ERECTION/ SERVICES

1 Erection, Installation, testing, FAT, SAT, commissioning of


LS
SCADA system as per scope of work.

2. Erection, Installation, testing, FAT, SAT, commissioning of 389 Nos


RTU system as per scope of work
3. Supply and laying of Signals cable including, termination,
LS
glanding, ferruling, tagging, lugging including supply of
consumables as per scope of work.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 2 of 6


Page 4 of 142
P.011489
MATERIAL REQUISITION I-11071
01

B. REMARKS / COMMENTS

1.0 GENERAL NOTES

VENDOR's compliance

Vendor shall submit his bid in full compliance with the requirements of this MR and attachments.

Vendor must include the following statement in his bid:

We certify that our bid is fully complying with your enquiry dated……………, and
referenced………………….

Compliance with this material requisition in any instance shall not relieve the Vendor of his responsibility
to meet the specified performance.

2.0 COMPLIANCE WITH SPECIFICATION

The VENDOR shall be completely responsible for the design, materials, fabrication, testing, inspection,
preparation for shipment and transport of the item strictly in accordance with the Material Requisition and
all attachments thereto.

3.0 VENDOR'S SCOPE

Vendor's scope of work includes all the items with its internals and accessories as shown on the data sheets,
specifications and all unmentioned parts necessary for a satisfactory operation.

4.0 INSPECTION

Vendor shall appoint anyone of the following TPIA for inspection purpose.

a) Lloyd Register of Industrial Services


b) TUV NORD
c) DNV-GL
d) Bureau Veritas (BV)
e) SGS
f) American Bureau Services (ABS).
g) Applus Velosi
Apart from inspection by TPIA, inspection shall also be performed by Owner and / or Owner authorised
representative.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 3 of 6


Page 5 of 142
P.011489
MATERIAL REQUISITION I-11071
01

5.0 APPLICABLE DOCUMENTS

General prescriptions, requirements and information are listed in annex C of this Material Requisition.

6.0 VENDOR'S DOCUMENTS

Vendor shall submit the documentation as listed under point D of this Material Requisition.
All documents shall be submitted in English language.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 4 of 6


Page 6 of 142
P.011489
MATERIAL REQUISITION I-11071
01

C. LIST OF ATTACHMENTS

The table herebelow lists the documents which are integral part of
Material Requisition revision
this Material
Requisition. The applicable revision index of each document is
mentioned in the column below the current Material Requisition
revision index.
When the Material Requisition revision index is “A” or “1”, all
0 1 2 3 4 5 6 7
listed documents are attached. For other Material Requisition
revision index, only modified or new documents are attached.

Documents Revision of documents


1. Volume I of II – Commercial
2. Volume II of II – Technical
2.1 Material Requisition 1
2.2 Special Instruction to contractor 0
2.3 Scope of work 2
2.4 SCADA Philosophy 3
2.5 PTS – SCADA and RTU 4
Annexure I – Source of supply
Annexure II- Power consumption requirement
Annexure III - IO Count for RTU
Annexure IV - List of Equipment
Annexure V – Total Phase stations
2.6 PTS – Instruments Cables 1
2.7 Recommended Vender List 1
2.8 SCADA system architecture 2

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 5 of 6


Page 7 of 142
P.011489
MATERIAL REQUISITION I-11071
01

D. DOCUMENTS & DATA REQUIREMENTS

The table hereunder specifies the quantities and the nature of the documents to be submitted by the CONTRACTOR to
the ENGINEER.
The documents required at the inquiry stage and to be included in the bid are listed under column A.
The documents required after award of the AGREEMENT and subject to the written approval of the ENGINEER are
listed under column B.
The final and certified documents are listed under column C.
Any document, even when preliminary, shall be binding and therefore duly identified and signed by the CONTRACTOR.
THE DOCUMENTS ARE FULLY PART OF THE SUPPLY WHICH SHALL BE COMPLETE ONLY IF AND WHEN
THE DOCUMENTS COMPLYING FULLY WITH THE MATERIAL REQUISITION REQUIREMENTS ARE
RECEIVED BY THE ENGINEER.

A B C
Documents and Data Number
Number Number Required Required
of
of copies of copies date date
copies
Field instruments documentation: Cable schedule, JB - 3 2 weeks 4 2 Weeks
wiring & Termination details, loop drawings, Instrument
index, Hook up drawings, Sizing Calculation etc
Bill of Material/list of all the equipment with make and 3 3 2 weeks 4 2 Weeks
model number
Specification for RTU & SCADA System with - 3 2 weeks 4 2 Weeks
catalogue, SCADA Control room GA drawing, RTU
cabinet GA drawing, wiring & Termination details, IO
allocation details, FDS, system architecture FAT, SAT
documents.
SCADA and RTU system- Annexure 1-SOS and 3 3 2 weeks 4 2 Weeks
Annexure II-PCR
Specification for Telecom System modem with - 3 2 weeks 4 2 Weeks
catalogue, VPN, band width calculation, fire wall
security.

List of all Bought out Items with supplier’s Name, 3 - - - 2 Weeks


Model No etc.
NOTES

1) Durations in column B (Required date) are weeks after LOA date or as indicated in table

2) Durations in column C (Required date) are weeks before final despatch.

3) Final technical document file shall be supplied in hard copy as indicated and in electronic format
(pdf Acrobat files) on six (6 Nos.) CD-ROMs.

Σ Σ Σ

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 6 of 6


Page 8 of 142
P.011489
PTS - SPECIAL INSTRUCTIONS
I-11078
TO CONTRACTOR
01

INDRAPRASTHA GAS LIMITED (IGL)


SCADA IMPLEMENTATION AT CNG STATION (INCLUDING
DTC & RETAIL OUTLET) & PNG SEGMENT

TRACTEBEL ENGINEERING PVT. LTD.

PARTCULAR TECHNICAL SPECIFICATION


SPECIAL INSTRUCTION TO CONTRACTOR

0 19.06.2018 Issued for procurement MA SHD BK


Rev. Date Subject of revision Author Checked Approved

Page 9 of 142
P.011489
PTS - SPECIAL INSTRUCTIONS
I-11078
TO CONTRACTOR
01

TABLE OF CONTENTS

1.0 GENERAL .............................................................................................................................. 1

2.0 DEFINITIONS ....................................................................................................................... 1

3.0 APPLICABLE CODES & STANDARDS ..................................................................................... 2

4.0 STATUTORY APPROVALS / CERTIFICATES (AFTER GETTING ORDER) ................................ 4

Σ Σ Σ

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page I of I

Page 10 of 142
P.011489
PTS - SPECIAL INSTRUCTIONS
I-11078
TO CONTRACTOR
01

1.0 GENERAL

1.1 Bidder shall submit their offer in a well-documented manner with all required documents as listed in
“Material Requisition” (but not limited to) of this tender document.

1.2 The language of bidder’s offer including catalogue, technical literature or any other documents or any
software shall be English language only. This shall be applicable for bought out items also.

1.3 Scope of the bidder shall be as per the PTS- Scope of Work. Any other activities not specifically mentioned
/covered in the tender documents but otherwise required for satisfactory completion /safety of work has to
be carried out by the contractor within specified schedule at no extra cost to CLIENT.

1.4 Bidder shall strictly follow the Recommended Vender List attached with the tender document for various
items.

2.0 DEFINITIONS

Subject to the requirements of the context, the terms (hereafter listed in alphabetical order) used in this
specification are given the following meaning:

AGREEMENT Designates the agreement concluded between the CLIENT and


the CONTRACTOR, under which the latter undertakes to the
former the GOODS and/or SERVICES according to the
stipulations which are agreed and specified in the form of an
order.

CLIENT Designates the purchaser of the GOODS and/or SERVICES


which are the subject of the AGREEMENT.

CONTRACTOR Designates the individual or legal entity with whom the order has
been concluded by the CLIENT. The term "CONTRACTOR"
may be used indifferently for a supplier, a manufacturer, an
erection contractor, etc.

DAYS - WEEKS – MONTHS Specify the number of calendar days, weeks or months and not of
working days, weeks or months.

ENGINEER Designates the individual or legal entity to which the CLIENT


has entrusted various tasks in relation with the carrying out of his
PROJECT

GOODS and/or SERVICES Designate, depending on the case, all or part of the drawings or
documents, substances, materials, materiel, equipment,
structures, plant, tools, machinery to be studied, designed,
manufactured, supplied, erected, built, assembled, adapted,
arranged or put into service by the CONTRACTOR under the
AGREEMENT, including all the studies, tasks, works and
services specified by the order. The Terms GOODS or
SERVICES may by indifferently used one for the other as
required by the context.

PROJECT Designates the aggregate of GOODS and/or SERVICES to be


provided by one or more CONTRACTORS.
2.1 REVIEW AND/OR APPROVAL

Whenever CLIENT and/or ENGINEER review and/or approval is requested on a document to be submitted
by the CONTRACTOR, or before an action is implemented by the CONTRACTOR, such review and/or

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 1 of 5

Page 11 of 142
P.011489
PTS - SPECIAL INSTRUCTIONS
I-11078
TO CONTRACTOR
01

approval shall always be requested in writing by the CONTRACTOR to the CLIENT and/or the
ENGINEER, before any action subject of this review and/or approval is taken.

CLIENT and/or ENGINEER approval shall always be given in writing.

3.0 APPLICABLE CODES & STANDARDS

The following Indian/ international or relevant codes and standards shall be used for designing the system.
In all cases, latest revisions with amendments, if any, to be followed Apart from the specific codes
mentioned herein, all other relevant and related codes concerning the specific job under consideration and/or
referred to in these codes and technical specifications will be followed wherever applicable. All codes will
be of the latest revision as on the date of issuing the tender/ bid document.

In the event of any conflict between this specification, related standards and codes, any other attachment to
this tender, the Contractor shall refer the matter to CLIENT’S/CLIENT’ REPRESENTATIVE for
clarification and only after obtaining the confirmation on the same, should proceed with the manufacture/
supply / engineering of the item in question. The decision of the CLIENT’S/CLIENT’ REPRESENTATIVE
shall be binding on the Contractor.

CONTRACTOR shall seek COMPANY's final interpretation of any conflicts prior to the execution of
work. Rework of engineering and relevant scope arising out of underestimation shall be done at no
additional cost to the COMPANY.

Sr. Codes Description


No

1 OISD-STD-226 Natural Gas Transmission Pipelines and City Gas Distribution


Networks.

2 ANSI/ISA S 51.1 Process Instrumentation Terminology.

3 ISA 5.4 Instruments Loop diagrams.

4 IEC 60529 / IS 2147 / Specification for Weather Proof Enclosure.


NEMA

5 IEC 60079/IS 2148 Specification for Flame Proof Enclosure

6 IEC 61000 Electromagnetic Compatibility for Industrial Process


Measurement and Control equipments.

7 IEC 60801 EMI and RF interference

8 IS-1554 Part 1 PVC insulated (heavy duty) electric cables- working voltage up
to and including 1100V.

9 BS-5308 Part 1, Type 2 Specification for PVC insulated cables.

10 IS 8130 Conductors of insulated cables

11 IS 5831 Specification for PVC insulation and sheath of insulated cables.

12 IS-3975 Mild steel wires, formed wires and tapes for armoring of cables.

13 ASTM D 2843 Test method for Max smoke density for cable

14 ASTM D 2863 Test method for measuring of Temp and O2 Index.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 2 of 5

Page 12 of 142
P.011489
PTS - SPECIAL INSTRUCTIONS
I-11078
TO CONTRACTOR
01

Sr. Codes Description


No

15 IEC 60754 Acid generation test

16 IEC-332-3 Part 3 Tests on bunched wires and cables.

17 BS 6121, EN 50262 Cable gland – flame proof Exd or Exe increase safety.

18 DIN- 50049 Document on Material Testing.

19 ASME PTC 19.3 Temperature Measurement- calculation of natural frequency.

20 IEC 751 / DIN 43760 RTD

21 IEC 584/DIN 43710 / Thermocouple


ANSI MC 96.1

ISO 5167 Measurement of fluid flow by means of orifice plates, Nozzles


22
and Venturi tube inserted in filled piping circular profile.

23 ASME B 16.36 Orifice flange with flange pressure tap.

24 ASME B16.5 Pipe line flanges and flanged fittings

25 API-RP-520 Sizing and selection of safety relief valves.

26 IS 3624 / BS EN 837 Pressure gauge

27 AGA 3 Orifice flow measurement

28 AGA 9 Ultrasonic flow measurement

29 AGA 8 Compressibility factor of natural gas.

30 AGA 10 Calculation of Speed of sound in Natural gas

31 API Spec 6A Valve design methodology

32 API 6D Petroleum and natural gas valve

33 ISA 75.01 Flow equation for sizing of control valve

34 ISA 75.02 Testing of CV rating, control valve capacity test

35 ISA 75.05 Control valve terminology

ISA 71.07 Laboratory measurement of aerodynamic noise generated by


36
control valves.

37 FCI 70.2/ANSI B 16.104 Control valve seat leakage.

38 ASME/ANSI B 16.34 Valves-Flanged, Threaded and welding end.

39 IEEE 802 The LAN standards.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 3 of 5

Page 13 of 142
P.011489
PTS - SPECIAL INSTRUCTIONS
I-11078
TO CONTRACTOR
01

Sr. Codes Description


No

IEC-60870-5-104/ DNP 3
40 SCADA Communication protocol
(TCP/IP)

41 IEC 61131 RTU, remote terminal unit

42 IEC 60870-5-101 Modbus serial RS232/Rs485

Graphic Symbols for Distributed Control/Shared Display


43 ISA 5.3-1983
Instrumentation, Logic, and Computer Systems.

44 ISA-5.5-1985 Graphic Symbols for Process Displays

45 TIA/EIA 58 Communication standard


Environmental Conditions for Process Measurement and Control
46 ISA 71.04
Systems: Airborne Contaminants,"
Cyber security Industrial Automation and Control Systems
47 IEC-27001/IEC 62443
(IACS)
All equipment and materials shall be in accordance with the relevant latest national / international standards
such as the recommendations of: -

• ISO (International Standards Organisation)

• IS (Indian Standards).

• IEC (International Electro Technical Commission).

• ASTM (American Society for Testing Materials).

• EIA (Electronics Industry Association).

• BIS (Bureau of Indian Standards).

• IEEE (International Electrical and Electronics Engineers).

• CCE (Chief Controller of Explosives, Nagpur).


• BASEEFA/ PTB/NEC/EN/FM/CENELAC for hazardous area application.

4.0 STATUTORY APPROVALS / CERTIFICATES (AFTER GETTING ORDER)

4.1 The bidder shall be responsible for obtaining all statutory approvals, as applicable for all instruments and
instrumentation systems.

4.2 Equipment / instrument / systems located in electrically hazardous areas shall be certified for use by
statutory authorities for their use in the area of their installation. In general, following certification shall be
provided by the bidder.

i) For all flameproof equipment / instrument / systems, which are manufactured abroad (outside India)
certification by any approving authority like BASEFA, FM, UL, PTB, LCIE, CENELEC etc. shall be
required.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 4 of 5

Page 14 of 142
P.011489
PTS - SPECIAL INSTRUCTIONS
I-11078
TO CONTRACTOR
01

ii) For all flameproof equipment / instrument / systems manufactured locally (within India), certification
shall be carried out by any of the approved testing houses – Central Mining Research Institute
(CMRI) etc. The manufacturer shall hold a valid Bureau of Indian Standards (BIS) license.

Approval certificate from Chief Controller of Explosives (CCE) or Petroleum and Explosive Safety
organisation (PESO) is mandatory for all electronic / electrical instruments / equipments to be installed in
India, irrespective of country of origin.

Σ Σ Σ

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 5 of 5

Page 15 of 142
P.011489
SCOPE OF WORK I-11075
01

INDRAPRASTHA GAS LIMITED (IGL)


SCADA IMPLEMENTATION AT CNG STATION (INCLUDING
DTC & RETAIL OUTLET) & PNG SEGMENT
TRACTEBEL ENGINEERING PVT. LTD.

SCOPE OF WORK

RERT

0 19.06.2018 Issued for procurement MA SHD BK


Rev. Date Subject of revision Author Checked Approved

Page 16 of 142
P.011489
SCOPE OF WORK I-11075
01

TABLE OF CONTENTS

1.0 INTRODUCTION ............................................................................................................................ 1

2.0 PROJECT BRIEF ............................................................................................................................. 1

3.0 SCOPE OF WORK .......................................................................................................................... 1

4.0 GENERAL TECHNICAL REQUIREMENTS ........................................................................................... 6

5.0 QUALITY ASSURANCE AND QUALITY CONTROL .............................................................................. 9

6.0 HSE REQUIREMENTS ..................................................................................................................... 9

Rev.0- 19.06.18 SCADA implementation at CNG station page I of I

Page 17 of 142
P.011489
SCOPE OF WORK I-11075
01

1.0 INTRODUCTION

1.1 This document details the scope of work to be carried out by Contractor for this Project of M/s IGL.

2.0 PROJECT BRIEF

2.1 This Project is all about to build a SCADA and Remote terminal unit for collection of important data and
control & monitoring from master station of CNG station and its ancillaries across the Delhi , NCR & NCT
of Delhi, Rewari City & Karnal City.

2.2 This project is divided into three phases and will be executed in phase wise. Scope of work is covered about
all the phases. For total number of stations and equipment covered in phase I refer “Annexure IV. This list
is indicative only, further details such as number of CNG compressor, dispensers, metering skid etc. at each
CNG station will be shared with successful bidder.

2.3 Phase I comprise of :

• Fully equipped SCADA system which cater the capacity of all the upcoming phases and future
expandable capability with scalability in terms of tags and license, as per PTS – SCADA and RTU
system.

• Each CNG station shall be equipped with RTU. Existing equipment and sub system shall be interfaced
with RTU. For details refer PTS- SCADA and RTU system, Input Output list and List of equipment.

3.0 SCOPE OF WORK


The contractor’s scope of work shall include but not limited to the following:

3.1 Contractor shall read this document in conjunction with material requisition and Particular specification.

3.2 Scope of work shall comprise of System Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, Installation, Inspection & Factory Acceptance Testing (total
Equipment & System Integration) & Testing of system, Packaging, forwarding, Insurance, Shipping related
all formalities, Inland Transportation to site, and Supply of all related goods including Mandatory,
Commissioning consumables spares, operational spares, Loading & Unloading, Handling, Storage & Safe
custody, Supply of all type of Erection Items, Erection, site engineering, Pre-Commissioning activity,
Testing, Interconnection and interfacing interface with Large Display Screens and Third Party leased line or
MPLS available Networks, Trial Run, Commissioning, Training, support and Warranty Including any civil
works etc.

3.3 SCADA vendor shall supply, install, integrate, configure and commission all software and hardware
equipment like RTU, Servers, Switches Routers, firewalls, installation materials computers, Operators
consoles with controller and panels and workstation, printers laptop etc customized to IGL requirements and
minimum specifications shall be complied refer [Refer PTS- SCADA &RTU system for details].

3.4 Owner reserves the right to increase or decrease the scope of work ± 50% of tender quantities on same rate,
terms & conditions, during the period of contract including AMC period.

3.5 Vendor shall integrate and configure any upcoming and /or additional or left out or upgraded equipment that
will be installed and /or available at existing CNG stations (mentioned in Contract / Purchase Order) and
upcoming CNG stations in station RTU and SCADA system without any cost to client within contract
period including AMC period.

3.6 Vendor shall integrate their SCADA System with any other SCADA system in IGL/ SAP applications/
Business Analytic Tool/ or any other upcoming Applications without any extra cost to client during their
contract period including AMC period.

Rev.0- 19.06.18 SCADA implementation at CNG station Page 1 of 9

Page 18 of 142
P.011489
SCOPE OF WORK I-11075
01

3.7 Vendor shall integrate other make of RTUs/PLCs or any other equipment (limited upto 300 Nos) from any
of IGL Sites (or Locations), having compatibility with their SCADA protocol in to their SCADA system
without any extra cost to client within their contract period including AMC period.

3.8 Vendor shall upgrade all the supplied software including SCADA system for the next 10 years, without any
cost to client.

3.9 Contractor shall collect all the necessary drawings , document and information require for interfacing for
those equipment which are not in contractor’s scope of supply from Client

3.10 Contractor shall carry all the required Tools and Tackles require for installation, erection , testing and
commissioning of SCADA and RTU. Quantities of all the tools and tackles shall be adequate as per the
quantum to work. These qualities may require to enhance as and when required by Client to achieve the
project schedule or to expedite the progress.

3.11 Contractor shall also carry all the calibration equipment/ testing equipment like multi-meter, hand held
calibrator /4-20mA simulator, MODBUS Simulator, Profibus / Profinet Simulator etc.

3.12 Interconnection & interfacing of signals and communication cables, cabling, laying, terminations, ferruling,
cable numbering, marking, testing including hot & cold loop testing. Cable shall be laid in cable tray.

 Between Junction box to RTU cabinet – Multi-pair cable 6P x 0.5mm² (IS &OS) for Analog/Modbus
serial RS 485 and 6P x 0.5mm² (OS) for digital. Tentative aerial distance between JB and RTU is 15
mtrs.

 Between RTU to router/Switch /modem- Ethernet cable - As applicable.

 Between LAN switches, Router SCADA system and Telecom system-Ethernet cable – As applicable

Note – Size and Type of cable as given above is indicative. Contractor shall choose the cable size and type
according to need bases to reduce the number of runs but cable size and type shall be according to PTS-
Instrument cables only. No extra claim will be entertained at any stage of project.

3.13 Required masonry works for installation of consoles/servers/PCs/RTU systems etc. shall be in contractor’s
scope of supply.

3.14 The contractor to submit the proposed site organization to be set up for the execution of the work. It is
understood that this will be augmented from time to time depending upon requirement for timely
completion of work as directed by CLIENT project manager/site in charge. A chart showing the manpower
allocation and deployment to this job with specific job allocations shall be submitted by the contractors to
CLIENT. The contractor shall take prior approval from CLIENT/ for any change in allocation and
deployment.

3.15 Drinking water, construction water, lodging, boarding, transportation for all workers shall be arranged by
contractor at their cost.

3.16 The contractor shall engage sufficient number of workforce skilled/semiskilled along with experienced and
competent supervisors and engineers to ensure quality of work and also for smooth and uninterrupted
progress of the works under this work order. The contractor shall arrange at its own cost the necessary
consumables, accessories, equipment, tools & tackles required for execution of the job under this work
order/contract. The contractor shall also arrange transportation, lodging, boarding of its personnel deployed
for executions of the work at site.

3.17 Contractor to plan and execute their work in a phased manner as directed by Client/PMC and from time to
time and fully co-operate with other agencies working at site simultaneously so as not to obstruct or retard
the work being executed simultaneously by other agencies.

Rev.0- 19.06.18 SCADA implementation at CNG station Page 2 of 9

Page 19 of 142
P.011489
SCOPE OF WORK I-11075
01

3.18 Any other equipment /material not specifically mentioned herein but required to complete the work (i.e. to
install, commission and successfully run the Installation) is covered under this document.

3.19 Labor license has to be taken by contractor; Form-V shall be issued by CLIENT. Any other local statutory
liasoning shall be in contractor scope.

3.20 Contractor shall prepare, maintain and submit inspection reports, erection/installation progress reports,
material log etc. as decided by Client.

3.21 Daily/Weekly/Monthly progress report, Documentation like procedure preparation and approval, furnish of
inspection reports, handing over the documents after completion of project etc shall be done by contractor at
their cost.

3.22 Contractor shall submit all test reports like Calibration reports, cable Megger Report, loop checking report,
material reconciliation report. Contractor shall also collect the Manufacture test certificate, Inspection
reports, Equipment drawing, wiring received along with equipment/packages and submit the same to Client.

3.23 Fabrication and installation of MS base frames, supports for Panels/cabinet, console/panel/ cabinet supports,
pipes, plates etc. including welding, bolting, riveting, supply of necessary anchor bolts, grouting etc., supply
of paint and applying one coat of anti-rust primer and two finished coats of approved synthetic enamel
paint, breaking walls, floors etc. for structures as required and supply of all GI hardware materials as
required

3.24 Contractor to supply the material as per recommended vendor list. If any item is not covered under
approved vendor list, contractor shall take written approval of CLIENT before supply of material.

3.25 Necessary documentation for Gate Passes and Work Permit for man power and
removal/shifting/Installation/Commissioning/or any project work will be in Vendor’s scope.

3.26 Unloading of material/equipment related received at site shall be in the scope of contractor. Bidder shall
depute requisite manpower to unload project material received on site. In addition to this bidder shall be
responsible to transport the project material from IGL store to site or site to site, if needed.

3.27 Inspection of received material by unpacking/opening boxes at site including spares & material to be
received at site in presence of Client/Engineer in charge/OEM.

3.28 Contractor shall store/shift the packing material at designated location decided by Client. Assistance in
temporary preservation of equipment.

3.29 Permission for late hours working and working on Saturday/Sunday and Holidays

3.30 Contractor shall follow Quality and Safety requirement during construction phases of the Project.

3.31 Contractor shall follow permit to work system of CLIENT. All activities shall be in line with CLIENT’s
HSE policy, contractor shall conduct tool box talks, safety review meetings, promotional activities,
awareness programs etc., machinery and equipment shall meet with HSE requirements, contractor has to
provide warning sign boards, cordoning of working area, PPE to workers. Contractor to comply
observations raised by any inspection agency/Client internal audit.

3.32 Any special training for height work, electrical/mechanical safety, Scaffolding work, special toolbox, etc.,
for workers, promotional programs, motivational programs etc., shall be in scope of contractor.

3.33 Contractor shall be responsible for safety and security of material/equipment.

3.34 Correction, updating and submission of all drawings/layouts/documents. Contractor shall submit marked up
drawings for final as built.

3.35 Scope matrix

Rev.0- 19.06.18 SCADA implementation at CNG station Page 3 of 9

Page 20 of 142
P.011489
SCOPE OF WORK I-11075
01

Part A

Sr. Equipment/Packages SCADA vendor Scope of work Free Issue Item/IGL


No Scope

1 SCADA System Supply, installation, testing, integrated 1. Master control room,


FAT with telecom system, console/furniture, chair.
commissioning, test run, SAT and
handover to Client as per PTS – 2. Uninterrupted power
SCADA and RTU system and supply from feeder to
“Material Requisition” SCADA vendor
supplied PDB.

2 Remote terminal Unit Supply, erection, installation, testing, 1. Station Control


integrated FAT with SCADA & room/mounting space at
telecom, interfacing with existing CNG station,
packages at CNG station,
commissioning, test run, SAT and 2. uninterrupted power
handover to Client as per PTS – supply upto RTU,
SCADA and RTU system and
“Material Requisition”. 3. Profibus (MPI/PPI) and
Profinet(Ethernet)
Erection, installation of RTU inside the protocol is available in
station control room including supply CNG Compressors.
of all the required erection materials
and civil works. 4. MODBUS RS485
available for CNG
SCADA Vendor shall ensure that RTU Compressors,
shall be compatible with profibus and Dispenser, Flowmeters,
profinet protocols and have RS485 Flow computers and
ports as per Annexure III. VFD's, Soft starters etc.

5. Providing the all


required information
regarding
communication ports
address, slave ID, baud
rate, parity etc to
SCADA vendor.

3 Telecommunication Supply, installation, of dual SIM 1. Supply of SIM cards


Modem modem and MPLS (two independent from service providers
ports for SIM i.e GPRS and one
dedicated port for MPLS) , testing and 2. Uninterrupted power
interfacing with RTU and SCADA supply.
system, co-ordination with service
provider, establish communication, test 3. Two broad band/MPLS
run, SAT and handover to Client as per connections at Master
PTS – SCADA and RTU system and station
“Material Requisition”.
4. MPLS (Wired/Wireless)
Calculation of bandwidth requirement 2G/3G/4G Connectivity
at remote station and master station at IGL sites.
shall be submitted by vendor.

4 Cables (Single cable, Cable laying, glanding, termination Supply and cable laying of
cable, communication (from existing JB to RTU), ferruling, communication and signal
Rev.0- 19.06.18 SCADA implementation at CNG station Page 4 of 9

Page 21 of 142
P.011489
SCOPE OF WORK I-11075
01

cable, LAN cable, RS- lugging, tagging, clamping, marking cables from CNG station
232/485 cables, OFC etc. Scope includes supply of cable tag, equipment and field
etc.) Cable ferrule, clamps and all the instruments to Junction
required items to complete the laying box, including loop testing,
works. Cable laying from as per above multi dropping etc.
clause 3.12 Providing terminal details
to SCADA vendor
SCADA & Telecom communication
cable (Ethernet) Multidrop loop testing
equipment wise on
LAN cable for work stations. For LAN simulator software at
cable, contractor shall supply conduit junction box end in
of proper size and lay cable inside the presence of SCADA
conduit. vendor

Supply and laying of


profibus cable, Profinet
cable, CAT 6 cable from
CNG compressor to RTU

5 Earthing pit Provision for earth connection (IE and Earthing pit (IE and PE)
PE) in system and laying of earthing strip
and connectivity upto
SCADA and RTU system.

6 Additional station / Integration and configuration of third Third party device


Upcoming station/ party/Vendors devices i.e. RTU/PLC RTU/PLC/FC with
Any IGL site (Refer FC etc in SCADA system. compatible protocol,
clause 3.5 to 3.7) telecommunication system
In case IGL wish to get install vendor’s including modem, modbus
proposed RTU system at any IGL site address etc.
then the supply, installation,
commissioning of RTU system shall be
done on same rates during the period of
contract including AMC period.

Part B

Scope

Sr. Item Description Contractor Client Remarks


No.

1 Unloading the material/equipments YES


received from vendors to site, shifting
of equipments/material from store to
installation location or site to site..

3 Staff and labor transportation YES

4 Labor accommodation. YES

Rev.0- 19.06.18 SCADA implementation at CNG station Page 5 of 9

Page 22 of 142
P.011489
SCOPE OF WORK I-11075
01

5 Labor license. YES

6 Wooden sleeper as required. YES

7 Office container as require YES

8 Required material for preparation of YES


platform

9 Obtaining statutory approval (if any) YES


for system of project.

10 Preparation Job Planning and schedule YES As per approval


and DPR by Client

11 All statutory compliance YES

12 Paid all government duties & taxes YES


applicable for contractor

13 Scaffolding material and installation as YES As per


require requirement.

14 welding machines YES As per


requirement.

15 Documentation like procedure YES Approved by


preparation, work schedule, calibration PMC/CLIENT
reports, inspection report, progress
report, termination details etc.

16 Temporary Illumination at work site YES

4.0 GENERAL TECHNICAL REQUIREMENTS


4.1 General site equipment shall be suitable for operation under the following site conditions.
Sand & dust : With a built-up of dust on operational surface to a level such as
may occur because of imperfections in the sealing of equipment,
housing and conditions prevailing in sub- tropical dust conditions.
Tropicalisation : The equipment shall be fully tropicalized.
Shock & vibration : The equipment shall withstand transportation and handling by air,
sea and road under packed conditions.
4.2 The equipment shall also be resistant to termite, fungus, rodents and salty environment. Environmental
Specification of Equipment to be supplied.
4.3 The equipment at Stations shall be designed for non-air conditioned environment and shall perform
satisfactorily under the following conditions.
Activity TEMPERATURE HUMIDITY
Design for 02 to 60°C 90% RH
Storage & transportation 02 to 60°C 90% RH

Rev.0- 19.06.18 SCADA implementation at CNG station Page 6 of 9

Page 23 of 142
P.011489
SCOPE OF WORK I-11075
01

4.4 Area and zone classification


All the control rooms wherever available are classified as Safe Areas.
All the fields wherever available are classified as Hazardous area.
4.5 Power supply, Reliable and rugged redundant 24V dc power supply unit shall be provided.

4.6 Surge Protection, Transient Suppressors, RFI filters

Equipments shall be designed with built-in safety to protect against the effects of monitor induced high
voltages.
4.7 Earthing

Transmitters, Junction box and control cabinets shall be provided with earthing lugs. All these lugs/ strips
shall be properly secured to the electrical earthing bus.
All system grounds of various cards and equipment, shields of instrument cables shall be connected to
system ground bus, which is electrically isolated from the AC mains earthing bus. The equipment shall
provide separate earthing strip for the same. The system ground bus shall be connected to independent
ground buses through insulated wires.
The wire and cable shielding is required to prevent the equipment from propagating interference and to
protect the equipment from the effect of interference propagated by other devices. Shielding is typically
floating on the device end, tied to IE at the control console.
a) System grounding (earth resistance less than 1 ohm)
b) Frame and AC mains grounding (earth resistance less than 5 ohms)
Accordingly, the equipments shall provide separate earthing strips as mentioned above.
a. Instrument earth(IE)/system ground
IE earth shall be copper earth. IE ground protects sensitive electrical and electronic device, circuit and
wiring from electromagnetic interference (EMI) and radio frequency interference (RFI). IE should be
free from transient voltages and electromagnetic noise. It is, therefore, normally isolated from PE
ground. Instrument earth should be tied in the most direct possible path to a common earth electrode.
IE grounds resistance is less than 1 ohm to ground
b. Power Earth (PE)/AC mains grounding
PE ground provides a route to dissipate the power line transient to earth potential. PE should be tied in
the most direct possible path to a common earth electrode
PE grounds resistance is less than 5 ohm to ground
4.8 Safety Requirements

It is the intent of the CLIENT that operational hazards be reduced to a minimum. Contractor shall use
sound engineering judgment to complete installation that will perform the required function without
compromise of safety.
All controls shall operate in a fail-safe mode. A fail-safe mode defines what a plant, equipment or system
will do when it fails, so as to ensure a safe condition.
Provision shall be made to isolate all 230 V AC (If any) incoming signals to a cabinet, before gaining access
to cabinet internals. Shrouded terminals with warning labels shall be provided, with these terminals being
segregated from other incoming terminals.
4.9 Electromagnetic Compatibility - EMC

The equipment shall be efficiently screened against EMI, RFI and conductive interference and shall not
interfere with other equipment in the vicinity or installed in the same building.

