COMMISSIONING
FOR THE EVERYDAY COMMISSIONING AGENT
Learning Objectives
Installation Inspections
Review Submittals , RFI’s, Change Orders, etc.
Equipment Start-Up (Expanded for Building Envelope)
Performance Verification
Performance Testing (Expanded for Building Envelope)
Building Simulation
Correction of Deficiencies
Re-Test of Systems
THE COMMISSIONING PROCESS
• Sub-Contractors
o Demonstrate correct system installation during
functional testing
o Mock up testing
WHY?
The interior and the building enclosure are interdependent.
Envelope Commissioning is different than Forensic investigation.
Which is conducted when a problem is identified usually after occupancy.
BUILDING ENVELOPE COMMISSIONING
What are the Issues?
• Roofs
o Uplift due to high winds, water
leakage
• Walls
o Damage due to improper water
drainage and water proofing
• Doors
o Water leakage
o Ability to open per ADA guidelines
• Windows
o Air and/or Water leakage
BUILDING ENVELOPE COMMISSIONING
10
BUILDING ENVELOPE COMMISSIONING
PREDESIGN
Owners Project Requirements: (Review Only)
- Occupant Requirements
11
BUILDING ENVELOPE COMMISSIONING
SD and DD
Prepare B.O.D. Document: (Completed By Determine Systems Manual Structure:
Subconsultant) (By Subconsultant)
- Description of each system option considered: - A systems manual is developed for each major
- Exterior Enclosure building exterior enclosure system
- Sub-systems
- Materials and Components - Roof
- Skylights
- Interaction of Building Exterior Enclosure with: - Atria
- Heating - Exterior Walls
- Cooling - Windows
- Mechanical and Natural Ventilation - Doors
- Lighting - Sealants & Expansion Joints
- Building Interior - Control Joints
- Flashings
- Reasoning for Final Building Exterior System - Shading Devices
- Curtain Walls
- Inter-relationships - Plaza Decks
- Stiffness/deflection of support structure - Planters
- Daylighting vs. Artificial Lighting - Below-Grade
- Impact on Mechanical Systems - Balconies
- Floors
- Operational Assumptions - Others
- Calculations
12
BUILDING ENVELOPE COMMISSIONING
CONSTRUCTION DOCUMENTS
Cx Process Requirements for Const. Doc. Phase
13
BUILDING ENVELOPE COMMISSIONING
CONSTRUCTION
QA/QC Plan & Site Specific Testing Plan: (By Pre-Construction Cx Process Meeting:
Subconsultant)
- Special Issues relative to sequencing and early
- Verify QA/QC Requirements: installation of equipment should be discussed
- Field Testing
- Manufacturing Performance Testing - Pre-Construction Conference (Pre-Bid Conference)
- Submittal & Shop Drawings
- Laboratory testing for Custom Systems
- Sample Construction
- Formal Mock-up Testing Submittal
Observe & Witness Testing: (By Subconsultant)
- Inspection
- Pre Construction/installation meeting
- AHSRAE Guideline 0-2005 listed items
- Participants Required for Testing
- The Cx Authority is to verify that tests were
performed
- Cx Team will develop a range of test verification
procedures both QA/QC
- The Cx is to re-verify test standards and
- Components
performance criteria to be consistent and appropriate
- System/Assembly
for the building enclosure being tested.
- Intersystem
- Owners Project Requirements
- Verify test Pass/Fail
- Random Sampling
14
BUILDING ENVELOPE COMMISSIONING
OCCUPANCY AND OPERATIONS
Training For Building Envelope: (By Subconsultant)
members
Measurement/Verification Specialist
Facilities Management
Construction Manager
Mechanical Engineer
Electrical Contractor
Vibrtation Specialist
A - Approve
Accoustic Specialist
Structural Engineer
General Contractor
R - Review
Test Contractor
I - Input From
Occupants
U - Use
Architect
Notes
Pre -Design
6.2.6 Cx Specification A R P R I I I I
Commissioning - Focused Design
6.2.7 A R U U U U U P U I I I I I
Reviews
Issues Log & Report A P U U U U U I U I I I I
Acceptance & Commissioning
6.3, 6.4 A P U U U U U I I I I I I I
Process Report
Construction
Pre-Bid Conference Commissioning
7.2.2 R P I I U I I I
Briefing
7.2.4 Owner's Project Requirements A U P U U U I I I
Commissioning Plan & Inspection
7.2.5 R R I P U U U U U I I I
Checklists Update
Pre-Construction Commissioning
7.2.6 A P I I U U U U U I I I
Process Briefing
7.2.7 Submittal Review Comments R R U P U U U U U I I I
• Damage to
waterproofing
membrane at
footing
Thermal Bridging
ENVELOPE TESTING
Note heat losses around the window frames. These metal frames often
conduct a substantial amount of heat because metal is an excellent
conductor of heat and cold, and the frames typically do not have as
much R-value as high efficiency glazing, or insulated wall sections.
ENVELOPE TESTING
IN SUMMARY:
• Envelope testing a key commissioning element
• Required to verify:
o Construction quality
o Design intent is met
• Teamwork is critical
o All parties must play their role
o Follow contractual lines
o Must be adequately specified
• Hidden issues are understood earlier 31
ENVELOPE TESTING
32
ENVELOPE TESTING
• National Museum
for African
American History
and Culture
• 15-acre site
• Last museum to be
placed on the
National Mall
• $500 Million
Project
• Seeking LEED
Gold
CASE STUDY: MSBA
REPRESENTATIVE PROJECTS:
• Avery Elementary School
• Freeman Elementary
• Maynard Middle School
• Wayland High School
• Hudson Middle School
• Willard Elementary School
CASE STUDY: MSBA
DESCRIPTION
Among other initiatives it has adopted
envelope commissioning as an important
step towards Quality assurance in their
Green Repair program.
OBSERVATIONS
This provides a systematic process of quality assurance to public schools
envelopes.
Before the program was initiated local school districts were less inclined to
perform envelope commissioning.
CxA was engaged in different stages of the project. In some cases only final
field inspection was possible. In other full design review was possible.
Envelope Cxing is still not well understood and roles and responsibilities not
yet firmed.