CONTRATO MODIFICATORIO

Proyecto: CONST. 6 SISTEMAS DE AGUA EN SANTA ROSA (SANTA ROSA) Fecha : 14/002/2012
Supervisor : EDGAR MORAN FLORES Empresa: CAMINO Moneda : US BS

Proyecto: FPS-07-00003415 CONSTRUCCION SIST. AGUA POTABLE EL COLORADO (SANTA ROSA)


CONTRATO VOLUMENES DE OBRA
VOLUMENES DE OBRA CONTRACTUALMENTE AUTORIZADOS MONTOS
MODIFICATORIO CERTIFICADOS
% EJEC.
PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANTIDAD PRECIO ANT. ACTUAL ACUMUL. ANTER. ACTUAL ACUMU.
UNITARIO TOTAL

Módulo: MPTS1029 MEDIDAS DE MITIGACION


93CC100 SEÑALIZACION GLB 1.00 3,818.31 3,818.31 1.00 3,818.31 0.85 0.85 3245.56 0.00 3245.56 0.00%
Módulo: MSCZ0007 RED DE DISTRIBUCION
02FB005 EXCAVACION M3 480.65 21.50 10,333.98 #REF! #REF! 351.36 351.36 7554.24 0.00 7554.24 0.00%
40DA035 PROV. TENDIDO TUBERIA PVC 2 PULG. - CLASE 9 ML 44.66 35.88 1,602.40 36.00 1,291.68 36.00 36.00 1291.68 0.00 1291.68 0.00%
40DB100 PROV. TENDIDO TUBERIA PVC 1 PULG. - CLASE 1 ML 1,264.54 28.05 35,470.35 828.00 23,225.40 704.65 704.65 19765.43 0.00 19765.43 0.00%
40IA001 PRUEBA HIDRAULICA-TUBERIA HASTA 4 PULG. ML 1,433.64 1.95 2,795.60 976.00 1,903.20 852.65 852.65 1662.67 0.00 1662.67 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 169.10 1.57 265.49 148.00 232.36 148.00 148.00 232.36 0.00 232.36 0.00%
41AD005 PROVISION Y COLOCADO DE VALVULA CHEKC BR. PZA 1.00 690.62 690.62 1.00 690.62 1.00 1.00 690.62 0.00 690.62 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 480.65 54.45 26,171.39 #REF! #REF! 350.78 350.78 19099.89 0.00 19099.89 0.00%
93BB056 CAMARA DE VALVULAS PZA 2.00 1,258.29 2,516.58 2.00 2,516.58 1.00 1.00 1258.29 0.00 1258.29 0.00%
93BC1007 ACCESORIOS DE RED DE DISTRIBUCCION GLB 1.00 10,335.95 10,335.95 1.00 10,335.95 1.00 1.00 10335.95 0.00 10335.95 0.00%
93BC647 REPLANTEO DE TUBERIAS ML 1,433.64 5.37 7,698.65 976.00 5,241.12 1,433.64 1433.64 7698.65 0.00 7698.65 0.00%
93FA017 LIMPIEZA GENERAL GLB 1.00 3,454.21 3,454.21 1.00 3,454.21 0.00 0.00 0.00 0.00 0.00 0.00%
93FB124 VALVULA CORTINA FV D=2 P/DESAGUE PROV. Y PZA 1.00 299.06 299.06 1.00 299.06 1.00 1.00 299.06 0.00 299.06 0.00%
93FB242 PROV. Y TENDIDO TUBERIA PVC 11/2¨ C-9 ML 124.44 31.00 3,857.64 112.00 3,472.00 112.00 112.00 3472.00 0.00 3472.00 0.00%
93GB178 CONEXIÓN DOMICILIARIA 1/2 INCL EXCAVACION PZA 45.00 916.48 41,241.60 31.00 28,410.88 25.00 25.00 22912.00 0.00 22912.00 0.00%
96DC132 CARPETA DE Hº POBRE M3 0.90 1,056.75 951.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 147,684.60 #REF!
Módulo: MSCZ0009 CASETA DE BOMBEO
93BB0302 PROV. CASETA PARA BOMBEO GLB 1.00 19,357.49 19,357.49 1.00 19,357.49 0.85 0.85 1.70 16453.87 16453.87 32907.73 85.00%
Módulo: MSCZ0053 TANQUE ELEVADO
02FB005 EXCAVACION M3 23.30 51.33 1,195.99 32.74 1,680.54 23.30 23.30 1195.99 0.00 1195.99 0.00%
06BA011 HORMIGON ARMADO LOSA DE FONDO 1:2:3 (H2O M3 3.75 2,861.87 10,732.01 #REF! #REF! 3.20 3.20 9157.98 0.00 9157.98 0.00%
06BA014 HORMIGON ARMADO PARA MUROS ESTRUCTURAS M3 8.95 2,861.87 25,613.74 #REF! #REF! 5.00 5.00 14309.35 0.00 14309.35 0.00%
31AD002 ESCALERAS CON GUARDACUERPOS ML 14.80 834.81 12,355.19 14.80 12,355.19 12.00 12.00 10017.72 0.00 10017.72 0.00%
31BD003 ESCALERA METALICA ML 1.80 411.01 739.82 1.80 739.82 1.00 1.00 411.01 0.00 411.01 0.00%
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 473.21 473.21 1.00 473.21 1.00 1.00 473.21 0.00 473.21 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 20.80 54.45 1,132.56 #REF! #REF! 6.00 6.00 326.70 0.00 326.70 0.00%
93AF018 CAMARA DE PASO DIRECTO BY-PASS PZA 1.00 863.23 863.23 1.00 863.23 1.00 1.00 863.23 0.00 863.23 0.00%
93BC0294 BARANDADO METALICO ML 14.80 367.11 5,433.23 14.80 5,433.23 10.00 10.00 3671.10 0.00 3671.10 0.00%
93DB105 HORMIGON ARMADO LOSA DE TAPA TANQUE DE M3 2.48 2,861.87 7,097.44 #REF! #REF! 1.00 1.00 2861.87 0.00 2861.87 0.00%
93FB028 INSTALACION DE FAENAS GLB 1.00 7,912.12 7,912.12 1.00 7,912.12 1.00 1.00 7912.12 0.00 7912.12 0.00%
93GB013 PRUEBA DE ESTANQUEIDAD Y DE DESINFECCION M3 20.00 31.10 622.00 20.00 622.00 0.00 0.00 0.00 0.00 0.00 0.00%
93PV002 REPLANTEO GLB 1.00 579.69 579.69 1.00 579.69 1.00 1.00 579.69 0.00 579.69 0.00%
96BC014 HºAºCOLUMNAS (TANQUE ELEVADO) M3 3.80 2,861.87 10,875.11 #REF! #REF! 3.80 3.80 10875.11 0.00 10875.11 0.00%
96BC015 HºAºVIGA (TANQUE ELEVADO) M3 7.28 2,754.85 20,055.31 #REF! #REF! 4.75 4.75 13085.54 0.00 13085.54 0.00%
96BC028 ACC TANQUE DE ALMACENANMIENTO D=2¨ GLB 1.00 3,787.12 3,787.12 1.00 3,787.12 0.00 0.00 0.00 0.00 0.00 0.00%
96CA010 ZAPATAS DE HºAº M3 2.50 2,108.00 5,270.00 #REF! #REF! 2.50 2.50 5270.00 0.00 5270.00 0.00%
96DC132 CARPETA DE HºPOBRE M3 1.30 1,056.75 1,373.78 1.30 1,373.78 1.30 1.30 1373.78 0.00 1373.78 0.00%
Costo Modulo 116,111.55 #REF!
ITEM NUEVO
REVOQUE INTERIOR IMPERMEABILIZANTE CON SIK M2 114.16 0.00 45.56 5,201.13 0.00%
PROV. Y COLOCADO DE MEDIDOR DE 1/2" PZA 580.73 0.00 36.00 20,906.28 0.00 0.00 0.00 0.00 #DIV/0!