Rev.0- 19.06.18 SCADA implementation at CNG station Page 7 of 9

Page 24 of 142
P.011489
SCOPE OF WORK I-11075
01

The equipment shall be required to meet one of the relevant EMC standards (IEC, MIL, VDE, BS, IEEE
etc.).
4.10 All the electronic component shall be protected from airborne contaminants as per ISA 71.04 environmental
conditions for process measurement and control system. For those equipment mounted in field shall be G3
compliant and control room mounted shall be G2 compliant.

4.11 Civil Works

a) Civil works required for interconnecting cabling as per scope of work.


b) Associated foundation, grouting for installation of equipment.
c) Providing and laying perforated trays etc. for point a) above.
d) Any other masonry work associated with entry and installation of equipment, painting and finishing etc.
e) Any other civil works not specifically mentioned in the tender but required as per site requirement.
4.12 Electrical Works

Electrical work associated at all the stations shall be consisting of (but not limited to):
a) All earth cable work associated with the installation of the supplied equipment.
b) Any temporary electrical works associated with the installation and commissioning of the system.
c) Testing and certification of all electrical works.
4.13 Measuring Units

The metric SI system shall be used for all documents. The following units of measurement as well as their
multiples and sub-multiples, shall be used:
Flow
Gas : Sm3/h (15.556OC; 1.01325 bar), MSCMD, Kg/Hr
Liquid : m3/h (at flowing temperature)
L/h for flow lower than 0.1 m3/h
Steam, condensate and mass flow: kg/h.
Pressure
Gauge pressure : kg/cm2 (g) and Bar (g)
Absolute pressure : kg/cm2 (a) and Bar (a)
Differential pressure : kg/cm2, mm of H2O, mm of Hg and mill bar
Level
0 - 100 % (Process)
Temperature
Deg C
Other Measurements
Current: A or mA
Voltage: V or mV
Power: kW
Force: N
Mass: kg or t
Rev.0- 19.06.18 SCADA implementation at CNG station Page 8 of 9

Page 25 of 142
P.011489
SCOPE OF WORK I-11075
01

Density: kg/m3
Time: d or h or s.
Scales and Charts
Temperature instruments shall have scales calibrated in °C.
Pressure + be 0 - 100 linear.
4.14 Cable Ties
All cable ties shall be constructed from black PVC and have a breaking load greater than 20 kg. They shall
be of a self-locking style and non-slip, but shall be releasable for the addition of extra cables. Cable ties for
use on trays shall fix into the tray slots (two-piece ties).
4.15 Nameplates Tags labels
The nameplates, tags and labels for identifying junction boxes, instruments, panels, cabinets, etc shall be
made from engraved trifoliate.
5.0 QUALITY ASSURANCE AND QUALITY CONTROL

CONTRACTOR/ VENDOR shall be fully responsible for their Quality Assurance and associated Quality
Control process.
Unless otherwise agreed by the PURCHASER, the CONTRACTOR/ VENDOR’s quality system shall meet
the requirements of ISO 9001:2007 Quality System and shall be accredited by a recognized authority.
CONTRACTOR/ VENDOR are required to establish an acceptable Quality Plan, inclusive of quality
manual and procedures that cover all activities of the order, in order to comply with the Quality System
requirements.
CONTRACTOR/ VENDOR shall be responsible for arranging/liaising with the Third Party Inspection
Agency and other agencies for design appraisal, inspection, survey and certification requirements as
required by the specification/requisition.
When required, waiver and acceptance of non-conformances shall be subjected to Third Party Inspection
Agency approval before COMPANY endorsement. These concession records shall be included in the
Manufacturer’s Final Documentation.
6.0 HSE REQUIREMENTS

The contactor shall abide by all the safety and other rules and regulations of COMPANY site.
The contractor shall provide the Personal Protective Equipment to his operators / electricians / labor / helper
/ engineer etc. This personal protective equipment includes a minimum of coverall, safety glasses, safety
hard hat, safety shoes, hand gloves and ear protection. The contractor will have to get these PPEs approved
by COMPANY HSE Engineer.
All waste generated at company site due to the contractor’s equipment / personnel shall be cleared by the
contractor and disposed of properly in accordance with company rules and local government regulations. A
record of such waste disposal shall be maintained by the contractor for submission to Company whenever
required.
Upon demobilization, the contractor shall ensure that the site is cleaned properly of all debris and waste.
These shall be disposed of properly by the contractor in accordance with company rules and local
government regulations.
Contractor shall ensure to carry out work after obtaining "WORK PERMIT" from CLIENT/COMPANY's
authorized engineer.
Σ Σ Σ

Rev.0- 19.06.18 SCADA implementation at CNG station Page 9 of 9

Page 26 of 142
P.011489
SCADA OPERATION PHILOSOPHY I-11049
01

1.0 SCADA PHILOSOPHY


1.1 SCADA system at Integrated Control Centre (ICC) will comprise of Server #A (Active) & Server #B
(Hot standby) and Server# C (future Hot standby refer note given below). All the RTUs at CNG station
shall directly report to Active server at that moment.
1.2 The system shall have complete SCADA database including the real-time database and integrated alarm/
event management summary for overall operations management & control for the entire network.
1.3 Three Servers i.e. Server # A(Active as primary) and Server # B (standby as secondary) & Server#C
(Standby as third) shall be configured in hot standby mode. Operator shall have privilege to select any
one server as active and standby initially. Each SCADA server shall be fully adequate to fulfill the entire
monitoring, operation and control requirements of the entire network and sizing of each server CPU such
as, average Memory, disc utilization do not exceed 60% in the implemented system.
1.4 SCADA system shall run on redundant LAN configuration LAN A (Primary) and LAN B (Secondary).
Both the servers shall have dedicated ports for primary LAN and secondary LAN.
1.5 Normally, Primary server shall poll all the RTUs on primary path. In case of any problem on primary
path, the Primary server shall poll the RTUs on secondary path. In case of problem in both primary and
secondary paths of primary server, Secondary server shall poll the RTUS on the primary path. In case of
problem in primary path of secondary server, RTU shall poll on secondary path of secondary server.
Therefore, in case of primary server failure, Secondary server shall Poll all the RTUs. The changeover
to secondary server shall accomplish within 1 minute automatically without causing any loss of data
and control without any effect on SCADA functionality. System shall inform the operator by flashing or
pop of message on HMI screen about the failed system by active SCADA server/standby server.
1.6 When RTU being poll through one path, the system shall continue to obtain health status of the RTU as
well as path status through the other path. On restoration of a failed path, system shall revert to the earlier
preferred path for polling as described above automatically without any human intervention whatsoever
or manually.
1.7 All the databases including Real time database, historic database, archive database and configuration
database shall be synchronized between Primary, Secondary & third Server. The interchange of health
messages between of Server shall be implemented through Local Area Network (LAN). Health status
of each of the SCADA Servers, system nodes and RTUs shall be updated at both servers in real-time.
1.8 Normally secondary & third server shall be in hot redundant standby mode but incase operator or
engineer decide to put in cold standby mode, it should be possible to switch over standby server in cold
standby mode manually when primary is in active. Once standby server is online, the data in secondary
server shall be synchronized with active server automatically.
1.9 In case any modification or creation of new points in database, it should be possible to use the standby
server for database creation and same shall be updated in active server without any interruption or data
loss.
1.10 The SCADA vendor shall have the option to implement the features of Alarm generation, association of
the alarm priority and engineering unit conversion at the RTU level or at the SCADA host level.
However, in case of RTU level, operator shall have privilege to modify or create new alarms in RTU
from master station.
1.11 Operator/supervisor shall have privilege to update manually the Primary Server database such as (manual
inputs, online SCADA database, alarm acknowledgements, alarm inhibit, digital controls, set-point
controls etc.) to database of Secondary Server to maintain database synchronization between Primary &
Secondary.
1.12 History database and archiving files between Primary Server, Secondary Server and third server shall
remain synchronized to maintain database consistency.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 1 of 3

Page 27 of 142
P.011489
SCADA OPERATION PHILOSOPHY I-11049
01
1.13 When the SCADA Server starts up after recovery from failure, the real time and historical SCADA
database shall become identical to the active SCADA Server. The event indicating that this recovered
SCADA Server has become STANDBY shall denote that SCADA databases have been synchronized.
1.14 The failed SCADA Server on recovery if it finds itself isolated from the active SCADA Server in the
Local area network, it shall not become active SCADA Server automatically. Additionally the active
Server, if it gets isolated from LAN (i.e. failure of both LAN connections) then it shall loss its active
(primary) status and the other SCADA Server (which is connected with the network Server) shall become
active Server automatically (i.e. implying that the disconnected Server from both LANs shall not
become active automatically). However, when the system is started for the first time, the network
connectivity shall be available and checked the SCADA Server being started first shall become active
SCADA Server or by operator choice.
1.15 For user presentation, the data source for SCADA displays, reports, trends, alarms/ events etc at HMI
workstations at ICC shall be from active SCADA Server. The HMI software shall operate in client-server
mechanism where the HMI shall make direct database connection to the directly accessible active
SCADA Server (which contains the complete SCADA database).

1.16 SCADA server # C will have all the functionality for operation as per ICC server. Server#C will be a
hot standby to ICC servers. In case both the server at ICC are down i.e ICC is not available then the
polling shall be done by this automatically using the above philosophy. All the OWS, EWS at ICC and
RTU will get connected to this.

1.17 Server # C will be started automatically for polling the RTUs as described above. On restoration of ICC,
it shall be possible by system engineer at ICC under suitable security password control to put cloud
SCADA server in hot standby and subsequently make ICC to take control.

1.18 Normally, server #C shall poll all the RTUs on primary path. In case of any problem on primary path,
server#3 shall poll the RTUs on secondary path. In case of problem in both primary and secondary paths,
System shall inform the operator by flashing or pop of message on HMI screen/Mobile/SMS/Email about
the failur of cloud system.

1.19 During standby mode of server #C, it should be possible for user to access the data with remote desktop
or on mobile in case of cloud. this should get synchronized with master server always. It shall also be
possible for authorized personnel of IGL to change dispenser price, same shall be updated in master
server even though cloud is in standby mode.

NOTE – At present, SCADA Server # C is not required. Server #C, may be cloud server of or
physical server at any different seismic location. Proposed SCADA system shall be compatible to
above philosophy and any make or services provider cloud system. Client is intended to implement third
server during any stage of project. Therefore, bidder is required to give their compliance to above
functionality.
2.0 RTU PHILOSOPHY
All the RTUS shall have two Ethernet communication for primary and secondary LAN, port A and Port
B respectively. Port A and Port B shall be reachable from ICC LAN A and LAN B.
Generally, ICC tries all the RTU on Port A from LAN A. In case of any problem in that path, the RTU
shall be tried on Port A through LAN B. In case of RTU not accessible through Port A from ICC end, it
shall try through Port B from either LAN A or LAN B from ICC.
Switch over from Port A to Port B or via-a-versa shall automatically without loss of data. Appropriate
fault message shall be generated on SCADA system about failure of fault port.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 2 of 3

Page 28 of 142
P.011489
SCADA OPERATION PHILOSOPHY I-11049
01
3.0 TELECOM MODEM
Telecom modem/gateway shall have three ports, two ports are dedicated to GPRS SIM and one ports is
dedicated to MPLS.
For those locations where MPLS line is available, there MPLS will work as a master ports, when MPLS
is down, one GPRS port will take over and communication with master station will continue. In this case
MPLS will be active ports and any one port of GPRS will act as a standby and second GPRS port will
remain spare.
For those location where MPLS line is not available, there one GPRS port will acts as master and second
port will be standby. Failure of master port, standby port will take over the communication with master
station. In this case MPLS port will remain spare.
4.0 WEB SERVER
• To view all the online SCADA MMI displays i.e. graphics and alarms with online updating trends
and reports using browser through Internet.

• Functionality for Important alarms and messages through email and SMS servers to concern person.
The email server shall also send daily reports/messages automatically and on event trigger basis. It
shall be possible to configure the users to whom the SMS and e-mails are sent. The mobile number
and e-mail addresses shall be editable/configurable as and when required.

• System shall have provision to escalate the levels for sending the SMSs and emails based on the
time elapsed from occurrence of alarm. In case of occurrence of a critical alarm, a SMS and email
shall be sent automatically to concerned maintenance persons. If the alarm does not return to normal
within a specific time of occurrence of alarm e.g. 1 hour (configurable), then the SMS/email shall
be sent to some higher officials (configurable) also. If the alarm does not return to normal within a
specific time of occurrence of alarm e.g. 6 hour (configurable), then the SMS shall be sent to some
further higher officials (configurable).

• Facility for control /ON-OFF operation for critical equipment(s) at CNG station such as CNG
Compressors, Station inlet valve, etc. and probable remote price in CNG Dispensers from web server
with administrative access level with One level of authorization.

4.1 MOBILE APPS


Mobile apps in web server shall have following min functionality
• All mobile apps must authenticate IMEI number of all mobile phones for secured data access.
Authentication shall fails if the IMEI number is not registered.

• Live data access based on hierarchy (configurable), with secure password authentication.

• Live station status data

• Historical data for min, max avg for day, week, month and year

• Provide easy navigation access to select any station

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 3 of 3

Page 29 of 142
P.011489
PTS - SCADA AND RTU
I-11097
SYSTEM
01

INDRAPRASTHA GAS LIMITED (IGL)


SCADA IMPLEMENTATION AT CNG STATION (INCLUDING
DTC & RETAIL OUTLET) & PNG SEGMENT

TRACTEBEL ENGINEERING PVT. LTD.

PARTCULAR TECHNICAL SPECIFICATION


SCADA AND RTU SYSTEM
RERT

0 19.06.2018 Release for Procurement MA SHD BK


Rev. Date Subject of revision Author Checked Approved

Page 30 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

TABLE OF CONTENTS

1.0 INTRODUCTION .................................................................................................................. 1

2.0 CONVENTIONS .................................................................................................................... 1

3.0 BRIEF DESCRIPTION .......................................................................................................... 1

4.0 ENVIRONMENTAL SPECIFICATIONS .................................................................................. 2

5.0 POWER SUPPLY .................................................................................................................. 3

6.0 SCADA AND RTU SYSTEM. .................................................................................................. 3

7.0 DESIGN CRITERIA .............................................................................................................. 6

8.0 SYSTEM FUNCTIONAL REQUIREMENTS ............................................................................. 8

9.0 REMOTE TERMINAL UNIT ................................................................................................. 20

10.0 DRAWINGS AND DOCUMENTATIONS ............................................................................... 25

11.0 INSTALLATION & COMMISSIONING ................................................................................ 28

12.0 EQUIPMENT INSPECTION & TESTING .............................................................................. 29

13.0 TRAINING ......................................................................................................................... 32

14.0 COMPREHENSIVE POST WARRANT MAINTENANACE CONTRACT (PWMC) ...................... 33

ANNEXURE -I - SOURCE OF SUPPLY (SOS) FORM

ANNEXURE -II- POWER CONSUMPTION REQUIREMENTS (PCR) FORM

ANNEXURE -III- TYPICAL I/O COUNTS DETAILS FOR RTU SYSTEM

ANNEXURE -IV – LIST OF EQUIPMENTS AT CNG STATION

ANNEXURE -V – TOTAL PHASE STATIONS

ANNEXURE-VI – EXISTING PLC DETAILS

Σ Σ Σ

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 1 of 1

Page 31 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

1.0 INTRODUCTION

1.1 This specification covers the basic requirements of SCADA AND RTU systems along with associated
equipment purchased as a "Single point responsibility package unit" for CNG stations and other field
segments/equipment(s) (i.e. MRS, FRS, TR Units etc.).

1.2 This Project is an important tool for IGL to maintain control over its exponential growth of CNG & PNG
Network across the Delhi , NCR & NCT of Delhi, Rewari City & Karnal City and upgrade existing
products and maintain competitive position in the market with the existing infrastructure, human resource
etc.

2.0 CONVENTIONS

In this document, the following words are used to define the significance of each particular requirement.

2.1 CNG Stations/ CNG Network


These words are used for all type of CNG stations in IGL and its ancillaries, which includes CNG facilities
at IGL Owned CNG stations, Retail Outlet and Bus Depots.

2.2 Field/ Field Equipment/ RTU station

These words are used for all type of Gas facilities/ equipment(s) in IGL, i.e. Gas Chromatograph,
Odourizing Units, Sectionalizing Valves etc.

2.3 Integrated Control Centre/ Master Station/ Master Control Station

These Words are used for main Control Centre where SCADA system will get installed which will
communicate with all type of RTU station.

3.0 BRIEF DESCRIPTION

3.1 Design, engineering, supply, installation, integration with existing CNG system, other Field Equipment &
its associated ancillary and commissioning of SCADA and RTU system. Refer “scope of work” enclosed
with tender document for detailed scope.

3.2 System shall ensure safety and reliable operation of the equipment as per following functionality.

• Monitoring and control (if required by IGL) of dispenser parameters as per defined authorization from
IGL Head Quarters or Master Control Station/ Integrated Control Centre (ICC) and web server (from
remote location) with one-layer authentication.

• Valve ON/OFF operation from MCS/ ICC as well as from web server

• Motor/compressor ON/OFF operation from MCS/ ICC as well as from web server

• Preventive and predictive maintenance of RTU and SCADA.

• Remote diagnostic and configuration of RTU and SCADA

• Single modem/router/gate way with MPLS and Dual SIM 3G/4G (1W+1S) functionality, compatible
with SCADA system with switchover facility to achieve uninterrupted data transfer from RTU station
to ICC.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 1 of 34

Page 32 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

3.3 Master control station /Integrated Control Centre (ICC), SCADA system shall be located at “IGL
Kakanagar office”, New Delhi for monitoring and controlling.

3.4 RTU, shall be installed at each CNG station/Field in safe area identified by IGL. The system shall be rugged
in construction and suitable for working in non-AC ambient. RTU, shall be designed by considering
required Inputs & outputs and future expansion. All the inputs & outputs including spares, shall be fully
wired upto the terminal blocks.

3.5 RTU shall be interfaced with telecommunication system for transferring data to Master control stations
/Integrated Control Centre. Telecom system shall be redundant wireless 3G/4G MPLS type. Telecom
modem at RTU end shall be compatible with dual SIM cards as well as MPLS connectivity and can be
inbuilt/ integrated with RTU or separate modem linked with RTU.

3.6 RTU shall be comprised of CPU, Power supply card, communication cards/ports, input cards, output cards,
controller card, interface cards, wall mounted IP 54 cabinet and required internal accessories such as fan,
illuminating lamps, barriers, relay MCBs, terminal blocks etc.

3.7 It is the prime responsibility of vendor to establish the communications between field instrument, RTU,
Telecom and SCADA. If any additional items are required to make the system fully functional during
interfacing stage, that shall be made available to Client by vendor without any price implication even
though it was not considered during bid submission.

3.8 The system shall meet the requirements of interoperability, portability and scalability as per the
international standards (latest version).

3.9 Vendor shall submit duly filled in and signed SCADA source of supply (SOS) and power consumption
requirement (PCR) form during bid submission.

3.10 Vendor shall undertake full responsibility for providing a complete and evolutionary state of the art SCADA
System with Open architecture, meeting the objectives, functional and specific requirements described in
the tender.

3.11 Vendor shall submit the drawings and documents of the complete system as indicated in Material
Requisition (MR). Vendor shall submit as-built documentation, drawings of the complete system. These
submissions shall be made in hard copies and in CDs

3.12 Execute civil works associated with the installation of supplied equipment(s) at various stations and at
master station/ Integrated Control Centre.

4.0 ENVIRONMENTAL SPECIFICATIONS

4.1 All equipment shall be designed for operation, storage and transportation under the following environmental
condition:

Max. / Min. Temperature : (-) 5 °C / 45 °C

Design temperature : (-) 20 °C to 65 °C

Relative Humidity : 95%

Hazardous Area Classification : Zone 2, Gas Group II A or B, Temp.


Class T 3

Control Room : Safe Area

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 2 of 34

Page 33 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

5.0 POWER SUPPLY

Electrical power supply shall be provided at one point inside the battery limit as per the details provided
below. Further distribution shall be in the scope of the CONTRACTOR. If any other voltage levels are
required, then all necessary conversions shall be in the scope of CONTRACTOR.

There may be the case of availability of passive port in existing system which are to be interfaced with RTU
as per tender requirement. In such a case, Vendor shall supply the appropriate voltage level converter with
require quantity (DC to DC) for establishment of communication between RTU and existing system on
Modbus (RS485). Vendor shall ascertain the requirement of voltage level converter for communication port
after consulting with client/OEM or their own site and supply accordingly.

Normal supply : 230 V AC UPS power supply will be provided at all the stations for RTU.

Field Transmitters: 24 V DC loop power through barrier/ isolators. Contractor will arrange to
convert the power supply from 230V AC to 24V DC.

230 V AC Non UPS power supply for panel lights, fans, power sockets, etc.

6.0 SCADA AND RTU SYSTEM.

6.1 SCADA Hardware at MCS/ ICC

a) SCADA system shall be inclusive of two number data polling Servers (real time server) on latest
Windows (OS) (one working and 1 standby) along with one number of 21” monitors (Common for real
time server, and history server), keyboard, mouse and KVM switch. Server must have OPC UA (server
and client) for third party interface. OPC UA may be inbuild in SCADA server or separate PC.

b) Web server with 21” monitor for remote monitoring.

c) License will be maintained by SCADA implementation agency during the entire tenure of AMC &
Project implementation without any cost to IGL.

d) One number archive server (History server) for providing offline storage of historical files for period of
three years.

e) One number Server cabinet for mounting all the servers, server monitor, key board, mouse, KVM
switch, GPS, network switches etc.

f) One number GPS with NPT server, antenna and cable min 30 mtrs for time synchronization.

The GPS clock envisaged at master station /Integrated Control Centre shall be used to synchronize the
clock of servers, workstations, engineering workstation on the dual SCADA LAN at master station /
Integrated Contrl Centre (ICC) and to synchronize the RTU time with ICC.

g) Two number 24 port LAN switch L2.

h) One number 10 port router/L3

i) One number 8 port KVM Switch: Keyboard, Video and Mouse.

j) A4 size printer colour

k) Fire wall security for SCADA server and web server shall be for complete system. This shall comply
ISA 99/ISO 27001 standard.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 3 of 34

Page 34 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

l) One number engineering work station (EWS), 21” monitor, mouse and keyboard. EWS operating
system shall be windows based. EWS shall have latest software with license like HMI/MMI
development, Microsoft office, antivirus etc. EWS is required for configuration, MMI development,
maintenance and engineering aspects of the SCADA system. EWS can also serve the purpose of
operator workstation.

m) Two number operator workstation (OWS), 21” monitor, mouse and keyboard. OWS shall have latest
software with license like HMI / MMI run time, Microsoft office, antivirus etc. Operator workstations
are required to allow the plant operator to monitor and control safely.

n) EWS& OWS shall have HDMI & DVI Ports for connecting to existing Video Wall (DELTA make).

o) Redundant LAN: The redundant LAN consists of two distinct Ethernet segments; each segment has its
own dedicated Ethernet switch. Critical components including SCADA servers, archive servers, GPS,
EWS and OWS will be provided with dual Ethernet ports allowing connection to both segments of the
LAN. Non-critical items including printers connect on single segment of the redundant LAN.

6.2 SCADA System software

a) The SCADA software with main SCADA database shall be in SCADA server resident. Operating
system for SCADA server shall be Windows latest.

b) EWS and OWS shall be loaded with Application software MMI and Microsoft office. Operating system
shall be built around latest windows based.

c) The networking shall support OSI TCP/IP network connectivity.

d) Web server shall loaded with latest windows operating system, Mobile Apps, SMS/email facility

e) The LAN shall meet IEEE 802 standards.

f) The Communication protocol with SCADA and RTU’s will conform to IEC 870-5-101/104 or DNP3
over TCPIP, OPC UA, Modbus TCP/IP, etc.

g) The Servers will be loaded with OPC (UA) software (both client and server.) with license for data
exchange (reading and writing) with other system like APPS, SAP, Business Analytical Platform,
existing SCADA system etc.

OPC UA shall Open Platform Communications Unified Architecture (OPC UA) for machine-to-
machine communication protocol and shall be the following requirement

• Security Model

• Mappings

• Profiles

• Data Access-Real time

• Alarms and Conditions

• Event

• Programs

• Historical Access

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 4 of 34

Page 35 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

Note: In case of integration of with 3rd party applications, SCADA vendor shall provide support and ensure
the same without any cost implication to IGL.

h) The solution shall be able to interoperate with Multiple RDBMS platforms like Oracle, MS SQL, MY
SQL, DB2, Informix, Sybase or any other RDBMS confirming to ANSI/ISO SQL-200n standards

i) The system shall support on multiple hardware such as Dell, HP, Cisco, etc.

6.3 Remote terminal Unit

The RTU shall comprise the following subsystems:

• Central processor with system software.

• Analogue input

• Contact (digital) input

• Contact (digital) output

• Modbus Serial ports (RS 232)

• Modbus Serial ports (RS 485) two wire connection type

• RTU shall support all Protocols like MPI/PPI/Profinet/profibus directly or using convertor of Siemens
PLC's and MODBUS RS485 for another device at stations like Dispensers, Flow Meters, Soft starters,
VFD's etc.

• Ethernet port (Redundant)

• SMPS Power supply

• Diagnostic port

• USB Port/SD card

6.4 RTU software

• Programming software as per IEC 61131

• Cyber security as per IEC 62443/ISO 27001

• Local and remote Diagnostic tool


Note:

All the Software License will be maintained by SCADA implementation agency during the entire tenure of
AMC & Project implementation without any cost to IGL.

6.5 Any additional interfacing device if required to achieve the functionality as per the philosophy mentioned
elsewhere in this document shall be provided or consider during bid stage.

6.6 Third party interface provision/compatibility shall be available in the SCADA servers for APPS system, any
other SCADA system, SAP system, Business Analytical Platform etc.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 5 of 34

Page 36 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

7.0 DESIGN CRITERIA

7.1 SCADA servers shall operate on a dual redundant configuration. All the SCADA servers at MCS /ICC are
of identical configuration and each server shall have capability of providing the full SCADA facilities in the
event of failure of the other machine. MCS/ ICC SCADA server(s) shall be rack mounted within the
equipment cabinets.

7.2 The servers with a redundant network connection interface card and connected to both segments of the
redundant LAN. In addition, servers shall be connected via a dedicated connection so that the standby
server to remain in synchronization with active server.

7.3 Operator control functions shall include alarming acknowledgments and suppression, request for printouts
of logs & reports, open-close-stop type discrete controls and controlling of set points at remote.

7.4 RTU shall have capability of updating process parameters data and configuration data in its own built-in
memory. Time stamping of all field values shall be required at RTU. In the event of failure or break of
communication link, the RTU shall continue to scan all parameters and update its database. RTU must
retain complete database analog & digital information of the field until it completely and correctly read by
SCADA Station to take care of no loss of data in case of failure of communication. The memory buffer is to
be sized (by considering min 15 days down time of SCADA system or communication between RTU and
SCADA) to store all the changing data (i.e. exception report for the data every poll time). SCADA system
shall receive the same without any loss of data after resuming the communication.

7.5 For “offline” storage of archive files , Network Attached Storage (NAS) device shall be attached to each
SCADA server. The NAS device provides a high capacity, fast access storage system allowing archive files.
Archive server shall store the data upto to minimum 36 month , automatic backup shall be initiated
before overwrite. This will be used for preparation of reports, historical trend and for detailed system
analysis. The archive server shall be located in the SCADA cabinet. The server shall have the feature to
store, configure and display the user defined trends /historical data of the operating parameters of the
machines in graphical / table format to facilitate the predictive maintenance.

7.6 Engineering workstation shall have the ability to undertake key system wide engineering functions such as:

• Configuration of the RTUs networks incl. Programming of devices

• Database generation, point ID and on-line modification

• HMI /MMI graphical development and/or modification

• Report development and/or modification using MS Excel

• System network administration

• System security

7.7 Specifications mentioned above are basic minimum requirements. However, Vendor shall upgrade / resize
(on higher side) specifications of offered system to meet functional requirements specified in this tender. At
any stage of system implementation, if it is found that Servers, HMI workstations and RTU by Vendor are
not having adequate processing power, main memory etc to meet system performance requirements of this
specification, Vendor shall replace these with higher end machines with no cost and time implication.

7.8 Web server

The supplied SCADA system shall be web enabled. The Web server shall be installed in MCS/ ICC. The
users using Internet explorer/chrome/Mozilla, and/ or any Navigator browser shall access the web server at

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 6 of 34

Page 37 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

MCS /ICC. The web server shall be able to provide the real-time trend and other information irrespective of
which SCADA server is primary at that instant. The supplied system shall have the following facilities
implemented: -

• To view all the online SCADA MMI displays i.e. graphics and alarms with online updation, trends and
reports using browser through Internet.

• Web server shall be inclusive of SMS/Email facility, Mobile application software compatible with
android, iOS and windows. Web server must be of unlimited user license, but concurrence users shall
have 30 number with auto refresh in 1-minute facility while viewing the data.

7.9 Mobile Apps

Mobile apps shall be developed by Vendor having minimum following functionality.

1. All mobile phones must be authenticated on IMEI number based for secured data access.
Authentication fails if the IMEI not registered.

2. Live station status data

3. Historical data for min, max avg for day, week, month and year

4. Provide easy navigation access to select any station

7.10 Web site information as per Mimic Graphic and flow chart section as a minimum. During contract period,
vendor to attend all additional web site viewing features as per IGL process requirements at his cost.

7.11 As a minimum requirement, SCADA software shall have the following facilities:

a) System and Database configuration.

b) Data Acquisition from the RTUs, generation and management of real time database.

c) Generation and management of historic data for trending and archival.

d) Alarm handling, including storage, display and printout.

e) Generation, storage, presentation of mimic diagrams with dynamic information on MMI monitor.

f) Display Management for Alarm, Alerts, Mimic diagrams, Analog and digital values, Trend graphs,
Bar charts in high-resolution colour graphic modes.

g) Free format report generation, storage and printout.

h) Data logging at periodic intervals, on operator request and automatically on occurrence of an event.

i) Transmission of control commands and configuration parameters to field / CNG stations.

j) Redundancy, fail-over and recovery processes.

7.12 System sizing

7.12.1 Contractor shall size both the servers and MMI capability considering as per tender requirement, future
requirement and data archiving period as per Annexure 1 SOS.

7.13 Input/Output Requirement

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 7 of 34

Page 38 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

7.13.1 Contractor is required to incorporate the complete requirements of telemetered points for SCADA system
taking the inputs from the I/O point list. The RTUs I/O cards shall be considering the complete I/O
requirements of RTU I/O count.

7.13.2 Contractor shall furnish the poll time calculations during detail engineering considering the requirements of
50% I/Os parameter changes every poll. The calculation shall be carried out by properly and evenly
distributing the RTU over the communication channels.

7.14 Real Time Database Access :

The supplied SCADA system shall be OPC UA compliant and have necessary provision for interfacing
(data interchange) with third party applications.

8.0 SYSTEM FUNCTIONAL REQUIREMENTS

8.1 Primary function

The primary function of the SCADA system shall have operational and monitoring interface to support the
operation and monitoring of the CNG Stations network/ Field Equipment. This interface shall provide the
capability to acquire process data from CNG Stations/ Field in respect to operating conditions and status,
abnormal or alarm conditions and will also facilitate remote operation.

8.2 Data acquisition

The data acquisition function shall provide all the aspects needed to support data collection from the field
including the requesting of data from RTU and the processing of analog and digital data received from the
RTU.

The data items listed below (but not limited to) are representative of the data required from the various
types of stations/Field.

a) Pressure

b) Temperature

c) Corrected Volumetric flow rate, mass flow rate

d) Totalized mass & volume flows

e) Pressure/Temperature high/low alarms

f) Valve controls

g) Valve position

h) Flow computer

i) Flow meter

j) CNG Dispenser

k) CNG compressor

l) VFD & Soft starter

m) Multifunction meter

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 8 of 34

Page 39 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

n) Gas generator set

o) Gas chromatograph

p) Odourizing Unit

8.3 Report by exception

All analog and status data shall be requested on a report by exception basis to avoid unnecessary processing
when the analog dead band has not been exceeded or no status changes have occurred. This is to avoid
unnecessary data communication between RTU & SCADA. Depending on the database downloaded to the
individual RTU, an RTU will scan the I/O points and determine the points to be reported when polled by
SCADA and communicate it along with time stamp.

The analog dead band, debounce time, backup report update time etc. shall be configurable as part of
database definition.

