Type of Structure : Slab

Clear Span(m) or Width: 2.00


Cear Height(m) : 1.20
length(m) : 3.920
Slab Thickness(m) : 0.20
BAR BENDING SCHEDULE
Length Total Length
Unit
Spacing No.of (m) of Bars Weight
Bar Dia Weight
Mark (mm)
(mm) Bars a b c Total (Kgs)
(Kg/m)
(m)
101 20 220 18 2.82 0.12 0.5 4.06 73.08 2.468 180.3614
102 20 220 18 2.82 2.82 50.76 2.468 125.2757
103 10 200 21 3.84 4.24 97.44 0.617 60.12048
12 150 38 0.72 0.705 0.725 2.15 81.7 0.888 72.5496
12 150 38 0.12 1.34 50.92 0.888 45.21696
10 12 2.82 2.82 33.84 0.617 20.87928
TOTAL WEIGHT IN KG 504.403
TOTAL WEIGHT IN TONS 0.504
Bar Bending
Remarks
Schedule

Main Bars
"
Distribution Bars
Beam
"
"
504.403
0.504
S.No Discription Length Weight Height Quatity M3 Per Cft No of Brick
1 Wall 10 20 3 600 6 8100
Concrete Components Calculation
Structure : Structure No. Nos of
Mixer
Dimension (m) Quantity Ratio machin Cement Sand Cruhs Required
S.No Description Nos Length Width Thick: m3
ft 3
Sand Crush e in Bags m3
ft 3
m3
ft3 Time(h)

1 Lean Concrete 1 10.00 9.70 0.10 9.7 342.604 3.0 6.0 1 42 4.48 158.283 17.93 633.132 1.41
Lean Concrete
3 Under Wings D/S 2 8.00 4.40 0.10 7.04 248.653 3.0 6.0 1 31 3.25 114.878 13.01 459.51 1.02

6 Base Slab 1 10.00 9.50 0.90 85.5 3019.86 2.0 3.0 1 620 43.89 1550.19 87.78 3100.39 20.67

7 Wall: No.01 1 10.00 6.00 0.75 45 1589.4 2.0 3.0 1 326 23.10 815.892 46.20 1631.78 10.88

9 Top Slab 1 10.00 9.50 0.90 85.5 3019.86 2.0 3.0 1 620 43.89 1550.19 87.78 3100.39 20.67

10 Class"A" 2 5.63 4.88 1.00 54.89 1938.80 2.0 3.0 1 398 28.18 995.252 56.36 1990.5 13.27

21 287.633 10159 2038 146.8 5184.69 309.1 10916 67.92


M3 '= L X W X H 4.4814

SAND M3 ' = CEMENT IN BAGE QTY / 28.26 X 3

SAND FT3 = SAND M3 X 35.32

CRSH FT3 = CRSUH M3 X 35.32 bags #VALUE!