Módulo: MSCZ0149 EQUIPAMIENTO


93BB5000 PROV. Y COL DE BOMBA SUMERGIBLE DE 2HP Y GLB 1.00 22,919.56 22,919.56 1.00 22,919.56 0.85 0.85 1.70 19481.63 19481.63 38963.25 85.00%
Módulo: MSCZ0641 TAREAS PRELIMINARES
90AA001 PROV. Y COLOCACION DE LETRERO DE OBRAS S/ PZA 1.00 977.83 977.83 1.00 977.83 1.00 1.00 977.83 0.00 977.83 0.00%
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 16,764.66 16,764.66 1.00 16,764.66 0.50 0.50 8382.33 0.00 8382.33 0.00%
93GB188 PROV. Y COLOCACION DE PLACA DE ENTREGA FP PZA 1.00 1,079.23 1,079.23 1.00 1,079.23 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 18,821.72 18,821.72
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIAS ML 90.17 5.45 491.43 90.17 491.43 85.00 85.00 463.25 0.00 463.25 0.00%
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 90.17 1.95 175.83 90.17 175.83 0.00 0.00 0.00 0.00 0.00 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 90.17 1.57 141.57 90.17 141.57 0.00 0.00 0.00 0.00 0.00 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 3.71 54.45 202.01 3.71 202.01 0.00 0.00 0.00 0.00 0.00 0.00%
93BC693 PROV. Y COLOC. TUBERIA FG 2¨ CON COPLAS ML 90.17 139.84 12,609.37 100.00 13,984.00 75.00 75.00 10488.00 0.00 10488.00 0.00%
93BC961 ACCESORIOS DE IMPULSION GLB 1.00 4,717.73 4,717.73 1.00 4,717.73 0.00 0.00 0.00 0.00 0.00 0.00%
93GG035 EXCAVACION MANUAL M3 5.19 51.33 266.40 3.00 153.99 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 18,604.34 19,866.56 238,149.69 35,935.49 274,085.19 10.35%
Costo Total 347,317.57 #REF!
Proyecto: FPS-07-00003416 CONSTRUCCION SIST. AGUA POTABLE RANCHO GRANDE (SANTA ROSA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANTIDAD PRECIO ANT. ACTUAL ACUMUL. ANTER. ACTUAL ACUMU. % EJEC.
UNITARIO TOTAL
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 3,818.31 3,818.31 1.00 3,818.31 0.90 0.90 3436.48 0.00 3436.48 0.00%
Módulo: MSCZ0007 RED DE DISTRIBUCION
02FB005 EXCAVACION M3 142.94 21.50 3,073.21 #REF! #REF! 142.94 142.94 3073.21 0.00 3073.21 0.00%
40DA035 PROV. TENDIDO TUBERIA PVC 2 PULG. - CLASE 9 ML 43.30 35.88 1,553.60 18.00 645.84 30.00 30.00 1076.40 0.00 1076.40 0.00%
40DB100 PROV. TENDIDO TUBERIA PVC 1 PULG. - CLASE 1 ML 70.25 28.05 1,970.51 186.90 5,242.55 70.25 70.25 1970.51 0.00 1970.51 0.00%
40IA001 PRUEBA HIDRAULICA-TUBERIA HASTA 4 PULG. ML 385.51 1.95 751.74 579.90 1,130.81 385.51 385.51 751.74 0.00 751.74 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 302.35 1.57 474.69 393.00 617.01 302.35 302.35 474.69 0.00 474.69 0.00%
41AD005 PROVISION Y COLOCADO DE VALVULA CHEKC BR. PZA 1.00 690.62 690.62 1.00 690.62 1.00 1.00 690.62 0.00 690.62 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 142.94 54.45 7,783.08 #REF! #REF! 142.94 142.94 7783.28 0.00 7783.28 0.00%
93BB056 CAMARA DE VALVULAS PZA 3.00 1,258.29 3,774.87 3.00 3,774.87 2.00 2.00 2516.58 0.00 2516.58 0.00%
93BC1007 ACCESORIOS DE RED DE DISTRIBUCCION GLB 1.00 10,335.95 10,335.95 1.00 10,335.95 1.00 1.00 10335.95 0.00 10335.95 0.00%
93BC647 REPLANTEO DE TUBERIAS ML 385.51 5.37 2,070.19 385.51 2,070.19 385.51 385.51 2070.19 0.00 2070.19 0.00%
93FA017 LIMPIEZA GENERAL GLB 1.00 3,454.21 3,454.21 1.00 3,454.21 0.00 0.00 0.00 0.00 0.00 0.00%
93FB124 VALVULA CORTINA FV D=2 P/DESAGUE PROV. Y PZA 1.00 299.06 299.06 1.00 299.06 1.00 1.00 299.06 0.00 299.06 0.00%
93FB242 PROV. Y TENDIDO TUBERIA PVC 11/2¨ C-9 ML 259.05 31.00 8,030.55 375.00 11,625.00 259.05 259.05 8030.55 0.00 8030.55 0.00%
93GB178 CONEXIÓN DOMICILIARIA 1/2 INCL EXCAVACION PZA 25.00 916.48 22,912.00 31.00 28,410.88 25.00 25.00 22912.00 0.00 22912.00 0.00%
96DC132 CARPETA DE Hº POBRE M3 0.20 1,056.75 211.35 0.20 211.35 0.20 0.20 211.35 0.00 211.35 0.00%
Costo Modulo 67,385.63 #REF!
Módulo: MSCZ0009 CASETA DE BOMBEO
93BB0302 PROV. CASETA PARA BOMBEO GLB 1.00 19,357.49 19,357.49 1.00 19,357.49 0.85 0.85 16453.87 0.00 16453.87 0.00%
Módulo: MSCZ0053 TANQUE ELEVADO
02FB005 EXCAVACION M3 23.30 51.33 1,195.99 23.30 1,195.99 23.30 23.30 1195.99 0.00 1195.99 0.00%
06BA011 HORMIGON ARMADO LOSA DE FONDO 1:2:3 (H2O M3 2.45 2,861.87 7,011.58 #REF! #REF! 2.45 2.45 7011.58 0.00 7011.58 0.00%
06BA014 HORMIGON ARMADO PARA MUROS ESTRUCTURAS M3 3.88 2,861.87 11,104.06 #REF! #REF! 3.88 3.88 11104.06 0.00 11104.06 0.00%
31AD002 ESCALERAS CON GUARDACUERPOS ML 14.80 834.81 12,355.19 14.80 12,355.19 11.00 11.00 9182.91 0.00 9182.91 0.00%
31BD003 ESCALERA METALICA ML 1.80 411.01 739.82 1.80 739.82 1.00 1.00 411.01 0.00 411.01 0.00%
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 473.21 473.21 1.00 473.21 1.00 1.00 473.21 0.00 473.21 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 20.64 54.45 1,123.85 8.81 479.70 6.00 6.00 326.70 0.00 326.70 0.00%
93AF018 CAMARA DE PASO DIRECTO BY-PASS PZA 1.00 863.23 863.23 1.00 863.23 1.00 1.00 863.23 0.00 863.23 0.00%
93BC0294 BARANDADO METALICO ML 14.80 367.11 5,433.23 14.80 5,433.23 13.00 13.00 4772.43 0.00 4772.43 0.00%
93DB105 HORMIGON ARMADO LOSA DE TAPA TANQUE DE M3 1.44 2,861.87 4,121.09 #REF! #REF! 0.40 0.40 1144.75 0.00 1144.75 0.00%
93FB028 INSTALACION DE FAENAS GLB 1.00 7,912.12 7,912.12 1.00 7,912.12 1.00 1.00 7912.12 0.00 7912.12 0.00%
93GB013 PRUEBA DE ESTANQUEIDAD Y DE DESINFECCION M3 15.00 31.10 466.50 15.00 466.50 5.00 5.00 155.50 0.00 155.50 0.00%
93PV002 REPLANTEO GLB 1.00 579.69 579.69 1.00 579.69 1.00 1.00 579.69 0.00 579.69 0.00%
96BC014 HºAºCOLUMNAS (TANQUE ELEVADO) M3 2.64 2,861.87 7,555.34 #REF! #REF! 2.64 2.64 7555.34 0.00 7555.34 0.00%
96BC015 HºAºVIGA (TANQUE ELEVADO) M3 3.54 2,754.85 9,752.17 #REF! #REF! 3.45 3.45 9504.23 0.00 9504.23 0.00%
96BC028 ACC TANQUE DE ALMACENANMIENTO D=2¨ GLB 1.00 3,787.12 3,787.12 1.00 3,787.12 1.00 1.00 3787.12 0.00 3787.12 0.00%
96CA010 ZAPATAS DE HºAº M3 5.70 2,108.00 12,015.60 2.25 4,743.00 4.00 4.00 8432.00 0.00 8432.00 0.00%
96DC132 CARPETA DE HºPOBRE M3 0.67 1,056.75 708.02 0.67 708.02 0.67 0.67 708.02 0.00 708.02 0.00%
Costo Modulo 87,197.81 #REF!
ITEM NUEVO
REVOQUE INTERIOR IMPERMEABILIZANTE CON SIK M2 114.16 0.00 37.22 4,249.04 0.00%
LETRERO DE OBRA SOBRE MURO DE LADRILLO PZA 5,510.79 0.00 1.00 5,510.79 0.00%
PROV. TENDIDO TUBERIA PVC 1/2 PULG. - CLASE ML 13.59 0.00 0.00 0.00 #DIV/0!