8.4 Data requests

The SCADA system shall be capable of periodically polling all RTUs with data request messages according
to polling information in polling tables developed by the Contractor. It shall be possible to define an RTU
or RTUs/PLCs more than once in a polling table per data channel.

8.5 Data updation

a) Report by exception data shall be updated maximum within 5 seconds or faster.

b) Backup update report updation for all parameters shall be every 5 minutes (user configurable).

c) Data polling rate in respect to SCADA and RTU for digital signals shall be instantaneously and Analog
signals shall be within 5 sec.

8.6 Data priorities

The retrieval of status data shall have a high priority than the retrieval of analogue data and check back
execute indications of just completed control actions shall have the higher priority.

8.7 Data validity

The SCADA system shall include data validity analysis function. This validity analysis shall be for out of
range, Instrument Bad, scan failure, point on test, RTU on test, manual input, point in alarm, alarm
inhibition, point off-scan, RTU off-scan, point in manual mode etc. Database qualifiers shall be indicated in
database, displayed in the graphics and logged in the reports. These quality tags shall be implemented on all
tags in SCADA system.

8.8 Poll modes

In addition to the general polling requirements outlined above, several other poll modes [user configurable]
shall be implemented as below: -

- Poll Inhibit - to enable individual points or complete RTUs from the polling function.

8.9 Control functions

The control function shall include the basic start/stop/open/close and set point capabilities. The basis of all
control actions shall be the select-check back-execute sequence.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 9 of 34

Page 40 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

Typical controls functionalities are as follows (but not limited to):

• Access and Change of Dispenser parameters (if required by IGL)

• Valve open [Device start]

• Valve close [Device stop]

• Set point control

• Station shutdown,

• Electrical devices Start/ Stop

8.10 Device control selection

Control requests initiated by the operator, SCADA system shall validate the control point and control the
action according to system status, defined interlocks, permissive and assigned responsibilities. System shall
display the error messages in case the operation is not permitted. Contractor shall incorporate the required
changes in the operation as desired by COMPANY during the site implementation phase. It shall also be
possible to override all interlocks /permissive under suitable password control and execute control. It shall
also be possible to configure from SCADA station the width of the digital output pulse used for remote
opening / closing of valves etc

8.11 Select-check back-execute

After verification of selected point and control action, the software shall initiate a select-check back-execute
control sequence with the selected RTU.

When the control action is initiated, the software shall set a flag showing that a device change-of-state is
expected. Failure to receive a status change within a predefined period shall show a faulty control action
and initiate a timeout alarm at SCADA. It shall also applicable for all the digital controls.

8.12 Telemetry fail and poll inhibit

Reliable detection and correction mechanism shall be implemented for data communication. If valid data is
not received from control device in response to a poll request, the software shall attempt to obtain the valid
data from that control device. The number of re-tries to be attempted shall be configurable.

If control device fails, or its communication channel fails, or control device is on test/masked, then all
individual points at that RTU shall be marked in the database to indicate telemetry failure but only one
alarm shall be generated linking with the corresponding failure status. The database shall retain the last
good value or status for every point affected until the telemetry returns to normal. Return to normal event
shall be generated and RTU shall update (when polled) w.r.t all points.

The operator shall have the capability to inhibit any point from scanning or an entire RTU from poll
processing. In this situation, the operator may substitute values for the data for points with defective
telemetry or which have been inhibited for poll processing. In addition, a point taken in manual mode shall
automatically put the point off scan. The substitute value shall retained until poll processing on that point or
station is restore.

8.13 Callup & Updation times

a) Call-up time of any graphic display on color monitor: not to exceed 2 sec.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 10 of 34

Page 41 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

b) Updation time of any graphic display on color monitor: not to exceed 2 sec. and Updation time of
Historical trend graphics not to exceed 10 sec.

c) Call-up & Updation time of Historical trend graphics: not to exceed 10 sec.

8.14 System diagnostics & test facilities

Comprehensive diagnostics and the test facility for each sub-system shall be an integral part of the SCADA
system.

8.15 MAN Machine Interface (MMI)

8.15.1 Features

The Man Machine Interface (MMI) system is the primary interface to the SCADA functionality. It is
critical to the operation of the SCADA system and the Contractor shall provide a secure, flexible and "User-
Friendly" interface by which engineers, supervisors and the operators may interact with the system and
CNG/ Field network by way of the computing equipment, database and software.

The MMI shall exploit the best characteristics of colour graphic monitors, keyboards, cursor control
devices, and printers.

The graphic displays shall be windowed, fully supported with appropriate graphics and symbolic diagrams.
All procedures shall be selectable by menu and context sensitive help displays shall be available.

The SCADA MMI shall support the feature of full screen data entry update wherein changes made to the
number of tags/ fields/ parameters on the graphical display shall be buffered and updated in the database of
SCADA.

8.15.2 The MMI shall, as a minimum, include the following functions:

- Display requests

- Supervisory control

- Alarm and event message display

- Alarm message acknowledge

- Alarm inhibit, poll inhibit, point scan inhibit

- Report and log output request

- Monitor hard copy printout

- Monitor analogue trending

- Bar graph display

- Manual data entry

- Free form text entry (scratch pad)

- Device warning indications (tagging)

- Assignment of console or workstation operating modes

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 11 of 34

Page 42 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

- Calculated variable definition and modification

- Display page definition and modification

- Report and log definition, modification and control

- Alarm and event message definition and modification

- Display and modification of system parameters

- Database management

- System configuration management

- Error statistics acquisition and management

- System resource utilization

- Daily alarms and operator actions

- System status displays including all system nodes.

8.15.3 The MMI shall be equipped with full-fledged graphic editor. The graphic editor as a standard shall contain
large no. of objects such as meters, bar graphs, slide bars, `Chart recorders', trend windows, alarm
annunciators control buttons and other such items which the user can create for placing in the library.
Objects shall include database links for alarm/mode/state/value fetching, for alarm coding and for animation
& dynamics.

Facility shall be provided to easily generate and edit the graphic displays, and to move, delete, change
symbols, characteristics, color, dynamic field assignments, copying etc.

8.15.4 Supervisory Control

Control to command a change of the state of CNG network/ Field devices from the console shall be
supported. In addition, control of the SCADA system functions for starting & stopping, network
management, diagnostics, maintenance & house keeping itself shall be supported.

8.15.5 Alarms and Events

The MMI shall support the presentation of alarms and events, on displays and printers, to provide
information regarding the behavior of the process. Facilities shall be provided to acknowledge alarms and
to inhibit alarms.

8.15.6 The facility to manually enter numeric and status data from an MMI.

8.16 Displays

8.16.1 Features

Displays shall be in a window format and standardized to the extent that fields necessary for effective
operational communication with the SCADA system are fixed. This shall provide efficient and standard
MMI procedures across all system functions and serve to reduce the risk of operating errors. However,
display support shall be flexible with regard to the presentation of data and customization with maintenance
utilities to suit the specific operating requirements shall be available. The operators shall have easy
operational access for data from hierarchy of display pages, using `point and click' cursor actions.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 12 of 34

Page 43 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

Using ‘command scripts' it shall be possible to automate many of the operators procedures such that mouse
click operation is all that is required to open/close valves, , change set points, while performing logical
checking permissive, authorization checking, check before execute security functions and time out
functions. The control points shall be selected by clicking their related symbols on the graphic display. The
Contractor shall supply standard set of control panel script and these shall be user configurable as well.

8.16.2 Display Requirements

a. The SCADA MMI shall support a comprehensive range of displays to enable maximum operational,
engineering, maintenance and planning benefit to be obtained from the system.

b. The Operator/Engineering Work Station displays to be split in such a manner to ensure proper view
ability and legibility covering all the facilities and covering all the signals & controls as per SCADA
telemetry database document.

c. The soft keys/buttons for accessing P&ID diagrams, station schematic displays, SCADA system status
displays, SCADA reports shall be available at all the time for direct access. Further displays shall have
navigation built-in covering Page forward, Page backward, Page up, Page down facilities indicating the
corresponding names of the displays for navigation.

The following types of graphics shall, as a minimum, be made available as applicable.

• Master and Sub Index Displays

• CNG stations/Field overall status display

• Pipeline single line diagram Displays for all CNG stations/Field

• Network and Station Overview Displays (google Geographical map).

• Station Displays

• Alarm and Event List Displays

• Data Trending

• Bar Graph Displays

• Electrical parameters

• Configuration Management Displays

• Database Review Displays

• RTU status display

• Communications status Displays & Communication statistics displays

• SCADA System Utility, Support & Diagnostic Displays

• System Resource [CPU, Memory, Disk loading]

• SCADA reports

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 13 of 34

Page 44 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

d. The dynamic field values along with engineering units shall be indicated next to the analog tag numbers
and serial link data. The tag numbers are to be displayed only wherever necessary and the remaining
tag nos. may be displayed in another layer of graphic. The attributes viz. change of colour, flashing
shall be done with the numeric value to show alarm on these tags in the displays.

e. The CNG station/ Field displays having Compressors, Dispensers, Flow computers/Flowmeters or
other equipment(s) shall constantly display the dynamic field/process values in engineering units. The
corresponding display to be obtained by clicking the “Poke point” related equipment as mentioned
above. This shall include the field values in engineering units for all the equipment parameters
telemetered through serial link along with corresponding tag nos.

f. The digital points along with their tags and alarm & normal status shall be shown in the displays.

g. The hot spots shall be configured in all the displays for further navigation/ selection and direct access.

h. The remote/ local status of ON/OFF valves shall be indicated by the static text 'R/ L' respectively, with
'R' in green and 'L' in red colour in all the station schematic displays.

i. Valve displays shall be Green open, red when closed, flashing red when bad, flashing green travel.

j. Stations/epuipment displays shall be Green when it is powered on, red when powered off, flashing
green when in operation and flashing red when there is communication problem of equipment/station
with RTU/SCADA system. Also the colour schematic shall be user configurable.

8.16.3 Display Requests

It shall be possible for the user to quick access to any required display with one or two mouse ‘clicks' using
the feature of inter page links (poke points) plus associated display links. .

At least the following types of display requests shall be provided:

• Select window

• Activate window

• Move window

• Re-size window (including maximize, minimize)

• Close window

• Zoom and pan windows

• Page forward/ backward/ left/ right

• Display requests via dedicated function pushbuttons

• Display requests via cursor selection points

• Display request via manual entry of a display page identifier.

8.16.3.1 Colour coding of device symbols and numeric values on the display pages shall be used to show the status
of the corresponding device or numeric value. Colour codes shall be subject to CLIENT/CLIENT’s
representative approval prior to implementation.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 14 of 34

Page 45 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

8.16.3.2 The display hierarchy to be built to permit overview of the CNG station/ Field with alarms and important
parameters & controls and linking with the detailed displays of various sections of the station with complete
details of all parameters & controls. All the displays will be linked by properly implementing the display
navigation mechanism through clicking the mouse.

8.17 Alarms & Events announcements

These fall into two categories:

- ALARMS

- EVENTS

Functions classified as monitored states shall present on the display for all possible states. It shall also be
required to announce the change of states as they occur and such change of state shall display discretely
identifying the function changing from one state to the other for operator interaction.

All the alarms shall be available in a consolidated alarm list. The event list shall also contain all alarms,
return to normal of alarms and change of state.

8.18 Alarms & Events processing

The SCADA station shall facilitate the alarm reporting to alert the system operator of abnormal conditions.

It will be required to give (but not limited to) alarm on the absolute value of measured variable, rate of
change of measured variable, deviation high and low, change in discrete status to abnormal state, sensor
bad, system related alarms. The system shall also be capable of generating alarms on the computed
variables. The user shall be able to acknowledge the alarms either from the alarms list (single alarm, full
page or own selection of alarms in a single go) or by selecting the point or object on the process graphics.
It shall be possible to assign points in various alarm categories differentiated through colour combination.
Alarms shall be flashing in respective colours before operator acknowledgment. Dedicated alarm summary
page shall be provided giving chronological information of tag no., set point, time/date of occurrence, text
descriptor etc. of the unacknowledged alarms and acknowledged but existing alarms in the system.

The alarms, which are returned to normal before operator acknowledgement, should continue to remain
flashing on the alarms display. The alarms, which are acknowledged and also return to normal should be
cleared from alarms summary. Also when the field conditions are abnormal and operator acknowledges the
alarm, the alarm message should go to steady state from flashing. Facility shall be provided to acknowledge
alarm on point/ page basis. Daily alarm/ event file should be available for further processing purpose.

The alarm manager shall provide alarm filtering current alarm/ historic alarm presentation group/ point
alarm acknowledgment plus enables/ disable alarm history logging & printing specifying start time, plus
audible and visual alarm presentation.

Alarms filter mechanism to be provided to screen the alarms and show specific alarms for review purposes.
A filter shall be able to operate based on:

• Location of CNG Station. Different types of station (IGL Owned, OMC & DTC).

• Location of devices installed at field (other than CNG stations) like Odourizing Units, Pilot Line, Gas
Chromatograph, etc.

• Various class of point database types like AI, DI, accumulators, calculated points, manual inputs etc.

• The associated process related point group type.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 15 of 34

Page 46 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

• Priority wise for various categories of alarms like unacknowledged alarms, acknowledged alarms etc.

• Reason code such as command, manual entry, acknowledgement, unsuccessful command etc.

• RTU wise alarms & events

• SCADA system/equipments related alarms

Typical events to be stored/printed with proper ID are:

• Commanded device changes

• Uncommanded device changes

• Device time out alarm

• Alarm enable/disable messages

• Control set point (SP) initiation for change, SP actually changed

• Alarm Return to normal

• Every operator action w.r.t configuration and database changes, ACKS, control commands etc.

• SCADA system events

• All alarms shall also be events

• The change of Alarm limits and Set-point changes shall be logged on SCADA system as events.

Alarm and events summary displays shall be different.

Alarm and event history shall be maintained in the history server upto 3 year, file indicating all the alarms
and events that occurred and acknowledged. Report of Alarms & Events shall be downloadable in .xls / pdf
/ any required format by OWNER.

A procedure shall provide to inhibit individual points from all or partial alarm processing. Inhibited alarms
shall not annunciate or display although an inhibited alarm list shall display all these points having inhibited
alarms. The action of inhibiting or enabling alarm shall be logged as event.

8.19 Barchart Display of Measurement

Telemetered analog measurement values shall also be capable of display as horizontal and vertical Bar
charts, in which the length/height of the bar shall vary according to the current telemetered value of the
measurement function.

8.20 Trending

8.20.1 Real time trends and historical trends shall be possible on any parameter or variable as measured variable,
set point, output, calculated variable and digital parameters, results etc., which shall also be capable of being
drawn out on printers as hardcopy. Contractor has to ensure that all analog inputs, analog outputs and
calculated parameters in SCADA database are configured in both real time and historical database with
correct telemetry tag names and engineering units & ranges.

8.20.2 Trend displays shall be single line type or bar graph type with additional information like tag no.,

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 16 of 34

Page 47 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

engineering units, span, present value of the trended point, alarm status etc. displayed. The display of
trending parameters from the screen should be user configurable.

8.20.3 Selection of the tag no. and sampling time for real time and historical trending shall be possible from
operator keyboard.

8.20.4 It shall be possible to select number of measurements for sampling and storing over selected polling
intervals.

8.20.5 The time interval shall be selectable up to one year (Customizable) for all process parameters.

8.20.6 Facility to select using mouse, the required period of displayed trend for zooming and to fall back to
previous trend screens. It shall be possible to see the value at a particular time on the trend curve by clicking
the mouse on the curve.

8.21 Report and logging requirements

8.21.1 General

The SCADA System shall support the definition, generation, scheduling, buffering, spooling and printing of
both logs and reports.

8.21.2 LOGS

A log is defined as a continuous and generally chronological listing of spontaneous messages such as alarms
and events. Logs shall contain no summations or other calculations using the logged quantities.

A log shall comprise single line alarm and event messages printed one at a time as they occur. Each
message shall have the same format as the corresponding message in the list displayed on the screen.

Operator interaction (commands, set points etc.) shall be logged with tagging of user ID of the operator and
shall be viewable at any time through the MMI.

8.21.3 Reports

a) Reports define as an output of preselected data organized in a specific format. Report software to
support output to all the three defined destinations-screen, printer and text file. Reports shall print on
demand or on the occurrence of predefined trigger events, such as the time of the day, shift wise, daily,
monthly. All reports shall be viewable on monitors prior to printing on demand.

b) Shift reports shall give hourly-metered values of parameters for the previous 8 hours from the time of
scheduling of these reports. These reports shall be printed three times a day on predefined times.
Definition of shifts to be incorporated in the shift definition screen and data to be sorted out
accordingly. For status shift reports, the ‘Abnormal state’ to be maintained for the complete hour even
though the status returns to normal within the same hour.

c) The SCADA shall allow the definition of new report formats and the modification of existing report
formats as “system maintenance mode function”. The report generator tool of SCADA package shall be
able to access real time database and history database. The reports software shall also support
embedded arithmetical functions.

d) All shifts & daily reports shall generate automatically at predefined time (configurable) and
automatically stored on hard disk (if ‘printing of reports’ option is enabled). The user shall be able to
enable or disable the “printing of reports” option.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 17 of 34

Page 48 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

e) The following types of reports (configurable as per Client/company requirements) shall, as a minimum,
be made available covering all the requirements of the P&IDs and not limited to:

• Metering data reports (shift, daily, and monthly) with various metering and related parameters for all
the metering runs.

• Gas Reconciliation reports (shift, daily, and monthly) related to IGL (drilled down to individual
station and equipment level), as and if required by IGL.

• CNG Station/ Field data reports (shift, daily, monthly) with parameters as parameters and related
station parameters

• Electrical parameters reports (shift, daily)

• SCADA System status reports

• Other daily/ monthly/ yearly/ on demand operational reports such as SCADA system abnormality
report, Operator tracking report, abnormal instrumentation report, station availability report etc.

• The monthly report will be generated every day containing the data from the start of the month to the
latest completed day.

• The yearly report will be generated every day containing monthly data up to the current month. The
current month data will be from starting of the current month up to the latest completed day.

8.22 Data archiving

The Contractor shall provide, as an integral part of the system, data archiving, reports archiving functions
and facilities.

The archiving process shall be automatic except for those tasks where manual operation is a fundamental
requirement.

The archiving function shall not interfere with the operational functionality of the SCADA.

Data archiving will be for 3 years with FIFO architecture.

8.23 Operator and engineering functions

8.23.1 All operator and engineering functions shall be initiated from the keyboards and mouse associated with the
works stations.

8.24 Access security

8.24.1 The facility shall be provided for restriction of access. Using this facility, the names, authorized access
level, access codes shall be entered.

8.24.2 Each workstation shall have no. of defined authorization for process control and for control system
interaction along with login capability with password protection. Each operator login account shall define
the level of access and the control for various equipment. The password security shall be built on all
SCADA MMI. , broadly within the following levels from SCADA MMI. These shall be finalized during
FDS stage.

Manager : Top level limited to persons authorized to modify software and


allocate access authority.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 18 of 34

Page 49 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

This is in addition to Engineer, Supervisor and Operator privileges.

Engineer : Allowed to access and modify anything in the database and display
& report formats (database, display & report configuration).

This is in addition to Supervisor and Operator privileges.

Supervisor level : Allowed to adjust configuration parameters during system


diagnostics/ maintenance level (Manual override, Alarm inhibit,
take point in/ out of scan, Take point in/ out of Test mode, Take
RTU in/out of scan, Take RTU in/out of Test mode, initiate
demand scan of RTU, etc.)

This is in addition to Operator privileges.

Operator level : Allowed to do day to day operation (access displays, Generate


reports, Alarms acknowledge, Supervisory digital controls and set-
point controls, CNG station shutdown, Valves Control etc.)

8.24.3 Operator functions

a) The operator functions shall be comprehensively covering all aspects of information call up, assignment
of display, function select, panning, and windowing for quick display call up and navigation from the
keyboard and mouse.

b) Operator control functions shall include alarming acknowledgments and suppression, request for
printouts of logs and reports, open-close-stop type discrete controls and set point controls (if required
by IGL) by transmission of set points to CNG station/Field equipment by telemetry.

c) Operator control functions shall also include entering non-telemetered values, constants, limits (if
required by IGL), set points (if required by IGL) and manual entered text messages for display on
selected frames. These values shall be retained until changed to new values by operator entry and
erased as would be the case for manually entered text messages. Manual data entry under password
control shall be available on all the displays with validity/limit checking feature.

8.24.4 Engineering functions

The system shall facilitate on line SCADA system configuration, compilation, modification of configurable
parameters i.e. Report by exception value, alarm limits, analog display range, addition and deletion of
points for installed I/O, display, logs and reports.

Engineering function shall include running of system diagnostics for on line system testing.

8.25 Supervisory control

8.25.1 Supervisory control functions shall comprise a multi-step interactive procedure to avoid accidental
operation of equipment(s).

8.25.2 Start/ Stop/ Open/ Close Control

This control function shall be used to control multiple state devices in the process and the SCADA system.
All these control functions shall utilize the select-check back-execute control sequence and Digital output
subsystem of RTUs/PLCs shall recognize two commands associated with device control.

8.25.3 Set point Control/write data

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 19 of 34

Page 50 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

The set point control function shall be used to provide a set point for controllers/ write data in dispenser.
Operator shall have a facility to change flow, pressure & speed set points manually from SCADA. Write
data in dispenser shall have manager login access.

8.26 Real time variable calculations

The system shall have capability of defining computed variables (including host resident analog
accumulator points) by arithmetic and logical operators from the real time parameters. The arithmetic
operators will include as a minimum +, -, *, /, SQRT, MAX, MIN. and logical operators will include AND,
OR, NOT functions on the real time operational parameters.

The calculation tool shall also include all types of database access and starting of programs with features of
specifying customer specific formulae.

These calculated results can be embedded for the purpose of display, reports etc.

8.27 TIME SYNCHRONIZATION

The GPS timeserver shall be connected with the SCADA system at Master control station(MCS)/ Integrated
Control Cenre (ICC). The primary SCADA server at MCS/ ICC shall be the "Master Clock" for the overall
system Date and Time Facility utilizing GPS time reference and all the nodes on the LAN at MCS/ ICC.

In case of failure of Master clock, the redundant SCADA server shall receive the signals from GPS
timeserver and shall have the Master Clock. Whenever the MCS/ ICC Date and Time is set or reset, an
automatic synchronizing signal shall be transmitted by telemetry to all remote stations. Any remote station
subject to a "Station Failure" shall automatically sent a synchronization signal on restoration of the same.

The RTUs shall also be synchronized with the master clock with the resolution of 100 msec.

9.0 REMOTE TERMINAL UNIT

9.1 RTU shall be rugged in construction, capability to implement control logics, interlocks & functionality as
specified in tender specification and suitable for working in hazardous area & open environment conditions.

9.2 This shall be microprocessor based programmable units with both erasable ROM and RAM memory.
Control device shall have its own processor, memory, power supply unit & communication processors and
I/O cards complete in all respects. All RTUs shall be modular and from the same model product line with
identical capabilities.

9.3 USB/SD card port shall be provided to collect the storage backup from RTU in pen drive/USB drive/SD
card, in readable format i.e. MS Excel.

9.4 The complete system shall be supplied with all its components including the cabinets.

9.5 The I/O cards can be combined for the functionalities (if required) w.r.t analog input, analog output, digital
input, digital output.

9.6 The entire supplied control device shall be with same make & model no., differing only in number of I/O
cards and communication ports.

9.7 Configruable Communication ports master or slave (MODBUS (RS 485) as per requirement.

9.8 Provision for Profibus / Profinet port in order to communicate with exsiting compressor’s PLC.

9.9 Digital inputs

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 20 of 34

Page 51 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

Typical specification of Digital Input channels is as given below:

Input Type : Volt free contacts (2 wire isolated)

Contact Wetting : 2-4mA per input at 24V DC

Resistance recognized : Not exceeding 1 Kilo Ohms as a closed contact

Resistance recognized : Not less than 50 Kilo Ohms as an open contact

Isolation : Using optocouplers or vendor specific.

Insulation resistance : 20M ohms at 500V DC inputs

Debounce circuitry : 10 m/sec

Indicators : Loop & state LEDs for each DI point

Voltage withstand : 1.5 KV RMS Capability

9.10 DIGITAL OUTPUTS

Typical specification of Digital Output channels is as given below:

Output Type : Relay contacts

Indicators : LED indication for each DO point

Relay Type : Miniature power relay

Contact arrangement : 1 NO + 1 NC relay contacts configuration to be provided up to the


RTU terminal block

Contact Rating : Potential free contact rating of output interposing relay for each DO
point
(Contact rating 48 V DC, 2A; 230V AC, 5A)

(Vendor to provide interposing relays for each digital output point)

Isolation : 2KV RMS Contacts to Logic

DO command activation : Configurable Pulse duration

Security : Output contacts shall be monitored via opto-isolators, shall be short


circuit proof and protected by suitable mechanism like fuse with
suitable visual fuse blown indication provided.

9.11 Analog inputs

Typical specification of Analog Input channels is as given below:

Input Type : Isolated, Current Inputs

Ranges : 4 - 20 mA/1-5V

Multiplexer : Vendor standard

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 21 of 34

Page 52 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

ADC Type : 12 bit binary (exclusive of sign bit)

Series Mode rejection : Greater than 30 db at 50 Hz

Common Mode rejection : Greater than 100 db at 50 Hz

Roll over error : 1 bit

Temperature : 0.005% per degree C

Coefficient

Accuracy : ± 0.1% of range including drop in resistor

9.12 The control device shall be configured such that failure of any part of an RTU subsystem (module) except
the CPU, power supply module shall not directly affect the integrity of the unit, as a whole.

9.13 COMMUNICATIONS

The RTU shall support both internal and external communications functions.

The communications network internal to the RTU shall be designed and implemented in such a way that the
passing of data and commands between modules shall not be prevented by the failure of any module not
directly involved in the communication exchange. In addition, the internal network shall not become
overloaded under the heaviest traffic possible in RTUs ultimate expansion configuration.

Each RTU shall recognize its own unique address. The LED indication shall be provided in the RTU to
check the health of RTU communication.

9.14 RTU FEATURES

9.14.1 The RTU sub-system shall support the following:

a) Scanning of Input and Output

b) Fast Scanning of selected I/O points.

c) Field input initiated discrete control action

d) Discrete control action corresponding to Remote Control command reception.

e) Operator initiated discrete control action with check before execute and time out feature.

f) Operator initiated discrete control with sequencing and interlocking.

g) Derivation of calculated digital points based on logical functions AND, OR, NOT etc. from digital and
analog points.

h) Derivation of calculated analog points based on arithmetic functions +, -, /, *, sq, root etc. and driving
external hardware. Calculation shall be performed in RTU in engineering units with 16 bit floating
point accuracy, required in case engineering conversion is being done at RTU level. (Calculations shall
be performed in the SCADA host in case engineering conversion is being implemented in the SCADA
server.)

i) Derivation of counter values using Integration of hardware and software generated Analog points.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 22 of 34

Page 53 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

j) RTU resident accumulator points driven by analog points.

k) Remote configuration of RTU from SCADA station through PDT/PC.

9.14.2 Automatic time synchronization of Remote telemetry units shall be implemented from master Station/
Integrated Control Centre with a resolution of 100 msec.

9.14.3 The RTUs shall have a self-diagnostic feature and software watchdog timer devices to monitor & report the
healthiness of CPU, memory, power supply, comm. interfaces and Input /Output channels at the local level.
Further, the RTUs shall support remote diagnostics from different station so that all these status shall be
transmitted to master station/ ICC and displayed in the RTU status graphic.

9.14.4 The analog input card shall generate an event, if it is out of calibration, which shall be sent to SCADA
station. Further, if analog output card is not self-calibrating type then all analog outputs shall be wired back
as analog inputs and calculations performed on each channel to detect AO card out of calibration. This out
of calibration shall be available as part of RTU status graphic along with set point value displayed in the
graphic, next to the corresponding controller symbol.

9.14.5 It shall scan and acquire parameters from process as per programmed scan cycles.

9.14.6 RTUs shall be intelligent in support of the following:

l) It shall process the analog data for high-low limit violations as per stored limit tables and communicate
the same to SCADA station along with time stamping.

m) Linear conversion to engineering units and input filtering, in case engineering unit conversion is being
done at RTU level [conversion of raw data to normalized value (e.g. 0 to 1.0) for communication shall
also be acceptable].

n) To support remote reconfiguration and downloading of parameters i.e. addition, deletion, modification
and reassignment with different range, limits etc. from SCADA station to avoid local engineering at
RTU level. The following requirements of RTU configuration from SCADA station shall be fulfilled:

• Analog alarm limits

• Analog scaling factor for engineering unit conversion

• Threshold value

• Smoothing factor (filter time constant) etc.

9.14.7 RTU shall be capable of updating process parameters data and configuration data in its own built-in
memory. Time stamping of all field values at RTU shall be required. In the event of failure or break of
communication link, the RTU shall continue to scan all parameters and update its database. RTU shall
retain in its database the complete analog & digital information of the field till it is completely and correctly
read by SCADA Station in order to take care of no loss of data in case of failure of dispatched, SV, and
Receiving Station. The RTU shall scan the field and the memory buffer is to be sized to store all the
changing data (i.e. exception report for the data every poll time) without any loss of data and alarms in the
SCADA system to take care of channel, SCADA server switchover times.

RTU shall have the memory capability to store the data of 15 days, at remote level in case of network
failure between RTU & SCADA server (located in Integrated Control Station).

9.14.8 Further to take care of long term communication outage with SCADA system , RTUs shall be designed to
scan the field and store in the memory upto 1000 field exception reports during the period of
communication outage for retrieval by Master Station/ ICC subsequently.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 23 of 34

Page 54 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

9.14.9 The RTU system shall have the facility to attach to each digital event signal a time tag generated by the
RTU local clock to enable the occurrence to be recorded and transferred with a resolution of 100 ms.

9.14.10 Every control associated with RTU shall report the status of the point after control execution. In case the
status has not changed within fixed specified time it shall report to SCADA station for not having executed
the control.

9.14.11 RTU shall not generate any false control signal due to power supply on-off conditions.

9.14.12 RTU shall support communication protocol supporting report by exception to prevent unnecessary data
communication when the data is not changing.

9.14.13 It shall provide error detection and control feature for data communication with SCADA Station to ensure
data integrity.

9.14.14 It shall have feature of connecting a pluggable Programmable Diagnostic Test unit (PDT) with keyboard &
monitors diagnostic and programming aid to trouble shoot and configuration tool for RTU and I/O boards.
It shall be possible to exercise all the functions of the RTU without disconnecting the RTU from process.

9.14.15 RTU shall have provision of applying filtering on the input signals and scaling for engg. units conversion.

9.14.16 In case of failure of complete RTU or off-scan of complete RTU, only one alarm shall be generated and the
RTU analog & digital points shown in various graphics and printed in reports shall correspondingly have
data integrity qualifier flag.

9.14.17 RTU shall operate from power supply as indicated in the tender. Separate on/off power supply switch and
fuse shall be supplied with each RTU. Adequate isolation of input, output and power supply circuits shall be
provided along with over voltage and short circuit protection.

9.14.18 Terminations for connections of power supply should be of standard industrial type. The PDT as diagnostic
aid to RTU shall be a notebook (laptop) with proper enclosure and shall operate on integral battery which
shall be rechargeable type. Also the PDT shall operate on 230 V AC power supply. Vendor shall provide all
the necessary converter/adaptor along with PDT.

9.14.19 The I/O point wires shall not be directly terminated on the RTU I/O boards. Screw less Terminal blocks/
shall be provided in the RTU cabinet. I/O termination blocks shall have both male and female portions so
that to isolate the field wiring at RTU level, male/ female termination block attached to the field wiring can
be pulled out instead of removing the wiring. Cross ferruling shall be done.

9.14.20 The electronics in the RTU shall consist of plug-in PCB's or units with Gold plated edge connectors that
utilize a wiping action for connection for PCB's to the back frame wiring. SCADA Vendor shall detail the
shelf and inter-shelf wiring and the termination of the wiring harness between the RTU and the terminal
block area. Easy access to cabinet wiring, for maintenance purposes is essential. The PCBs and RTU
components shall be designed for high temp rating and low power consumption so that air exchange with
the ambient environment will not be required.

9.14.21 The RTU shall be immune to radio frequency interference generated by any nearby source meeting the
latest international standards in this regard (MIL, VDE etc.).

9.14.22 The RTU equipment shall function continuously without requiring any preventive maintenance.

9.14.23 SCADA Vendor to ensure that the open/ close status of valves (open state first wired and thereafter close
state) be wired consecutively in the RTUs.

9.14.24 Identification labels for RTUs, RTU card files, power distribution boards, terminations etc complete in all
respects properly correlating with the drawings is to be ensured by the SCADA Vendor.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 24 of 34

Page 55 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

9.15 SCAN Rates

The local scan rates for individual I/O channels shall be such that the time-tagging resolution and system
performance requirements are achieved.

The consideration of scan times shall include the acquisition of data, processing and updating of the RTU
database. The overall local scan shall be defined as the time required to acquire field data and update the
RTU database and the same shall be much faster than RTU poll time by SCADA station. It is expected that
scan rate shall not exceed 100 msec.

9.16 SET-Point Controls (If required by IGL)

a) All analog output control functions shall utilize the select-check-operate control sequence associated
with set point control.

b) At the RTU, failure of a module in a subsystem shall be identified by an individual LED display.

c) Each I/O protected against the reversal polarity of the power voltage to I/O.

d) All the data shall be available in the engineering units in the RTU database. The Contractor has the
option to implement the feature of engineering unit conversion at the RTU level.

