HSE-CF-19-R0
Almabani General Contractors
Hazard Identification and Risk Assessment
HSE-NTT- RA-
Description of Activity INSTALLATION OF SANITARY WASTE PIPING SYSTEM Project NTT Project Risk Assessment Ref#
29
Risk Assessment
Risk Assessment
Item Activity/Process Hazard Controls (Residual Risk)
P S R P S R
Page 2 of 9
HSE-CF-19-R0
Almabani General Contractors
Hazard Identification and Risk Assessment
HSE-NTT- RA-
Description of Activity INSTALLATION OF SANITARY WASTE PIPING SYSTEM Project NTT Project Risk Assessment Ref#
29
Risk Assessment
Risk Assessment
Item Activity/Process Hazard Controls (Residual Risk)
P S R P S R
Page 3 of 9
HSE-CF-19-R0
Almabani General Contractors
Hazard Identification and Risk Assessment
HSE-NTT- RA-
Description of Activity INSTALLATION OF SANITARY WASTE PIPING SYSTEM Project NTT Project Risk Assessment Ref#
29
Risk Assessment
Risk Assessment
Item Activity/Process Hazard Controls (Residual Risk)
P S R P S R
Ensure:
o Never stand behind trucks when materials are
Struck by falling objects being tipped from truck
Crush injuries Handling and Storage of pipes and other material Ensure:
• Check bundles of pipes before releasing retaining
frames or straps.
• Pipes are chocked to prevent rolling.
Truck rollover • Do not climb onto pipes.
• Ground is stable
Page 4 of 9
HSE-CF-19-R0
Almabani General Contractors
Hazard Identification and Risk Assessment
HSE-NTT- RA-
Description of Activity INSTALLATION OF SANITARY WASTE PIPING SYSTEM Project NTT Project Risk Assessment Ref#
29
Risk Assessment
Risk Assessment
Item Activity/Process Hazard Controls (Residual Risk)
P S R P S R
Page 5 of 9
HSE-CF-19-R0
Almabani General Contractors
Hazard Identification and Risk Assessment
HSE-NTT- RA-
Description of Activity INSTALLATION OF SANITARY WASTE PIPING SYSTEM Project NTT Project Risk Assessment Ref#
29
Risk Assessment
Risk Assessment
Item Activity/Process Hazard Controls (Residual Risk)
P S R P S R
Drowning The water level must be lowered below the base of the
proposed trench and maintained at that level for the
Excavating
duration of the excavation works.
Trench – Water
10
charged
3 3 9 Operate on flat, level ground 2 2 4
• The removed water must not be discharged into a
ground
Hazardous atmosphere location where it will cause damage to property or
the environment
• The removed water must not be discharged, either
directly or indirectly, into the sewer.
Environmental/ Property Damage
Page 6 of 9
HSE-CF-19-R0
Almabani General Contractors
Hazard Identification and Risk Assessment
HSE-NTT- RA-
Description of Activity INSTALLATION OF SANITARY WASTE PIPING SYSTEM Project NTT Project Risk Assessment Ref#
29
Risk Assessment
Risk Assessment
Item Activity/Process Hazard Controls (Residual Risk)
P S R P S R
Person at risk; Pipe fitter & plumber shall be trained & competent to
Supervisor, Inspector, Pipe fitter, Plumber, perform the testing task.
helpers. o Ensure all connections are adequately secured
o Adequate support where a change in direction or
reduction occurs
Page 8 of 9
HSE-CF-19-R0
Almabani General Contractors
Hazard Identification and Risk Assessment
HSE-NTT- RA-
Description of Activity INSTALLATION OF SANITARY WASTE PIPING SYSTEM Project NTT Project Risk Assessment Ref#
29
Risk Assessment
Risk Assessment
Item Activity/Process Hazard Controls (Residual Risk)
P S R P S R
Page 9 of 9