Módulo: MSCZ0641 TAREAS PRELIMINARES


90AA001 PROV. Y COLOCACION DE LETRERO DE OBRAS S/ PZA 1.00 977.83 977.83 1.00 977.83 1.00 1.00 977.83 0.00 977.83 0.00%
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 16,764.66 16,764.66 1.00 16,764.66 0.50 0.50 8382.33 0.00 8382.33 0.00%
93GB188 PROV. Y COLOCACION DE PLACA DE ENTREGA FP PZA 1.00 1,079.23 1,079.23 1.00 1,079.23 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 18,821.72 18,821.72
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIAS ML 90.17 5.45 491.43 90.17 491.43 85.00 85.00 463.25 0.00 463.25 0.00%
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 90.17 1.95 175.83 90.17 175.83 0.00 0.00 0.00 0.00 0.00 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 90.17 1.57 141.57 90.17 141.57 0.00 0.00 0.00 0.00 0.00 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 3.71 54.45 202.01 3.71 202.01 0.00 0.00 0.00 0.00 0.00 0.00%
93BC693 PROV. Y COLOC. TUBERIA FG 2¨ CON COPLAS ML 90.17 139.84 12,609.37 90.17 12,609.37 75.00 75.00 10488.00 0.00 10488.00 0.00%
93BC961 ACCESORIOS DE IMPULSION GLB 1.00 4,717.73 4,717.73 1.00 4,717.73 1.00 1.00 4717.73 0.00 4717.73 0.00%
93GG035 EXCAVACION MANUAL M3 5.19 51.33 266.40 5.19 266.40 1.00 1.00 51.33 0.00 51.33 0.00%
Costo Modulo 18,604.34 18,604.34 182,286.84 0.00 182,286.84 0.00%
Costo Total 215,185.30 #REF!
Proyecto: FPS-07-00003416 CONSTRUCCION SIST. AGUA POTABLE COPACABANA (SANTA ROSA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANTIDAD PRECIO ANT. ACTUAL ACUMUL. ANTER. ACTUAL ACUMU. % EJEC.
UNITARIO TOTAL
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 3,818.31 3,818.31 1.00 3,818.31 0.80 0.80 3054.65 0.00 3054.65 0.00%
Módulo: MSCZ0007 RED DE DISTRIBUCION
02FB005 EXCAVACION M3 710.22 21.50 15,269.73 #REF! #REF! 392.36 392.36 8435.74 0.00 8435.74 0.00%
40DA035 PROV. TENDIDO TUBERIA PVC 2 PULG. - CLASE 9 ML 37.80 35.88 1,356.26 30.00 1,076.40 30.00 30.00 1076.40 0.00 1076.40 0.00%
40DB100 PROV. TENDIDO TUBERIA PVC 1 PULG. - CLASE 1 ML 725.59 28.05 20,352.80 985.90 27,654.50 725.59 725.59 20352.80 0.00 20352.80 0.00%
40IA001 PRUEBA HIDRAULICA-TUBERIA HASTA 4 PULG. ML 1,044.90 1.95 2,037.56 1,210.30 2,360.09 949.59 949.59 1851.70 0.00 1851.70 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 319.31 1.57 501.32 224.40 352.31 224.00 224.00 351.68 0.00 351.68 0.00%
41AD005 PROVISION Y COLOCADO DE VALVULA CHEKC BR. PZA 1.00 690.62 690.62 1.00 690.62 1.00 1.00 690.62 0.00 690.62 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 710.22 54.45 38,671.48 #REF! #REF! 391.65 391.65 21325.34 0.00 21325.34 0.00%
93BB056 CAMARA DE VALVULAS PZA 2.00 1,258.29 2,516.58 2.00 2,516.58 2.00 2.00 2516.58 0.00 2516.58 0.00%
93BC1007 ACCESORIOS DE RED DE DISTRIBUCCION GLB 1.00 10,335.95 10,335.95 1.00 10,335.95 1.00 1.00 10335.95 0.00 10335.95 0.00%
93BC647 REPLANTEO DE TUBERIAS ML 1,044.90 5.37 5,611.11 1,044.90 5,611.11 1,044.90 1044.90 5611.11 0.00 5611.11 0.00%
93FA017 LIMPIEZA GENERAL GLB 1.00 3,454.21 3,454.21 1.00 3,454.21 0.00 0.00 0.00 0.00 0.00 0.00%
93FB124 VALVULA CORTINA FV D=2 P/DESAGUE PROV. Y PZA 1.00 299.06 299.06 1.00 299.06 1.00 1.00 299.06 0.00 299.06 0.00%
93FB242 PROV. Y TENDIDO TUBERIA PVC 11/2¨ C-9 ML 281.51 31.00 8,726.81 194.40 6,026.40 194.40 194.40 6026.40 0.00 6026.40 0.00%
93GB178 CONEXIÓN DOMICILIARIA 1/2 INCL EXCAVACION PZA 49.00 916.48 44,907.52 49.00 44,907.52 25.00 25.00 22912.00 0.00 22912.00 0.00%
96DC132 CARPETA DE Hº POBRE M3 0.50 1,056.75 528.38 0.50 528.38 0.50 0.50 528.38 0.00 528.38 0.00%
Costo Modulo 155,259.39 #REF!
Módulo: MSCZ0009 CASETA DE BOMBEO
93BB0302 PROV. CASETA PARA BOMBEO GLB 1.00 19,357.49 19,357.49 1.00 19,357.49 0.85 0.85 16453.87 0.00 16453.87 0.00%
Módulo: MSCZ0053 TANQUE ELEVADO
02FB005 EXCAVACION M3 23.30 51.33 1,195.99 32.74 1,680.54 23.30 23.30 1195.99 0.00 1195.99 0.00%
06BA011 HORMIGON ARMADO LOSA DE FONDO 1:2:3 (H2O M3 3.75 2,861.87 10,732.01 #REF! #REF! 3.75 3.75 10732.01 0.00 10732.01 0.00%
06BA014 HORMIGON ARMADO PARA MUROS ESTRUCTURAS M3 8.95 2,861.87 25,613.74 5.04 14,423.82 2.84 2.84 8127.71 0.00 8127.71 0.00%
31AD002 ESCALERAS CON GUARDACUERPOS ML 14.80 834.81 12,355.19 14.80 12,355.19 12.00 12.00 10017.72 0.00 10017.72 0.00%
31BD003 ESCALERA METALICA ML 1.80 411.01 739.82 1.80 739.82 1.00 1.00 411.01 0.00 411.01 0.00%
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 473.21 473.21 1.00 473.21 1.00 1.00 473.21 0.00 473.21 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 20.80 54.45 1,132.56 #REF! #REF! 8.74 8.74 475.89 0.00 475.89 0.00%
93AF018 CAMARA DE PASO DIRECTO BY-PASS PZA 1.00 863.23 863.23 1.00 863.23 1.00 1.00 863.23 0.00 863.23 0.00%
93BC0294 BARANDADO METALICO ML 14.80 367.11 5,433.23 14.80 5,433.23 10.00 10.00 3671.10 0.00 3671.10 0.00%
93DB105 HORMIGON ARMADO LOSA DE TAPA TANQUE DE M3 2.48 2,861.87 7,097.44 #REF! #REF! 1.00 1.00 2861.87 0.00 2861.87 0.00%
93FB028 INSTALACION DE FAENAS GLB 1.00 7,912.12 7,912.12 1.00 7,912.12 1.00 1.00 7912.12 0.00 7912.12 0.00%
93GB013 PRUEBA DE ESTANQUEIDAD Y DE DESINFECCION M3 20.00 31.10 622.00 20.00 622.00 10.00 10.00 311.00 0.00 311.00 0.00%
93PV002 REPLANTEO GLB 1.00 579.69 579.69 1.00 579.69 1.00 1.00 579.69 0.00 579.69 0.00%
96BC014 HºAºCOLUMNAS (TANQUE ELEVADO) M3 3.80 2,861.87 10,875.11 4.13 11,819.52 3.80 3.80 10875.11 0.00 10875.11 0.00%
96BC015 HºAºVIGA (TANQUE ELEVADO) M3 7.28 2,754.85 20,055.31 4.75 13,085.54 7.28 7.28 20055.31 0.00 20055.31 0.00%
96BC028 ACC TANQUE DE ALMACENANMIENTO D=2¨ GLB 1.00 3,787.12 3,787.12 1.00 3,787.12 1.00 1.00 3787.12 0.00 3787.12 0.00%
96CA010 ZAPATAS DE HºAº M3 2.50 2,108.00 5,270.00 #REF! #REF! 2.50 2.50 5270.00 0.00 5270.00 0.00%
96DC132 CARPETA DE HºPOBRE M3 1.30 1,056.75 1,373.78 0.20 211.35 0.20 0.20 211.35 0.00 211.35 0.00%
Costo Modulo 116,111.55 #REF!
ITEM NUEVO
REVOQUE INTERIOR IMPERMEABILIZANTE CON SIK M2 114.16 0.00 45.56 5,201.13 0.00%
PROV. TENDIDO TUBERIA PVC 1/2 PULG. - CLASE ML 13.59 0.00 0.00 0.00 #DIV/0!
PROV. Y COLOC. DE GENERADOR DE 5,5 KVA SK PZA 7,899.94 0.00 1.00 7,899.94 0.00%

Módulo: MSCZ0149 EQUIPAMIENTO


93BB5000 PROV. Y COL DE BOMBA SUMERGIBLE DE 2HP Y GLB 1.00 24,141.00 24,141.00 1.00 24,141.00 0.85 0.85 20519.85 0.00 20519.85 0.00%
Módulo: MSCZ0641 TAREAS PRELIMINARES
90AA001 PROV. Y COLOCACION DE LETRERO DE OBRAS S/ PZA 1.00 977.83 977.83 1.00 977.83 1.00 1.00 977.83 0.00 977.83 0.00%
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 16,764.66 16,764.66 1.00 16,764.66 0.50 0.50 8382.33 0.00 8382.33 0.00%
93GB188 PROV. Y COLOCACION DE PLACA DE ENTREGA FP PZA 1.00 1,079.23 1,079.23 1.00 1,079.23 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 18,821.72 18,821.72
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIAS ML 90.17 5.45 491.43 90.17 491.43 85.00 85.00 463.25 0.00 463.25 0.00%
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 90.17 1.95 175.83 90.17 175.83 0.00 0.00 0.00 0.00 0.00 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 90.17 1.57 141.57 90.17 141.57 0.00 0.00 0.00 0.00 0.00 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 3.71 54.45 202.01 3.71 202.01 0.00 0.00 0.00 0.00 0.00 0.00%
93BC693 PROV. Y COLOC. TUBERIA FG 2¨ CON COPLAS ML 90.17 139.84 12,609.37 90.17 12,609.37 75.00 75.00 10488.00 0.00 10488.00 0.00%
93BC961 ACCESORIOS DE IMPULSION GLB 1.00 4,717.73 4,717.73 1.00 4,717.73 1.00 1.00 4717.73 0.00 4717.73 0.00%
93GG035 EXCAVACION MANUAL M3 5.19 51.33 266.40 5.19 266.40 1.00 1.00 51.33 0.00 51.33 0.00%
Costo Modulo 18,604.34 18,604.34 255,254.03 0.00 255,254.03 0.00%
Costo Total 356,113.80 #REF!
Proyecto: FPS-07-00003418 CONSTRUCCION SIST. AGUA POTABLE 4 DE MARZO (SANTA ROSA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANTIDAD PRECIO ANT. ACTUAL ACUMUL. ANTER. ACTUAL ACUMU. % EJEC.
UNITARIO TOTAL
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 3,818.31 3,818.31 1.00 3,818.31 1.00 1.00 3818.31 0.00 3818.31 0.00%
Módulo: MSCZ0007 RED DE DISTRIBUCION 0.00
02FB005 EXCAVACION M3 1,366.89 21.50 29,388.14 931.63 20,030.05 920.05 920.05 19781.08 0.00 19781.08 0.00%
40DA035 PROV. TENDIDO TUBERIA PVC 2 PULG. - CLASE 9 ML 32.10 35.88 1,151.75 12.00 430.56 25.00 25.00 897.00 0.00 897.00 0.00%
40DB100 PROV. TENDIDO TUBERIA PVC 1 PULG. - CLASE 1 ML 3,533.47 28.05 99,113.83 2,384.70 66,890.84 2,409.41 2409.41 67583.95 0.00 67583.95 0.00%
40IA001 PRUEBA HIDRAULICA-TUBERIA HASTA 4 PULG. ML 151.99 1.95 296.38 2,676.00 5,218.20 151.99 151.99 296.38 0.00 296.38 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 151.99 1.57 238.62 291.30 457.34 151.99 151.99 238.62 0.00 238.62 0.00%
41AD005 PROVISION Y COLOCADO DE VALVULA CHEKC BR. PZA 1.00 690.62 690.62 1.00 690.62 1.00 1.00 690.62 0.00 690.62 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 1,366.89 54.45 74,427.16 939.70 51,166.74 939.70 939.70 51166.74 0.00 51166.74 0.00%
93BB056 CAMARA DE VALVULAS PZA 2.00 1,258.29 2,516.58 2.00 2,516.58 2.00 2.00 2516.58 0.00 2516.58 0.00%
93BC1007 ACCESORIOS DE RED DE DISTRIBUCCION GLB 1.00 10,335.95 10,335.95 1.00 10,335.95 1.00 1.00 10335.95 0.00 10335.95 0.00%
93BC647 REPLANTEO DE TUBERIAS ML 3,685.41 5.37 19,790.65 2,702.15 14,510.55 2,702.15 2702.15 14510.55 0.00 14510.55 0.00%
93FA017 LIMPIEZA GENERAL GLB 1.00 3,454.21 3,454.21 1.00 3,454.21 0.00 0.00 0.00 0.00 0.00 0.00%
93FB124 VALVULA CORTINA FV D=2 P/DESAGUE PROV. Y PZA 1.00 299.06 299.06 1.00 299.06 1.00 1.00 299.06 0.00 299.06 0.00%
93FB242 PROV. Y TENDIDO TUBERIA PVC 11/2¨ C-9 ML 119.89 31.00 3,716.59 279.30 8,658.30 119.89 119.89 3716.59 0.00 3716.59 0.00%
93GB178 CONEXIÓN DOMICILIARIA 1/2 INCL EXCAVACION PZA 55.00 916.48 50,406.40 76.00 69,652.48 55.00 55.00 50406.40 0.00 50406.40 0.00%
96DC132 CARPETA DE Hº POBRE M3 0.90 1,056.75 951.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 296,777.02 254,311.48
Módulo: MSCZ0009 CASETA DE BOMBEO
93BB0302 PROV. CASETA PARA BOMBEO GLB 1.00 19,357.49 19,357.49 1.00 19,357.49 0.92 0.92 17808.89 0.00 17808.89 0.00%
Módulo: MSCZ0053 TANQUE ELEVADO
02FB005 EXCAVACION M3 23.30 51.33 1,195.99 32.74 1,680.54 23.30 23.30 1195.99 0.00 1195.99 0.00%
06BA011 HORMIGON ARMADO LOSA DE FONDO 1:2:3 (H2O M3 3.75 2,861.87 10,732.01 #REF! #REF! 3.75 3.75 10732.01 0.00 10732.01 0.00%
06BA014 HORMIGON ARMADO PARA MUROS ESTRUCTURAS M3 8.95 2,861.87 25,613.74 #REF! #REF! 5.04 5.04 14423.82 0.00 14423.82 0.00%
31AD002 ESCALERAS CON GUARDACUERPOS ML 14.80 834.81 12,355.19 14.80 12,355.19 13.00 13.00 10852.53 0.00 10852.53 0.00%
31BD003 ESCALERA METALICA ML 1.80 411.01 739.82 1.80 739.82 1.80 1.80 739.82 0.00 739.82 0.00%
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 473.21 473.21 1.00 473.21 1.00 1.00 473.21 0.00 473.21 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 20.80 54.45 1,132.56 #REF! #REF! 8.74 8.74 475.89 0.00 475.89 0.00%
93AF018 CAMARA DE PASO DIRECTO BY-PASS PZA 1.00 863.23 863.23 1.00 863.23 1.00 1.00 863.23 0.00 863.23 0.00%
93BC0294 BARANDADO METALICO ML 14.80 367.11 5,433.23 14.80 5,433.23 14.00 14.00 5139.54 0.00 5139.54 0.00%
93DB105 HORMIGON ARMADO LOSA DE TAPA TANQUE DE M3 2.48 2,861.87 7,097.44 #REF! #REF! 1.00 1.00 2861.87 0.00 2861.87 0.00%
93FB028 INSTALACION DE FAENAS GLB 1.00 7,912.12 7,912.12 1.00 7,912.12 1.00 1.00 7912.12 0.00 7912.12 0.00%
93GB013 PRUEBA DE ESTANQUEIDAD Y DE DESINFECCION M3 20.00 31.10 622.00 20.00 622.00 15.00 15.00 466.50 0.00 466.50 0.00%
93PV002 REPLANTEO GLB 1.00 579.69 579.69 1.00 579.69 1.00 1.00 579.69 0.00 579.69 0.00%
96BC014 HºAºCOLUMNAS (TANQUE ELEVADO) M3 3.80 2,861.87 10,875.11 #REF! #REF! 3.80 3.80 10875.11 0.00 10875.11 0.00%
96BC015 HºAºVIGA (TANQUE ELEVADO) M3 7.28 2,754.85 20,055.31 #REF! #REF! 4.75 4.75 13085.54 0.00 13085.54 0.00%
96BC028 ACC TANQUE DE ALMACENANMIENTO D=2¨ GLB 1.00 3,787.12 3,787.12 1.00 3,787.12 0.80 0.80 3029.70 0.00 3029.70 0.00%
96CA010 ZAPATAS DE HºAº M3 2.50 2,108.00 5,270.00 #REF! #REF! 2.50 2.50 5270.00 0.00 5270.00 0.00%
96DC132 CARPETA DE HºPOBRE M3 1.30 1,056.75 1,373.78 1.10 1,162.43 1.10 1.10 1162.43 0.00 1162.43 0.00%
Costo Modulo 116,111.55 #REF!
ITEM NUEVO
REVOQUE INTERIOR IMPERMEABILIZANTE CON SIK M2 114.16 0.00 45.56 5,201.13 0.00%
PROV. TENDIDO TUBERIA PVC 1/2 PULG. - CLASE ML 13.59 0.00 90.00 1,223.10 0.00%
PROV. Y COLOC. DE GENERADOR DE 5,5 KVA SK PZA 7,899.94 0.00 1.00 7,899.94 0.00%