9.17 Serial Link Requirement

a) RTU vender shall provide appropriate number of RS 485 & RS 232 serial ports for each RTU as per
tender requirement.

b) Vendor shall provide all the software tools and programs (source code) used to interface RTUs with
different IEDs. CLIENT shall integrate other IEDs with the RTU in future. Hence, RTUs shall have all
necessary software, compilers, tools that makes device compatible with third-party IED device.
Integration of IEDs (of any protocol and not just MODBUS) with the RTUs shall be totally end-user
configurable.

c) The alarms for power supply/ serial link failure/ malfunction through serial link.

d) The RTU memory sizing shall be adequate for required nos. (As applicable) of IED system & serially
connected with the RTU including the spare ports.

e) All RTUs shall be user programmable for interfacing with any kind of IEDs like Flow Computers, flow
meter , Gas Chromatographs , pressure and temperature transmitters etc.

10.0 DRAWINGS AND DOCUMENTATIONS

10.1 The language used in all correspondence, documentation, literature, drawings, markings etc., shall be
English.

10.2 Contractor shall furnish all relevant technical manuals, literature and other technical data as required at the
various stages of the project indicated in MR.

10.3 All the drawings and documents shall be verified by the Contractor before presenting the same for review.

10.4 All these documentation shall be furnished in hard cover loose ring folders in A4 size (210mm x 297 mm).

10.5 All documents shall also be supplied in “SOFT COPY” form.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 25 of 34

Page 56 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

10.6 Review/approval of documents by CLIENT’S/CLIENT’S REPRESENTATIVE does not absolve the


Contractor of their responsibilities to satisfactory completion of the project as per the requirements of
contract document. Contractor is required to make necessary rectification in the system to meet the
requirements of the contract document at any stage of system implementation, without additional
implication of cost and schedule to the CLIENT.

10.7 It is Contractor’s responsibility to incorporate all the comments of the CLIENT’S/CLIENT’S


REPRESENTATIVE in the next revision itself. Contractor shall be responsible for incorporation of
additional comments at any stage of the system implementation, without implication of extra cost and
schedule to the CLIENT. If any comment is not incorporated in the revised document, the same shall be
brought to the notice of the CLIENT’S/CLIENT’S REPRESENTATIVE with justification for review before
submission of revised documents.

10.8 Contractor shall take care of the complete requirements of designing, generation and implementation of
SCADA displays for monitoring & control, SCADA reports, SCADA alarms/ events, SCADA trending
taking care of P&IDs and list of electrical parameters and covering the requirements outlined in this
specification for SCADA implementation.

10.9 The review code will be furnished by CLIENT’S/CLIENT’S REPRESENTATIVE only when the complete
document is furnished by Contractor.

10.10 Contractor shall furnish point wise response to CLIENT’S/CLIENT’S REPRESENTATIVE comments
indicating the document section/clause/page no. reference where the same has been included in the revised
document. The body of the document and corresponding pages will show the revision bars only at the
places where the revision has been carried out. CLIENT’S/CLIENT’S REPRESENTATIVE will be
required to check the revised document w.r.t. these changes only, while considering that rest of the
document has remained unchanged.

10.11 Contractor to note that all programming langauges, commands, display langauges etc. for the entire SCADA
system shall be in ENGLISH langauge only.

10.12 Latest anti-virus software shall be provided by the Contractor for all SCADA server and it shall be
upgraded by the Contractor ( as and when required) during warranty period and AMC period.

10.13 Documents

10.13.1 Factory acceptance test (FAT) plans and procedure documents

FAT document for SCADA systems and shall contain test sections to test all the aspects of SCADA System
integrated with RTU as covered in FDS and MMI documents.

10.13.2 Site acceptance test (SAT) plans and procedure documents

SAT document for SCADA systems and shall contain test sections to test all the aspects of integrated
SCADA System.

Test Run Plans and procedure documents.

10.13.3 RTU Documentation

RTU documentation shall be covering engineering manuals, user manuals, installation, operation &
maintenance manuals for all software, hardware and equipments.

10.13.4 SCADA Documentation

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 26 of 34

Page 57 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

SCADA documentation covering engineering manuals, user manuals, installation, operation & maintenance
manuals for all software and hardwares.

10.13.5 Other Documentation

Bill of Material, Quality assurance plan, Billing procedure, Installation & Test procedure (which also
includes the mounting arrangement of each cabinet), Site execution plan.

10.13.6 Functional Design Specifications (FDS)

1. Contractor to note that the SCADA System completely covers the operational and functional
requirements of this project and the requirement of FDS shall focus on the implementation aspects of
these requirements.

2. FDS shall be custom defined for this project and include the implementation aspects of tender
requirements.

3. FDS document shall cover SCADA implementation aspects such as complete details of systems
configuration, process parameter monitoring, changing of set points (if required by IGL), control
philosophy, Redundancy and backup (system failovers & fail backs). Also covers the implementation
aspects of tender requirements, Integration between various subsystems such as telecom system, RTU
system, description of SCADA/ third party software interface, System resource sizing basis and
performance parameters covering CPU, disk and main memory utilization, memory mapping, system
timeouts, computers switchover timings, Display updates, Display call-ups, poll time calculations etc.

4. Man Machine Interface (MMI) Document

The MMI documents shall cover all the displays, graphics and reports, in colour printouts ensuring
proper view ability and legibility. The colouring scheme for various displays taking care of the colours
for the titles/ headings/ sub-headings, background color, static text, dynamic values, CNG station/Field
process parameters and other equipments etc. shall be highlighted in the dedicated section of the
MMI document.

5. SCADA telemetry points database document.

Contractor is required to incorporate the complete requirements of telemeted points for SCADA system
taking the inputs from the I/O point database (I/O Point list). The information like engineering units,
ranges, alarm limits, set points, and digital contact configuration shall be taken care of by Contractor
during detailed engineering.

6. All the calculated, server resident points and system status related points are also be included in this
document.

10.14 Drawings

10.14.1 Engineering drawings/ documents: -

This document shall be submitted covering the following drawings:- interconnection diagrams, supplied
RTU cubicle typical layout and GA, RTU internal layout and interconnection drawings for each type of IO
cards, PDB internal layout, Internal layout of RTU cabinets,.

10.14.2 Construction drawings/ documents: -

This document shall also be submitted covering the following drawings: - Mounting arrangement of each
cabinet, cable schedule, IO Termination & Wiring diagrams, grounding schemes/ diagrams.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 27 of 34

Page 58 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

11.0 INSTALLATION & COMMISSIONING

11.1 The installation and commissioning of all the equipments associated with SCADA,Teelcom and RTU
system at various sites including the activities of interconnections between RTU & Telecom facilities,
including termination of all signal & power cables & points into RTU (from Junction Box) & RTU to
Telelmetry system. Further SCADA implementation agency will also be responsible to facilitate and
cordinate with various sub-contractors is the responsibility of the vendor.

11.2 Contractor shall be responsible for proper selection of the communication cables [with suitable cable
properties, shielded cable with low capacitance (8-10 pF/foot)] for ensuring good quality communication
with telecommunications & other panels.

11.3 Contractor shall bring all installation aids, test equipments and qualified and experienced personnel, in order
to carry out the job successfully. A list of the same shall be submitted to the CLIENT’S/CLIENT’
REPRESENTATIVE for review.

11.4 Contractor shall carry all the necessary tool and tackles like 4-20 mA current source, multimeter,
RS232/RS485 converters, protocol analyser and other diagnostic tools as required during testing and
commissioning.

11.5 All technical personnel assigned to the site by Contractor must be fully conversant with the specific system
and its software packages. The Contractor’s field personnel shall have both hardware and software
capability to bring the system on line quickly and efficiently and with a minimum of interference with other
concurrent construction and commissioning activity.

11.6 The commissioning spares for all the items/ equipments is included along with commissioning services as
required to commission the complete system. The consumables required during commissioning of system is
included as part of commissioning spares.

11.7 Contractor shall at his own expense supply and provide all the equipment, tools, temporary works materials
both for temporary and for permanent works, labour, supervisors, engineers and specialists, movement of
the supplied equipment at the site, required for installation, commissioning, execution and completion of the
works. The Contractor shall make his own arrangements at his own cost for the transport where necessary
of his staff and labour to and from the Site of the works.

11.8 Appropriate storage of the materials to be supplied in this contract will be arranged at the site by the
Contractor at the various stations after the materials have been delivered by the Contractor. The Contractor
shall be responsible for the storage, security and safety of all other materials, tools etc. brought by the
Contractor for the installation and commissioning of the system at the site.

11.9 The Contractor's responsibility at site shall include all the activities necessary to be performed to complete
the entire job as per the contract requirements including the following as a minimum.

a) Receipt of hardware, software and checking the adequacy and completeness of supply.

b) Storage, safety and security of the equipments and other materials including software at site.

c) Installation of the complete system including power supply, earthing, cable terminations, calibration,
civil & electrical works. Obtaining information/ Coordination/ interfacing with various other
contractors (Electrical, Instrumentation, Telecom etc.) through CLIENT’S/CLIENT’
REPRESENTATIVE.

d) Checking of equipment installation.

e) Checking of interconnection and overall system functionality.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 28 of 34

Page 59 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

f) Online/ offline debugging of the system.

g) Coordination/ interfacing (including obtaining relevant details) with Metering contractor through
CLIENT’S/CLIENT’ REPRESENTATIVE

h) On line testing and commissioning of SCADA & RTU system.

11.10 Contractor to note that there could be minor database changes & logic changes during site commissioning
phase as required by the CLIENT’S. The same to be taken care by the Contractor as part of the project
requirements.

12.0 EQUIPMENT INSPECTION & TESTING

12.1 Inspection

a) All factory tests will be witnessed by CLIENT’S/CLIENT’ REPRESENTATIVE.

b) CLIENT’S/CLIENT’ REPRESENTATIVE shall have free entry and access at all phases of the project
to all parts of Contractor's facilities associated with manufacturing and testing of system.

c) Contractor shall invite CLIENT’S/CLIENT’ REPRESENTATIVE well in advance with minimum 1


month notice of the date at which the system is ready for testing.

d) The equipment will not be shipped before they have been officially released in the form of release notes
by CLIENT’S/CLIENT’ REPRESENTATIVE.

e) Contractor shall provide CLIENT’S/CLIENT’ REPRESENTATIVE with all reasonable facilities


necessary to determine compliance to the system specification.

f) Contractor to note that acceptance of the equipments and the system by CLIENT or exemption of
inspection & testing shall in no way absolve the Contractor of his responsibility to deliver the system
meeting all the requirements specified in the specification. Contractor shall be responsible till the
completion of the warranty, for any corrections/ modifications including supply and implementation of
hardware & software to fulfill the requirements of the contract/ up gradation including supply and
implementation of hardware & software to meet the functionality and performance of the contract.

g) Contractor personnel shall be actively involved during factory acceptance and site acceptance testing.

h) All the RTU tests as per the approved documents shall be carried out at the Contractor's works, testing
laboratory and work sites at Contractor's cost. The Contractor shall provide assistance; instruments,
labor and materials as are normally required for the examining, measuring and testing any
workmanship as may be selected and required.

i) These tests will encompass all the material, equipment delivered, and software pertaining to SCADA
system including the equipment and software supplied by Contractor. Pre-FAT report duly witnessed
and cleared by Contractor shall be available for reference during FAT.

12.2 Testing

Testing of SCADA system shall consist of:

a) Pre-Factory Acceptance Test (Pre-FAT)

b) Factory Acceptance Testing (FAT)

c) Pre SAT & Site Acceptance Testing (SAT)

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 29 of 34

Page 60 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

d) Test Run

12.2.1 Pre-FAT

Pre-FAT shall be conducted based on the approved FAT document and the same shall be duly witnessed &
cleared by the system engineering group of the Contractor.

During the Pre-FAT testing phase, the Contractor shall ensure that the SCADA and RTU system performs
according to the requirements of tender, FDS & other finalised engineering documents and furnishes the
written undertaking to the CLIENT in this regard, prior to offering the system for FAT to CLIENT.

Contractor shall submit pre FAT report for our review before FAT call. Pre FAT shall be conducted as per
the approved FAT procedure and on real or project specific component with observed results. Pre FAT test
shall covers minimum aspect as specified in FAT clause. Pre FAT result shall be verified during FAT.

12.2.2 Factory acceptance testing (FAT)

The FAT document shall be prepared covering all hardware, software and system functionalities including
system expansion requirements of tender & FDS. Factory acceptance test will be done based on the
stipulations in the approved FAT document, which shall completely fulfill the contract requirements and
approved RTU FDS documents.

FAT shall be carried out in Contractor’s premises.

The system testing shall cover the following aspects as a minimum:

a) Visual and mechanical testing to ensure correct, proper, good and neat workmanship.

b) Demonstration of the complete system functionalities, hardware & software compliances wrt all the
equipments including RTUs.

c) Checking of complete database definitions for the proper system configuration.

d) Testing of system passwords and security features.

e) Checking of various log formats, reports, archiving functions.

f) Checking of system loading w.r.t CPU, memory, disk, as per the requirements.

g) Checking of system diagnostics for all the equipments as per the requirements, power failure and
system restarts.

h) Redundancy check for dual communication channel.

i) IO & Serial communication checking by simulation

j) System building procedures and verifications.

k) On/Off Control and various sequences and interlocks as per Operation and Control Philosophy if any.

l) Checking of monitor updates of HMI/MMI, database updates and display call up timings.

12.2.3 On line testing, Commissioning

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 30 of 34

Page 61 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

a) Prior to SAT, Contractor shall test all the stations hardware & software such as correctness of complete
SCADA database, complete checking and testing of I/O database, testing of serial interfaces as
applicable.

b) Prior to SAT, the activities of installation, system on-line testing and commissioning shall be performed
by Contractor as per their Company standard & established practices & procedures to ensure that good
techniques and best engineering practices had been followed, while ensuring correctness &
completeness of the same.

c) Contractor shall conduct the SAT after successful integration & commissioning of the complete system
and after interfacing of all actual field signals with the system including the successful completion of
on-line testing of all the system.

12.2.4 Site Acceptance Testing (SAT)

a) The SAT document shall be prepared for RTU system and SCADA system and Contractor to submit it
one month in advance to CLIENT’S/CLIENT’S REPRESENTATIVE for review and approval.

b) SAT shall involve integrated testing of complete system including third party devices. Site Acceptance
Testing will be done based on the stipulations in the approved SAT document. Once the test is
successfully performed, then the system would be ready for commencement of test run.

c) SAT shall be conducted by the experienced system-engineering group of the Contractor (earlier
involved in system design, engineering, integration & FAT).

d) Checking of hot standby functions, switchover of data channels to meet the system functional
requirements without any loss of data and operation.

12.2.5 RTU Testing

Testing shall be carried out as per the following stages:

• Real data testing of all the serial interface signals and hardwired interface signal, third party signals to
RTU with SCADA.

• Time stamping, storage capacity during communication failure, off loading data after communication
recovers, set point changing from remote, control function, etc.

Contractor shall submit to CLIENT’S/CLIENT’S REPRESENTATIVE detailed test plans and procedures,
three months prior to actual testing for all factory and site acceptance tests and test run for review.

12.2.6 Test Run

a) Test for continuous functional operation of the system with the required system reliability and
availability. This test aims at keeping the complete integrated system operation for a period of 21 days
for all the 24 hours a day.

b) In case of failure, the tests will be restarted again till the system operates without failure of any system
functionality for 21 days. Failure of tests shall be limited to such system failures which will affect
system availability & reliability and shall not be dependent upon established failure of third party
supplied items. CLIENT’S/CLIENT’S REPRESENTATIVE shall have the right to reject the complete
system or part there of in the event of the acceptance tests failing in two attempts.

c) Test run shall be carried out as per the approved test plans and procedures. The 'Test Run' shall be
carried out after successful SAT, duly witnessed by CLIENT’S/CLIENT’ REPRESENTATIVE.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 31 of 34

Page 62 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

d) The observations, exceptions and test results obtained during the test run shall be documented and
produced in the form of a report by the Contractor within seven days of the completion of Test Run
which shall be subsequently reviewed / approved by CLIENT’S/CLIENT’ REPRESENTATIVE within
ten days of submission of test report by Contractor. After that the PREWARRANTY COMPLETION
CERTIFICATE shall be issued by the CLIENT’S and thereafter Warranty phase will start.

12.2.7 Failure of Components

a) During test run a log of all failed hardware and software modules shall be maintained which shall give
date and time of failure, description of the failed components & cards/ software along with designation,
effect of failure on the system, cause of failure and number of hours of operation of the part before it
failed.

b) Upon failure of the components/ cards/ modules, the same shall be replaced by better-graded
components/cards and the test shall be restarted from the beginning or the previous logical point as the
case may be. If after this one replacement the unit of sub-system still fails to meet the specifications,
the Contractor shall replace the complete unit or sub-system with the one that meets the requirements
and restarts the test all over again.

c) At least one Contractor engineer fully conversant with the system hardware and software shall be
present at SCADA station during the test run.

d) If a unit or sub-system has failed during the test, contractor is responsible to repair failure part or
replace within few hours of active repair time after the failure and made successfully operational, the
test shall be suspended and restarted all over again only after the Contractor has placed the device back
into acceptable operation. The CLIENT’s/CLIENT’ Representative approval shall be obtained for any
allowable logistic time required to replace the failed component/sub-system. All cost for repair/
replacement of defective component/ system shall be to Contractor's account.

e) The CLIENT’S/CLIENT’ REPRESENTATIVE shall be free to request any specific test on any
equipment and the system considered necessary by him, although not listed in the testing documents to
verify the compliance with the specifications.

f) Contractor is responsible to provide any statutory test/ inspection certificate, as may be required, under
any law or directive issued by Govt. or any competent authority.

g) For operational software tests, the plans shall include summary of the method, a list of typical test
cases, the sequence of execution and expected results.

h) For hardware tests, the plans shall include purpose of the test, definition of test inputs, specifications of
test procedures and definition of results to be obtained.

13.0 TRAINING

13.1 Site Training :

Contractor shall train CLIENT’S operation engineers on internals and maintenance of the supplied system.
The training shall include the following:

a) Operation & Maintenance of the SCADA system

b) Back up procedure-archiving & retrieving

c) Add RTUs, new tag, modification, etc..

d) RTU configuration

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 32 of 34

Page 63 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

e) Modem configuration

f) Generation & modification Point database

g) Integration of IEDs with the system.

h) Integration of third party software usage of OPC UA.

i) System internals.

14.0 COMPREHENSIVE POST WARRANT MAINTENANACE CONTRACT (PWMC)

14.1 The bidder shall include proposal at the time of bid for providing post warranty maintenance for three years
after completion of warranty period and provide the total i.e comprehensive maintenance of the SCADA &
RTU system and any other system/ sub system which is part of this MR.

14.2 The proposal shall include supply of maintenance spares, tools and tackle as required; travel, boarding &
lodging of service engineer. The bid shall be made year wise upto 3 years and the price validity shall be
available for the entire period of contract.

14.3 In the event of any malfunction of the system hardware/ system software , experienced service engineer
shall be made available at site within 24 h ours on the receipt of such information from owner.

14.4 Client personnel will work on system day to day basis and wherever possible, owner shall inform the type
of failure of hardware/ software to vendor based on diagnostic available with the system. However bidder
shall be fully responsible to attend and rectify the root cause and the failure at the shortest possible time.

14.5 The service under Comprehensive Post Warranty Maintenance Agreement, including supply of spare parts
and services, shall broadly comprise of

 Preventive Maintenance

 Periodic Maintenance

 Emergency Service

 Software Support

• Preventive Maintenance:

Once in a year during planning shutdown, client will inform the bidder one month in advance for shutdown
dates. Preventive maintenance shall involve complete overhaul of the system, inspection of hardware and
software, fault prediction, inspection of power supply quality, environmental operating condition checks,
calibration checks, major repairs/ replacements, replacement of cards and accessories because of expected
ageing failure and detailed reporting, manual cleaning of each card and cabinet filters.

This visit is in addition to visit required for periodic maintenance.

• Periodic Maintenance:

Site visits, minimum two (2) times in a year (total days expected 10 in a year), schedule of visits to be
discussed and finalized jointly between bidder and client after placement of order/ delivery. It shall include
inspection of general healthiness of the system, study and advice on daily maintenance, inspection of H /W
& S /W, if any problem is reported, running of test programs, on-line servicing and solving reported
problems. Checks shall be conducted on running system i.e.

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 33 of 34

Page 64 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

 System check

 Power supply checks

 LED

 Printer etc.

Cleaning of cabinet filters, minor modification / addition related to system configuration/ data base. Bidder
shall take backup in 2 copies of last updated software and commented program also and provide it to IGL in
desirable open format.

In the event of any malfunction of the system hardware/system software during this period, Service
Engineer must report at site within 24 hours of report of failure, with necessary spares. The system must be
brought back within 24 hours after reporting at site.

14.6 Emergency Service:

In the event of any malfunction of the system hardware/system software during this period, Service
Engineer must report at site within 24 hours of report of failure, with necessary spares. The system must
be brought bac k within 24 hours after reporting at site.

14.7 Software Maintenance/ Support:

Bidder to maintain the existing operating & application software to improve upon performance of the
system. Software modification and up gradation, as & when required, shall also be covered under this scope
at no extra cost.

Σ Σ Σ

Rev. 0 –19.06.18 SCADA implementation at CNG station Page 34 of 34

Page 65 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
ANNEXURE I

SOURCE OF SUPPLY (SOS) FORM

This form shall be duly filled and signed by bidder and shall be submitted along with bid. All the points shall be
unambiguously responded, if anything is kept blank by the bidder, it shall be considered as non-compliance of the tender.
1. SCADA SYSTEM

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance No.

1 SCADA Latest Version with license client (in


Software addition to requirement client, 2 spare
clients with license shall be provided)

2 SCADA Tag Minimum 100000 tags

3 System As per Tender system architecture


configuration

4 Communication IEC 870-5-104 / DNP3 (TCP/IP)


protocol

5 System 99.98 %
availability

6 SCADA Philosophy as per specified in tender


System
Functionality

7 Servers Hot Stand by auto switch over within 1


Minutes

8 MMI updata
Call-up time of any graphic display on
time
color monitor: not to exceed 2 sec.

Updation time of any graphic display


on color monitor: not to exceed 2 sec.
and Updation time of Historical trend
graphics not to exceed 10 sec.

Call-up & Updation time of Historical


trend graphics: not to exceed 10 sec.
9 Percentage Should not exceed 60 % (Including
Utilization of future expansion)
Server, Average
CPU, Average
Memory, Disc
etc.

10 Communication SCADA system shall support the


protocols following protocols as standard and
other proprietary protocols as
applicable to establish the

SCADA implementation at CNG station Page 1 of 22

Page 66 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance No.

communication between RTU and


third-party devices

1. IEC 870-101/104 Protocol


2. OPC Protocol
3. DNP 3 over TCP/IP/Modbus
4. BSAP Protocol
5. Allan Bradley RS link
Protocol
6. OEM specific
11 Future In addition to above SCADA tag,
Expansion SCADA system should be adequate to
accommodate at least 200 additional
RTUs without adding any hardware &
software. Vendor shall consider
SCADA tags accordingly.

12 Server/SCADA Servers/SCADA shall have 100 %


Capacity packet data capture technology and
shall have capability to receive data
from 1000 fields devices (RTUs)
simultaneously.

2. SCADA SERVER:

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

1 Make As per recommended vendor list

2. Model -

3. Processor One or two numbers of latest


generation Intel 4/6/8/10/12/14/18
Core E5-2600v3 processor

or

One or two numbers of latest


generation Intel
4/6/8/10/12/14/18/20/22 Core E5-
2600v4 processor

4. External CPU 10 MB
cache

5 RAM 16 GB expandable to 32 GB

6 PCI slots Min 3

7 Hard disk Dual channel ultra wide SAS with


controller RAID 5 supported.

SCADA implementation at CNG station Page 2 of 22

Page 67 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

8 Hot Pluggable 4
bays

9 Hard Disk drive 2 X 500 GB ultra hot pluggable SAS,


OEM make (RAID 5)

10 16x DVD R/W Required, along with necessary


optical drive- Software for archiving and retrieving
4.7 GB Min or the data to & from the disk.
dual layer

11 Manage LAN Redundant embedded fast Ethernet


Network port 10/100 Mbps UTP.

Minimum Number of LAN port-

1. LAN A

2. LAN B

3. Server to server synchronisation

4. MMI

12 Ports Min 2 serial and 4 USB

13 Operating Latest Windows server 2012 or latest


System std license operating system with
media and latest service pack

14 Graphic card Integrated

15 Key Board Alphanumeric & Function Keys

16 Mouse Optical

17 Monitor Min 21” high resolution, flat colour Common for


TFT/LED SCADA
server, and
archive

18 Third party OPC(UA) License for min 4 users


software

19 FAN Redundant

20 Power Supply 230 V AC 1 Ph, Power failure protect


&, Auto Restart, redundant hot
pluggable.

21 Mounting Rack mounted inside the server

SCADA implementation at CNG station Page 3 of 22

Page 68 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.
cabinet

22 Antivirus Latest Antivirus with 3-year


subscription.

23 Quantity As per MR

3. WEB SERVER

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

1 Make As per recommended vendor list

2. Model -

3. Processor One or two numbers of latest


generation Intel 4/6/8/10/12/14/18
Core E5-2600v3 processor

or

One or two numbers of latest


generation Intel
4/6/8/10/12/14/18/20/22 Core E5-
2600v4 processor

4. External CPU 10 MB
cache

5 RAM 16 GB expandable to 32 GB

6 PCI slots Min 2

7 Hard disk Dual channel ultra-wide SAS with


controller RAID 5 supported.

8 Hot Pluggable 4
bays

9 Hard Disk drive 2 X 500 GB ultra-hot pluggable SAS,


OEM make (RAID 5)

10 16x DVD R/W Required, along with necessary


optical drive- Software for archiving and retrieving
4.7 GB Min or the data to & from the disk.
dual layer

11 Manage LAN Redundant embedded fast Ethernet


Network port 10/100 Mbps UTP.

Minimum Number of LAN port-

SCADA implementation at CNG station Page 4 of 22

Page 69 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

1. LAN A

2. LAN B

12 Ports Min 2 serial and 4 USB

13 Operating Latest Windows server 2012 or latest


System std license operating system with
media and latest service pack

14 Web users Unlimited users with 30 number


concurrence users with 1-minute
refresh time (shall be configurable)

15 Graphic card Integrated

16 Key Board Alphanumeric & Function Keys

17 Mouse Optical

18 Monitor Min 21” high resolution, flat colour


TFT/LED

19 Mobile Apps Require as per tender specification

20 SMS/Email Require as per tender specification


facility

21 FAN Redundant

22 Power Supply 230 V AC 1 Ph, Power failure protect


&, Auto Restart, redundant hot
pluggable.

23 Mounting Rack mounted inside the server


cabinet

24 Antivirus Latest Antivirus with 3-year


subscription.

25 Quantity As per MR
4. ARCHIVE SERVER:

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

1 Make As per recommended vendor list

2. Model -

SCADA implementation at CNG station Page 5 of 22

Page 70 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

3. Processor
One or two numbers of latest
generation Intel 4/6/8/10/12/14/18
Core E5-2600v3 processor

or
One or two numbers of latest
generation Intel
4/6/8/10/12/14/18/20/22 Core E5-
2600v4 processor

4. External CPU 10 MB
cache

5 RAM 16 GB expandable to 32 GB

6 PCI slots Min 3

7 Hard disk Dual channel ultra-wide SATA


controller

8 Hot Pluggable 6
bays

9 Hard Disk drive Min 3 X 1TB ultra hot pluggable


SATA, OEM make (RAID 5), NAS
connectivity

10 Hard disk Dual channel ultra-wide SAS with


controller RAID 5 supported.

11 8x DVD R/W Required, along with necessary


optical drive- Software for archiving and retrieving
4.7 GB Min or the data to & from the disk.
dual layer

12 LAN Network Redundant embedded fast Ethernet


port 10/100 Mbps UTP

13 Ports Min 2 serial and 4 USB

14 Operating Latest Windows operating system


System

15 Storage minimum 36 months

16 Graphic card Integrated

17 FAN Redundant

18 Power Supply 230 V AC 1 Ph, Power failure protect


&, Auto Restart, redundant hot

SCADA implementation at CNG station Page 6 of 22

Page 71 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

pluggable.

19 Mounting Rack mounted inside the server


cabinet

20 Antivirus Latest Antivirus with 3-year


subscription.

21 Quantity As per MR

5. OWS/EWS

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

1 Make As per recommended vendor list

2. Model -

3. Processor 64 bits Quad core Intel Xeon 2.5


GHz(Dual Processor)

4 RAM 8 GB, 1600 MHz DDR3 expandable


to 16 GB.

5 PCI slots Min 3

6 Hard Disk drive 500GB SATA

7 8x DVD R/W Required, along with necessary


optical drive- Software for archiving and retrieving
4.7 GB Min or the data to & from the disk.
dual layer

8 LAN Network Redundant embedded fast Ethernet


port 10/100 Mbps UTP

9 Ports Min 2 serial and 4 USB

10 Operating Latest Microsoft Windows 7


System profession edition 64 bit OS or higher
with latest service pack.

11 MS office MS office home 2013 and business or


latest with latest service pack and
media

12 Key Board Alphanumeric & Function Keys

SCADA implementation at CNG station Page 7 of 22

Page 72 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

13 Mouse Optical

14 Monitor Min 21” high resolution, flat colour


TFT/LED

15 Graphic card 1GB, External high-resolution graphic

16 FAN Require

17 Power Supply 230 V AC 1 Ph,

18 Mounting Desk mounted

19 Antivirus Latest Antivirus with 3-year


subscription.

20 Quantity As per SOR

6. SPECIFICATION OF L3 & L2SWITCH:

Sl. No Items As per Tender Bidder Make and model Remark


Compliance number
1 Make As per recommended vendor list

2 General Features Manageable, equivalent layer-3, fixed-


configuration
Non-blocking switching architecture
Wire speed performance on each port.

Auto negotiation on all the


10/100/1000Mbps UTP ports

Switches shall be supplied with the


management modules /Management
Port, licenses required for the switching
solution as per this MR

3. High Availability Switch should have dual internal


redundant, modular power supplies and
fans

SCADA implementation at CNG station Page 8 of 22

Page 73 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Spanning Tree (IEEE 802.1 d), Multiple
Spanning Tree Protocols (IEEE 802.1
w)

Support for VRRP or equivalent for


switch redundancy

Link Aggregation across multiple ports


of the same switch and across multiple
ports of multiple switches through
LACP (IEEE 803.ad)

IGMP snooping
4 Connectivity/ Total 24 port switches with a minimum
Ports Required of 22 nos. non-blocking, wire speed
Fast Ethernet (10/100 BASE-T) ports
and 2 nos. non-blocking, wire speed
Fast Ethernet Fibre Optic (100 Base-FX
ports) per switch along with SFPs

Total 8 port switches with a minimum


of 2 nos. non-blocking, wire speed Fast
Ethernet (10/100 BASE-T) ports and 2
nos. non-blocking, wire speed Fast
Ethernet Fibre Optic (100 Base-FX
ports) per switch along with SFPs

At Master station

• LAN switch (L2) -24 ports

• WAN Router/L3 – min 10 ports

Remote station

• LAN switch min 10 port

• Modem with integrated router

5 Performance Non-blocking, wire-speed performance


at each port after populating all the
/Features required & considering all the planned
Required ports

Broadcast suppression functionalities


no performance / bandwidth
oversubscription in the switching
architecture considering all the required
& considering all the planned ports

shall be able to perform L2 switching

SCADA implementation at CNG station Page 9 of 22

Page 74 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Support for broadcast / multicast/
unicast storm control to prevent
degradation of switch performance from
faulty end station.

shall be able to perform multi-layer


switching (L2, L3)

capabilities to implement minimum 255


active VLANs

Support for at least 32000 MAC


Address entries
6. Switching 160 Gbps per switch
Capacity
7. Minimum IPv4 Minimum 119 Mbps or more
Packet
Forwarding Rate

8. Layer-1 Support for 10/100 Base-T, 100 Base-


Services / FX, 10/100/1000 Base-T, 1000 Base-
Features SX, 1000 Base- LX
Required
IEEE 802.3ab
IEEE 802.3u
IEEE 802.3z
9. Layer-2 Services IEEE 802.1d Bridging, Spanning Tree
IEEE 802.1p Priority Queuing
Required IEEE 802.1q VLAN Tagging
Port- based VLAN
MAC- based VLAN
IEEE 802.1s Multiple Spanning Tree
IEEE 802.1w Rapid Spanning Tree
IEEE 802.1x Port Based Network
IEEE 802.1ab Link Layer Discovery
IEEE 802.3ad Link Aggregation
IEEE 802.3x Flow Control
IGMP snooping v1, v2, and v3
Link Aggregation and Port Trunking
(based on IEEE 802.3ad)

SCADA implementation at CNG station Page 10 of 22

Page 75 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
10. Layer-3 Services Should support static routing, RIP
v1/v2.
Required
Shall be able to support OSPF and BGP
by upgrading the software in future

IGMP v1, v2 and v3

Per Port QoS Configuration

IP Multicast Routing based on open


industry Standards

Should have congestion avoidance


capability

IEEE 802.1p Priority Queuing


11. Security Capabilities to deploy filters / access-
Services / lists on all the ports
Features
Required capabilities to implement IP and TCP
based filters on inter-VLAN routing

IEEE 802.1x Network Security and


Authentication along with port based
network access control

SSHv1 and SSHv2

DHCP Snooping

12. Management SNMP V1, v2 and V3 implementation

Features Command-line interface (CLI)-based


Required management console to provide
detailed and complete device
management capabilities
Capabilities implemented mirroring
ports at ingress and egress for
detailed traffic and network usage
analysis
Remote Monitoring (RMON) software
agent to support four RMON groups
(history, statistics, alarms, and events)
for enhanced traffic management,
monitoring, and analysis

13. Software Version of software for supplied


switch should be latest release to
support all required features.

