- ASSEMBLY AND INSTALLATION -


Most Important! This framework can be assembled to suit a 100 mm finished wall thickness (75 mm
studwork) or a 125 mm finished wall thickness (100 mm studwork)…HOWEVER…the supplied jamb
kit is specific to either 100 mm or 125 mm BUT NOT BOTH ! so you must estabilish if your jamb kit
is for a 100 mm or 125 mm and assemble the frame accordingly (see sticker on jamb box or delivery
document).
For 100 mm finished walls start at page 2 and for 125 mm finished walls start at page 5

METAL FRAMEWORK-KIT CONTENTS

a
c
f
e h
g
b
d i m l
125 mm FINISHED WALL-BRACKETS
x y

a Central vertical f Metal door post m Pack of screws: 4,2 x 9,5 (9 pcs) - 3,9 x 19 (55 pcs)
b Pocket horizontals (12 pcs) g Bracers (2 pcs)
c Rear vertical h Polistyrene spacers 125 mm FINISHED WALL-BRACKETS
d Pocket header i Pocket-to-floor brackets x Rear vertical (12 pcs) (c) brackets 125 mm
e Top beam with track l Door mounting kit y Pocket header brackets 125 mm

Tools required
Drill Tape measure

Saw
Bits PZ2 -PH2 Gloves
N° 13 spanner

Electric Hammer
screwdriver Sprit level
Plumb line

1
100 mm Finished wall thickness assembly instructions

1 2

b
e

c
b
g a

b
ol
invite
rf le
f t
nlo
ef
o
o
a vhiemd
b F
P
in i s

g h
22

i 78 4
10

l
viteo
rflien
loto
fn
o
emde
FiPn
aisvhi
FRAME MUST BE INSTALLED AT FINISHED FLOOR LEVEL, USE PACKING IF NECESSARY

2
100 mm Finished wall thickness assembly instructions

a c
d

STEP 1
a Assemble the pocket header (d)
to the central verticals (a)
and rear verticals (c)
using 4.2 x 9.5 mm screws (m).

a a c

STEP 2
Assemble both sides of the
b pocket using the horizontals b
(b) locking them into position
securely on central verticals (a)
and rear verticals (c) at the
pre-determined positions.
Make sure they are firmly
locked in place.

h
b

h STEP 3
Insert the polistyrene spacers (h)
in between the horizontals (b).

e d
d

e
a

STEP 4
Insert the top beam with track (e)
e d into the pocket header (d) using
the bayonet system.
When it “clicks” into place,
secure with 4.2 x 9.5 mm screws.

3
100 mm Finished wall thickness assembly instructions
e

e f

STEP 5
Insert the metal tongues at the
e end of the top beam (e) into
f f
the slots at the top of the
metal doorpost.
Bend the metal tongues using
the hammer.

g f a
a

g
STEP 6
Bend the ends of the bracers g
b (g) backwards through 90° and
locate in the positions on vertical
(a) and doorpost (f).

STEP 7
Insert the assembled framework
into your prepared studwork
(metal or wood) making sure it
is installed at finished floor level,
plumb and perfectly horizontal.

f c
STEP 8
Attach the frame to the studwork
by screwing through the vertical
e (c), metal doorpost (f) and top
beam with track (e) (use ONLY
the larger holes so that the screw
head goes through the track and
locates the top beam).
Screw the internal pocket-to-floor
brackets to the floor.

4
125 mm Finished wall thickness assembly instructions

1 2

y
d
c x

x
b
e
x
b
a
x
b
g
x
b
ivteol
ilne
f x de fnlot
oorf
m
aisvhi
e
b FiPn

g h
22

i 10
4
78

l
voe
ofrinleit
lo
fto
eedn
FPian
visihm
FRAME MUST BE INSTALLED AT FINISHED FLOOR LEVEL, USE PACKING IF NECESSARY

5
125 mm Finished wall thickness assembly instructions

z
STEP 1
z
Unscrew and turn through 90°
the brackets (z) holding the
central verticals (a) together.
a Screw into place.
a This widens the verticals
for 125 mm.

STEP 2
Attach the pocket header
brackets 125 (y)
y to the pocket header (d)
using 4.2 x 9.5 mm screws.

y a

a d
y
STEP 3

a Insert the central verticals (a)


into the pocket header brackets
(y) on the pocket header (d)
using 4.2 x 9.5 mm screws.

x
c

c x

STEP 4
c
Split the rear vertical brackets
(x) and fix into their pre-cut
positions on the rear vertical (c)
using a hammer to locate.

6
125 mm Finished wall thickness assembly instructions

d
d
a
c

c
STEP 5
Assemble the pocket header (d)
to the rear vertical (c)
using 4.2 x 9.5 mm screws.

d
a a c

b
x STEP 6
b
Assemble both sides of the
pocket using the horizontals (b)
locking them at the
c pre-determined positions.
Make sure they are firmly
located in place (a) and (x).

h c b

STEP 7
Insert the polistyrene spacers (h)
in between the horizontals (b).

e d
d

a STEP 8
Insert the top beam with track (e)
e d into the pocket header (d) using
the bayonet system.
When it “clicks” into place,
secure with 4.2 x 9.5 mm screws.