Módulo: MSCZ0149 EQUIPAMIENTO


93BB5000 PROV. Y COL DE BOMBA SUMERGIBLE DE 2HP Y GLB 1.00 24,141.00 24,141.00 1.00 24,141.00 0.85 0.85 20519.85 0.00 20519.85 0.00%
Módulo: MSCZ0641 TAREAS PRELIMINARES
90AA001 PROV. Y COLOCACION DE LETRERO DE OBRAS S/ PZA 1.00 977.83 977.83 1.00 977.83 1.00 1.00 977.83 0.00 977.83 0.00%
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 16,764.66 16,764.66 1.00 16,764.66 0.50 0.50 8382.33 0.00 8382.33 0.00%
93GB188 PROV. Y COLOCACION DE PLACA DE ENTREGA FP PZA 1.00 1,079.23 1,079.23 1.00 1,079.23 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 18,821.72 18,821.72
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIAS ML 90.17 5.45 491.43 90.17 491.43 85.00 85.00 463.25 0.00 463.25 0.00%
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 90.17 1.95 175.83 90.17 175.83 0.00 0.00 0.00 0.00 0.00 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 90.17 1.57 141.57 90.17 141.57 0.00 0.00 0.00 0.00 0.00 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 3.71 54.45 202.01 3.71 202.01 0.00 0.00 0.00 0.00 0.00 0.00%
93BC693 PROV. Y COLOC. TUBERIA FG 2¨ CON COPLAS ML 90.17 139.84 12,609.37 90.17 12,609.37 75.00 75.00 10488.00 0.00 10488.00 0.00%
93BC961 ACCESORIOS DE IMPULSION GLB 1.00 4,717.73 4,717.73 1.00 4,717.73 1.00 1.00 4717.73 0.00 4717.73 0.00%
93GG035 EXCAVACION MANUAL M3 5.19 51.33 266.40 5.19 266.40 1.00 1.00 51.33 0.00 51.33 0.00%
Costo Modulo 18,604.34 18,604.34 379,806.02 0.00 379,806.02 0.00%
Costo Total 497,631.43 #REF!
Proyecto: FPS-07-00003419 CONSTRUCCION SIST. AGUA POTABLE MONTE RICO (SANTA ROSA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANTIDAD PRECIO ANT. ACTUAL ACUMUL. ANTER. ACTUAL ACUMU. % EJEC.
UNITARIO TOTAL
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 3,818.31 3,818.31 1.00 3,818.31 1.00 1.00 3818.31 0.00 3818.31 0.00%
Módulo: MSCZ0007 RED DE DISTRIBUCION
02FB005 EXCAVACION M3 835.30 21.50 17,958.95 573.37 12,327.46 573.37 573.37 12327.46 0.00 12327.46 0.00%
40DA035 PROV. TENDIDO TUBERIA PVC 2 PULG. - CLASE 9 ML 91.98 35.88 3,300.24 95.00 3,408.60 91.98 91.98 3300.24 0.00 3300.24 0.00%
40DB100 PROV. TENDIDO TUBERIA PVC 1 PULG. - CLASE 1 ML 1,287.28 28.05 36,108.20 1,171.60 32,863.38 1,126.87 1126.87 31608.70 0.00 31608.70 0.00%
40IA001 PRUEBA HIDRAULICA-TUBERIA HASTA 4 PULG. ML 1,491.62 1.95 2,908.66 1,588.00 3,096.60 1,491.62 1491.62 2908.66 0.00 2908.66 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 204.33 1.57 320.80 416.40 653.75 204.33 204.33 320.80 0.00 320.80 0.00%
41AD005 PROVISION Y COLOCADO DE VALVULA CHEKC BR. PZA 1.00 690.62 690.62 1.00 690.62 1.00 1.00 690.62 0.00 690.62 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 835.30 54.45 45,482.09 571.99 31,144.86 571.99 571.99 31144.86 0.00 31144.86 0.00%
93BB056 CAMARA DE VALVULAS PZA 2.00 1,258.29 2,516.58 2.00 2,516.58 1.00 1.00 1258.29 0.00 1258.29 0.00%
93BC1007 ACCESORIOS DE RED DE DISTRIBUCCION GLB 1.00 10,335.95 10,335.95 1.00 10,335.95 1.00 1.00 10335.95 0.00 10335.95 0.00%
93BC647 REPLANTEO DE TUBERIAS ML 1,491.62 5.37 8,010.00 1,437.00 7,716.69 1,437.00 1437.00 7716.69 0.00 7716.69 0.00%
93FA017 LIMPIEZA GENERAL GLB 1.00 3,454.21 3,454.21 1.00 3,454.21 0.00 0.00 0.00 0.00 0.00 0.00%
93FB124 VALVULA CORTINA FV D=2 P/DESAGUE PROV. Y PZA 1.00 299.06 299.06 1.00 299.06 1.00 1.00 299.06 0.00 299.06 0.00%
93FB242 PROV. Y TENDIDO TUBERIA PVC 11/2¨ C-9 ML 112.35 31.00 3,482.85 321.40 9,963.40 112.35 112.35 3482.85 0.00 3482.85 0.00%
93GB178 CONEXIÓN DOMICILIARIA 1/2 INCL EXCAVACION PZA 49.00 916.48 44,907.52 68.00 62,320.64 49.00 49.00 44907.52 0.00 44907.52 0.00%
96DC132 CARPETA DE Hº POBRE M3 0.90 1,056.75 951.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 180,726.81 180,791.80
Módulo: MSCZ0009 CASETA DE BOMBEO
93BB0302 PROV. CASETA PARA BOMBEO GLB 1.00 19,357.49 19,357.49 1.00 19,357.49 0.92 0.92 17808.89 0.00 17808.89 0.00%
Módulo: MSCZ0053 TANQUE ELEVADO
02FB005 EXCAVACION M3 23.30 51.33 1,195.99 32.74 1,680.54 23.30 23.30 1195.99 0.00 1195.99 0.00%
06BA011 HORMIGON ARMADO LOSA DE FONDO 1:2:3 (H2O M3 3.75 2,861.87 10,732.01 #REF! #REF! 3.75 3.75 10732.01 0.00 10732.01 0.00%
06BA014 HORMIGON ARMADO PARA MUROS ESTRUCTURAS M3 8.95 2,861.87 25,613.74 #REF! #REF! 5.04 5.04 14423.82 0.00 14423.82 0.00%
31AD002 ESCALERAS CON GUARDACUERPOS ML 14.80 834.81 12,355.19 14.80 12,355.19 12.00 12.00 10017.72 0.00 10017.72 0.00%
31BD003 ESCALERA METALICA ML 1.80 411.01 739.82 1.80 739.82 1.80 1.80 739.82 0.00 739.82 0.00%
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 473.21 473.21 1.00 473.21 1.00 1.00 473.21 0.00 473.21 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 20.80 54.45 1,132.56 #REF! #REF! 6.01 6.01 327.24 0.00 327.24 0.00%
93AF018 CAMARA DE PASO DIRECTO BY-PASS PZA 1.00 863.23 863.23 1.00 863.23 1.00 1.00 863.23 0.00 863.23 0.00%
93BC0294 BARANDADO METALICO ML 14.80 367.11 5,433.23 14.80 5,433.23 12.00 12.00 4405.32 0.00 4405.32 0.00%
93DB105 HORMIGON ARMADO LOSA DE TAPA TANQUE DE M3 2.48 2,861.87 7,097.44 #REF! #REF! 1.20 1.20 3434.24 0.00 3434.24 0.00%
93FB028 INSTALACION DE FAENAS GLB 1.00 7,912.12 7,912.12 1.00 7,912.12 1.00 1.00 7912.12 0.00 7912.12 0.00%
93GB013 PRUEBA DE ESTANQUEIDAD Y DE DESINFECCION M3 20.00 31.10 622.00 20.00 622.00 14.00 14.00 435.40 0.00 435.40 0.00%
93PV002 REPLANTEO GLB 1.00 579.69 579.69 1.00 579.69 1.00 1.00 579.69 0.00 579.69 0.00%
96BC014 HºAºCOLUMNAS (TANQUE ELEVADO) M3 3.80 2,861.87 10,875.11 #REF! #REF! 3.80 3.80 10875.11 0.00 10875.11 0.00%
96BC015 HºAºVIGA (TANQUE ELEVADO) M3 7.28 2,754.85 20,055.31 #REF! #REF! 4.75 4.75 13085.54 0.00 13085.54 0.00%
96BC028 ACC TANQUE DE ALMACENANMIENTO D=2¨ GLB 1.00 3,787.12 3,787.12 1.00 3,787.12 1.00 1.00 3787.12 0.00 3787.12 0.00%
96CA010 ZAPATAS DE HºAº M3 2.50 2,108.00 5,270.00 #REF! #REF! 2.50 2.50 5270.00 0.00 5270.00 0.00%
96DC132 CARPETA DE HºPOBRE M3 1.30 1,056.75 1,373.78 1.00 1,056.75 1.00 1.00 1056.75 0.00 1056.75 0.00%
Costo Modulo 116,111.55 #REF!
ITEM NUEVO
REVOQUE INTERIOR IMPERMEABILIZANTE CON SIK M2 114.16 0.00 45.56 5,201.13 0.00%
PROV. TENDIDO TUBERIA PVC 1/2 PULG. - CLASE ML 13.59 0.00 30.00 407.70 0.00%