Regulatory Compliances

SCADA implementation at CNG station Page 11 of 22

Page 76 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Safety UL 60950/ EN 60950/CSA-C22.2
Certifications No.60950/ IEC 60950

Electromagnetic FCC Part 15 (CFR 47), Class A/ ICES-


Emission 003, Class A/ EN 55022, Class A/
Certificate CISPR 22, Class A/ VCCI Class A/
EN300 386
Environmental RoHS Compliant
Safety
14 Power Supply 230 V AC

15 Communication PVC insulated with grey colour, AWG


cable 22 (0.3 mm²)or AWG 24 (0.2mm²)
4Pair, solid conductor, CAT 5e, UTP
cable (TIA/EIA 568) as per requirement
with flexible PVC conduit and PVC
gland & 8 pin RJ/Male /Female
connector wherever require.

7. LASER JET PRINTER:

Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

1 Make As per recommended vendor list

2 Print Laser jet colour


Technology

3 Graphic 600 x 600 dpi


Resolution

4 Text Resolution 600 x 600 dpi

5 Printer speed Typical min 15 colour pages per


minute

6 Paper eject Min 250 Sheets


capacity

7 interface USB and Ethernet

8 Buffer size Min 160 MB

9 Paper Size A4

10 Noise Level at Less than 56 dBA


1 mtr. Distance

SCADA implementation at CNG station Page 12 of 22

Page 77 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sr. Items As per Tender requirement Bidder Make & model Remark
No. Compliance no.

11 Power Supply 230V AC, 50 Hz

12 Quantity As per MR

8. REMOTE TERMINAL UNIT (RTU)


Sr. Items As per Tender requirement Bidder Make & Remark
No. Compliance model no.

1 Type Modular based rack mounted RTU

2 Model -

3 RTU feature RTU should have its own


processor, memory, power supply
unit, dedicated I/O cards &
communication ports also self
diagnostic feature and software
watch dog timer device to monitor
& report the healthiness of CPU,
I/O Cards, Power supply, Comm
Unit etc. Software Logic
implementation, data storage
capacity.

4 Processor 32 bit Microprocessor based.

5 RAM Min 16 MB

6 Communication IEC870-5-104/DNP3 over Ethernet


protocols

7 Digital Input As per PTS and Annexure III

8 Digital Output As per PTS and Annexure III

9 Analog Input As per PTS and Annexure III

10 Mix input output Mix analog /digital cards is also


cards acceptable subject to compliance to
requirement of IOs including
spares as per input output list

11 Interfacing
ports

11.1 RS232C As per PTS and Annexure III

11.2 RS485 As per PTS and Annexure III

11.3 USB Port/SD Storage data backup

SCADA implementation at CNG station Page 13 of 22

Page 78 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sr. Items As per Tender requirement Bidder Make & Remark
No. Compliance model no.

card

11.4 Profibus and As per PTS and Annexure III In case these ports
profinet are not available in
RTU, then bidder
shall consider a
protocol converter
compatible to their
RTU.

12 Data Time At RTU Level


Stamping

13 Internal battery The RTU shall be able to store the


backup configuration data and the process
database upon power failure for at
least one month on continuous
basis. Upon restoration of the
power, RTU shall resume the
normal operation automatically.

14 Communication RTUs shall be communication on a


ports pair of communication
channels/ports (Ethernet) with
telecom unit. Upon failure of
primary channel, RTU shall
respond to SCADA station
requests/ interrogation on
secondary channel automatically
without any loss of data &
operation. System shall provide
status on the availability of each of
the channels.

15 Features In the event of failure or break of


communication link, the RTU shall
continue to scan all parameters and
update its database. RTU shall
retain in its database the complete
analog & digital information of the
field till it is completely and
correctly read SCADA station to
take care of no loss of data in case
of failure of communication. The
RTU shall scan the field and the
memory buffer is to be sized (by
considering min 15 days down
time for SCADA system) to store
all the changing data (i.e. new
exception report for the data every
poll time) and SCADA station
receive the same without any loss

SCADA implementation at CNG station Page 14 of 22

Page 79 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sr. Items As per Tender requirement Bidder Make & Remark
No. Compliance model no.

of data.

RTU vender shall size the storage


memory as per tender requirement
to meet the above functionality.

16 Security as per Cyber security Industrial


IEC-62443 Automation and Control Systems
(IACS). Bidder shall provide
details about security type with
specification along with standards
and certificate

17 Protection from G3 compliant.


environment
airborne
contaminants as
per ISA 71.04

18 Quantity As per MR

9. RTU CABINET SPECIFICATION:


Sl.No Items As per Tender Bidder Make & model Remark
Compliance

1 Make As per recommended vendor list

2 Cabinet Mounting - Wall or stand mounted.


Area – safe area, inside control room

Protection - IP 52.

CRCA sheet steel enclosure of


minimum thickness of 1.5 mm and
gland plate is 3 mm Size – vendor to
specify.

3 Colour RAL 7035 for exterior and interior

4 Power supply Required (24 V DC)


unit

5 Cable entry Bottom

6 Provision for Required


separate ground
connections for
signals and

SCADA implementation at CNG station Page 15 of 22

Page 80 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sl.No Items As per Tender Bidder Make & model Remark
Compliance

power earth.

7 MCBs and TBs 20 % spare MCBs and 20% spare TBs


will be provided

8 Doors Single door with door switch

9 Light Front– interlock with panel door


switches.

10 Terminal blocks Din rail mounted, Screw less terminals


blocks, adequate rating fuses with LED
indication and easy isolation for DI, AI,
AO and DO. The metallic portion shall
be coated against rust/corrosion.

11 Barriers/ Analog and digital barriers are required


Isolators for hazardous area equipment.

12 Quantity As per MR

10. CABINET FOR MOUNTING SERVERS AND TELECOM EQUIPMENT ETC.


Sl.No Items As per Tender Bidder Make & model Remark
Compliance

1 Make As per recommended vendor list

2 Cabinet type The cabinet shall be mounted in IP 41


CRCA sheet steel enclosure of
minimum thickness of 1.5 mm and
gland plate is 3 mm, free standing
cabinets with front and back lockable
doors and with gasket

3 Anti vibration All system cabinets/ panels will have


pads provided anti vibration pads with minimum
15mm thickness.

4 Cabinet size As per requirement. Server cabinet is


transparent at front door) of size 800 x
800 x 2100 (2100 including plinth
100mm) with power sockets, lights,
fans and internal wiring. Frame
minimum thickness shall be 1.5 mm.

5 Colour RAL 7035 for exterior and interior

SCADA implementation at CNG station Page 16 of 22

Page 81 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sl.No Items As per Tender Bidder Make & model Remark
Compliance

6 Base/Plinth Black colour


frame colour

7 Cable entry bottom

8 Provision for Required


separate ground
connections for
power supply.

9 MCBs and TBs 20 % spare MCBs and 20% spare TBs


will be provided

10 Doors Double doors at back and transparent


single door at front with neoprene
gaskets at every 1.5 m at back & front

11 Fans in the As required for cooling and ventilation


system cabinets

12 Terminal blocks As per requirement

13 Lifting eye bolt Removable type required

14 Indicating RED color ----- Power ON


Lamps

15 As per MR
Quantity

16 Server cabinet shall also have the provision to mount


Monitor, four servers and IT equipment like LAN
switches, GPS, routers etc.

17
Cabinets shall be with lockable front and rear doors with
gasket and fittings to keep out moisture, corrosive,
salts, dust & gases. All doors, drawers, trays and other
weight supporting parts shall be fabricated of metal
adequately reinforced to limit vibration and ensure plane
surfaces and shall be well housed and tidy in appearance.
All fasteners including nuts, bolts, flat/ lock washers and
screws shall be of SS. All doors shall have flush mounted
handles with key operated mechanical door locking
arrangement. The locking arrangement shall be
interchangeable and shall have common key for
locking/ unlocking all locks (master keying
arrangement).

SCADA implementation at CNG station Page 17 of 22

Page 82 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Sl.No Items As per Tender Bidder Make & model Remark
Compliance

Cabinets shall also include a foldable/ sliding tray at


convenient location for mounting the PDT to facilitate
diagnostic, programming and maintenance functions.

11. POWER DISTRIBUTION CABINET.


Sl.No Items As per Tender Bidder Make & model Remark
Compliance

1 Make As per recommended vendor list

2 Cabinet type The cabinet shall be mounted in IP 41


CRCA sheet steel enclosure of
minimum thickness of 1.5 mm and
gland plate is 3 mm with front lockable
doors.

3 Cabinet size As per requirement

4 Colour RAL 7035 for exterior and interior

5 Base/Plinth Black colour


frame/back
frame colour

6 Cable entry bottom

7 Provision for Required


separate ground
connections for
power supply.

8 MCBs and TBs 20 % spare MCBs and 20% spare TBs


will be provided

9 Power DP MCB for incoming and outgoing


Distribution power.

Independent DP MCBS for servers,


Monitors, EWS, OWS, GARC,
Telecom, printers, LAN switches etc.
as the requirement

10 Indicating RED color ----- Power ON


Lamps

11 As per MR
Quantity

SCADA implementation at CNG station Page 18 of 22

Page 83 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
12. PROGRMMABLE DIAGNOSTIC TOOL (PDT)
One number of note book PDT/Laptop is used for programmable and diagnostic test tool. Programming and
unity pro configuration software is being loaded in the laptop and used for the development of logic and
diagnostic of RTU hardware and software.

Sl.No Items As per Tender Bidder Make & model Remark


Compliance

1 Make As per recommended vendor list

2 Model -

3 CPU 5th generation Intel core i7,min 2.0


GHz

4 Cache 4 MB

5 RAM Min 4 GB

6 Hard Disk Min 500 GB SATA

7 DVD R/W 4.7GB min

8 Display Min 12.5” TFT

9 Operating Microsoft windows 7 professional


system edition 32 bit OS

10 MS Office Latest 2013

11 Ports 3 USB / Ethernet port RJ45 port 2 nos

12 Application RTU system configuration, simulation


software & Diagnostic software.

13 Anti-virus Loaded with license version Latest


Anti-virus

14 Battery backup Min 6 Hrs

15 Accessories Carrying case if applicable for flame


proof, LAN cable, USB cable, AC
adaptor 240 VAC 50 Hz

16 Quantity As per MR

Note:

All the electronic component shall be protected from airborne contaminants as per ISA 71.04 environmental
conditions for process measurement and control system. For those equipment mounted in field/CNG stations shall
be G3 compliant and master control room mounted shall be G2 compliant.

SCADA implementation at CNG station Page 19 of 22

Page 84 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
13. Signal Multiplier & Barrier
• Function: To limit the transfer of energy to hazardous area.

• Hazardous Area (Field): IEC Zone I Gr. IIA & IIB, T3 as per IS 2148.

• Location of Barriers: RTU Cabinet (Safe Area)

• Type: Isolating three ports for input/output and power supply.

• Power Supply Source: External Power.

• Nominal Voltage of operation: 24V DC

• Signal Type: 4-20mA

• Cable Type: 0.5mm2 shielded to 1.5 mm2

• Cable Resistance: 39.7 /km

• Cable L/R ratio: 25 H/

• Cable Capacitance: 400pf/m

• Max Fault Voltage: 250 V (RMS)

• Grounding: Individual through bus bar.

• Certifications: Approved certificate from recognized statutory body (CCOE).

• Suitability: Smart transmitter with HART protocol.

• Mounting Accessories: Required (For mounting on panel back).

• Make: as per recommended vendor list

• Model: By Vendor.

14. Power Supply 24 VDC


Type Solid state redundant
Input 230 VAC 50 Hz
Output 24 VDC
Current rating As required
Line regulation 0.05%
Load regulation 0.05%
Stability 0.2% Under constant load
Transient recovery period < 100 micro seconds
Auto tracking of the output < 1% error

SCADA implementation at CNG station Page 20 of 22

Page 85 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
Indication LED for SUPPLY ON
Fuse To be provided on AC & DC lines
Output monitoring Socket to be provided with adjustment facility
Protection Short circuit and over load, potential free contact required for
health signal of power supply
Ripple and noise 1 mV (rms) or less
Make As per recommended vendor list

15. MODEM/GATE WAY HARDWARE SPECIFICATIONS:

This shall be an intelligent computing platform of industrial grade capable of running 24x7 having central
processing unit of having RAM min 1GB, clock speed min 1 Ghz, storage of min 4GB

This should consist of minimum of 2 number ethernet ports with two different IP address for communication with
RTU. And one number for local configuration

Modem/gateway shall support MPLS on VPN and GPRS(wireless) on VPN

Modem/gateway must also support cloud communication with protocol like MQTT/AMQP/equivalent for
supporting industrial cloud network technology.

Modem /gate way shall have following features:

 Industrial Grade

 EMC Specifications:

o ESD Electrostatic Discharge Immunity:

o RFI Radio Frequency Immunity:

o EFT Electrical Fast Transient/Burst Immunity:

o Surge Immunity:

 Mechanical: DIN Rail Mount Metal Housing IP42 must

 Environment

o Humidity 5 to 95% relative humidity (noncondensing)

o Storage 6 to 60℃

o Working 6 to 50℃

 Power Supply DC 12-48V

 Features

o Link Backup

o Link Detection & Auto-Recover

SCADA implementation at CNG station Page 21 of 22

Page 86 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
o Various Heartbeat Package, Automatic Recover from Failure

o Watchdog Self-diagnostic, Automatic Recover from Failure


Note:

1. The above specification of servers and workstations are the minimum that is required. The SCADA vendor shall
also refer other documents/drawing attached elsewhere in RFP during the system sizing and shall accordingly
select the hardware. If at any stage of system implementation, it is found that the servers & work stations,
selected by SCADA vendor are not having adequate processing power, main memory etc to meet the system
performance requirement of this specification, SCADA vendor shall replace these with higher end machine with
no cost and time implication

2. The above specification and functional details of server/HMI/MMI are the minimum that is required. The
SCADA vendor shall provide SCADA system by meeting all the requirement mentioned in tender document and
has to finalize equipment in total for successful functioning of SCADA system.

Σ Σ Σ

SCADA implementation at CNG station Page 22 of 22

Page 87 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

ANNEXURE II

POWER CONSUMPTION REQUIREMENTS (PCR) FORM

This form shall duly fill and signed by bidder and submit along with bid.

1. SCADA SYSTEM

Item Qty Max. power consumption In rush current Peak current

Unit (VA) Total Power Unit Total Duration Total Duration


(VA) factor (A) (A) (m sec) (A) (m sec)

SCADA Server

Archive server

Operator work
station

Engineering work
station

Web server

GPS

Monitors

LAN Switch

Cabinet accessories

1. FAN

2. Illumination
lamp

Printer

Any item/s not


included above

SCADA implementation at CNG station Page 1 of 2

Page 88 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

2. RTU/PLC DC Load Requirements(Typical)

S. RTUs All RTU/PLC cards Max. power consumption Complete RTUC DC


No. name power requirements
Type Quantity Unit Total (watts)
consumption consumption
(watts) (watts)

1 AI

2 DI

3 DO

4 AO

5 Serial
cards

6 CPU,

7 Any item/s
not included
above like
GSM or
GPRS
modem

NOTE:

1. All RTU cards (including CPU, communication cards, AI, AO, DI, DO, Serial cards along with power
supply unit) are included for power consumption.

2. The digital output cards power consumption (watts) shall also include the power requirements for
interposing relays.

Σ Σ Σ

SCADA implementation at CNG station Page 2 of 2

Page 89 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

ANNEXURE III
TYPICAL I/O COUNTS DETAILS FOR RTU SYSTEM

Category – 1 Station having 1 number of CNG compressor

Total Input / output in Spare slots- future


Sl. No. Type Actual spare 20% Total IO Remarks
RTU cards

1 AI(4-20mA) Analog input 3 0.6 4

2 DI(24 V DC) Digital Input 2 0.4 3 1

3 DO(24 V DC) Digital output 2 0.4 3

Modbus serial master


4 Modbus RS 485 2 1 3
port

5 Profibus Profibus Port 1 1 2

6 Profinet Profinet Port 1 1 2

Modbus serial
7 Modbus RS 232/RS 485 0 1 1
configruable port

Category – 2- Station having 2 number of CNG compressor

Total Input / output in Spare slots- future


Sl. No. Type Actual spare 20% Total IO Remarks
RTU cards

1 AI(4-20mA) Analog input 6 1.2 8

SCADA implementation at CNG station Page 1 of 5


Page 90 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

ANNEXURE III
TYPICAL I/O COUNTS DETAILS FOR RTU SYSTEM

2 DI(24 V DC) Digital Input 2 0.4 3 1

3 DO(24 V DC) Digital output 2 0.4 3

Modbus serial master


4 Modbus RS 485 2 1 3
port

5 Profibus Profibus Port 1 1 2

6 Profinet Profinet Port 1 1 2

Modbus serial
7 Modbus RS 232/RS 485 0 1 1
configruable port

Category – 3- Station having 3 or 4 number of CNG compressor

Total Input / output in Spare slots- future


Sl. No. Type Actual spare 20% Total IO Remarks
RTU cards

1 AI(4-20mA) Analog input 9 1.8 11

2 DI(24 V DC) Digital Input 2 0.4 3 1

3 DO(24 V DC) Digital output 2 0.4 3

Modbus serial master


4 Modbus RS 485 3 1 4
port

SCADA implementation at CNG station Page 2 of 5


Page 91 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

ANNEXURE III
TYPICAL I/O COUNTS DETAILS FOR RTU SYSTEM

5 Profibus Profibus Port 1 1 2

6 Profinet Profinet Port 1 1 2

Modbus serial
7 Modbus RS 232/RS 485 0 1 1
configruable port

Note
1 Refer below table for ports distribution. However this may be change as per site requirement.

Category – 1

Equipment No of port Type of interface Remark


Compressor 1 Profibus/Profinet Refer note 2
Dispenser 1 RS 485 Master Multidrop , master port
Flow meter
Flow computer
VFD
Softstarter 1 RS 485 Master Multidrop , master port
Multifunction meter
GGset
Air compressor

Category – 2
Equipment No of port Type of interface Remark
Compressor 1 Profibus/Profinet Refer note 2 & 3
Dispensers 1 RS 485 Master Multidrop , master port
Flow meter

SCADA implementation at CNG station Page 3 of 5


Page 92 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

ANNEXURE III
TYPICAL I/O COUNTS DETAILS FOR RTU SYSTEM
Flow computer
VFD
Softstarter 1 RS 485 Master Multidrop , master port
Multifunction meter
GGset
Air compressor

Category – 3
Equipment No of port Type of interface Remark
Compressors 1 Profibus/Profinet Refer note 2
Dispensers 2 RS 485 Master Multidrop , master port
Flow meter
Flow computer
VFD
Softstarter 1 RS 485 Master Multidrop , master port
Multifunction meter
GGset
Air compressor

RTU shall have both the ports profibus and profinet or bidder shall consider a compatiable protocol converter. Few compressors are with Profibus, few
2 compressors are with profinet and few compressors are with both. Number of ports as shown above are tentative, SCADA vendor shall ascertain the quantity of
ports in RTU category wise by considering with or without daisy chain or switch as applicable wherever number of CNG compressors are more than one

RTU shall be compatible to communicate with both PPI and MPI ports of Siemens PLC. For reference of identification and compatibility check with Siemens
3
PLC refer Annexure VI consisting MLFB numbers of Siemens PLC's in IGL

4 In addition to above, RTU shall have dual ethernet communication port for telecom modem , dedicated diagnostic and USB port etc.

5 Modbus serial port RS 485 shall be master and slave configruable

6 Modbus serial port RS 485/RS232 shall be configruable either RS 485 or RS 232

SCADA implementation at CNG station Page 4 of 5


Page 93 of 142
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01

ANNEXURE III
TYPICAL I/O COUNTS DETAILS FOR RTU SYSTEM
Spare slot shall be compatible/configurable for inserting all type of cards as analog input, analog output , digital input or digital out cards or mix /hybrid IOs or
7
RS485, Profibus, Profinet.

S.N. RTU Category Description

1 Category – 1 Configuration of MODBUS RS485 ports at Stations having 1 number of CNG Compressors

2 Category – 2 Configuration of MODBUS RS485 ports at Stations having 2 number of CNG Compressors

3 Category – 3 Configuration of MODBUS RS485 ports at Stations having 3 to 4 number of CNG Compressors

SCADA implementation at CNG station Page 5 of 5


Page 94 of 142
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - IV
Phase -I
List of Equipment at CNG stations (Tentative)
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Control Detail Detail equipment RTU
Sno. Station Name Meter Skid
Room Flow Categories
Compressor No.of Make/ Flow Meter Make (IF VFD/Soft
PLC Make Computer Make Make quantity quantity
Make Dispensers SUCTION Make PRESENT) Starter
Make
METERING
D-RAND (1200 MICRO
MADANPUR
CR01
SCM)
Siemens S7-300 Compac 4 EMERSON MICRO MOTION FISHER
MOTION
KOHLER INGERSOLL RAND 2 1
1
KHADAR I
CTG 1
CR01

2 NH 8 DEFENCE CR02 DELTA (1200 SCM) Siemens S7-200 Compac 6 EMERSON MICRO MOTION FISHER KOHLER INGERSOLL RAND Soft Starter 2 1 CTG 1

D-RAND (1200 BRISTOL


CR07
SCM)
Siemens S7-300 Delta 1 CHEMTROLS HEINRICHS
BABCOCK
E&H KOHLER INGERSOLL RAND 2 1

D-RAND (1200
3 ROHINI MEGA CR07
SCM)
Siemens S7-300 Compac 3 KOHLER INGERSOLL RAND CTG 3

CR07 DELTA (1200 SCM) Siemens S7-300 Compac 2 ATLAS COPCO Soft Starter

D-RAND (1200 BRISTOL MICRO


CR08
SCM)
Siemens S7-300 Compac 6 CHEMTROLS HEINRICHS
BABCOCK MOTION
KOHLER INGERSOLL RAND 2 1
4 DWARKA SEC IX CTG 2
KIRLOSKAR (1200
CR08 Siemens S7-300 ELGI Soft Starter
SCM)
BRISTOL
CR05
BURCKHARDT
Compac 1 CHEMTROLS HEINRICHS
BABCOCK
KOHLER INGERSOLL RAND 2 1
Siemens S7-300
(1200 SCM)
5 I F C GAZIPUR II CR05 FTI 3 INGERSOLL RAND CTG 2

CR05 DELTA (2400 SCM) Siemens S7-300 Compac 2 BRAVO VFD


BRISTOL
DWARKA CR08 BURCKHARDT Compac 2 CHEMTROLS HEINRICHS
BABCOCK
KOHLER INGERSOLL RAND 2 1
6
SECTOR 23 (1200 SCM)
Siemens S7-300 CTG 1
CR08 Compac 2
BRISTOL
CR04 Compac 2 EMERSON MICRO MOTION
BABCOCK
KOHLER INGERSOLL RAND 2 1
7 NARELA DSIIDC CTG 1
CR04 DELTA (1200 SCM) Siemens S7-300 Compac 1 INGERSOLL RAND
MICRO
CR03 SAFE 1 Emerson MICRO MOTION FISHER
MOTION
KOHLER INGERSOLL RAND Soft Starter 2 1
8 MAYAPURI CR03 DELTA (1200 SCM) Siemens S7-200 Delta 1 CTG 1
CR03 FTI 3

CR05 SAFE 1 CHEMTROLS HEINRICHS SCHNEIDER E&H KOHLER INGERSOLL RAND Soft Starter 2 1
CBD KIRLOSKAR (1200
9 Siemens S7-300 CTG 1

Page 951 of
of 2142
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - IV
Phase -I
List of Equipment at CNG stations (Tentative)
CBD KIRLOSKAR (1200
9
SHAHDARA CR05 SCM)
Siemens S7-300
Delta 1 CTG 1
CR05 Compac 3
BURCKHARDT (400 SUCTION
SHAKURPUR CR06
SCM)
Siemens S7-300
METERING
MICRO MOTION E&H INGERSOLL RAND 2 1
10 CTG 1
DIESEL SHED CR06
MICRO
MOTION
SUCTION
CR06 Compac 4
METERING
MICRO MOTION KOHLER cp 2 1
11 SHAKURPUR CTG 1
INTERMECH (2400
CR06 Siemens S7-1200 VFD
SCM)
KIRLOSKAR (1200 BRISTOL
CR07
SCM)
Siemens S7-300 Compac 4 CHEMTROLS HEINRICHS
BABCOCK
KOHLER INGERSOLL RAND 2 1
12 ROHINI SEC X CTG 2
KIRLOSKAR (2400
CR07 Siemens S7-300 Compac 2 ELGI VFD
SCM)
D-RAND (1200 BRISTOL
CR07
SCM)
Siemens S7-300 Compac 3 EMERSON MICRO MOTION
BABCOCK
KOHLER INGERSOLL RAND 2 1
ROHINI -22
13 (NEAR AGARSEN CR07 Compac 1 INGERSOLL RAND CTG 2
COLLEGE)
CR07 DELTA (1200 SCM) Siemens S7-300 Compac 1 Soft Starter
BRISTOL
ROHINI -22 CR07 Compac 3 EMERSON MICRO MOTION
BABCOCK
KOHLER INGERSOLL RAND 2 1
14 (NEAR MGF CTG 2
MALL) CR07 DELTA (1200 SCM) Siemens S7-300 Compac 2 INGERSOLL RAND Soft Starter

CR02 Delta 3 EMERSON MICRO MOTION FISHER KOHLER INGERSOLL RAND Soft Starter 2 1
15 SHANTI PATH CR02 DELTA (1200 SCM) Siemens S7-300 Compac 3 CTG 1
CR02
KIRLOSKAR (1200
16 JAHANGIRPURI CR04
SCM)
Siemens S7-300 Compac 6 EMERSON MICRO MOTION FISHER KOHLER ELGI Soft Starter 2 1 CTG 1
BRISTOL
CR01 Delta 2 CHEMTROLS HEINRICHS
BABCOCK
KOHLER 2 1
17 NEHRU PLACE CTG 1
CR01 DELTA (1200 SCM) Siemens S7-200 Compac 3 INGERSOLL RAND Soft Starter

D-RAND (1200
CR07
SCM)
Siemens S7-300 Safe 1 EMERSON MICRO MOTION FISHER KOHLER INGERSOLL RAND 2 1
18 ROHINI SEC XIX CR07 compac 4 ELGI CTG 2
KIRLOSKAR (1200
CR07 Siemens S7-300 FTI 1 INGERSOLL RAND Soft Starter
SCM)
BURCKHARDT
CR31
(1200 SCM)
Siemens S7-300 COMPAC 5 CHEMTROLS HEINRICHS FISHER E&H KOHLER INGERSOLL RAND 2 1
19 NOIDA SEC 122 CTG 2
CR31 DELTA (1200 SCM) Siemens S7-300 COMPAC 2 INGERSOLL RAND

BRISTOL
NH-24 POCKET A
CR05 Compac 3 CHEMTROLS HEINRICHS
BABCOCK
KOHLER INGERSOLL RAND 2 1
20
IFC-III GAZIPUR
CTG 1
CR05 DELTA (1200 SCM) Siemens S7-200 Soft Starter

Page 962 of
of 2142
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
GALILEO (1150 MICRO
CR01 SAIA Compac 1 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) MOTION
1 OKHLA I DEPOT CTG 2 2
Siemens S7-
CR01 SULZER (600 SCM) Compac 1 INGERSOLL RAND STAR/DELTA
300
GALILEO (1150 MICRO
CR01 SAIA Compac 2 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) MOTION
2 OKHLA II DEPOT CTG 2 2
Siemens S7-
CR01 SULZER (600 SCM) INGERSOLL RAND STAR/DELTA
300
MICRO
CR01 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
MOTION
GALILEO (1150
3 I P DEPOT CR01
SCM)
SAIA Compac 1 INGERSOLL RAND CTG 1 2

CR01 TGT 1

D-RAND (1200 Siemens S7- MICRO


CR05 TGT 2 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
PATPARGANJ SCM) 300 MOTION
4
DEPOT
CTG 2 2
Siemens S7-
CR05 DELTA (1200 SCM) Compac 1 INGERSOLL RAND Soft Starter
300
GALILEO (1150 MICRO
CR04 SAIA Compac 2 EMERSON FISHER INGERSOLL RAND 2 1
SCM) MOTION
5 B B M I DEPOT CTG 2 2
SULZER (600 Siemens S7-
CR04 STAR/DELTA
SCM) 300
GALILEO (1150 MICRO
CR04 SAIA Compac 2 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) MOTION
6 B B M II DEPOT CTG 2 2
SULZER (600 Siemens S7-
CR04 STAR/DELTA
SCM) 300
D-RAND (1200 Siemens S7- MICRO
CR07 SAFE 2 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION
7 ROHINI I DEPOT CTG 1 2
CR07 INGERSOLL RAND

BRISTOL
CR07 NP 1 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
D-RAND (1200 Siemens S7- BABCOCK
8 ROHINI II DEPOT
SCM) 300
CTG 1 2
CR07 Compac 2 INGERSOLL RAND

D-RAND (1200 Siemens S7- MICRO


CR06 SAFE 2 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
WAZIRPUR I SCM) 300 MOTION
9
DEPOT
CTG 1 2
CR06 INGERSOLL RAND

MICRO
MAYAPURI CR03 D-RAND (1200 Siemens S7- SAFE 1 Emerson FISHER INGERSOLL RAND 2 1
10
DEPOT SCM) 300
MOTION CTG 1 2
CR03 Compac 1
HARI NAGAR I D-RAND (1200 Siemens S7-
11
DEPOT
CR03
SCM) 300
NP 2 KOHLER INGERSOLL RAND 2 1 CTG 1 2

Page 971 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
MICRO
HARI NAGAR II CR03 D-RAND (1200 Siemens S7- NP 1 Emerson FISHER INGERSOLL RAND 2 1
12
DEPOT SCM) 300
MOTION CTG 1 2
CR03 Compac 1
D-RAND (1200 Siemens S7- BRISTOL
CR05 NP 1 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
13 E V N DEPOT CTG 2 2
KIRLOSKAR (1200 Siemens S7-
CR05 Compac 2 INGERSOLL RAND Soft Starter
SCM) 300
GALILEO (1150 MICRO
CR02
SCM)
SAIA TGT 2 EMERSON
MOTION
FISHER KOHLER INGERSOLL RAND 2 1
14 S N DEPOT CTG 1 2
CR02 INGERSOLL RAND

MICRO
CR02 TGT 1 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
VASANT VIHAR MOTION
15
DEPOT
CTG 1 2
KIRLOSKAR (1200 Siemens S7-
CR02 Compac 1 ELGI Soft Starter
SCM) 300
BURCKHARDT Siemens S7- MICRO
16 OKHLA III DEPOT CR02
(1200 SCM) 300
Compac 2 EMERSON
MOTION
FISHER INGERSOLL RAND 2 1 CTG 1 2

D-RAND (1200 Siemens S7- MICRO


CR02 TGT 2 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION
17 KALKAJI DEPOT CTG 2 2
BURCKHARDT Siemens S7-
CR02 INGERSOLL RAND
(1200 SCM) 300
GALILEO (1150 MICRO
CR04 SAIA Compac 2 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) MOTION
18 G T K DEPOT CTG 2 2
KIRLOSKAR (1200 Siemens S7-
CR04 Soft Starter
SCM) 300
GALILEO (1150 MICRO
CR06 SAIA TGT 1 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
WAZIRPUR II SCM) MOTION
19
DEPOT
CTG 2 2
SULZER (600 Siemens S7-
CR06 Compac 1 INGERSOLL RAND STAR/DELTA
SCM) 300
D-RAND (1200 Siemens S7-
CR06 SAFE 1 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1
PEERAGARHI SCM) 300
20
DEPOT
CTG 2 2
KIRLOSKAR (1200 Siemens S7-
CR06 Compac 1 INGERSOLL RAND Soft Starter
SCM) 300
MICRO
CR03 NP 1 EMERSON FISHER INGERSOLL RAND 2 1
KESHAVPUR D-RAND (1200 Siemens S7- MOTION
21
DTC SCM) 300
CTG 1 2
CR03 Compac 2 INGERSOLL RAND

MICRO
CR06 EMERSON FISHER INGERSOLL RAND 2 1
D-RAND (1200 Siemens S7- MOTION
22 NANGLOI DEPOT
SCM) 300
CTG 1 2
CR06 Compac 2 INGERSOLL RAND

