CITY OF MUTARE

QUICK WINS REPORT FOR WEEK-ENDING 10 AUGUST 2018


Item Project Ward Constituency Total Cost Total %ge for Current Funding Total Economic And Major Possible
Name Of The Amount Used Previous Progress &Implementatio Number Of Social Impact Challenges Solutions
Project To Date week %ge n Agency Jobs
Created
1. Christmas Mutare South, $3 000 000 $2 200 000  80%  80% Mutare City 30 Increased per Turnaround Engaging
Pass to Dangamvura/ capita potable time of RBZ to
Dangamvura Chikanga water. procuremen prioritise
450mm Improved state t allocation
Diameter of sanitation & of forex for
Water hygiene in Forex purchase of
Pipeline. Dangamvura challenges the pipeline
Township. materials.
A total number
of 30 people
have been hired
for project
execution.
2. z Servicing of Dangamvura $1,065,000 $13,091.28  Water:  Water: Mutare City 25 Contributing Shortage of Strict
z 300 85% 85% towards the materials follow-ups
Dangamvura  Sewer:  Sewer: 2018 Zim – on the on suppliers
Area 3 High 53% 53% Asset target of market so that they
Density  Roads:  Roads: 125 000 (Suppliers consider
Residential 30% 30% housing units by failing to other
Stands  Overall:  Overall: 300 fully supply avenues to
make the
(Water, 55% 55% serviced stands. paid-up
materials
Sewer & Increased access materials
available.
Roads) to decent and in time).
affordable
housing.
3. Servicing of Dangamvura $828,000 $91,554.96  Water:  Water: Mutare City 35 Increased access Shortage of Strict
184 99% 99% to decent and materials follow-ups
Dangamvura  Sewer:  Sewer: affordable on the on
Area 16 High 62% 62% housing. market suppliers.
Density  Roads:  Roads: Contributing (Suppliers
Residential 0% 0% towards the failing to
Stands  Overall:  Overall: 2018 Zim–Asset supply
(Water, 54% 54% target of 125 paid-up
Sewer & 000 housing materials
Roads) units by 184 in time).
CITY OF MUTARE
fully serviced
stands.

4. Construction Hobhouse Hobhouse Hobhouse 86% 87% Mutare City Hobhouse Improved Shortage of Strict
of Hob – & School: School: Primary access to materials follow-ups
House & Fernvalley $370 000 $185,000 School: primary on the on
Fern – Valley 30 people education. market suppliers so
Primary Fernvalley Fernvalley Alleviate deficit (Suppliers that they
Schools. School: School: Fernvalley of primary failing to consider
$7 000 $4 200 Primary schools by 25% supply other
School: (ZIM–ASSET paid-up avenues to
12 people. Cluster 4) materials make the
in time). materials
available.
5. Rehabilitatio Dangamvura $7 364.68 $6 628.21 100% Completed Mutare City 7 Improved Work is Work is
n of 225mm Sanitation complete. complete.
sewer river Services
crossing at
Nyamauru.
6. Repair of Hobhouse $18 597 $18 039.09 100% Completed Mutare City 7 Improved Work is Work is
375mm Sanitation complete. complete.
diameter Services
sewer river
crossing
along
Hobhouse
line
7. Surfacing of Chikanga 3, $1 270 723 $611 723 85% 85% Funding Agency: Improving Late Frequent
3.8km Jeff Garikai, Zimta, ZINARA trafficability disburseme follow ups
road &2.5km Bernwin, nts from on ZINARA
Blessing Dangamvura Implementation Zinara for
Makunike Agency: outstanding
road Mutare City & disbursemen
Forit Contractors ts
8. Construction Dangamvura $21 000 $17 000 95% 97% Mutare City 16 Provision of Increased Temporarily
of Area C access to Dora, flows in the suspended
footbridge. Dangamvura river operations
Cemetery and disturbing to remain
31 Brigade. operations within
budget.
CITY OF MUTARE
9. Construction Sakubva River/ $18 000 $12 000 72% 72% Mutare City 16 Increased per Increased Temporarily
of Pipe Chikanga capita potable flows in the suspended
bridge water. river operations
columns for Improved state disturbing to remain
Dangamvura of sanitation & operations within
450mm water hygiene in budget.
main. Dangamvura
Township.