Módulo: MSCZ0149 EQUIPAMIENTO


93BB5000 PROV. Y COL DE BOMBA SUMERGIBLE DE 2HP Y GLB 1.00 22,918.56 22,918.56 1.00 22,918.56 0.85 0.85 19480.78 0.00 19480.78 0.00%
Módulo: MSCZ0641 TAREAS PRELIMINARES
90AA001 PROV. Y COLOCACION DE LETRERO DE OBRAS S/ PZA 1.00 977.83 977.83 1.00 977.83 1.00 1.00 977.83 0.00 977.83 0.00%
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 16,764.66 16,764.66 1.00 16,764.66 0.50 0.50 8382.33 0.00 8382.33 0.00%
93GB188 PROV. Y COLOCACION DE PLACA DE ENTREGA FP PZA 1.00 1,079.23 1,079.23 1.00 1,079.23 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 18,821.72 18,821.72
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIAS ML 90.17 5.45 491.43 90.17 491.43 85.00 85.00 463.25 0.00 463.25 0.00%
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 90.17 1.95 175.83 90.17 175.83 0.00 0.00 0.00 0.00 0.00 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 90.17 1.57 141.57 90.17 141.57 0.00 0.00 0.00 0.00 0.00 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 3.71 54.45 202.01 3.71 202.01 0.00 0.00 0.00 0.00 0.00 0.00%
93BC693 PROV. Y COLOC. TUBERIA FG 2¨ CON COPLAS ML 90.17 139.84 12,609.37 90.17 12,609.37 75.00 75.00 10488.00 0.00 10488.00 0.00%
93BC961 ACCESORIOS DE IMPULSION GLB 1.00 4,717.73 4,717.73 1.00 4,717.73 1.00 1.00 4717.73 0.00 4717.73 0.00%
93GG035 EXCAVACION MANUAL M3 5.19 51.33 266.40 5.19 266.40 1.00 1.00 51.33 0.00 51.33 0.00%
Costo Modulo 18,604.34 18,604.34 306,104.48 0.00 306,104.48 0.00%
Costo Total 380,358.78 #REF!
Proyecto: FPS-07-00003418 CONSTRUCCION SIST. AGUA POTABLE NUEVO HORIZONTE (SANTA ROSA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANTIDAD PRECIO ANT. ACTUAL ACUMUL. ANTER. ACTUAL ACUMU. % EJEC.
UNITARIO TOTAL
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 3,818.31 3,818.31 1.00 3,818.31 1.00 1.00 3818.31 0.00 3818.31 0.00%
Módulo: MSCZ0007 RED DE DISTRIBUCION
02FB005 EXCAVACION M3 599.26 21.50 12,884.09 #REF! #REF! 599.26 599.26 12884.09 0.00 12884.09 0.00%
40DA035 PROV. TENDIDO TUBERIA PVC 2 PULG. - CLASE 9 ML 36.41 111.83 4,071.73 192.00 21,471.36 36.41 36.41 4071.73 0.00 4071.73 0.00%
40DB100 PROV. TENDIDO TUBERIA PVC 1 PULG. - CLASE 1 ML 37.80 35.88 1,356.26 0.00 0.00 37.80 37.80 1356.26 0.00 1356.26 0.00%
40IA001 PRUEBA HIDRAULICA-TUBERIA HASTA 4 PULG. ML 2,032.36 1.95 3,963.10 2,032.00 3,962.40 1,600.00 1600.00 3120.00 0.00 3120.00 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 2,032.36 1.57 3,190.81 3,041.00 4,774.37 1,600.00 1600.00 2512.00 0.00 2512.00 0.00%
41AD005 PROVISION Y COLOCADO DE VALVULA CHEKC BR. PZA 1.00 690.62 690.62 1.00 690.62 1.00 1.00 690.62 0.00 690.62 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 599.26 54.45 32,629.71 #REF! #REF! 599.26 599.26 32629.71 0.00 32629.71 0.00%
93BB056 CAMARA DE VALVULAS PZA 2.00 1,258.29 2,516.58 2.00 2,516.58 1.00 1.00 1258.29 0.00 1258.29 0.00%
93BC1007 ACCESORIOS DE RED DE DISTRIBUCCION GLB 1.00 10,335.95 10,335.95 1.00 10,335.95 0.86 0.86 8888.92 0.00 8888.92 0.00%
93BC647 REPLANTEO DE TUBERIAS ML 2,032.36 5.37 10,913.77 2,870.00 15,411.90 2,032.36 2032.36 10913.77 0.00 10913.77 0.00%
93FA017 LIMPIEZA GENERAL GLB 1.00 3,454.21 3,454.21 1.00 3,454.21 0.00 0.00 0.00 0.00 0.00 0.00%
93FB124 VALVULA CORTINA FV D=2 P/DESAGUE PROV. Y PZA 1.00 299.06 299.06 1.00 299.06 0.00 0.00 0.00 0.00 0.00 0.00%
93FB242 PROV. Y TENDIDO TUBERIA PVC 11/2¨ C-9 ML 2,032.36 31.00 63,003.16 2,849.00 88,319.00 2,032.36 2032.36 63003.16 0.00 63003.16 0.00%
93GB178 CONEXIÓN DOMICILIARIA1 1/2 INCL EXCAVACION PZA 21.00 916.48 19,246.08 30.00 27,494.40 21.00 21.00 19246.08 0.00 19246.08 0.00%
96DC132 CARPETA DE Hº POBRE M3 0.90 1,056.75 951.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 169,506.21 #REF!
Módulo: MSCZ0009 CASETA DE BOMBEO
93BB0302 PROV. CASETA PARA BOMBEO GLB 1.00 19,357.49 19,357.49 1.00 19,357.49 0.88 0.88 17034.59 0.00 17034.59 0.00%
Módulo: MSCZ0053 TANQUE ELEVADO
02FB005 EXCAVACION M3 23.30 51.33 1,195.99 32.74 1,680.54 23.30 23.30 1195.99 0.00 1195.99 0.00%
06BA011 HORMIGON ARMADO LOSA DE FONDO 1:2:3 (H2O M3 3.75 2,861.87 10,732.01 #REF! #REF! 3.60 3.60 10302.73 0.00 10302.73 0.00%
06BA014 HORMIGON ARMADO PARA MUROS ESTRUCTURAS M3 8.95 2,861.87 25,613.74 #REF! #REF! 5.00 5.00 14309.35 0.00 14309.35 0.00%
31AD002 ESCALERAS CON GUARDACUERPOS ML 14.80 834.81 12,355.19 14.80 12,355.19 12.00 12.00 10017.72 0.00 10017.72 0.00%
31BD003 ESCALERA METALICA ML 1.80 411.01 739.82 1.80 739.82 1.00 1.00 411.01 0.00 411.01 0.00%
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 473.21 473.21 1.00 473.21 1.00 1.00 473.21 0.00 473.21 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 20.80 54.45 1,132.56 8.74 475.89 18.16 18.16 988.81 0.00 988.81 0.00%
93AF018 CAMARA DE PASO DIRECTO BY-PASS PZA 1.00 863.23 863.23 1.00 863.23 1.00 1.00 863.23 0.00 863.23 0.00%
93BC0294 BARANDADO METALICO ML 14.80 367.11 5,433.23 14.80 5,433.23 14.00 14.00 5139.54 0.00 5139.54 0.00%
93DB105 HORMIGON ARMADO LOSA DE TAPA TANQUE DE M3 2.48 2,861.87 7,097.44 #REF! #REF! 1.00 1.00 2861.87 0.00 2861.87 0.00%
93FB028 INSTALACION DE FAENAS GLB 1.00 7,912.12 7,912.12 1.00 7,912.12 1.00 1.00 7912.12 0.00 7912.12 0.00%
93GB013 PRUEBA DE ESTANQUEIDAD Y DE DESINFECCION M3 20.00 31.10 622.00 20.00 622.00 10.00 10.00 311.00 0.00 311.00 0.00%
93PV002 REPLANTEO GLB 1.00 579.69 579.69 1.00 579.69 1.00 1.00 579.69 0.00 579.69 0.00%
96BC014 HºAºCOLUMNAS (TANQUE ELEVADO) M3 3.80 2,861.87 10,875.11 #REF! #REF! 3.80 3.80 10875.11 0.00 10875.11 0.00%
96BC015 HºAºVIGA (TANQUE ELEVADO) M3 7.28 2,754.85 20,055.31 #REF! #REF! 4.75 4.75 13084.74 0.00 13084.74 0.00%
96BC028 ACC TANQUE DE ALMACENANMIENTO D=2¨ GLB 1.00 3,787.12 3,787.12 1.00 3,787.12 1.00 1.00 3787.12 0.00 3787.12 0.00%
96CA010 ZAPATAS DE HºAº M3 2.50 2,108.00 5,270.00 #REF! #REF! 2.50 2.50 5270.00 0.00 5270.00 0.00%
96DC132 CARPETA DE HºPOBRE M3 1.30 1,056.75 1,373.78 1.00 1,056.75 1.00 1.00 1056.75 0.00 1056.75 0.00%
Costo Modulo 116,111.55 #REF!
ITEM NUEVO
REVOQUE INTERIOR IMPERMEABILIZANTE CON SIK M2 114.16 0.00 45.56 5,201.13 0.00%
PROV. TENDIDO TUBERIA PVC 1/2 PULG. - CLASE ML 0.00 0.00 0.00 0.00 #DIV/0!
PROV. Y COLOCADO DE MEDIDOR PZA 580.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0!