D-RAND (1200 Siemens S7- BRISTOL


CR05 SAFE 1 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
NAND NAGARI SCM) 300 BABCOCK
23
DEPOT
CTG 2 2
KIRLOSKAR (1200 Siemens S7-
CR05 Compac 2 INGERSOLL RAND Soft Starter
SCM) 300

Page 982 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BRISTOL
CR06 FTI 1 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
D-RAND (1200 Siemens S7- BABCOCK
24 ROHINI III DEPOT
SCM) 300
CTG 1 2
CR06 NP 1 INGERSOLL RAND

MICRO BRISTOL
CR02 Compac 2 EMERSON INGERSOLL RAND 2 1
AMBEDKAR MOTION BABCOCK
25
NAGAR DTC
CTG 1 2
BURCKHARDT Siemens S7-
CR02
(1200 SCM) 300
D-RAND (1200 Siemens S7-
DWARKA CR08 Compac 2 CHEMTROLS HEINRICHS FISHER INGERSOLL RAND 2 1
SCM) 300
26 SECTOR VIII CTG 2 2
Siemens S7-
DEPOT CR08 DELTA (1200 SCM) INGERSOLL RAND
300
BURCKHARDT Siemens S7- BRISTOL
DWARKA CR08 FTI 2 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
(1200 SCM) 300 BABCOCK
27 SECTOR II CTG 2 2
DEPOT BURCKHARDT Siemens S7-
CR08 INGERSOLL RAND
(1200 SCM) 300
BURCKHARDT Siemens S7- BRISTOL
CR05 Compac 2 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
DILSHAD (1200 SCM) 300 BABCOCK
28
GARDEN DEPOT
CTG 2 2
BURCKHARDT Siemens S7-
CR05 INGERSOLL RAND
(1200 SCM) 300
D-RAND (1200 Siemens S7- MICRO
29 NARELA DTC CR04
SCM) 300
Compac 2 EMERSON
MOTION
FISHER KOHLER INGERSOLL RAND 2 1 CTG 1 2

BURCKHARDT Siemens S7- MICRO BRISTOL


CR01 Compac 5 EMERSON INGERSOLL RAND 2 1
(1200 SCM) 300 MOTION BABCOCK
30 RAJGHAT DTC CTG 2 2
BURCKHARDT Siemens S7-
CR01 INGERSOLL RAND
(1200 SCM) 300
BURCKHARDT Siemens S7- BRISTOL
CR05 Compac 2 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
(1200 SCM) 300 BABCOCK
31 SEEMAPURI DTC CTG 2 2
BURCKHARDT Siemens S7-
CR05 INGERSOLL RAND
(1200 SCM) 300
D-RAND (1200 Siemens S7- MICRO
CR03 Compac 2 EMERSON FISHER INGERSOLL RAND 2 1
PUNJABI BAGH SCM) 300 MOTION
32 CTG 1 2
DTC
CR03 INGERSOLL RAND

BURCKHARDT Siemens S7- MICRO BRISTOL


33 GAZIPUR DTC CR05
(1200 SCM) 300
Compac 2 CHEMTROLS
MOTION BABCOCK
INGERSOLL RAND 2 1 CTG 1 2

KANJHAWALA Siemens S7- BRISTOL


34
DEPOT
CR07 DELTA (1200 SCM)
300
Compac 3 CHEMTROLS HEINRICHS
BABCOCK
INGERSOLL RAND 2 1 CTG 1 2

ROHINI IV Siemens S7- BRISTOL


35
DEPOT
CR07 DELTA (1200 SCM)
300
Compac 2 CHEMTROLS HEINRICHS
BABCOCK
INGERSOLL RAND 2 1 CTG 1 2

YAMUNA VIHAR Siemens S7- MICRO BRISTOL


36
DTC
CR05 DELTA (1200 SCM)
300
Compac 2 EMERSON
MOTION BABCOCK
INGERSOLL RAND 2 1 CTG 1 2

Siemens S7-
37 BAWANA DTC CR07 DELTA (1200 SCM)
300
Compac 2 CHEMTROLS HEINRICHS FISHER INGERSOLL RAND 2 1 CTG 1 2

Page 993 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BURCKHARDT Siemens S7- MICRO BRISTOL
CR06 Compac 1 EMERSON INGERSOLL RAND 2 1
(1200 SCM) 300 MOTION BABCOCK
38 SHADIPUR DTC CTG 2 2
BURCKHARDT Siemens S7-
CR06 Compac 1 INGERSOLL RAND
(1200 SCM) 300
BURCKHARDT Siemens S7-
39 NARAYANA DTC CR03
(1200 SCM) 300
Compac 2 CHEMTROLS HEINRICHS FISHER INGERSOLL RAND 2 1 CTG 1 2

DICHAU KALA Siemens S7- MICRO


40
DTC
CR03 DELTA (1200 SCM)
300
Compac 2 EMERSON
MOTION
FISHER INGERSOLL RAND 2 1 CTG 1 2

BURCKHARDT Siemens S7- BRISTOL


CR02 Compac 2 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
LADO SARAI (1200 SCM) 300 BABCOCK
41
DTC
CTG 2 2
BURCKHARDT Siemens S7-
CR02 INGERSOLL RAND
(1200 SCM) 300
MANGLA PURI Siemens S7- SUCTION MICRO
42
DTC
CR08 DELTA (1200 SCM)
300
Compac 2
METERING MOTION
2 1 CTG 1 2

Siemens S7-
CR08 DELTA (1200 SCM) Compac 4 CHEMTROLS HEINRICHS FISHER INGERSOLL RAND 2 1
300
43 KAIR DEPOT CTG 2 2
Siemens S7-
CR08 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
300
SUNHERI PULA Siemens S7- MICRO BRISTOL
44
(DIMTS DEPOT)
CR01 DELTA (1200 SCM)
300
Compac 2 EMERSON
MOTION BABCOCK
INGERSOLL RAND 2 1 CTG 1 2

KANJHAWALA- II Siemens S7-


45
DEPOT
CR07 DELTA (1200 SCM)
300
Compac 2 CHEMTROLS HEINRICHS FISHER INGERSOLL RAND 2 1 CTG 1 2

KUSHAK NALLAH Siemens S7-


46
(DIMTS DEPOT)
CR01 DELTA (2400 SCM)
300
Compac 4 CHEMTROLS HEINRICHS FISHER SCHULZ(BRAVO) VFD 2 1 CTG 1 2

OKHLA DIMTS Siemens S7- SUCTION MICRO


47
DTC
CR02 DELTA (1200 SCM)
300
Compac 2
METERING MOTION
INGERSOLL RAND 2 1 CTG 1 2

GALILEO (1150 MICRO


CR01 SAIA FTI 4 EMERSON FISHER MICRO MOTION KOHLER INGERSOLL RAND 2 1
PRAGATI SCM) MOTION
48
MAIDAN
CTG 2 2
Siemens S7-
CR01 DELTA (1200 SCM) Compac 1 INGERSOLL RAND Soft Starter
200

CR01 GALILEO (1150 Compac 1 MICRO MOTION KOHLER 2 1


SAIA
SCM)
CR01 Compac 2
D-RAND (1200 Siemens S7- MICRO BRISTOL
SARAI KALE CR01 EMERSON KOHLER INGERSOLL RAND 2 1
49
KHAN I & 2
SCM) 300 MOTION BABCOCK CTG 3 2
D-RAND (1200 Siemens S7-
CR01 Compac 6 INGERSOLL RAND
SCM) 300

CR01 INGERSOLL RAND

GALILEO (1150 MICRO


CR01 SAIA Delta 6 EMERSON FISHER MICRO MOTION KOHLER INGERSOLL RAND 2 1
SCM) MOTION
50 OKHLA MORH CTG 2 2
Siemens S7-
CR01 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
200

Page 1004 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
D-RAND (1200 Siemens S7- MICRO
CR01 Compac 6 EMERSON FISHER E&H KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION
51 CRRI CTG 2 2
D-RAND (1200 Siemens S7-
CR01 Compac 3 INGERSOLL RAND
SCM) 300
GALILEO (1150 MICRO
CR05 SAIA Compac 6 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) MOTION
52 NH 24 GAZIPUR CTG 2 2
Siemens S7-
CR05 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
200
D-RAND (1200 Siemens S7- BRISTOL
CR05 SAFE 12 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK

CR05 FTI 2 KOHLER INGERSOLL RAND

PATPARGANJ
53
MEGA
CR05 FTI 1 INGERSOLL RAND CTG 3 2

Siemens S7-
CR05 DELTA (1200 SCM) Compac 2 INGERSOLL RAND Soft Starter
200
KIRLOSKAR (2400 Siemens S7-
CR05 Compac 3 ELGI VFD
SCM) 300
D-RAND (1200 Siemens S7- MICRO
CR01 Compac 4 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION
54 SARITA VIHAR CTG 2 2
Siemens S7-
CR01 DELTA (1200 SCM) Compac 1 INGERSOLL RAND Soft Starter
200
MADANPUR D-RAND (1200 Siemens S7- MICRO
55
KHADAR I
CR01
SCM) 300
Compac 4 EMERSON
MOTION
FISHER MICRO MOTION KOHLER INGERSOLL RAND 2 1 CTG 1 1

Siemens S7-
CR01 DELTA (1200 SCM) Compac 2 INGERSOLL RAND Soft Starter 2 1
MADANPUR 200
56
KHADAR II
CTG 2 2
Siemens S7-
CR01 DELTA (1200 SCM) Compac 3 Soft Starter
300
GALILEO (1150 MICRO
CR02 SAIA EMERSON FISHER E&H KOHLER INGERSOLL RAND 2 1
SCM) MOTION
R K PURAM SEC D-RAND (1200 Siemens S7-
57
XII
CR02 Compac 4 INGERSOLL RAND CTG 3 2
SCM) 300
Siemens S7-
CR02 DELTA (1200 SCM) Compac 4 Soft Starter
200
D-RAND (1200 Siemens S7- MICRO
CR02 Compac 7 EMERSON FISHER E&H KOHLER INGERSOLL RAND 2 1
R K PURAM SEC SCM) 300 MOTION
58
X
CTG 2 2
D-RAND (1200 Siemens S7-
CR02 INGERSOLL RAND Soft Starter
SCM) 300
D-RAND (1200 Siemens S7- MICRO
CR02 Delta 6 EMERSON FISHER E&H KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION

CR02 INGERSOLL RAND


R K PURAM SEC D-RAND (1200 Siemens S7-
59
III SCM) 300
CTG 3 2
CR02 Compac 1 INGERSOLL RAND

Page 1015 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
Siemens S7-
CR02 DELTA (1200 SCM) Compac 2 Soft Starter
200
D-RAND (1200 Siemens S7- MICRO
CR02 Compac 3 EMERSON FISHER MICRO MOTION KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION
60 MAHIPALPUR CTG 2 2
Siemens S7-
CR02 DELTA (1200 SCM) Compac 4 INGERSOLL RAND Soft Starter
300
D-RAND (1200 Siemens S7-
CR02 Compac 3 CHEMTROLS HEINRICHS SCHNEIDER KOHLER INGERSOLL RAND 2 1
NELSON SCM) 300
61
MANDELA
CTG 2 2
Siemens S7-
CR02 DELTA (1200 SCM) Compac 2 INGERSOLL RAND Soft Starter
200
Siemens S7- MICRO
62 NH 8 DEFENCE CR02 DELTA (1200 SCM)
200
Compac 6 EMERSON
MOTION
FISHER KOHLER INGERSOLL RAND Soft Starter 2 1 CTG 1 1

KIRLOSKAR (1200 Siemens S7- BRISTOL


CR05 Compac 2 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
63 I F C GAZIPUR I CTG 2 2
Siemens S7-
CR05 DELTA (1200 SCM) Compac 4 INGERSOLL RAND Soft Starter
200
GALILEO (1150 MICRO BRISTOL
CR04 SAIA Compac 2 EMERSON MICRO MOTION KOHLER INGERSOLL RAND 2 1
SCM) MOTION BABCOCK
METCALFE
64
HOUSE
CR04 DELTA (1200 SCM) SAIA Compac 2 INGERSOLL RAND CTG 3 2

Siemens S7-
CR04 DELTA (2400 SCM) Delta 3 VFD
300
GALILEO (1150
CR04 SAIA Compac 3 E&H KOHLER INGERSOLL RAND 2 1
SCM)
DHEERPUR I
CR04 KOHLER INGERSOLL RAND

CR04 ATLAS COPCO


65
MICRO
CTG 3 2
CR04 D-RAND (1200 Siemens S7- SAFE 3 EMERSON FISHER E&H 2 1
MOTION
SCM) 300
DHEERPUR II CR04 FTI 1
CR04 D-RAND (1200 Siemens S7- Compac 1
CR04 SCM) 300 TGT 1
MICRO
CR04 Compac 3 EMERSON FISHER MICRO MOTION KOHLER INGERSOLL RAND 2 1
D-RAND (1200 Siemens S7- MOTION
SCM) 300
66 S G T N PH I CR04 Compac 1 INGERSOLL RAND CTG 2 2

Siemens S7-
CR04 DELTA (1200 SCM) FTI 1 Soft Starter
200
GALILEO (1150 BRISTOL
CR03 SAIA Compac 4 CHEMTROLS HEINRICHS E&H KOHLER INGERSOLL RAND 2 1
SCM) BABCOCK
GHERGO (1200
CR03 GE Phanukh Compac 3 KOHLER INGERSOLL RAND
SCM)
67 JAIL ROAD CTG 3 2
BURCKHARDT Siemens S7-
CR03 FTI 8
(1200 SCM) 300

Page 1026 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
Siemens S7-
CR03 DELTA (1200 SCM) Soft Starter
200
D-RAND (1200 Siemens S7- MICRO
CR03 Delta 1 Emerson FISHER E&H KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION

JANAKPURI D CR03 D-RAND (1200 Siemens S7- Safe 1 INGERSOLL RAND


68
BLOCK SCM) 300 CTG 3 2
CR03 FTI 1
CR03 Siemens S7- Compac 1 Soft Starter
DELTA (1200 SCM)
CR03 200 Compac 2
BRISTOL
CR06 Delta 1 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
D-RAND (1200 Siemens S7- BABCOCK
SCM) 300
69 PEERAGARHI CR06 Safe 1 INGERSOLL RAND CTG 2 2

INTERMECH (2400 Siemens S7-


CR06 Compac 3 cp VFD
SCM) 1200
D-RAND (1200 Siemens S7- BRISTOL
CR07 Delta 1 CHEMTROLS HEINRICHS E&H KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
D-RAND (1200 Siemens S7-
70 ROHINI MEGA CR07 Compac 3 KOHLER INGERSOLL RAND CTG 3 1
SCM) 300
Siemens S7-
CR07 DELTA (1200 SCM) Compac 2 ATLAS COPCO Soft Starter
300
D-RAND (1200 Siemens S7- MICRO
CR03 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION

71 PASCHIM VIHAR CR03 Compac 6 INGERSOLL RAND CTG 2 2

Siemens S7-
CR03 DELTA (1200 SCM) Soft Starter
200
D-RAND (1200 Siemens S7- BRISTOL
CR08 Compac 6 CHEMTROLS HEINRICHS MICRO MOTION KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
72 DWARKA SEC IX CTG 2 1
KIRLOSKAR (1200 Siemens S7-
CR08 ELGI Soft Starter
SCM) 300
BRISTOL
CR05 Compac 1 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
BURCKHARDT Siemens S7- BABCOCK
(1200 SCM) 300
73 I F C GAZIPUR II CR05 FTI 3 INGERSOLL RAND CTG 2 1

Siemens S7-
CR05 DELTA (2400 SCM) Compac 2 BRAVO VFD
300
BRISTOL
CR08 Compac 4 CHEMTROLS HEINRICHS MICRO MOTION KOHLER 2 1
BABCOCK
Siemens S7-
CR08 DELTA (1200 SCM) Compac 2 INGERSOLL RAND Soft Starter
DWARKA SEC 300
74
XX
CTG 3 2
Siemens S7-
CR08 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
300

Page 1037 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BURCKHARDT Siemens S7-
CR08
(1200 SCM) 300
BURCKHARDT Siemens S7- BRISTOL
CR08 Compac 5 CHEMTROLS HEINRICHS E&H KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 BABCOCK
75 KAPASHERA CTG 2 2
Siemens S7-
CR08 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
300
MICRO BRISTOL
CR06 Compac 2 CHEMTROLS E&H ELGI 2 1
MOTION BABCOCK
PITAMPURA Siemens S7-
76
(NEW)
CR06 DELTA (1200 SCM) Compac 6 ATLAS COPCO Soft Starter CTG 2 2
200
KIRLOSKAR (1200 Siemens S7-
CR06 INGERSOLL RAND Soft Starter
SCM) 300
BRISTOL
DWARKA CR08 BURCKHARDT Siemens S7- Compac 2 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
77
SECTOR 23 (1200 SCM) 300
BABCOCK CTG 1 1
CR08 Compac 2
MICRO BRISTOL
CR04 Compac 2 EMERSON KOHLER INGERSOLL RAND 2 1
MOTION BABCOCK
78 NARELA DSIIDC CTG 1 1
Siemens S7-
CR04 DELTA (1200 SCM) Compac 1 INGERSOLL RAND
300
MICRO
CR03 SAFE 1 Emerson FISHER MICRO MOTION KOHLER INGERSOLL RAND Soft Starter 2 1
Siemens S7- MOTION
79 MAYAPURI
CR03
DELTA (1200 SCM)
200 Delta 1
CTG 1 1

CR03 FTI 3
Siemens S7- MICRO BRISTOL
CR05 DELTA (1200 SCM) Delta 1 EMERSON E&H KOHLER INGERSOLL RAND Soft Starter 2 1
300 MOTION BABCOCK
80 MAYUR VIHAR CTG 2 2
Siemens S7-
CR05 DELTA (1200 SCM) Compac 7 Soft Starter
200
BRISTOL
CR05 Delta 1 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
NAND NAGARI I BABCOCK
81
&2
CTG 2 2
Siemens S7-
CR05 DELTA (2400 SCM) Compac 5 VFD
300

CR05 SAFE 1 CHEMTROLS HEINRICHS SCHNEIDER E&H KOHLER INGERSOLL RAND Soft Starter 2 1
CBD KIRLOSKAR (1200 Siemens S7-
82
SHAHDARA CR05 SCM) 300 Delta 1
CTG 1 1

CR05 Compac 3
Siemens S7- MICRO
CR01 DELTA (1200 SCM) Compac 8 EMERSON FISHER MICRO MOTION KOHLER INGERSOLL RAND Soft Starter 2 1
200 MOTION
Siemens S7-
83 NAGLA MACHI CR01 DELTA (1200 SCM) KOHLER INGERSOLL RAND Soft Starter CTG 3 2
300
Siemens S7-
CR01 DELTA (1200 SCM)
300
Siemens S7- MICRO BRISTOL
CR05 DELTA (1200 SCM) Compac 5 EMERSON MICRO MOTION KOHLER INGERSOLL RAND Soft Starter 2 1
300 MOTION BABCOCK
84 SHASTRI PARK CTG 2 2

Page 1048 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
84 SHASTRI PARK CTG 2 2
Siemens S7-
CR05 DELTA (1200 SCM) Compac 2 INGERSOLL RAND
300
BURCKHARDT Siemens S7- SUCTION MICRO
SHAKURPUR CR06
(400 SCM) 300 METERING MOTION
E&H INGERSOLL RAND 2 1
85 CTG 1 1
DIESEL SHED CR06 MICRO MOTION

SAROJINI D-RAND (1200 Siemens S7- MICRO BRISTOL


CR02 Compac 4 EMERSON KOHLER INGERSOLL RAND 2 1
NAGAR - I SCM) 300 MOTION BABCOCK
SAROJINI BURCKHARDT Siemens S7-
86 CR02 Compac 3 INGERSOLL RAND 2 1 CTG 3 2
NAGAR - II (1200 SCM) 300
SAROJINI Siemens S7-
CR02 DELTA (250 SCM) Delta 1 INGERSOLL RAND Soft Starter 2 1
NAGAR - III 200
D-RAND (1200 Siemens S7- MICRO
CR03 Compac 3 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION
87 BRAR SQUARE CTG 2 2
D-RAND (1200 Siemens S7-
CR03 Compac 2 INGERSOLL RAND
SCM) 300
D-RAND (1200 Siemens S7- BRISTOL
CR03 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
88 PUNJABI BAGH CTG 2 2
Siemens S7-
CR03 DELTA (1200 SCM) Compac 6 INGERSOLL RAND Soft Starter
300
BURCKHARDT Siemens S7-
CR04 Compac 4 CHEMTROLS HEINRICHS SCHNEIDER KOHLER ELGI 2 1
(1200 SCM) 300
89 S G T N PH II CTG 2 2
KIRLOSKAR (1200 Siemens S7-
CR04 Compac 1 INGERSOLL RAND Soft Starter
SCM) 300
D-RAND (1200 Siemens S7-
CR06 Compac 8 CHEMTROLS E&H FISHER KOHLER INGERSOLL RAND 2 1
SCM) 300
90 PITAMPURA CTG 2 2
Siemens S7-
CR06 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
200
SUCTION MICRO
CR06 Compac 4 KOHLER cp 2 1
METERING MOTION
CR06 KOHLER
91 SHAKURPUR CTG 1 1
CR06
INTERMECH (2400 Siemens S7-
CR06 VFD
SCM) 1200
MICRO
CR04 Compac 3 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
D-RAND (1200 Siemens S7- MOTION
CHHATRASAL SCM) 300
92
STADIUM
CR04 Compac 1 INGERSOLL RAND CTG 2 2

KIRLOSKAR (1200 Siemens S7-


CR04 Compac 1 Soft Starter
SCM) 300
D-RAND (1200 Siemens S7- MICRO
CR06 SAFE 2 EMERSON FISHER INGERSOLL RAND 2 1
SCM) 300 MOTION
INTERMECH (2400 Siemens S7-
93 MANGOLPURI CR06 Delta 1 INGERSOLL RAND VFD CTG 2 2
SCM) 1200

Page 1059 ofof29142


P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
CR06 FTI 1 INGERSOLL RAND

MICRO
CR06 Delta 1 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
D-RAND (1200 Siemens S7- MOTION
SCM) 300
94 ROHTAK ROAD CR06 SAFE 1 INGERSOLL RAND CTG 2 2

CR06 KIRLOSKAR (1200 Siemens S7- Compac 3 ATLAS COPCO Soft Starter
CR06 SCM) 300 FTI 1
KIRLOSKAR (1200 Siemens S7- BRISTOL
CR03 Delta 1 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
CR03 SAFE 1 ATLAS COPCO
95 JANAKPURI D C CR03 Compac 2 CTG 2 2
CR03 FTI 1
Siemens S7-
CR03 DELTA (1200 SCM) Compac 1 Soft Starter
200
KIRLOSKAR (1200 Siemens S7- BRISTOL
CR02 Compac 6 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK

96 LADO SARAI CR02 INGERSOLL RAND CTG 2 2

Siemens S7-
CR02 DELTA (1200 SCM) Soft Starter
300
BURCKHARDT Siemens S7- MICRO
CR02 Delta 4 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
PUSHPA (1200 SCM) 300 MOTION
97 CTG 2 2
BHAWAN Siemens S7-
CR02 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
300
D-RAND (1200 Siemens S7- BRISTOL
CR05 Delta 4 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
DILSHAD BURCKHARDT Siemens S7-
98 CR05 Compac 3 INGERSOLL RAND CTG 3 2
GARDEN (1200 SCM) 300
Siemens S7-
CR05 DELTA (1200 SCM) Compac 3 INGERSOLL RAND Soft Starter
200
BRISTOL
CR05 Compac 3 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
NH-24 POCKET A BABCOCK
99 CTG 1 1
IFC-III GAZIPUR Siemens S7-
CR05 DELTA (1200 SCM) Soft Starter
200
KIRLOSKAR (1200 Siemens S7- BRISTOL
CR07 Compac 4 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SCM) 300 BABCOCK
100 ROHINI SEC X CTG 2 1
KIRLOSKAR (2400 Siemens S7-
CR07 Compac 2 ELGI VFD
SCM) 300
Siemens S7- MICRO BRISTOL
CR07 DELTA (1200 SCM) Compac 2 EMERSON KOHLER INGERSOLL RAND 2 1
300 MOTION BABCOCK
101 ROHINI 21 CTG 2 2
Siemens S7-
CR07 DELTA (1200 SCM) Compac 2 INGERSOLL RAND Soft Starter
300

Page 106 of29142


10 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BRISTOL
102 ROHINI 29 CR07 DELTA (1200 SCM) siemens s7-300 Compac 2 CHEMTROLS HEINRICHS KOHLER Soft Starter 2 1 CTG 1 2
BABCOCK
MICRO BRISTOL
CR07 Compac 4 EMERSON KOHLER INGERSOLL RAND 2 1
Siemens S7- MOTION BABCOCK
DELTA (1200 SCM)
300
103 ROHINI 25 CR07 Compac 1 INGERSOLL RAND CTG 2 2

Siemens S7-
CR07 DELTA (1200 SCM) Compac 1 Soft Starter
300
CR07 KIRLOSKAR (1200 Siemens S7- Compac 1 CHEMTROLS HEINRICHS FISHER ELGI Soft Starter 2 1
104 ROHINI 25 - II CTG 2 2
CR07 SCM) 300 Compac 4
D-RAND (1200 Siemens S7- MICRO BRISTOL
CR07 Compac 3 EMERSON KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION BABCOCK
ROHINI -22
105 (NEAR AGARSEN CR07 Compac 1 INGERSOLL RAND CTG 2 1
COLLEGE)
Siemens S7-
CR07 DELTA (1200 SCM) Compac 1 Soft Starter
300
MICRO BRISTOL
ROHINI -22 CR07 Compac 3 EMERSON KOHLER INGERSOLL RAND 2 1
MOTION BABCOCK
106 (NEAR MGF CTG 2 1
Siemens S7-
MALL) CR07 DELTA (1200 SCM) Compac 2 INGERSOLL RAND Soft Starter
300
MICRO
CR02 Delta 3 EMERSON FISHER KOHLER INGERSOLL RAND Soft Starter 2 1
Siemens S7- MOTION
107 SHANTI PATH DELTA (1200 SCM) CTG 1 1
CR02 300 Compac 3
CR02
Siemens S7- MICRO
CR01 DELTA (2400 SCM) Compac 15 EMERSON FISHER KOHLER SCHULZ(BRAVO) VFD 2 1
300 MOTION
BURCKHARDT Siemens S7-
CR01 Compac 2 INGERSOLL RAND
(1200 SCM) 300
108 C G O COMPLEX CTG 3 2
Siemens S7-
CR01 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
200
BURCKHARDT Siemens S7-
CR01
(1200 SCM) 300
KIRLOSKAR (1200 Siemens S7- MICRO
109 JAHANGIRPURI CR04 Compac 6 EMERSON FISHER KOHLER ELGI Soft Starter 2 1 CTG 1 1
SCM) 300 MOTION
Siemens S7- MICRO
CR01 DELTA (1200 SCM) Compac 6 EMERSON FISHER KOHLER INGERSOLL RAND Soft Starter 2 1
200 MOTION
110 JASOLA CTG 2 2
BURCKHARDT Siemens S7-
CR01 INGERSOLL RAND
(1200 SCM) 300
BRISTOL
CR01 Delta 2 CHEMTROLS HEINRICHS KOHLER 2 1
BABCOCK
111 NEHRU PLACE CTG 1 1
Siemens S7-
CR01 DELTA (1200 SCM) Compac 3 INGERSOLL RAND Soft Starter
200
Siemens S7- BRISTOL
OKHLA CR02 DELTA (1200 SCM) Delta 4 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND Soft Starter 2 1
300 BABCOCK
112 INDUSTRIAL CTG 2 2

Page 107 of29142


11 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
112 INDUSTRIAL CTG 2 2
Siemens S7-
AREA PH I CR02 DELTA (1200 SCM) INGERSOLL RAND Soft Starter
200
MICRO
CR05 Safe 1 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
GALILEO (1150 MOTION
113 LONI ROAD SAIA CTG 1 2
CR05 SCM) Delta 1
CR05 Compac 2
KIRLOSKAR (570 Siemens S7- SUCTION MICRO
CR01 Compac 4 KHOSLA 2 1
SCM) 300 METERING MOTION
114 UDYAN MARG CTG 2 2
Siemens S7-
CR01 DELTA (730 SCM) INGERSOLL RAND Soft Starter
300
BURCKHARDT Siemens S7- BRISTOL
CR08 Compac 1 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
(600 SCM) 300 BABCOCK
115 IGI AIRPORT CTG 2 2
BURCKHARDT Siemens S7-
CR08 Compac 2 INGERSOLL RAND
(600 SCM) 300
MICRO BRISTOL
CR02 Compac 5 EMERSON KOHLER 2 1
MOTION BABCOCK
VASANT KUNJ Siemens S7-
116 CR02 DELTA (1200 SCM) INGERSOLL RAND CTG 2 2
(KISHAN GARH) 300
KIRLOSKAR (2400 Siemens S7-
CR02 ELGI VFD
SCM) 300
MICRO BRISTOL
CR07 Compac 4 EMERSON KOHLER INGERSOLL RAND 2 1
Siemens S7- MOTION BABCOCK
117 BAWANA - 4 DELTA (1200 SCM) CTG 1 2
300
CR07 Compac 2 INGERSOLL RAND

Siemens S7- BRISTOL


CR05 DELTA (1200 SCM)
300
Compac 6 CHEMTROLS HEINRICHS
BABCOCK
KOHLER ELGI 2 1
118 VIVEK VIHAR CTG 2 2
KIRLOSKAR (2400 Siemens S7-
CR05 INGERSOLL RAND VFD
SCM) 300
BRISTOL
CR07 Siemens S7- Compac 2 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
119 BAWANA -5 DELTA (1200 SCM) BABCOCK CTG 1 2
300
CR07 Compac 3
MICRO BRISTOL
CR07 Compac 3 EMERSON KOHLER ELGI 2 1
MOTION BABCOCK
120 ROHINI SEC 30 CTG 1 2
KIRLOSKAR (1200 Siemens S7-
CR07 Compac 2 INGERSOLL RAND Soft Starter
SCM) 300
Siemens S7- SUCTION MICRO
121 BAKHARWALA - I CR03 DELTA (1200 SCM) Compac 1 2 1 CTG 1 2
300 METERING MOTION
LOKNAYAKPURA CR03 KIRLOSKAR (1200 Siemens S7- Compac 1 CHEMTROLS HEINRICHS FISHER ELGI Soft Starter 2 1
122 CTG 1 2
M CR03 SCM) 300 Compac 1
MICRO BRISTOL
CR08 Compac 2 Emerson KOHLER INGERSOLL RAND 2 1
DWARKA Siemens S7- MOTION BABCOCK
123 DELTA (1200 SCM) CTG 1 2
SECTOR 12 300
CR08 Compac 2 INGERSOLL RAND

Page 108 of29142


12 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
CR04 Siemens S7- Compac 1 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1
124 BHORGARH-I DELTA (1200 SCM)
300
CTG 1 2
CR04 Compac 1
MICRO BRISTOL
CR06 Compac 2 EMERSON KOHLER INGERSOLL RAND 2 1
Siemens S7- MOTION BABCOCK
125 PVC MARKET DELTA (1200 SCM) CTG 1 2
300
CR06 Compac 2 INGERSOLL RAND

Siemens S7-
CR08 DELTA (1200 SCM) Compac 3 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1
DWARKA SEC 300
126 CTG 2 2
XIV KIRLOSKAR (1200 Siemens S7-
CR08 ELGI Soft Starter
SCM) 300
Siemens S7-
127 NARELA SEC X CR04 DELTA (1200 SCM) Compac 2 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1 CTG 1 2
300
DWARKA SEC 23 Siemens S7-
128 CR08 DELTA (1200 SCM) Compac 3 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1 CTG 1 2
PH II 300
BURCKHARDT Siemens S7- BRISTOL
CR08 CHEMTROLS HEINRICHS 2 1
DWARKA (1200 SCM) 300 BABCOCK
129 CTG 2 2
SECTOR 17 KIRLOSKAR (1200 Siemens S7-
CR08 Soft Starter
SCM) 300
D-RAND (1200 Siemens S7- MICRO BRISTOL
CR04 Compac 3 CHEMTROLS KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION BABCOCK
130 NARELA CTG 1 2
CR04 Compac 2 INGERSOLL RAND