7
125 mm Finished wall thickness assembly instructions
e

e f

STEP 9
Insert the metal tongues at the
e end of the top beam (e) into
f f
the slots at the top of the
metal doorpost.
Bend the metal tongues using
the hammer.

a
g
f a

g
STEP 10
b Bend the ends of the bracers g
(g) backwards through 90° and
locate in the positions on vertical
(a) and doorpost (f).

STEP 11
Insert the assembled framework
into your prepared studwork
(metal or wood) making sure it
is installed at finished floor level,
plumb and perfectly horizontal.

f c
STEP 12
Attach the frame to the studwork
by screwing through the vertical
e (c), metal doorpost (f) and top
beam with track (e) ( use ONLY
the larger holes so that the screw
head goes through the track and
locates the top beam).
Screw the internal pocket-to-floor
brackets to the floor.

8
FIXING THE PLASTERBOARD TO THE FRAME
The plasterboard can be attached at any time after the frame is installed

PHASE 1
The frame is made to accept 12,5 mm plasterboard
on each side. Using a 2 mm drill, drill appropriate
holes through the plasterboard and Pocket
horizontals (b) (2 to each side as shown)

Temporary polistyrene spacers


to be removed after screwing
on plasterboard

PHASE 2
Using ONLY the black 3,5 x 19 mm screws
provided, attached the plasterboard to the frame.
If you use any other screws you will be responsible
for any scratches on the door!

INSTALLING THE DOOR


DOOR MOUNTING KIT 1 - Contents

1 8

2
3 9

4
6 10
5 11
6

7 12

1 Runners (2 pcs) 5 Bolt (2 pcs) 9 Lock washer (1 pc)


2 Runner nut (2 pcs) M8 6 Screws (8 pcs) 10 Screw 6 x 30 (1 pc)
3 Lock nut (2 pcs) M8 7 Door bracket (2 pcs) 11 Guide with posts (1 pc)
4 Washer (2 pcs) 8 Adjustable stop (1 pc) 12 Self-drilling screws (2 pcs)

9
INSTALING THE DOOR - PHASE:

1 6

Single door Double doors

Install the door brackets (7)


on the top of the doors using
the screws (8) as shown for
single and double doors.

2 3

1
11

2 3
75

4
10
0

Only if you have a 100 mm finished wall thickness then


you need to break off the ends of the guide base (11).
Assemble both runners (1) using a runner nuts (2), Insert the posts into the holes on the guide and attach
lock nuts (3), washers (4) and bolts (5) as shown to the frame at the pocket entrance at finished floor
and insert into the overhead track at the doorpost end. level using the self-drilling screws (12).

4 5

Eclisse sliding door


furniture can be
supplied as:

• bathroom lock;
Cut the Under Door Profile to • lock and key;
10 mm longer than the door width. • simple recessed discs
Route a channel 10,3 x 17 mm into
the bottom of the door from the For the bathroom
rear of the door to the 5 mm from lock and lock and key
the front edge of the door. Using a the door should be
small amount of silicon insert the prepared as shown.
under door profile into the channel.
It should protude 15 mm at
the rear of the door.

10
INSTALING THE DOOR - PHASE:

6 the rear of the track.


This can be adjusted as required
even after the plasterboard is
fixed thanks
to the extractable track.
The door can be adjusted to
slide completely back into the
pokcket however, should you
Hook the door onto the runners decide to do this we cannot be
using the door brackets fixed to held responsible for any damage
the top of the door. Insert the to persons or property as a
under door profile over the door consequence of this adjustment.
guide and slide into the pocket. Position the second stop at the
There is one adjustable stop front of the track and adjust as
already installed 70 mm from required.

INSTALLING THE JAMBS AND DOORPOST


KIT CONTENTS

C A Top horizontal jambs

A B Vertical pocket jambs (2 pcs)

C Wooden door post


B
s Brushes (3 pcs)
s g Rubber bumpers (2 pcs)
g
s

g A2
A1

 Jambs for A
C
s
B single door
A
B

s
A2
s
g
B
A1
C

s
s B
A B
A
B

Jambs for
double doors  B

Cut the doorpost (C)


and the vertical
jambs (B) to the exact
dimension to fit the frame

11
603002900
INSTALING THE JAMBS AND DOORPOST - PHASE:

07/2007 © ECLISSE, all rights reserved.-The use, filing and total or partial reproduction, using any mechanical or electronic means, of texts, drawings and pictures contained in this publication is strictly prohibited, unless specifically approved in writing by ECLISSE.
g FOR SINGLE DOORS ONLY
Place the wooden door post (C) into position
C and drill 4 pairs of holes equidistant along
g its length through the recess for the rubber
bumpers and through the metal door post.
Countersink these holes and screw the
wooden doorpost into place.
Detach the rubber bumpers and insert each
length into the recesses.

B B

Trim the lower position of the vertical


pocket jamb (B) to accommodate the
guide and attach to both sides of the pocket
entrance using 4/5 blobs of silicon.

The top horizontal jamb (A) needs to be


cut to size. Note the rebate on both ends
is used to match the top of each of the
vertical pocket jambs (B).
Fix into place using silicon or if preferred
pin or screw into place.
A