Módulo: MSCZ0149 EQUIPAMIENTO


93BB5000 PROV. Y COL DE BOMBA SUMERGIBLE DE 2HP Y GLB 1.00 24,141.00 24,141.00 1.00 24,141.00 0.80 0.80 19312.80 0.00 19312.80 0.00%
Módulo: MSCZ0641 TAREAS PRELIMINARES
90AA001 PROV. Y COLOCACION DE LETRERO DE OBRAS S/ PZA 1.00 977.83 977.83 1.00 977.83 1.00 1.00 977.83 0.00 977.83 0.00%
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 16,764.66 16,764.66 1.00 16,764.66 0.50 0.50 8382.33 0.00 8382.33 0.00%
93GB188 PROV. Y COLOCACION DE PLACA DE ENTREGA FP PZA 1.00 1,079.23 1,079.23 1.00 1,079.23 0.00 0.00 0.00 0.00 0.00 0.00%
Costo Modulo 18,821.72 18,821.72
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIAS ML 90.17 5.45 491.43 90.17 491.43 85.00 85.00 463.25 0.00 463.25 0.00%
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 90.17 1.95 175.83 90.17 175.83 0.00 0.00 0.00 0.00 0.00 0.00%
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 90.17 1.57 141.57 90.17 141.57 0.00 0.00 0.00 0.00 0.00 0.00%
93AD562 RELLENO COMUN COMPACTADO M3 3.71 54.45 202.01 3.71 202.01 0.00 0.00 0.00 0.00 0.00 0.00%
93BC693 PROV. Y COLOC. TUBERIA FG 2¨ CON COPLAS ML 90.17 139.84 12,609.37 90.17 12,609.37 75.00 75.00 10488.00 0.00 10488.00 0.00%
93BC961 ACCESORIOS DE IMPULSION GLB 1.00 4,717.73 4,717.73 1.00 4,717.73 1.00 1.00 4717.73 0.00 4717.73 0.00%
93GG035 EXCAVACION MANUAL M3 5.19 51.33 266.40 5.19 266.40 1.00 1.00 51.33 0.00 51.33 0.00%
Costo Modulo 18,604.34 18,604.34 315,260.79 0.00 315,260.79 0.00%
Costo Total 370,360.62 #REF! ### 35,935.49 1,712,797.35 1.66%
Costo Total proyecto 2,166,967.50 #REF!
#REF!

%
PRECIO %
INCREME % SOBRE
PRECIO CONTRATO Planilla % DE
COMUNIDAD NTO/ PROYECT AV. N°4 ACUMULADO
TOTAL MODIFICAT SOBRE Anteriores AVANCE
DECREM O
ORIO O.C.
ENTO
EL COLORADO 347,317.57 #REF! #REF! 16.03% #REF! 238,149.69 35935.49 274085.19 78.91%
RANCHO GRANDE 215,185.30 #REF! #REF! 9.93% #REF! 182,286.84 0.00 182286.84 84.71%
COPACABANA 356,113.80 #REF! #REF! 16.43% #REF! 255,254.03 0.00 255254.03 71.68%
4 DE MARZO 497,631.43 #REF! #REF! 22.96% #REF! 379,806.02 0.00 379806.02 76.32%
MONTE RICO 380,358.78 #REF! #REF! 17.55% #REF! 306,104.48 0.00 306104.48 80.48%
NUEVO HORIZONTE 370,360.62 #REF! #REF! 17.09% #REF! 315,260.79 0.00 315260.79 85.12%
COSTO PROYECTO 2,166,967.50 #REF! #REF! 100.00% #REF! ### 35,935.49 1,712,797.35 79.04%
79.04%

Unidad volumen precio unitario

Excavacion m3 26.42 21.50 568.03


tuberia de 2" ml 25 111.83 2795.75
Tuberia de 1" ml 213.00 35.88
relleno m3 47.30 54.45 2575.485

3143.515
se incremento, debido a que se planillo en demasia, especialmentes en 4 de marzo, lo que espero compensar a su tuberia de FºGºy otras cosa, puesto que modfique la excavacion y relleno de
ANALICELO INGENIERO AHÍ ESTA EL CONTRATO MODIFICATORIO Cantidad que se incrementara para la localidad de 4 de marzo en 214 metros de tuberia en 1"
Cantidades que se tiene que reducir en el contato modificatorio y planilla
V
O
L
U
M
E
N
E
CONTRATO MODIFICATORIO Nº1 S

Proyecto: CONST. 7 SISTEMAS DE AGUA EN COTOCA (COTOCA) Fecha : 25/03/2012 D


Supervisor : EDGAR MORAN FLORES Empresa: CITECO Moneda : US BS E

Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA) O
B
VOLUMENES DE OBRA CONTRACTUALMENTE AUTORIZADOS CONTRATO MODIFICATORIO R
A
PRECIO PRECIO INCREMENTOS DECREMENTOS
PRECIO A
ACTIVIDAD DESCRIPCION UNID CANTIDAD UNITARIO TOTAL CANTIDAD
Bs Bs CANT. P. PARCIAL CANT. P. PARCIAL TOTAL C
N
E
T
CONSTRUCCION NUEVA .R
Módulo: MPTS1029 MEDIDAS DE MITIGACION
T
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
###
I
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
F
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
I
Costo Modulo 8,903.77 8,903.77
C
Módulo: MSCZ0009 CASETA DE BOMBEO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 25.00 186.75
###
A
02FB005 EXCAVACION M3 3.80 95.68 363.58 3.80 363.58
###
D
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
### O
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 3.80 14,677.58
### S
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 0.75 1,592.10
###
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 23.00 2,927.21
###
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 28.00 3,536.40
###
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 18.00 7,611.12
###
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.80 1,178.55
###
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 2.00 919.10
###
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
###
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
###
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 52.00 2,016.56
###
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
###
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
###
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 15.20 222.83
###
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 0.55 2,015.87
###
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
###
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 44.00 2,770.68
###
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 24.00 3,564.00
###
Costo Modulo 50,496.44 50,496.44
Módulo: MSCZ0053 TANQUE ELEVADO
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 26.00 2,487.68
###
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 17.50 10,097.33
###
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 2.00 921.54
###
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
###
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
###
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
###
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
###
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
###
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 15.00 347.10
###
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
###
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
###
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 7.60 35,874.51
###
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 4.25 19,924.98
###
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 3.70 17,551.02
###
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 3.90 14,144.13
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 1.41 1,906.00
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 46.00 3,716.80
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
###
Costo Modulo 122,505.61 122,505.61
Módulo: MSCZ0057 CERCO MALLA OLIMPICA
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 144.00 1,147.68
02FB001 EXCAVACION M3 0.87 95.68 83.24 0.87 83.24
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 0.22 660.13
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 21.50 2,715.45
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 0.65 1,970.51
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 43.00 8,144.20
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 43.00 116.96
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 8.25 6,570.88
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.24 1,037.43
###
Costo Modulo 26,308.33 26,308.33
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
###
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
###
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
###
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
###
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
###
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
###
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
###
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
###
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
###
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
###
Costo Modulo 11,343.38 11,343.38
###
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
###
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
###
Costo Modulo 16,736.87 16,736.87
NUEVOS MODULOS Y ACTIVIDADES
Módulo: MDL070002 RED DE DISTRIBUCCION 2,792.00
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2.86 0.00 2,792.00 7,985.12 2,792.00 7,985.12
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 1.78 0.00 2,792.00 4,969.76 2,792.00 4,969.76
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 2.92 0.00 2,792.00 8,152.64 2,792.00 8,152.64
42BC008 CAMARA DE LLAVES PZA 653.37 0.00 6.00 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 702.52 0.00 2.00 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 26.58 0.00 664.72 17,668.26 664.72 17,668.26
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 2,526.69 0.00 1.00 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 82.39 0.00 670.08 55,207.89 670.08 55,207.89
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 17.17 0.00 2,972.00 51,029.24 2,972.00 51,029.24
Costo Modulo 0.00 152,864.86
Módulo: MDL070002 TORRE HIDRONEUMATICA E IMPULSION
TORRE HIDRONEUMATICA PZA 28,000.00 0.00 1.00 28,000.00 1.00 28,000.00
DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 2.92 0.00 20.00 58.40 20.00 58.40
PRUEBA HIDRAULICA D=4",8" ML 1.78 0.00 78.90 140.44 78.90 140.44
PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 96.05 0.00 78.90 7,578.35 78.90 7,578.35
REPLANTEO DE LINEAS DE TUBERIA ML 2.86 0.00 20.00 57.20 20.00 57.20
PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1,992.50 0.00 1.00 1,992.50 1.00 1,992.50
Costo Modulo 0.00 37,826.89
Módulo: MSCZ0009 CASETA DE BOMBEO E INSTALACION
93BB0302 PROV. CASETA PARA BOMBEO E INSTALACION GLB 19,357.49 0.00 1.00 19,357.49 1.00 19,357.49
Costo Modulo 0.00 19,357.49
TOTAL GENERAL 240,137.81 450,187.05
Proyecto: FPS-07-00003600 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD 15 DE ABRIL (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
###
Costo Modulo 8,903.77 8,903.77
###
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -25.00 -186.75 0.00 ###
0.00
02FB005 EXCAVACION M3 3.80 95.68 363.58 -3.80 -363.58 0.00 ###
0.00
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 -2.60 -172.74 0.00 ###
0.00
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -3.80 -14,677.58 0.00 ###
0.00
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.75 -1,592.10 0.00 ###
0.00
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 -23.00 -2,927.21 0.00 ###
0.00
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -28.00 -3,536.40 0.00 ###
0.00
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 -18.00 -7,611.12 0.00 ###
0.00
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 -1.80 -1,178.55 0.00 ###
0.00
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 -2.00 -919.10 0.00 ###
0.00
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 -1.00 -404.74 0.00 ###
0.00
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 -1.00 -416.89 0.00 ###
0.00
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 -1.00 -1,465.33 0.00 0.00
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 -1.00 -807.33 0.00 ###
0.00
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -15.20 -222.83 0.00 0.00
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 -2,015.87 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 -1.00 -3,647.08 0.00 ###
0.00
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 ###
0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 -24.00 -3,564.00 0.00 ###
0.00
Costo Modulo 50,496.44 ###
0.00
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 -1.00 -570.30 0.00 ###
0.00
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 -26.00 -2,487.68 0.00 ###
0.00
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -17.50 -10,097.33 0.00 ###
0.00
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -2.00 -921.54 0.00 ###
0.00
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 -1.00 -690.14 0.00 ###
0.00
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 -20.00 -1,328.80 0.00 ###
0.00
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 -1.00 -770.31 0.00 ###
0.00
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 -1.00 -2,463.56 0.00 ###
0.00
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 -1.00 -430.31 0.00 ###
0.00
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 -15.00 -347.10 0.00 ###
0.00
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 -150.00 -3,738.00 0.00 ###
0.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 -46.00 -1,331.24 0.00 ###
0.00
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 -7.60 -35,874.51 0.00 0.00
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -4.25 -19,924.98 0.00 0.00
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 -3.70 -17,551.02 0.00 ###
0.00
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 -3.90 -14,144.13 0.00 ###
0.00
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -1.41 -1,906.00 0.00 ###
0.00
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 -46.00 -3,716.80 0.00 0.00
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 -1.00 -4,211.86 0.00 0.00
Costo Modulo 122,505.61 ###
0.00
Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.98 1,149.12 -144.00 -1,149.12 0.00 ###
0.00
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.87 -83.24 0.00 ###
0.00
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.22 -660.13 0.00 ###
0.00
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 -2.58 -3,861.85 0.00 ###
0.00
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -21.50 -2,715.45 0.00 ###
0.00
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.65 -1,970.51 0.00 ###
0.00
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 -43.00 -8,144.20 0.00 0.00
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -43.00 -116.96 0.00 0.00
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -8.25 -6,570.88 0.00 0.00
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 -0.24 -1,037.43 0.00 ###
0.00
Costo Modulo 26,309.77 ###
0.00
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
###
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
###
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
###
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
###
Costo Modulo 3,843.41 3,843.41
###
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 -9.60 -918.53 0.00 ###
0.00
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 -20.00 -58.40 0.00 ###
0.00
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 -9.00 -597.96 0.00 ###
0.00
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 -78.90 -140.44 0.00 ###
0.00
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 -78.90 -7,578.35 0.00 ###
0.00
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 -20.00 -57.20 0.00 ###
0.00
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 -1.00 -1,992.50 0.00 ###
0.00
Costo Modulo 11,343.38 ###
0.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
###
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
###
Costo Modulo 16,736.87 16,736.87
NUEVOS MODULOS Y ACTIVIDADES
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2.86 0.00 4,715.00 13,484.90 4,715.00 13,484.90
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 1.78 0.00 4,715.00 8,392.70 4,715.00 8,392.70
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 2.92 0.00 4,715.00 13,767.80 4,715.00 13,767.80
42BC008 CAMARA DE LLAVES PZA 653.37 0.00 6.00 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 702.52 0.00 2.00 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 26.58 0.00 1,122.00 29,822.76 1,122.00 29,822.76
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 2,526.69 0.00 1.00 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 82.39 0.00 1,131.16 93,196.27 1,131.16 93,196.27
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 17.17 0.00 4,715.00 80,956.55 4,715.00 80,956.55
Costo Modulo 0.00 247,472.93
Módulo: MDL070002 TORRE HIDRONEUMATICA E IMPULSION
TORRE HIDRONEUMATICA PZA 28,000.00 0.00 1.00 28,000.00 1.00 28,000.00
DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 2.92 0.00 20.00 58.40 20.00 58.40
PRUEBA HIDRAULICA D=4",8" ML 1.78 0.00 78.90 140.44 78.90 140.44
PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 96.05 0.00 78.90 7,578.35 78.90 7,578.35
REPLANTEO DE LINEAS DE TUBERIA ML 2.86 0.00 20.00 57.20 20.00 57.20
PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1,992.50 0.00 1.00 1,992.50 1.00 1,992.50
Costo Modulo 0.00 37,826.89
Módulo: MSCZ0009 CASETA DE BOMBEO E INSTALACION
93BB0302 PROV. CASETA PARA BOMBEO E INSTALACION GLB 19,357.49 0.00 1.00 19,357.49 1.00 19,357.49
Costo Modulo 0.00 19,357.49
TOTAL GENERAL 240,139.25 334,141.36
Proyecto: FPS-07-00003599 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD VILLA NUEVA (COTOCA) ###
###