KIRLOSKAR (2400
CR04 siemens s7-300 Compac 5 CHEMTROLS HEINRICHS SCHNEIDER KOHLER ELGI VFD 2 1
131 NANAK PYAU SCM) CTG 1 2
CR04 FTI 1
CR02 Compac 6 CHEMTROLS HEINRICHS SCHNEIDER ATLAS COPCO 2 1
132 SAN MARTIN INTERMECH (2400 Siemens S7- CTG 1 2
CR02 VFD
SCM) 1200
D-RAND (1200 Siemens S7- MICRO
CR07 Safe 1 EMERSON FISHER KOHLER INGERSOLL RAND 2 1
SCM) 300 MOTION
133 ROHINI SEC XIX CR07 compac 4 ELGI CTG 2 1
KIRLOSKAR (1200 Siemens S7-
CR07 FTI 1 INGERSOLL RAND Soft Starter
SCM) 300
Siemens S7- BRISTOL
134 ROHINI SEC 28 CR07 DELTA (1200 SCM) Compac 2 CHEMTROLS HEINRICHS INGERSOLL RAND Soft Starter 2 1 CTG 1 2
300 BABCOCK
Siemens S7- SUCTION MICRO
135 ANAND PARBAT CR06 DELTA (730 SCM) Delta 2 KOHLER INGERSOLL RAND Soft Starter 2 1 CTG 1 2
300 METERING MOTION
Siemens S7-
136 DWARKA SEC V CR08 DELTA (1200 SCM) Compac 2 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1 CTG 1 2
300
Siemens S7-
137 ROHINI SEC 27 CR07 DELTA (1200 SCM) Compac 2 CHEMTROLS HEINRICHS FISHER Soft Starter 2 1 CTG 1 2
300
MICRO
CR05 Siemens S7- Delta 2 EMERSON FISHER E&H KOHLER INGERSOLL RAND Soft Starter 2 1
138 GEETA COLONY DELTA (1200 SCM) MOTION CTG 1 2
300

Page 109 of29142


13 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
300
CR05 Compac 2
Siemens S7- BRISTOL
CR02 DELTA (1200 SCM) Compac 4 CHEMTROLS HEINRICHS INGERSOLL RAND Soft Starter 2 1
139 SURAJ KUND 300 BABCOCK CTG 1 2
CR02
DWARKA SEC 16 Siemens S7-
140 CR08 DELTA (1200 SCM) Compac 2 CHEMTROLS HEINRICHS FISHER Soft Starter 2 1 CTG 1 2
B 300
SUCTION MICRO
CR05 Siemens S7- Compac 2 Soft Starter 2 1
141 CHILLA- 1 DELTA (1200 SCM) METERING MOTION CTG 1 3
300
CR05 TGT 1
BRISTOL
SAWADA CR07 Siemens S7- Compac 1 CHEMTROLS HEINRICHS Soft Starter 2 1
142 DELTA (1200 SCM) BABCOCK CTG 1 2
GHERWARA 300
CR07 Compac 1
SUCTION
CR05 Siemens S7- TGT 2 E&H Soft Starter 2 1
143 CHILLA- 2 DELTA (1200 SCM) METERING CTG 1 3
200
CR05 Compac 1
Siemens S7- MICRO
144 SEELAMPUR CR05 DELTA (1200 SCM) Compac 2 EMERSON FISHER Soft Starter 2 1 CTG 1 2
300 MOTION
Siemens S7- SUCTION MICRO
145 OKHLA DSIIDC CR02 DELTA (1200 SCM) Compac 3 Soft Starter 2 1 CTG 1 2
300 METERING MOTION
DILSHAD
146 GARDEN DTC CR05 HYBRID Compac 1 2 1 NR
(HYBRID)
DWARKA SEC 8
147 CR08 HYBRID Compac 1 2 1 NR
(HYBRID)
NARELA DTC
148 CR04 HYBRID Compac 1 2 1 NR
(HYBRID)
LADO SARAI
149 CR02 HYBRID Compac 3 2 1 NR
DTC HYBRID
SEEMAPURI DTC
150 CR05 HYBRID Compac 1 2 1 NR
HYBRID
KANJHAWALA
151 CR07 HYBRID Compac 1 2 1 NR
DEPOT HYBRID
ROHINI IV
152 CR07 HYBRID TGT 1 2 1 NR
DEPOT HYBRID
MICRO
CR08 Siemens S7- Safe 1 EMERSON FISHER VFD 2 1
153 ARAWALI S S DELTA (600 SCM) MOTION CTG 1 3
200
CR08 Compac 1
Siemens S7- MICRO
154 SYALL S S CR03 DELTA (600 SCM) Compac 2 EMERSON FISHER Soft Starter 2 1 CTG 1 3
200 MOTION

CR04 Delta 1 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1


155 S S SIDHU DELTA (600 SCM) SAIA CTG 1 3
CR04 Compac 1
DEEPAK Siemens S7- SUCTION MICRO
156 CR05 DELTA (1200 SCM) Compac 3 VFD 2 1 CTG 1 3
AUTOMOBILES 300 METERING MOTION

Page 110 of29142


14 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
SUCTION MICRO
SAKSHAM CR03 D-RAND (400 Siemens S7- Safe 1 INGERSOLL RAND 2 1
157 METERING MOTION CTG 1 3
MOTORS SCM) 300
CR03 Compac 1
KIRLOSKAR (1200 Siemens S7-
158 MUKUL DIESELS CR05 Compac 4 CHEMTROLS HEINRICHS SCHNEIDER ELGI VFD 2 1 CTG 1 3
SCM) 300
SUCTION MICRO
CR03 Compac 2 2 1
METERING MOTION
159 VAIBHAV S S CTG 1 3
Siemens S7-
CR03 DELTA (600 SCM) VFD
200
Siemens S7- SUCTION MICRO
BUDH SINGH CR02 DELTA (600 SCM) Compac 2 Soft Starter 2 1
160 200 METERING MOTION CTG 1 3
GULAB SINGH
CR02
BURCKHARDT Siemens S7- SUCTION MICRO
161 AUTO CARE S S CR03 Compac 2 INGERSOLL RAND 2 1 CTG 1 3
(600 SCM) 300 METERING MOTION
NEMICHAND Siemens S7- MICRO
162 CR04 DELTA (600 SCM) Compac 2 EMERSON FISHER VFD 2 1 CTG 1 3
TARACHAND 200 MOTION
HARICHAND & GHERGO (400
163 CR05 GE Phanukh Compac 1 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1 CTG 1 3
CO SCM)
Siemens S7-
164 PAUL S/S CR04 DELTA (600 SCM) Compac 2 CHEMTROLS HEINRICHS SCHNEIDER VFD 2 1 CTG 1 3
200
JAIPUR GOLDEN D-RAND (400 Siemens S7- SUCTION MICRO
165 CR08 Compac 1 INGERSOLL RAND 2 1 CTG 1 3
SS SCM) 300 METERING MOTION
Siemens S7- MICRO
166 GYMKHANA S S CR02 DELTA (600 SCM) Compac 2 EMERSON FISHER Soft Starter 2 1 CTG 1 3
200 MOTION
MOOLCHAND Siemens S7- SUCTION MICRO
167 CR04 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
SHRIPAL JAIN 200 METERING MOTION
Siemens S7- SUCTION MICRO
168 M L SETHI CR07 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
SAI FILLING
Siemens S7- SUCTION MICRO
169 STATION, CR04 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
BURARI
JAI SHRI Siemens S7- SUCTION MICRO
170 CR04 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
GANESH 200 METERING MOTION
Siemens S7- SUCTION MICRO
171 MANGAL S S CR08 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
172 GREEN HEART CR07 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
GARG ROAD Siemens S7- SUCTION MICRO
173 CR06 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
LINE 200 METERING MOTION
Siemens S7- SUCTION MICRO
174 G S BHASIN CR01 DELTA (600 SCM) Compac 1 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
175 JAGLAN FS CR08 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION

Page 111 of29142


15 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BHAGWATI F S
Siemens S7- SUCTION MICRO
176 GHEWARA CR06 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
MORH
JAI SHRI Siemens S7- SUCTION MICRO
177 CR08 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
KRISHNA 200 METERING MOTION
Siemens S7- SUCTION MICRO
178 RAJENDRA S S CR04 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
179 SHANTI PETRO CR08 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
NEW HARYANA Siemens S7- SUCTION MICRO
180 CR06 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
SS 200 METERING MOTION
SHOKEEN Siemens S7- SUCTION MICRO
181 CR08 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
PETRO 200 METERING MOTION
Siemens S7- SUCTION MICRO
182 JAI MATA DI CR07 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
TRIYAMJEET Siemens S7- SUCTION MICRO
183 CR07 DELTA (600 SCM) Compac 1 VFD 2 1 CTG 1 3
ENERGIES 200 METERING MOTION
Siemens S7- SUCTION MICRO
184 ANIL F S CR03 DELTA (600 SCM) Compac 1 VFD 2 1 CTG 1 3
200 METERING MOTION
AJANTA FILL N Siemens S7- SUCTION MICRO
185 CR04 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
FLY 300 METERING MOTION
VIJ AUTO Siemens S7- SUCTION MICRO
186 CR05 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
CENTRE 200 METERING MOTION
SUCTION MICRO
CR06 Siemens S7- Compac 1 Soft Starter 2 1
187 GANPATI DELTA (600 SCM) METERING MOTION CTG 1 3
200
CR06 TGT 1
Siemens S7- SUCTION MICRO
188 BAWANA BP CR07 DELTA (1200 SCM) Compac 1 VFD 2 1 CTG 1 3
200 METERING MOTION
RAIZADA Siemens S7- SUCTION MICRO
189 CR01 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
MOTORS 200 METERING MOTION
Siemens S7- SUCTION MICRO
190 KRISHNA F S CR01 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION

191 KANWAR & CO. CR04 HYBRID Compac 2 2 1 NR

SAHAS FILLING
192 CR03 HYBRID Compac 2 2 1 NR
STATION

193 VAIBHAV CR06 HYBRID Compac 2 2 1 NR


PUSHPANJALI S
194 CR02 HYBRID Compac 1 2 1 NR
S
SUCTION
195 DAWAR CR07 DAUGHTER Compac 1 MICRO MOTION 2 1 CTG 1 3
METERING
SUCTION
CR06 Siemens S7- E&H INGERSOLL RAND STAR/DELTA 2 1
196 VEEJAY S S ICL BOOSTER METERING CTG 1 3
200

Page 112 of29142


16 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
200
CR06 Compac 2
SUCTION MICRO
CR02 Siemens S7- Compac 2 Soft Starter 2 1
197 AUTO GRIT S S DELTA (600 SCM) METERING MOTION CTG 1 3
200
CR02
SUCTION
CR04 Delta 1 E&H INGERSOLL RAND STAR/DELTA 2 1
198 R S BHOLARAM ICL BOOSTER METERING CTG 1 3
CR04 Compac 1
SUCTION
CR06 Siemens S7- Safe 1 E&H INGERSOLL RAND STAR/DELTA 2 1
199 BAGGA LINK ICL BOOSTER METERING CTG 1 3
200
CR06 Compac 1
Siemens S7- SUCTION
200 MODERN S S CR01 ICL BOOSTER Compac 1 MICRO MOTION INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
SUCTION
201 JFJ MOTORS CR02 Compac 1 E&H 2 1 CTG 1 3
METERING
TRIYAMJEET SUCTION
202 CR07 ICL BOOSTER Compac 1 MICRO MOTION VFD 2 1 CTG 1 3
ADHOC METERING
SUCTION MICRO
CR08 Siemens S7- Compac 3 VFD 2 1
203 SETHI S S DELTA (600 SCM) METERING MOTION CTG 1 3
200
CR08 Compac 3
Siemens S7- SUCTION MICRO
204 SUPER AUTO CR01 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- MICRO
205 IPSS CR01 DELTA (600 SCM) Compac 2 EMERSON FISHER VFD 2 1 CTG 1 3
200 MOTION
Siemens S7- MICRO
206 SPEEDWAYS CR03 DELTA (600 SCM) Compac 2 Emerson FISHER VFD 2 1 CTG 1 3
200 MOTION
R K AMAR Siemens S7- MICRO
207 CR07 DELTA (600 SCM) Compac 2 EMERSON FISHER Soft Starter 2 1 CTG 1 3
SHAHEED 200 MOTION
Siemens S7- MICRO
208 KAPOOR AUTO CR05 DELTA (600 SCM) Delta 1 EMERSON FISHER VFD 2 1 CTG 1 3
200 MOTION

209 JINDAL S S CR01 DELTA (600 SCM) SAIA Compac 1 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1 CTG 1 3

BURCKHARDT Siemens S7-


210 FORTUNE CR07 Compac 3 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1 CTG 1 3
(600 SCM) 300
BAKSHI BURCKHARDT Siemens S7- SUCTION MICRO
211 CR07 Compac 2 INGERSOLL RAND 2 1 CTG 1 3
ENTERPRISES (600 SCM) 300 METERING MOTION
Siemens S7- SUCTION MICRO
212 GURU S S CR08 DELTA (600 SCM) Compac 2 INGERSOLL RAND Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
213 PRIYANKA CR07 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
214 BG MOTORS CR04 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
215 SETHI AUTO FS CR06 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION

Page 113 of29142


17 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
Siemens S7- SUCTION MICRO
216 GAY S S CR04 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
217 YASHOMAL CR06 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
TYAGI Siemens S7- SUCTION MICRO
218 CR06 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
PETROLEUM 200 METERING MOTION

IOCL COCO Siemens S7- MICRO


219 CR08 DELTA (600 SCM) Compac 1 EMERSON FISHER VFD 2 1 CTG 1 3
DWARKA SEC 19 200 MOTION

Siemens S7- SUCTION MICRO


220 PARAS S S CR08 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
221 DELHI DIESEL CR05 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
222 PRAGATI S S CR01 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION

MANSA FILLING Siemens S7- SUCTION MICRO


223 CR05 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
STATION 200 METERING MOTION

CITY SERVICE Siemens S7- SUCTION MICRO


224 CR06 DELTA (600 SCM) Compac 1 Soft Starter 2 1 CTG 1 3
CENTER 200 METERING MOTION
Siemens S7- SUCTION MICRO
225 RISHAL S S CR04 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
226 MADHAV FUELS CR08 DELTA (600 SCM) Compac 1 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
227 DADA MALDEV CR07 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
228 SAI RAM CR07 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
229 SABHARWAL CR02 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
230 MANGAL PETRO CR06 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
231 SARITA S S CR01 DELTA (1200 SCM) Compac 1 VFD 2 1 CTG 1 3
300 METERING MOTION
Siemens S7- SUCTION MICRO
232 RAMA ASHRAM CR06 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
300 METERING MOTION
Siemens S7- SUCTION MICRO
233 AUTO FUEL CR06 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
300 METERING MOTION
SUCTION MICRO
CR05 Siemens S7- Compac 1 VFD 2 1
234 MAHENDRA S S DELTA (1200 SCM) METERING MOTION CTG 1 3
300
CR05 TGT 1
RAMESH SUCTION MICRO
CR03 Siemens S7- Compac 1 Soft Starter 2 1
235 SERVICE DELTA (1200 SCM)
200
METERING MOTION CTG 1 3
STATION CR03 TGT 1

Page 114 of29142


18 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
Siemens S7- SUCTION MICRO
236 ATC CR06 DELTA (1200 SCM) Compac 1 VFD 2 1 CTG 1 3
300 METERING MOTION
SUCTION MICRO
VAISH FILLING CR08 Siemens S7- Compac 1 VFD 2 1
237 DELTA (1200 SCM) METERING MOTION CTG 1 3
STATION 200
CR08 TGT 1

NAMAN FILLING Siemens S7- SUCTION MICRO


238 CR07 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
STATION 300 METERING MOTION

KIRLOSKAR (1200 Siemens S7- SUCTION MICRO


239 POOJA S/S CR07 Compac 2 ELGI VFD 2 1 CTG 1 3
SCM) 300 METERING MOTION
Siemens S7- SUCTION MICRO
240 BHARAT S S CR04 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
300 METERING MOTION
KISHORE & KIRLOSKAR (1200 Siemens S7- SUCTION MICRO
241 CR02 Compac 1 INGERSOLL RAND VFD 2 1 CTG 1 3
COMPANY SCM) 300 METERING MOTION
Siemens S7- SUCTION MICRO
242 LOTUS ADHOC CR02 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
300 METERING MOTION
SHREE HARI Siemens S7- SUCTION MICRO
243 CR07 DELTA (1200 SCM) Compac 1 VFD 2 1 CTG 1 3
KRISHNA 300 METERING MOTION
KIRLOSKAR (1200 Siemens S7- SUCTION MICRO
244 SULOCHANA SS CR06 Compac 2 VFD 2 1 CTG 1 3
SCM) 300 METERING MOTION
KIRLOSKAR (1200 Siemens S7- SUCTION MICRO
245 SHREE NATH CR07 Compac 1 ELGI VFD 2 1 CTG 1 3
SCM) 300 METERING MOTION
Siemens S7- SUCTION MICRO
246 R.N PETRO CR07 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
KIRLOSKAR (1200 Siemens S7- SUCTION MICRO
247 DRIVEWELL CR05 Compac 2 ELGI VFD 2 1 CTG 1 3
SCM) 300 METERING MOTION
KIRLOSKAR (1200 Siemens S7- SUCTION MICRO
248 ROHIT S S CR04 Compac 1 VFD 2 1 CTG 1 3
SCM) 300 METERING MOTION
Siemens S7- SUCTION MICRO
249 NEW AMRIT CR06 DELTA (1200 SCM) Compac 1 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
250 CHANAKYAPURI CR03 DELTA (600 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
QUEEN'S ROAD Siemens S7- SUCTION MICRO
251 CR02 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
SS 300 METERING MOTION
Siemens S7- SUCTION MICRO
252 SATBIR CR08 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
200 METERING MOTION
SHAURYA Siemens S7- SUCTION MICRO
253 CR07 DELTA (600 SCM) Compac 1 Soft Starter 2 1 CTG 1 3
BHUSHAN 200 METERING MOTION
RAJASTHAN Siemens S7- SUCTION MICRO
254 CR08 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
RAJPATH 200 METERING MOTION
Siemens S7- SUCTION MICRO
255 GANGA PETRO CR08 DELTA (600 SCM) Compac 2 BRAVO Soft Starter 2 1 CTG 1 3
200 METERING MOTION
CAPT. AMIT Siemens S7- SUCTION MICRO
256 CR03 DELTA (1200 SCM) Compac 1 VFD 2 1 CTG 1 3
VERMA 300 METERING MOTION

Page 115 of29142


19 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
Siemens S7- SUCTION MICRO
257 GLOBAL PETRO CR02 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
300 METERING MOTION
Siemens S7- SUCTION MICRO
258 CITY FUELS CR03 DELTA (600 SCM) Compac 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
259 RAM MURTI S S CR02 DELTA (1200 SCM) Compac 2 VFD 2 1 CTG 1 3
300 METERING MOTION
260 UNITED FUEL CR06 HYBRID Compac 2 2 1 NR
261 ASHISH S S CR05 HYBRID Compac 2 2 1 NR
SUCTION
262 MILLENIUM F S CR08 DAUGHTER Compac 2 MICRO MOTION 2 1 CTG 1 3
METERING
263 SENANI F S CR07 HYBRID Compac 1 2 1 NR
264 TYAGI ADHOC CR06 HYBRID COMPAC 2 2 1 NR
265 SANJEEV SS CR02 HYBRID Compac 1 2 1 NR
SUCTION
266 ARORA S S CR06 ICL BOOSTER DELTA 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
METERING
Siemens S7- SUCTION
267 AJIT MOTORS CR03 ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
268 SHANKAR F S CR01 DELTA BOOSTER COMPAC 2 MICRO MOTION Soft Starter 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
269 SHREE SAI CR07 ICL BOOSTER COMPAC 1 MICRO MOTION STAR/DELTA 2 1 CTG 1 3
200 METERING
siemens S7- SUCTION
270 KAILASH CR01 DELTA BOOSTER COMPAC 1 E&H Soft Starter 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
271 LOTUS AUTO CR02 DELTA BOOSTER Compac 1 MICRO MOTION Soft Starter 2 1 CTG 1 3
200 METERING
CHAUDHARY
SUCTION
272 FILLING CR04 DAUGHTER Compac 1 MICRO MOTION 2 1 CTG 1 3
METERING
STATION
SUCTION
273 MOTORADES CR06 DAUGHTER COMPAC 2 MICRO MOTION 2 1 CTG 1 3
METERING
Siemens S7- MICRO
274 ANAND S S CR08 DELTA (600 SCM) COMPAC 2 EMERSON FISHER VFD 2 1 CTG 1 3
200 MOTION
MICRO
275 EVERGREEN S S CR02 COMPAC 2 EMERSON FISHER 2 1 CTG 1 3
MOTION
D-RAND (400 Siemens S7- SUCTION MICRO
276 WALIA S S CR01 DELTA 1 INGERSOLL RAND 2 1 CTG 1 3
SCM) 300 METERING MOTION
D-RAND (400 Siemens S7-
277 GOPI S S CR05 DELTA 1 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1 CTG 1 3
SCM) 300
Siemens S7- MICRO
278 HEMKUNT S S CR01 DELTA (600 SCM) COMPAC 2 EMERSON FISHER VFD 2 1 CTG 1 3
200 MOTION
SHYAM BURCKHARDT Siemens S7- SUCTION MICRO
279 CR05 COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
PRAKASH S S (400 SCM) 300 METERING MOTION
BHARAT HP Siemens S7- SUCTION MICRO
280 CR08 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
CENTER 200 METERING MOTION

Page 116 of29142


20 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
Siemens S7- SUCTION MICRO
281 LAXMI SUPER CR02 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
282 OM SS CR04 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
283 KUNDAN LAL F S CR05 DELTA (600 SCM) COMPAC 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
BATRA OIL Siemens S7- SUCTION MICRO
284 CR04 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
COMPANY 200 METERING MOTION
Siemens S7- SUCTION MICRO
285 KAMLESH HP CR08 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
ESS JAY FUEL Siemens S7- SUCTION MICRO
286 CR08 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
DWARKA 200 METERING MOTION
Siemens S7- SUCTION MICRO
287 BEDI MOTORS CR02 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
DELHI PUNJAB
Siemens S7- SUCTION MICRO
288 FILLING CR04 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
STATION
AISHIRAM Siemens S7- SUCTION MICRO
289 CR05 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
BATRA S S 200 METERING MOTION
AISHIRAM
Siemens S7- SUCTION MICRO
290 BATRA, VIVEK CR05 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
VIHAR
BHAGWATI
Siemens S7- SUCTION MICRO
291 SERVICE CR04 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
STATION
Siemens S7- MICRO
292 NEW ANGRA SS CR02 DELTA (600 SCM) COMPAC 1 EMERSON FISHER VFD 2 1 CTG 1 3
200 MOTION
Siemens S7- SUCTION MICRO
293 BALWAN SS CR07 DELTA (600 SCM) COMPAC 1 VFD 2 1 CTG 1 3
200 METERING MOTION
ROHTAK OIL & Siemens S7- SUCTION MICRO
294 CR06 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
CO 200 METERING MOTION
SHAHEED
ANUSUYA Siemens S7- SUCTION MICRO
295 CR03 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
FILLING 200 METERING MOTION
STATION
Siemens S7- SUCTION MICRO
296 PANCHSHILA SS CR02 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
297 SHREYANSH S S CR06 DELTA (600 SCM) COMPAC 1 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
CR06 DELTA (600 SCM) COMPAC 2 VFD 2 1 3
298 TIKRI S S 200 METERING MOTION CTG 1
CR06
Siemens S7- SUCTION MICRO 3
299 DRIVE & FILL CR03 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1
200 METERING MOTION

Page 117 of29142


21 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BALAJI SERVICE Siemens S7- SUCTION MICRO
300 CR04 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
STATION 200 METERING MOTION

BATRA CAR Siemens S7- SUCTION MICRO


301 CR01 DELTA (600 SCM) COMPAC 1 Soft Starter 2 1 CTG 1 3
CARE 200 METERING MOTION
AUTOMOTIVE S Siemens S7- SUCTION MICRO
302 CR01 DELTA (600 SCM) COMPAC 2 Soft Starter 2 1 CTG 1 3
S 200 METERING MOTION
Siemens S7- SUCTION MICRO
303 PURAN SS CR03 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
PANDIT HP Siemens S7- SUCTION MICRO
304 CR08 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
STATION 200 METERING MOTION
Siemens S7- SUCTION MICRO
305 RAJEEV S S CR01 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
UGGARSAIN & CR05 DELTA (600 SCM) COMPAC 1 VFD 2 1 3
306 200 METERING MOTION CTG 1
SONS
CR05 DELTA 1
Siemens S7- SUCTION MICRO 3
KRISHNA HP CR03 DELTA (600 SCM) COMPAC 2 Soft Starter 2 1
307 200 METERING MOTION CTG 1
RANAULLAH
CR03
BATRA Siemens S7- SUCTION MICRO 3
308 CR01 DELTA (600 SCM) COMPAC 1 Soft Starter 2 1 CTG 1
BROTHERS 200 METERING MOTION
ASSOCIATED S Siemens S7- SUCTION MICRO
309 CR04 DELTA (1200 SCM) COMPAC 2 VFD 2 1 CTG 1 3
S 300 METERING MOTION
Siemens S7- SUCTION MICRO
310 CHADDHA OIL CR06 DELTA (1200 SCM) COMPAC 1 VFD 2 1 CTG 1 3
300 METERING MOTION
Siemens S7- SUCTION MICRO
311 CHADDHA S S CR01 DELTA (1200 SCM) COMPAC 2 VFD 2 1 CTG 1 3
300 METERING MOTION
312 BADARPUR HP CR05 HYBRID COMPAC 2 2 1 NR
313 AJAY AHUJA CR02 HYBRID COMPAC 2 2 1 NR
314 BANSIWAL CR02 HYBRID COMPAC 2 2 1 NR
315 SHANTI S S CR01 HYBRID COMPAC 1 2 1 NR
Siemens S7- SUCTION
316 DEWAN SS CR03 ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
317 AZADPUR S S CR06 ICL BOOSTER COMPAC 1 E&H ELGI STAR/DELTA 2 1 CTG 1 3
200 METERING
NATHUMAL Siemens S7- SUCTION
318 CR01 DELTA BOOSTER COMPAC 2 MICRO MOTION VFD 2 1 CTG 1 3
AHUJA 200 METERING

MAA Siemens S7- SUCTION MICRO


319 CR08 DELTA (600 SCM) COMPAC 1 Soft Starter 2 1 CTG 1 3
DHANESHWARI 200 METERING MOTION

Siemens S7- SUCTION


320 R . L. BANSIWAL CR06 DELTA BOOSTER COMPAC 1 MICRO MOTION Soft Starter 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
321 BANSAL S S CR06 DELTA BOOSTER COMPAC 1 MICRO MOTION Soft Starter 2 1 CTG 1 3
200 METERING

Page 118 of29142


22 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
CR01 DELTA (600 SCM) SAIA COMPAC 2 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1
322 SAVITA S S CTG 2 3
Siemens S7-
CR01 DELTA (600 SCM) FTI 1 VFD
200
D-RAND (400 Siemens S7-
323 RAKESH F S CR06 DELTA 1 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1 CTG 1 3
SCM) 300
ABHISHEK D-RAND (400 Siemens S7- SUCTION MICRO
324 CR03 DELTA 1 INGERSOLL RAND 2 1 CTG 1 3
MOTORS SCM) 300 METERING MOTION
BURCKHARDT Siemens S7-
CR04 COMPAC 1 CHEMTROLS HEINRICHS SCHNEIDER INGERSOLL RAND 2 1
325 MOTOR CENTRE (600 SCM) 300 CTG 1 3
CR04 DELTA 1
Siemens S7- SUCTION MICRO
326 RUCHIKA S S CR05 DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
CR02 DELTA (600 SCM) FTI 2 Soft Starter 2 1
327 CAR CARE S S 200 METERING MOTION CTG 1 3
CR02
SUCTION
328 R N SOIN CR01 ICL BOOSTER COMPAC 2 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
METERING
BURCKHARDT Siemens S7-
CR31 COMPAC 2 CHEMTROLS HEINRICHS FISHER INGERSOLL RAND 2 1
(1200 SCM) 300
329 NOIDA DEPOT CTG 2 2
BURCKHARDT Siemens S7-
CR31 INGERSOLL RAND
(1200 SCM) 300
BURCKHARDT Siemens S7- BRISTOL
CR31 COMPAC 3 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 BABCOCK
UPSRTC NOIDA BURCKHARDT Siemens S7-
330 CR31 FTI 1 INGERSOLL RAND CTG 2 2
SEC 35 (1200 SCM) 300

CR31 INGERSOLL RAND

BURCKHARDT Siemens S7- BRISTOL


CR31 COMPAC 6 CHEMTROLS HEINRICHS E&H KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 BABCOCK
BURCKHARDT Siemens S7-
CR31 FTI 2 INGERSOLL RAND
(1200 SCM) 300
331 NOIDA SEC 53 CTG 3 2
BURCKHARDT Siemens S7-
CR31 INGERSOLL RAND
(1200 SCM) 300

CR31 INGERSOLL RAND

BURCKHARDT Siemens S7-


CR31 COMPAC 7 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300
332 NOIDA SEC 105 CTG 2 2
Siemens S7-
CR31 DELTA (1200 SCM) COMPAC 2 INGERSOLL RAND
300
BURCKHARDT Siemens S7-
CR31 COMPAC 5 CHEMTROLS HEINRICHS FISHER E&H KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300
333 NOIDA SEC 122 CTG 2 1
Siemens S7-
CR31 DELTA (1200 SCM) COMPAC 2 INGERSOLL RAND
300

Page 119 of29142


23 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BURCKHARDT Siemens S7-
CR31 COMPAC 4 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300
334 NOIDA SEC 71 Siemens S7- CTG 2 2
CR31 DELTA (1200 SCM) COMPAC 2 INGERSOLL RAND
300
CR31
BURCKHARDT Siemens S7-
CR31 COMPAC 5 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300
Siemens S7-
335 NOIDA SEC 82 CR31 DELTA (1200 SCM) COMPAC 1 INGERSOLL RAND CTG 2 2
300

CR31 INGERSOLL RAND

BURCKHARDT Siemens S7-


336 NOIDA SEC 51 CR31 COMPAC 4 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1 CTG 1 2
(1200 SCM) 300
BURCKHARDT Siemens S7-
CR31 COMPAC 3 CHEMTROLS HEINRICHS FISHER KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300
337 NOIDA SEC 142 CTG 2 2
BURCKHARDT Siemens S7-
CR31 COMPAC 2 INGERSOLL RAND
(1200 SCM) 300
NMRC NOIDA BURCKHARDT Siemens S7- SUCTION MICRO
338 CR31 COMPAC 2 INGERSOLL RAND 2 1 CTG 1 2
SEC 90 DEPOT (1200 SCM) 300 METERING MOTION

NMRC NOIDA
339 CR31 HYBRID COMPAC 1 2 1 NR
SEC 90 HYBRID

BURCKHARDT Siemens S7- SUCTION MICRO


340 HP CENTRE-62 CR31 COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
(600 SCM) 300 METERING MOTION

KUNDAN LAL & SUCTION MICRO


341 CR31 DELTA (600 SCM) SAIA COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
SONS, NOIDA METERING MOTION

BURCKHARDT Siemens S7- SUCTION MICRO


342 BHAGWATI S S CR31 COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
(400 SCM) 300 METERING MOTION
PADAM BURCKHARDT Siemens S7- MICRO
343 CR31 COMPAC 1 EMERSON FISHER INGERSOLL RAND 2 1 CTG 1 3
PETROLEUM (600 SCM) 300 MOTION
NOIDA Siemens S7- SUCTION MICRO
344 CR31 DELTA (600 SCM) COMPAC 2 Soft Starter 2 1 CTG 1 3
AUTOMOBILES 200 METERING MOTION
Siemens S7- SUCTION MICRO
SHEETAL CR31 DELTA (1200 SCM) COMPAC 3 VFD 2 1
345 200 METERING MOTION CTG 1 3
AUTOMOBILE
CR31
BURCKHARDT Siemens S7- BRISTOL
CR31 COMPAC 3 CHEMTROLS HEINRICHS E&H KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 BABCOCK
KASNA (OPP
346 KIRLOSKAR (2400 Siemens S7- CTG 2 2
HONDA SIEL) CR31 COMPAC 2 INGERSOLL RAND VFD
SCM) 300
CR31 ELGI
BURCKHARDT Siemens S7- BRISTOL
CR31 COMPAC 3 CHEMTROLS HEINRICHS KOHLER INGERSOLL RAND 2 1
SURAJPUR (OPP (1200 SCM) 300 BABCOCK

Page 120 of29142


24 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
347 DAEWOO KIRLOSKAR (2400 Siemens S7- CTG 2 2
CR31 COMPAC 2 ELGI VFD
MOTORS) SCM) 300
CR31 ELGI
BURCKHARDT Siemens S7- MICRO BRISTOL
CR31 COMPAC 9 EMERSON KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 MOTION BABCOCK
BURCKHARDT Siemens S7-
348 BETA-II CR31 INGERSOLL RAND CTG 2 2
(1200 SCM) 300

CR31 INGERSOLL RAND

BURCKHARDT Siemens S7- MICRO BRISTOL


CR31 COMPAC 5 EMERSON E&H KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 MOTION BABCOCK
349 IT CITY CTG 2 2
BURCKHARDT Siemens S7-
CR31 COMPAC 2 KOHLER INGERSOLL RAND
(1200 SCM) 300
BURCKHARDT Siemens S7- MICRO BRISTOL
CR31 COMPAC 5 EMERSON KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 MOTION BABCOCK
KNOWLEDGE BURCKHARDT Siemens S7-
350 CR31 INGERSOLL RAND CTG 2 2
PARK V (1200 SCM) 300

CR31 INGERSOLL RAND

Siemens S7- SUCTION MICRO


TYAGI CR31 DELTA (600 SCM) COMPAC 2 VFD 2 1
351 200 METERING MOTION CTG 1 3
BROTHERS
CR31 COMPAC 1

ISHWAR FILLING D-RAND (400 Siemens S7- SUCTION MICRO


352 CR31 COMPAC 2 INGERSOLL RAND 2 1 CTG 1 3
STATION SCM) 300 METERING MOTION

JRO,UDYOG BURCKHARDT Siemens S7- SUCTION MICRO


353 CR31 COMPAC 2 INGERSOLL RAND 2 1 CTG 1 3
VIHAR (400 SCM) 300 METERING MOTION
KASANA SUCTION MICRO
354 CR31 DELTA (600 SCM) SAIA COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
MOTORS METERING MOTION
BURCKHARDT Siemens S7- SUCTION MICRO
355 OM SAI CR31 COMPAC 2 INGERSOLL RAND 2 1 CTG 1 3
(600 SCM) 300 METERING MOTION
SUCTION
356 CRC BHATI F S CR31 ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
METERING
JAYPEE
SUCTION
357 INFRATECH KM- CR31 ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
METERING
35
Siemens S7- SUCTION
358 SHIV MOHAN S S CR31 ICL BOOSTER COMPAC 2 MICRO MOTION INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
SUCTION
359 KBS MOTORS CR31 ICL BOOSTER COMPAC 1 MICRO MOTION MOTHERSON STAR/DELTA 2 1 CTG 1 3
METERING
KIRAN FILLING SUCTION
360 CR31 DAUGHTER COMPAC 1 MICRO MOTION 2 1 CTG 1 3
STATION METERING
SHUBASH BURCKHARDT Siemens S7- SUCTION MICRO
361 CR31 COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
AUTOMOBILES (600 SCM) 300 METERING MOTION

Page 121 of29142


25 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
SUCTION
362 SHARMA F S GHZ DAUGHTER COMPAC 1 E&H 2 1 CTG 1 3
METERING
MOHAN NAGAR SUCTION
363 GHZ DAUGHTER COMPAC 1 E&H 2 1 CTG 1 3
SS METERING
SUCTION
364 SAHIL AUTO GHZ ICL BOOSTER COMPAC 1 MICRO MOTION INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
METERING
SRI GANESH SUCTION
365 GHZ ICL BOOSTER COMPAC 1 MICRO MOTION ELGI STAR/DELTA 2 1 CTG 1 3
AUTO CENTRE METERING
RAMAVTAR SUCTION
366 GHZ ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
TYAGI METERING
KANSAL ROAD SUCTION
367 GHZ ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
LINES METERING
SUCTION
368 MAHALAXMI FS GHZ DAUGHTER COMPAC 1 E&H 2 1 CTG 1 3
METERING
Siemens S7- SUCTION
369 RAJ AUTO GHZ ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
370 RAMAN & CO. GHZ ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
371 BAJAJ PRIME GHZ DELTA BOOSTER COMPAC 1 E&H VFD 2 1 CTG 1 3
200 METERING
SUCTION
372 MAYANK SS GHZ DAUGHTER COMPAC 1 E&H 2 1 CTG 1 3
METERING
INDRAPURAM
Siemens S7- SUCTION MICRO
373 AUTO FUELS GHZ DELTA (600 SCM) COMPAC 2 Soft Starter 2 1 CTG 1 3
200 METERING MOTION
&SERVICES
TYAGI SS, Siemens S7- SUCTION MICRO
374 GHZ DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
SAHIBABAD 200 METERING MOTION
JAY Siemens S7- SUCTION MICRO
375 GHZ DELTA (600 SCM) COMPAC 2 Soft Starter 2 1 CTG 1 3
AUTOMOBILES 200 METERING MOTION
Siemens S7- SUCTION MICRO
376 RUKMANI SS GHZ DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
Siemens S7- SUCTION MICRO
377 RAMA S S GHZ DELTA (600 SCM) COMPAC 2 VFD 2 1 CTG 1 3
200 METERING MOTION
VIBHOR
Siemens S7- SUCTION
378 SERVICE GHZ DELTA BOOSTER COMPAC 2 E&H VFD 2 1 CTG 1 3
200 METERING
STATION
SHREE Siemens S7- SUCTION
379 GHZ ICL BOOSTER COMPAC 1 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
SHUBHAM F S 200 METERING
Siemens S7- SUCTION
380 DEV FUEL GHZ ICL BOOSTER COMPAC 1 MICRO MOTION INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
381 NCR FUEL GHZ ICL BOOSTER COMPAC 1 MICRO MOTION INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
Siemens S7- SUCTION
382 SHIV S S GHZ ICL BOOSTER COMPAC 1 MICRO MOTION INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING

Page 122 of29142


26 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
NANDINI FILL Siemens S7- SUCTION MICRO
383 GHZ DELTA (1200 SCM) COMPAC 1 VFD 2 1 CTG 1 3
POINT 300 METERING MOTION
RAJ DRASS BURCKHARDT Siemens S7- SUCTION MICRO
384 GHZ COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
HEIGHT (600 SCM) 300 METERING MOTION
QUALITY HP FILL Siemens S7- SUCTION MICRO
385 GHZ DELTA (600 SCM) COMPAC 1 Soft Starter 2 1 CTG 1 3
POINT 200 METERING MOTION
D-RAND (400 Siemens S7- SUCTION MICRO
386 BAJAJ MOTORS GHZ COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
SCM) 300 METERING MOTION
BURCKHARDT Siemens S7- SUCTION MICRO
387 HINDON S S GHZ COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
(400 SCM) 300 METERING MOTION
SRI RAM
SUCTION MICRO
388 SERVICE GHZ DELTA (600 SCM) SAIA COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
METERING MOTION
STATION
GHAZIABAD Siemens S7- SUCTION MICRO
389 GHZ DELTA (600 SCM) COMPAC 1 Soft Starter 2 1 CTG 1 3
PETROLEUM 200 METERING MOTION
D-RAND (400 Siemens S7- SUCTION MICRO
390 RADHEY SHYAM GHZ COMPAC 2 INGERSOLL RAND 2 1 CTG 1 3
SCM) 300 METERING MOTION
BURCKHARDT Siemens S7- SUCTION MICRO
391 MOHAN SHIVA GHZ COMPAC 1 INGERSOLL RAND 2 1 CTG 1 3
(400 SCM) 300 METERING MOTION
Siemens S7- SUCTION
392 TYAGI ESSAR GHZ ICL BOOSTER COMPAC 2 E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3
200 METERING
BURCKHARDT Siemens S7- MICRO BRISTOL
GHZ COMPAC 6 EMERSON E&H INGERSOLL RAND 2 1
(1200 SCM) 300 MOTION BABCOCK
BURCKHARDT Siemens S7-
393 VAISHALI GHZ COMPAC 1 E&H INGERSOLL RAND CTG 3 2
(1200 SCM) 300
BURCKHARDT Siemens S7-
GHZ KOHLER
(1200 SCM) 300
BURCKHARDT Siemens S7- BRISTOL
GHZ COMPAC 4 CHEMTROLS HEINRICHS INGERSOLL RAND 2 1
(1200 SCM) 300 BABCOCK
SANJAY NAGAR BURCKHARDT Siemens S7-
394 GHZ KOHLER INGERSOLL RAND CTG 3 2
ALT GAZIABAD (1200 SCM) 300
Siemens S7-
GHZ DELTA (1200 SCM) COMPAC 2 INGERSOLL RAND
300
BURCKHARDT Siemens S7- MICRO BRISTOL
GHZ COMPAC 8 EMERSON E&H KOHLER INGERSOLL RAND 2 1
(1200 SCM) 300 MOTION BABCOCK
BURCKHARDT Siemens S7-
GOVINDPURAM GHZ COMPAC 2 INGERSOLL RAND
395 (1200 SCM) 300 CTG 3 2
A BLOCK
BURCKHARDT Siemens S7-
GHZ
(1200 SCM) 300
GHZ
BURCKHARDT Siemens S7- MICRO BRISTOL
GHZ COMPAC 6 EMERSON E&H KOHLER INGERSOLL RAND 2 1
NH 58 (1200 SCM) 300 MOTION BABCOCK
396 CTG 2 2
MURADNAGAR Siemens S7-
GHZ DELTA (1200 SCM) COMPAC 1 INGERSOLL RAND
300

Page 123 of29142


27 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING
BURCKHARDT Siemens S7- SUCTION MICRO
MADHUBAN GHZ COMPAC 3 KOHLER INGERSOLL RAND 2 1
397 (1200 SCM) 300 METERING MOTION CTG 1 2
BAPUDHAM
GHZ COMPAC 1
GOVINDPURAM BURCKHARDT Siemens S7- MICRO BRISTOL
398 GHZ COMPAC 3 EMERSON MICRO MOTION KOHLER INGERSOLL RAND 2 1 CTG 1 2
G BLOCK (1200 SCM) 300 MOTION BABCOCK
CROSSING BURCKHARDT Siemens S7- MICRO BRISTOL
399 GHZ COMPAC 3 EMERSON KOHLER INGERSOLL RAND 2 1 CTG 1 2
REPUBLIC - I (1200 SCM) 300 MOTION BABCOCK
CROSSING BURCKHARDT Siemens S7- MICRO BRISTOL
400 GHZ COMPAC 3 EMERSON INGERSOLL RAND 2 1 CTG 1 2
REPUBLIC - II (1200 SCM) 300 MOTION BABCOCK
DWARKA 2
401 CR08 HYBRID Compac 1 2 1 NR
HYBRID
SUCTION
402 ANAND SUPER CR04 DAUGHTER Compac 1 METERING
E&H INGERSOLL RAND STAR/DELTA 2 1 CTG 1 3

KIRLOSKAR (1200 Siemens S7-


403 BHORGARH 02 CR04
SCM) 300
Compac 3 CHEMTROLS HEINRICHS FISHER ELGI VFD 2 1 CTG 1 2

Siemens S7-
404 NARELA SEC 7 CR04 DELTA (1200 SCM)
300
Compac 4 CHEMTROLS HEINRICHS FISHER INGERSOLL RAND 2 1 CTG 1 2

Siemens S7- SUCTION MICRO


405 TEJ CR04 DELTA (600 SCM)
200
Compac 2 METERING MOTION
Soft Starter 2 1 CTG 1 3

MAHESHWARI Siemens S7- SUCTION MICRO


406
S/S
CR04 DELTA (1200 SCM)
300
Compac 1 METERING MOTION
Soft Starter 2 1 CTG 1 3

KIRLOSKAR (1200 Siemens S7- SUCTION MICRO


407 DWARKA SEC 10 CR04
SCM) 300
Compac 2 METERING MOTION
ELGI VFD 2 1 CTG 1 2

KIRLOSKAR (1200 Siemens S7- MICRO


408 DWARKA SEC 13 CR04
SCM) 300
Compac 1 EMERSON
MOTION
FISHER ELGI VFD 2 1 CTG 1 2

KIRLOSKAR (1200 Siemens S7-


CR04
SCM) 300
Compac 3 CHEMTROLS HEINRICHS FISHER ELGI VFD 2 1 CTG 2 2
409 DWARKA SEC 18
BURCKHARDT Siemens S7-
CR04
(1200 SCM) 300
TGT 1

PARADISE
FILLING Siemens S7- SUCTION MICRO
410
STATION, BPCL
CR21 ICL BOOSTER
200
Compac 2 METERING MOTION
ELGI STAR/DELTA 2 1 CTG 1 3
RO REWARI

PICK & MOVE,


Siemens S7- SUCTION MICRO
411 BPCL RO CR21 ICL BOOSTER
200
Compac 2 METERING MOTION
ELGI STAR/DELTA 2 1 CTG 1 3
REWARI

S.N. RTU Category Description

Page 124 of29142


28 of
P.011489
PTS - SCADA AND RTU SYSTEM I-11097
01
ANNEXURE - V
Total List of Equipment at CNG stations
LCV Air compressor
GG Set
Compressor Package Detail Dispenser Detail Station Inlet /Meter Skid Detail flowmeter Compressor electrical cascade UPS
Detail
Detail Detail equipment
Control RTU Implementatio
Sno. Station Name
Room Meter Skid CATEGORIES n Phase 1, 2,
Flow Flow
Compressor No.of Make/ Make (IF VFD/Soft and 3
PLC Make Meter Computer Make Make quantity quantity
Make Dispensers SUCTION PRESENT) Starter
Make Make
METERING

Configuration of RTUs at Stations having 1


1 Category – 1
number of CNG Compressors

Configuration of RTUs at Stations having 2


2 Category – 2
number of CNG Compressors

Configuration of RTUs at Stations having 3 to 4


3 Category – 3
number of CNG Compressors

These are hybrid stations, which will be merged


4 NR (Not Required)
with their principal station RTU

5 Phase-I 20 RTUs
6 Phase II 151 RTUs
7 Phase III 218 RTUs

Page 125 of29142


29 of
P.011489
PTS- SCADA AND RTU SYSTEM I-11097
01
ANNEXURE VI
Existing PLC details
Type of Siemens PLCs in IGL

Nos of packages
Sno CPU Description Type of PLC Siemens Part No
(Approx)
1 CPU 315-2DP S7 300 6ES7 315-2AG10-0AB0/6ES7 315-2AH14-0AB0 170
CPU ET200S,PN/DP CPU IM151-
2 S7 300 6ES7 151-8AB01-0AB0 112
8
3 CPU 226/ CPU 226-CN S7 200 6ES7 216-2BD23-0XB0/6ES7 216-2BD23-0XB8 155
6ES7 216-2AD23-0XB0/6es7 214-1AD23-0XB0/6ES7
4 CPU 226 /CPU 224/CPU 226-CN S7 200 13
216-2AD23-0XB8
5 Siemens CPU-1214C(DC/DC/DC) S7 1200 6ES7 214-1AG31-0XB0 5

6 CPU 315 S7 300 6ES7 315-1AF03-0AB0/6ES7 315-2AF03-0AB0 54

Note: This list of CPU is indicative only. However quantity and MLFB numbers may differ.

Page 126 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

INDRAPRASTHA GAS LIMITED (IGL)


SCADA IMPLEMENTATION AT CNG STATION (INCLUDING
DTC & RETAIL OUTLET) & PNG SEGMENT

TRACTEBEL ENGINEERING PVT. LTD.

PARTCULAR TECHNICAL SPECIFICATION


INSTRUMENTS CABLE
RERT

0 19.06.2018 Issued for Procurement MA SHD BK


Rev. Date Subject of revision Author Checked Approved

Page 127 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

TABLE OF CONTENTS

1.0 SCOPE ................................................................................................................................... 1

2.0 APPLICABLE CODES & STANDARDS ..................................................................................... 1

3.0 DESIGN & CONSTRUCTION .................................................................................................. 1

4.0 CABLE GLANDS ..................................................................................................................... 3

5.0 CABLE TRAYS AND CABLE DUCTS ........................................................................................ 3

6.0 JUNCTION BOX..................................................................................................................... 4

7.0 ELECTRICAL CHARACTERISTICS.......................................................................................... 4

8.0 INSPECTION AND TESTING ................................................................................................. 6

Σ Σ Σ

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 1 of 1

Page 128 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

1.0 SCOPE

Contactor’s scope covers supply, design, testing at works, dispatch in well packed condition, laying,
glanding, termination of signals cables and power cables. Scope also includes the supply of cable tray, cable
glands and associated accessories of Instrument cables required for this Project.

2.0 APPLICABLE CODES & STANDARDS

The related standards referred to herein (but not limited to) and mentioned below shall be of the latest
editions prior to the date of purchaser’s enquiry:

a) IS-1554 Part 1- PVC insulated (heavy duty) electric cables – working voltage up to and including 1100
V.

b) IS-2633 - Method for testing uniformity of coating on zinc coated articles.

c) IS-3975 - Mild steel wires, formed wires and tapes for armouring of cables.

d) IS 8130 - Conductor: Annealed tinned copper conductor.

e) IS-5831- PVC insulation and sheath of electric cables.

f) BS-5308 Part 1, Type 2 - Specification for PVC insulated cables.

g) IEC-332-3 Part 3 - Tests on bunched wires and cables.

h) ASTM D 2863 - Test method for measuring the minimum oxygen concentration to support candle, like
combustion of plastics (oxygen index).

i) ASTM D 2843 - Max Smoke Density.

j) IEC 60754 - Acid Gas Generation.

k) DIN-50049 - Document on Material Testing.

3.0 DESIGN & CONSTRUCTION

All cables shall be FRLS type.

1P x1.5 mm², 2P x1.5 mm², 6P x 0.5 mm², 12P x 0.5 mm², 1Q x 1.5 mm² and 3 c x 2.5mm² power cable
shall be used for instrumentation purposes. No other combination shall be acceptable. Contractor to also
note that all multipair cables shall have 20% spare pairs which may be used in future. These spare pairs
shall be terminated in junction box.

Separate multipair cables shall be used for analog input, analog output, digital input & digital output signal.
No signal mixing shall be permitted.

Triad or Quad cable shall be used for temperature element to temperature transmitter. Vendor shall consider
the length as required.

3.1 Single Pair & Triad Shielded Cable

 Each core shall be 1.5 mm2 made of 7 stranded annealed electrolytic copper conductor. Each strand
shall be 0.53 mm dia.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 1 of 7

Page 129 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

 For Intrinsically safe application, primary insulation shall be low density poly ethylene (LDPE). For
non-intrinsically safe application, primary insulation shall be 85 °C poly-vinyle chloride (PVC) as per
IS5831 Type C. Thickness shall be 0.5 mm minimum.

 A pair shall have twisted cores and number of twists shall be not less than 10 per metre. Colour of
core insulation shall be black blue in pair and black, blue and brown in triad.

 Individual pair shall be shielded. Shield shall be Aluminium backed by mylar / polyester tape with the
metallic side down helically applied with either side 25% overlap and 100% coverage. Minimum
shield thickness shall be 0.05 mm. Drain wire shall be 0.5 mm2 multi-strand bare tinned annealed
copper conductor. The drain wire shall be in continuous contact with Aluminium side of the shield.

 Inner and outer jacket shall be made of extruded flame retardant 90oC PVC to IS 5831-Type ST2.
Oxygen index of PVC shall be over 30%. Temperature Index shall be over 250oC. The thickness of
the jacket shall be as per IS-1554 Part 1.

 Inner jacket colour shall be black. Outer jacket colour shall be black except, for cables to be used in
intrinsically safe systems, where it shall be light blue. A rip cord shall be provided for inner jacket.

 Armour over inner jacket shall be galvanized steel wire as per IS-1554 Part 1.

3.2 Multipair Cable with Individual Pair and Overall Shield

 Generally the cable shall be same as single pair shielded cable except conductor sizes shall be 0.5 mm2
made of 7 strands of annealed electrolytic copper conductor. Each strand shall be of 0.30 mm dia.

 Overall shield shall be of Aluminium backed up by mylar / polyester tape helically applied with the
metallic side down with either side 25% overlap and 100% coverage. Minimum shield thickness shall
be 0.075 mm. Drain wire shall be similar to individual pair drain wire and shall be of the overall
shield.

 A pair of communication wire shall be provided for multi-pair cables. Each wire shall be 0.5 mm2 of
plain annealed single or multi-strand copper conductor with 0.4 mm thick 85 °C PVC insulation.
Insulation shall be green and red colour coded.

 Pair identification shall be with numbers at interval of not more than 250 mm as per vendor’s
standard.

3.3 Multipair cable with only Overall Shield

 These cables shall be same as described in above Section except that the individual pair shall not have
shielding.

3.4 Control Cable (Non IS)

 Two core Control cables shall be used between field mounted solenoid valves and junction
boxes/local control panels.

 Multi core shall be multi-strand of size 4C x 1.5mm², 6C x 1.5 mm², 12C x 1.5mm² control cables
shall be used between junction boxes/local control panel and control room mounted devices in
general.

 These control cables shall have 1.5 sq mm conductor size with 7 stranded conductors of annealed
electrolytic grade copper, with each strand of 0.53 mm diameter.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 2 of 7

Page 130 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

3.5 Thermocouple Extension Cables

 Single pair shielded thermocouple extension cables shall be used between thermocouple head and
junction boxes transmitters/local control panel mounted instruments.

 Multi pair, individually and overall shielded thermocouple extension cables shall be used between
junction boxes and control room mounted devices.

 The type of thermocouple extension cables shall be compatible with thermocouple used. In addition
the colour coding of the primary insulation shall be as per ANSI MC 96.1.

 The cable shall have 16 AWG and 20AWG solid conductors for single and multipairs respectively.

 Shield shall be aluminium backed by mylar/polyester tape bonded together, helically applied with the
metallic side down with either side having 25% overlap and 100% coverage. The minimum shield
thickness shall be 0.05 mm in case of single pair/ traid and 0.075 mm incase of multipair/triad cable
surface. Minimum shield thickness shall be 0.05 mm for single pair and 0.075 mm for multipair cable.
Drain wire shall be 0.5 mm2 multistrand bare tinned annealed copper conductor. The drain wire shall
be in continuous contact with the aluminium side of the shield.

 Inductance shall not exceed 4mH/Km. However for J-type thermocouple inductance could be 8
mH/km.

 All multi-pair cables shall have preferably 6 pairs/12 pairs/20 pairs.

3.6 Power Supply and Other Cables

 All power supply cables shall be as per IS-1554 Part I and shall have copper /aluminium conductors
depending on conductor size.

 Power cables shall be 3-core, minimum 2.5 mm2 copper conductors with PVC insulation, galvanized
steel armoring and overall PVC sheathing.

3.7 Earthing cable

 Earthing cable/wire shall be single core, outer sheath green in colour, size 1C x 6mm² mult-strand.

3.8 Communication cable (Ethernet)

 PVC insulated with grey colour, AWG 22 (0.3 mm²)or AWG 24 (0.2mm²) 4Pair, solid conductor,
CAT 5e, UTP cable (TIA/EIA 568) as per requirement with flexible PVC conduit and PVC gland & 8
pin RJ/Male /Female connector wherever require.

4.0 CABLE GLANDS

 Cable gland shall be provided for all the above mentioned cables both at field instrument, junction
boxes side, RTU and at control room side along with PVC hood.

 All cables glands shall be of nickel-plated brass, Double compression type, & WP to IP 65 as per IEC
60529 / IS 2147 and they shall be double compression type suitable for armoured cables.

 Contractor shall provide insulating glands wherever applicable to protect the CP current drainage.

 Ex/Flame proof glands at hazardous area location and shall be supplied with Ex (d) certification.

5.0 CABLE TRAYS AND CABLE DUCTS


Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 3 of 7

Page 131 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

All branch cables/tubes shall run on cable trays.

These cable trays shall be made out of galvanized iron-perforated type of 2.5 mm thickness. 50 mm x 50
mm angle shall be used as a minimum.

Suitable cable clamps shall be supplied for binding the cables/tubes at every 500 mm. Instrument
Support/Structural Steel.

Maximum width of the cable tray shall be 600mm and height 50mm, 75mm or 100mm as applicable. 25%
spare capacity shall be provided for cable trays.

6.0 JUNCTION BOX

Size - by contractor
Junction box Protection – As per IEC 60529 WP IP 52, with certificate
Material - dia cast aluminium (LM6),
Colour - RAL 7035 interior and exterior.
Terminal blocks – Din rail mounted screw less clamp type, wire terminal screw less press
to fit type. TB shall be of traceable standard make. Number of TBs shall be as per requirement with 20%
spare
Gasket – Neoprene rubber
Power earth and system earth bus bar – required
Hings - require
Entry –
Left entry – 6 nos (1/2” NPT) with blind plug (SS 304)
Right entry – 6 nos (1/2” NPT) with blind plug (SS304)
Top entry – Not recommended
Bottom entry – 4 Nos 1 ½” with Bling plug (SS304) along with adapter
Appropriate gland size SS 304 adaptor shall be provided by contractor in case varies in sizes or contractor
shall consider the size according to cable size. Spare 20% inlet and out let cable entries with plugs shall be
provided in each junction box in case of occupancy of all above entries.
7.0 ELECTRICAL CHARACTERISTICS

7.1 Resistance:

Maximum DC resistance of the conductor of the completed cable shall not exceed 12.3 Ω / km at 20oC for
cables with 1.5 mm2 conductors and 39.7 Ω / km at 20oC for cables with 0.5 mm2 conductors.

7.2 Mutual Capacitance:

The mutual capacitance of the pairs or adjacent cores shall not exceed a maximum of 250 pF / m at a
frequency of 1 kHz.

7.3 Capacitance between any core or screen:

The capacitance between any core or screen shall not exceed a maximum of 400 pF / m at a frequency of 1
kHz.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 4 of 7

Page 132 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

7.4 L/R ratio of adjacent core shall not exceed 40 µH / Ω for cables with 1.5 mm2 conductors and 25 µH / Ω for
cables with 0.5 mm2 conductors.

7.5 The drain wire resistance including shield shall not exceed 30 Ω / km.

7.6 Electrostatic noise rejection ratio shall be over 76 dB.

8.0 PPI AND MPI CABLES

8.1 Mechanical data

 Cable shall be two cores with each core shall be of 0.65 mm dia

 For Intrinsically safe application, primary insulation shall be low density poly ethylene (LDPE).

 Both the cores shall be shielded. Shield shall be Aluminium backed by mylar / polyester tape with the
metallic side down helically applied with either side 25% overlap and 100% coverage. Minimum
shield thickness shall be 0.05 mm. Drain wire shall be 0.5 mm2 multi-strand bare tinned annealed
copper conductor. The drain wire shall be in continuous contact with Aluminium side of the shield.

 Inner and outer jacket shall be made of extruded flame retardant 90oC PVC to IS 5831-Type ST2.
Oxygen index of PVC shall be over 30%. Temperature Index shall be over 250oC. The thickness of
the jacket shall be as per IS-1554 Part 1.

 Inner and outer jacket colour shall be violet. Insulation colour shall be red/green. A rip cord shall be
provided for inner jacket.

8.2 Electrical data

Damping ration per length –

9.6 kHz/maximum – 0.0025dB/m

38.4 kHz/Maximum – 0.004 dB/m

4 MHz/Maximum – 0.022 dB/m

16 MHz/Maximum – 0.042dB/m

Impedance

Rated value - 150Ω

9.6 kHz – 270Ω

38.4 kHz - 185Ω

3MHz to 20MHz - 150Ω

38.4 kHz/Maximum – 0.004 dB/m

4 MHz/Maximum – 0.022 dB/m

16 MHz/Maximum – 0.042dB/m

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 5 of 7

Page 133 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

Loop resistance per length/maximum – 110mΩ/m

Shield resistance per length/maximum – 9.5 Ω/m

Capacity per length/at 1 kHz – 28.5pF/m

RMS Valve - 100V

8.3 CONNECTORS

Transfer rate – 9.6 Kbits/s…12 Mbits/s

Number and type of connectors- as per requirement

Design of terminating resistor – Integrated resistor combination that can be selected with slide switch.

Material of enclosure – plastic

Locking mechanism design – screw

Design temperature - (-)20 to 65 deg C

Protection class IP – IP42

9.0 INSPECTION AND TESTING

Owner reserves the right to test and inspect all the items at the manufacture’s works.

Manufacturer shall furnish documents such as test certificates to prove the quality and composition of the
materials used for manufacturing the cable to the satisfaction of Owner/Owner’s Representative during
expediting and inspection.

9.1 Type Test:

a) Type Certificates shall be furnished.

b) Cable shall be flame retardant to IEC 332-3 Part 3 Cat A.

9.2 Routine Tests:

a) These tests shall be carried out by manufacturer during various stages of manufacturing. Owner shall
review the related documents.
a) Insulation and Sheaths : All tests as per IS-5831 except insulation resistance, voltage and spark test
shall be as per BS-5308 Part 2.
b) Armour test as per IS-3975.
d) Conductor resistance.
e) Cable capacitance, L/R ratio.
9.3 Acceptance Test:

These tests shall be carried out in the presence of Owner / Owner’s Representative.

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 6 of 7

Page 134 of 142


P.011489
PTS – INSTRUMENT CABLES I-11097
02

9.3.1 Continuity test:

a) Voltage test as per BS-5308 Part 2.


b) Conductor resistance and drain wire resistance.
c) Cable capacitance and L/R ratio test.
d) Electrostatic noise rejection test, type wise for each lot.
e) Tests for uniformity of galvanization of armour as per IS-2633.
f) Oxygen index test as per ASTM D 2863, temp. index test, smoke density rating test, acid gas
generation test and flammability test.
g) Dimensional check for overall diameter and under armour/over armour diameter.
h) Overall finish check. In case of any lump purchaser will have the right to cut outer sheath for lump
portion and reject the cable.
i) Check of Drum length and overall length tolerances.
Immediately after completion of electrical tests, the ends of the cable shall be sealed to prevent ingress of
moisture with suitable PVC/Rubber caps.

Σ Σ Σ

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 7 of 7

Page 135 of 142


P.011489
RECOMMENDED VENDOR LIST I-11073
01

INDRAPRASTHA GAS LIMITED (IGL)


SCADA IMPLEMENTATION AT CNG STATION (INCLUDING
DTC & RETAIL OUTLET) & PNG SEGMENT

TRACTEBEL ENGINEERING PVT. LTD.

RECOMMENDED VENDOR LISTRERT

Page 136 of 142


P.011489
RECOMMENDED VENDOR LIST I-11073
01
1.0 LIST OF RECOMMENDED VENDORS

Sr.No Equipment Recommended vendor


1 RTU a) Invensys/ Foxboro
b) Electronic corporation of India
limited (ECIL)
c) Schneider
d) ABB
e) Yokogawa
f) Siemens AG
g) Bristol Babcock
h) Allan Bradley
i) GE. Fanuc
j) LMD Hitech
k) Hitachi India
l) TAS India Limited
m) Schneider
n) Wago
o) Masibus
2 RTU Cabinet/server cabinet a) Rittal
b) ICA
c) Pyrotech
3 SCADA server/Web server/Achieve a) DELL
server/HMI
b) HP
c) IBM
4 LAN Switch/Routers/Fire wall a) 3COM
b) CISCO
c) NORTEL
d) IBM
e) CABLETRON
5 PDT(Laptop) a) DELL
b) HP
c) IBM
d) LENOVO
6 Laser jet colour printer a) HP
b) Canon

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 1 of 3

Page 137 of 142


P.011489
RECOMMENDED VENDOR LIST I-11073
01
c) Epson
7 Large LED Screen a) Samsung
b) Sony
c) LG
d) Panasonic
8 GPS a) Masibus
b) Meinberg
c) Tekron
9 Telecommunication a) In Hand Networks
System(Modem)
b) Calamp – USA
c) Elpro – Australia
d) T-CAM Singapore
10 Junction Box and cable glands a) Baliga lighting Equipment
b) Flame proof equipment Pvt Ltd
c) Flexpro Electricals Pvt Ltd
d) Sudhir switchgears Pvt Ltd
e) FCG Flameproof Control Gears
11 Cables a) Associated Cables Pvt Lid
b) Cord cable Industries Ltd
c) Delton Cables Limited
d) KEL Industries Limited
e) Polycab wires Pvt Ltd.
a) Emerson Process Management
b) Honeywell
12 Pressure / Temperature Transmitter c) Yokogawa
d) ABB
e) Invensys

13 Isolator/Barriers a) MTL India Pvt Ltd


b) P&F

14 24 V DC power supply unit a) SITOP


b) Phoenix
a) Omron
15 Reply b) OEN
c) Jyoti

16 Cable Gland a) Control switch gear


b) Electromac

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 2 of 3

Page 138 of 142


P.011489
RECOMMENDED VENDOR LIST I-11073
01
c) Commet
d) Baliga
e) Flame Proof Control gear
a) Elemex
17 Terminal BLocks b) Wago
c) Phoenix

Note
1) Above vendor list is indicative recommended vendor list only and any other vendor(s) apart from mentioned above
are acceptable subject to approval by Owner/Owners representative based on past track record. Also for the vendors
of items not covered in above vendor list, but required for project, bidder has to take approval from Owner/Owners
representative for the same.
2) The details of Vendors indicated in this list are based on the information available with TE; Contractor shall verify
capabilities and timely deliveries of material of each vendor for producing the required quantity and delivery.
Consultant does not guarantee any responsibility on the performance of the Vendor; it is the contractor's
responsibility to verify the correct status of vendor and quality control of each party and also to expedite the
material in time. Any delays in deliveries by vendors, shall not be a cause of schedule and cos implication.
3) Contractor may consider additional/alternate “Owner/Owners representative approved Indian vendor” not included
in above list, with prior intimation of Owner/Owner’s Representative approval status, documents /credentials
furnished by vendors in such cases shall solely be the responsibility of the contractor.

Σ Σ Σ

Rev. 0 – 19.06.18 SCADA implementation at CNG station Page 3 of 3

Page 139 of 142


Page 140 of 142
Page 141 of 142
Page 142 of 142
At the helm of the Energy Transition, Tractebel provides a full range of engineering and consulting services
throughout the life cycle of its clients’ projects, including design and project management. As one of the world’s
largest engineering consultancy companies and with more than 150 years of experience, it's our mission to actively
shape the world of tomorrow. With about 4,500 experts and offices in 33 countries, we are able to offer our
customers multidisciplinary solutions in energy, water and infrastructure.

TRACTEBEL ENGINEERING PVT. LTD.


Intec House 37
Institutional Area, Sector 44
122 002 - Gurgaon - INDIA
tractebel-engie.com

Manish CHANDRA
tel. +91 124 471 22 00
fax + 91 124 4698585
manish.chandra@tractebel.engie.com

Potrebbero piacerti anche