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
###
CONSTRUCCION NUEVA ###
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
###
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
###
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
###
Costo Modulo 8,903.77 8,903.77
###
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -25.00 -186.75 0.00 ###
0.00
02FB005 EXCAVACION M3 3.80 95.68 363.58 -3.80 -363.58 0.00 ###
0.00
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 -2.60 -172.74 0.00 ###
0.00
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -3.80 -14,677.58 0.00 ###
0.00
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.75 -1,592.10 0.00 ###
0.00
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 -23.00 -2,927.21 0.00 ###
0.00
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -28.00 -3,536.40 0.00 ###
0.00
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 -18.00 -7,611.12 0.00 ###
0.00
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 -1.80 -1,178.55 0.00 0.00
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 -2.00 -919.10 0.00 0.00
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 -1.00 -404.74 0.00 ###
0.00
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 -1.00 -416.89 0.00 0.00
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,456.33 1,456.33 -1.00 -1,456.33 0.00 ###
0.00
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 -1.00 -807.33 0.00 ###
0.00
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -15.20 -222.83 0.00 ###
0.00
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 -2,015.87 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 -1.00 -3,647.08 0.00 0.00
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 ###
0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 -24.00 -3,564.00 0.00 ###
0.00
Costo Modulo 50,487.44 ###
0.00
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 -1.00 -570.30 0.00 ###
0.00
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 -26.00 -2,487.68 0.00 ###
0.00
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -17.50 -10,097.33 0.00 ###
0.00
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -2.00 -921.54 0.00 ###
0.00
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 -1.00 -690.14 0.00 0.00
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 -20.00 -1,328.80 0.00 0.00
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 -1.00 -770.31 0.00 ###
0.00
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 -1.00 -2,463.56 0.00 ###
0.00
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 -1.00 -430.31 0.00 0.00
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 -15.00 -347.10 0.00 0.00
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 -150.00 -3,738.00 0.00 0.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 -46.00 -1,331.24 0.00 0.00
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 -7.60 -35,874.51 0.00 0.00
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -4.25 -19,924.98 0.00 ###
0.00
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 -3.70 -17,551.02 0.00 0.00
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 -3.90 -14,144.13 0.00 ###
0.00
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -1.41 -1,906.00 0.00 ###
0.00
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 -46.00 -3,716.80 0.00 ###
0.00
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 -1.00 -4,211.86 0.00 ###
0.00
Costo Modulo 122,505.61 ###
0.00
Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -144.00 -1,147.68 0.00 ###
0.00
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.87 -83.24 0.00 ###
0.00
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.22 -660.13 0.00 ###
0.00
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 -2.58 -3,861.85 0.00 ###
0.00
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -21.50 -2,715.45 0.00 ###
0.00
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.65 -1,970.51 0.00 ###
0.00
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 -43.00 -8,144.20 0.00 ###
0.00
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -43.00 -116.96 0.00 ###
0.00
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -8.25 -6,570.88 0.00 ###
0.00
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 -0.24 -1,037.43 0.00 ###
0.00
Costo Modulo 26,308.33 0.00
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
###
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
###
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
###
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
###
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
###
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
###
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
###
Costo Modulo 3,843.41 3,843.41
###
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 -9.60 -918.53 0.00 ###
0.00
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 -20.00 -58.40 0.00 ###
0.00
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 -9.00 -597.96 0.00 ###
0.00
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 -78.90 -140.44 0.00 ###
0.00
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 -78.90 -7,578.35 0.00 ###
0.00
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 -20.00 -57.20 0.00 ###
0.00
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 -1.00 -1,992.50 0.00 ###
0.00
Costo Modulo 11,343.38 ###
0.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
###
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
NUEVOS MODULOS Y ACTIVIDADES
Módulo: MDL070002 RED DE DISTRIBUCCION 4,400.00
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2.86 0.00 4,400.00 12,584.00 4,400.00 12,584.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 1.78 0.00 4,400.00 7,832.00 4,400.00 7,832.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 2.92 0.00 4,400.00 12,848.00 4,400.00 12,848.00
42BC008 CAMARA DE LLAVES PZA 653.37 0.00 6.00 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 702.52 0.00 2.00 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 26.58 0.00 1,047.00 27,829.26 1,047.00 27,829.26
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 2,526.69 0.00 1.00 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 82.39 0.00 1,056.00 87,003.84 1,056.00 87,003.84
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 17.17 0.00 4,400.00 75,548.00 4,400.00 75,548.00
Costo Modulo 0.00 231,497.05
Módulo: MDL070002 TORRE HIDRONEUMATICA E IMPULSION
TORRE HIDRONEUMATICA PZA 28,000.00 0.00 1.00 28,000.00 1.00 28,000.00
DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 2.92 0.00 20.00 58.40 20.00 58.40
PRUEBA HIDRAULICA D=4",8" ML 1.78 0.00 78.90 140.44 78.90 140.44
PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 96.05 0.00 78.90 7,578.35 78.90 7,578.35
REPLANTEO DE LINEAS DE TUBERIA ML 2.86 0.00 20.00 57.20 20.00 57.20
PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1,992.50 0.00 1.00 1,992.50 1.00 1,992.50
Costo Modulo 0.00 37,826.89
Módulo: MSCZ0009 CASETA DE BOMBEO E INSTALACION
93BB0302 PROV. CASETA PARA BOMBEO E INSTALACION GLB 19,357.49 0.00 1.00 19,357.49 1.00 19,357.49
Costo Modulo 0.00 19,357.49
TOTAL GENERAL 240,128.81 318,165.48
###

Proyecto: FPS-07-00003617 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD ARROYITO (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
###
CONSTRUCCION NUEVA ###
Módulo: MCBB0342 TRABAJOS COMPLEMENTARIOS
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
41HA001 HIPOCLORADOR COMPLETO (SG/DETALLE); ENVASE PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
93FB042 CASETA PARA HIPOCLORADOR PZA 1.00 3,075.29 3,075.29 1.00 3,075.29
93GB187 PROV. Y COLOC. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
###
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
###
Costo Modulo 20,966.42 20,966.42
###
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 1,500.00 2.86 4,290.00 2,312.00 0.00 3,812.00 10,902.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 360.00 95.68 34,444.80 554.88 0.00 914.88 87,535.72
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 150.00 66.44 9,966.00 -150.00 -9,966.00 0.00 0.00
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 210.00 53.15 11,161.50 -210.00 -11,161.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 1,500.00 1.78 2,670.00 0.00 1,500.00 2,670.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 1,500.00 2.92 4,380.00 1,500.00 4,380.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 0.00 6.00 3,920.22
93DC693 LIMPIEZA GENERAL GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93IB0015 ANCLAJE DE HªSª H-18 M3 6.00 702.52 4,215.12 0.00 6.00 4,215.12
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 1,500.00 17.17 25,755.00 2,312.00 3,812.00 65,452.04
Costo Modulo 105,083.38 183,356.16
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 3.00 1,193.40 3,580.20 3.00 3,580.20
Costo Modulo 10,097.17 10,097.17
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 25.00 186.75
###
02FB005 EXCAVACION M3 3.80 95.68 363.58 3.80 363.58
###
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
###
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 2,617.98 9,948.32 3.80 9,948.32
###
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 1,937.67 1,453.25 0.75 1,453.25
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 77.99 1,793.77 23.00 1,793.77
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 28.00 3,536.40
###
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 377.03 6,786.54 18.00 6,786.54
###
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.80 1,178.55
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 2.00 919.10
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 27.09 1,408.68 52.00 1,408.68
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
###
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 15.20 222.83
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,408.21 1,874.52 0.55 1,874.52
###
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 44.00 2,770.68
###
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 24.00 3,564.00
###
Costo Modulo 39,274.00 39,274.00
###
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
###
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 6.74 644.88 32.74 3,132.56
###
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -2.70 -1,557.87 14.80 8,539.45
###
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
###
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
###
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
###
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
###
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
###
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
###
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
###
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,592.56 19,518.38 -0.12 -551.11 4.13 18,967.27
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 1.05 4,980.70 4.75 22,531.72
###
96CA010 ZAPATAS DE HªAª M3 3.90 3,371.57 13,149.12 0.10 337.16 4.00 13,486.28
###
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.64 -865.13 0.77 1,040.86
###
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 -0.44 -35.55 45.56 3,681.25
###
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
###
Costo Modulo 121,104.00 137,108.72
###
Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 144.00 1,147.68
###
02FB001 EXCAVACION M3 0.87 95.68 83.24 0.87 83.24
###
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 0.22 660.13
###
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
###
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 21.50 2,715.45
###
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 0.65 1,970.51
###
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 138.87 5,971.41 43.00 5,971.41
###
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 43.00 116.96
###
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 8.25 6,570.88
###
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.24 1,037.43
###
Costo Modulo 24,135.54 24,135.54
###
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 30.00 829.14 24,874.20 -29.00 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 30.00 997.92 29,937.60 -29.00 1.00 997.92
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 30.00 805.29 24,158.70 -29.00 1.00 805.29
###
Costo Modulo 78,970.50 2,632.35
###
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
###
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
###
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
###
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 0.00 78.90 140.44
###
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 93.13 7,347.96 0.00 78.90 7,347.96
###
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 0.00 1.00 1,992.50
Costo Modulo 11,112.99 19,106.55 -24,229.32 11,112.99
###
TOTAL GENERAL 410,744.00 428,683.35

Proyecto: FPS-07-00003613 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CUMAVI (COTOCA)


PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION 2,097.00
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,000.00 2.86 8,580.00 -903.00 -2,582.58 2,097.00 5,997.42
###
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 840.00 79.73 66,973.20 -336.72 -26,846.69 503.28 40,126.51
###
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 300.00 53.15 15,945.00 -300.00 -15,945.00 0.00 ###
0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,000.00 1.78 5,340.00 -903.00 -1,607.34 2,097.00 3,732.66
###
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,000.00 2.92 8,760.00 -903.00 2,097.00 6,123.24
###
42BC008 CAMARA DE LLAVES PZA 5.00 653.37 3,266.85 0.00 5.00 3,266.85
###
93AD562 RELLENO COMUN COMPACTADO M3 540.00 26.58 14,353.20 -36.72 -976.02 503.28 13,377.18
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
###
93IB0015 ANCLAJE DE HªSª H-18 M3 1.50 1,289.66 1,934.49 0.00 1.50 1,934.49
###
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,000.00 16.29 48,870.00 -903.00 2,097.00 34,160.13
###
Costo Modulo 176,549.43 111,245.17
###
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
###
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
###
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 713.07 34,940.43 -29.00 20.00 14,261.40
###
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 928.45 45,494.05 -29.00 20.00 18,569.00
###
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 576.73 28,259.77 -29.00 20.00 11,534.60
###
Costo Modulo 108,694.25 44,365.00
###
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
###
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
###
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
###
Costo Modulo 14,982.82 14,982.82
###
TOTAL GENERAL 309,130.30 179,496.79
###
Proyecto: FPS-07-00003614 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD LA CRUCEÑA (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
###
CONSTRUCCION NUEVA ###
Módulo: MDL070002 RED DE DISTRIBUCCION 3,900.00 ###
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 400.00 1,144.00 0.00 3,900.00 11,154.00
###
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 0.00 3,500.00 6,230.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 3,500.00 10,220.00
###
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 0.00 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 0.00 2.00 1,405.04
###
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 350.00 9,303.00 0.00 840.00 22,327.20
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 90.36 75,902.40 96.00 8,674.56 0.00 936.00 84,576.96
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 400.00 6,868.00 3,900.00 66,963.00
###
Costo Modulo 201,936.05 209,323.11
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
###
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
###
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
###
Costo Modulo 8,903.80 8,903.80
###
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 45.00 829.14 37,311.30 -5.00 40.00 33,165.60
###
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 45.00 997.92 44,906.40 -5.00 40.00 39,916.80
###
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 45.00 805.29 36,238.05 -5.00 40.00 32,211.60
###
Costo Modulo 118,455.75 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
###
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
###
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
TOTAL GENERAL 347,186.73 341,412.04
###

Proyecto: FPS-07-00003615 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD NUEVO AMANECER (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 -600.00 -1,716.00 2,900.00 8,294.00
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 -600.00 -1,068.00 2,900.00 5,162.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 -600.00 2,900.00 8,468.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 0.00 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 0.00 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 200.12 0.00 690.12 18,343.39
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 82.39 69,207.60 -144.00 -11,864.16 696.00 57,343.44
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 -600.00 2,900.00 49,793.00
Costo Modulo 195,241.25 155,255.78
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 829.14 40,627.86 -9.00 40.00 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 997.92 48,898.08 -9.00 40.00 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 805.29 39,459.21 -9.00 40.00 32,211.60
Costo Modulo 128,985.15 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
TOTAL GENERAL 351,021.33 287,344.71
CONSTRUCCION SISTEMAS DE AGUA POTABLE EN YAPACANI

Proyecto: CONST. 7 SISTEMAS DE AGUA EN YAPACANI (YAPACANI) Fecha : 25/03/2012

Proyecto: CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD BARRIENTOS (YAPACANI)

PRESUPUESTO GENERAL

PRECIO PRECIO
ACTIVIDA/
DESCRIPCION UNID CANTIDAD UNITARIO TOTAL
MODULO
Bs Bs
CONSTRUCCION NUEVA
Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB 1.00 5,036.39 5,036.39
2 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 1,126.02 1,126.02
4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 5,307.18 5,307.18
Costo Modulo 13,223.64
Módulo: MEDIDAS DE MITIGACION
1 CONSTRUCCION LETRINA SECA PZA 1.00 687.76 687.76
2 CONTENEDORES DE BASURA PZA 3.00 178.70 536.10
3 CINTA PLASTICA DE SEGURIDAD ML 100.00 0.75 75.00
4 SEÑALIZACION DE SEGURIDAD DE MADERA PZA 2.00 235.26 470.52
5 SEÑALIZACION DE SEGURIDAD DE PVC PZA 4.00 230.81 923.24
6 LIMPIEZA Y RETIRO DE ESCOMBROS GLB 1.00 1,856.36 1,856.36
Costo Modulo 4,548.98
Módulo: CASETA DE BOMBEO
1 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 13.80 311.24 4,295.11
2 EXCAVACION M3 2.38 37.88 90.15
3 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.38 66.44 158.13
4 CIMIENTO CORRIDO DE HªCª M3 2.38 995.56 2,369.43
5 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.72 1,144.48 824.03
6 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 24.22 125.88 3,048.81
7 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 21.02 137.79 2,896.35
8 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 21.25 422.84 8,985.35
9 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 3.22 440.16 1,417.32
10 PROVISION Y COLOCACION DE VENTANA METALICA M2 7.97 459.55 3,662.61
11 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74
12 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 1,282.08 1,282.08
13 PINTURA LATEX M2 52.00 41.65 2,165.80
14 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33
15 INSTALACION ELECTRICA GLB 1.00 1,723.95 1,723.95
16 IMPERMEABILIZACION SOBRECIMIENTO ML 14.90 14.66 218.43
17 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.89 2,936.28 2,613.29
18 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08
19 REVOQUE CON MORTERO DE CEMENTO M2 44.00 76.47 3,364.68
20 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.22 82.94 2,008.81
21 COLUMNAS DE HORMIGON ARMADO M3 0.31 4,390.47 1,361.05
22 ZAPATAS DE HORMIGON ARMADO M3 0.10 3,904.00 390.40
Costo Modulo 48,392.93
Módulo: TANQUE ELEVADO
1 REPLANTEO ML 17.60 20.00 352.00
2 RELLENO DE ESTRUCTURAS M3 26.00 34.02 884.52
3 EXCAVACION M3 26.00 37.88 984.88
4 ESCALERA CON GUARDACUERPOS ML 12.10 460.56 5,572.78
5 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 282.71 565.42
6 TAPA METALICA DE 70X70 CM PZA 1.00 461.47 461.47
7 RELLENO COMPACTADO COMUN M3 20.00 34.02 680.40
8 CAMARA DE VALVULAS PZA 1.00 705.12 705.12
9 ACCESORIA DE TANQUE GBL 1.00 10,126.12 10,126.12
10 MEDIDOR DE NIVELES TANQUES DE H20 GBL 1.00 4,169.58 4,169.58
11 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M3 20.00 33.04 660.80
12 PINTURA LATEX M2 150.00 24.92 3,738.00
13 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M2 46.00 158.68 7,299.28
14 HªAª H21 CUBA M3 10.36 4,419.00 45,780.84
15 HªAª COLUMNAS (TANQUE ELEVADO) M3 3.30 4,390.47 14,488.55
16 HªAª VIGA (TANQUE ELEVADO) M3 3.80 4,505.78 17,121.96
17 ZAPATAS DE HªAª M3 8.00 3,904.62 31,236.96
18 CARPETA DE Hº POBRE M3 0.80 1,818.75 1,455.00
19 REVOQUE CON SIKA IMPERMEABILIZANTE M2 47.24 108.28 5,115.15
20 BARANDA METALICA DE PROTECCION ML 1.00 56.29 56.29
Costo Modulo 151,455.12
Módulo: CERCO MALLA OLIMPICA
1 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68
2 EXCAVACION M3 7.28 28.97 210.90
3 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.19 3,000.59 570.11
4 CIMIENTO CORRIDO DE HºCº M3 48.96 995.56 48,742.62
5 MURO DE LADRILLO ADOBITO M2 11.67 76.47 892.40
6 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.09 3,031.55 272.84
7 CERCO DE MALLA OLIMPICA ML 76.00 189.40 14,394.40
8 REPLANTEO CERCO PERIMETRAL ML 40.00 2.72 108.80
9 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88
10 COLUMNAS DE HºAº PREFABRICADAS PZA 26.00 130.00 3,380.00
Costo Modulo 76,290.63
Módulo: RED DE DISTRIBUCCION
1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2,057.66 3.36 6,913.74
2 EXCAVACION MANUAL M3 493.84 37.88 18,706.66
3 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 2,057.66 2.84 5,843.75
4 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 2,057.66 2.1 4,321.09
5 CAMARA DE LLAVES PZA 5.00 1177.81 5,889.05
6 ANCLAJE DE HªSª H-18 M3 2.00 1917.6 3,835.20
7 RELLENO Y COMPACTADO CON TIERRA COMUN M3 485.76 34.02 16,525.55
8 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 1187.04 1,187.04
9 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 2,057.66 39.24 80,742.58
Costo Modulo 143,964.66
Módulo: CONEXIONES DOMICILIARIAS
1 PEDESTAL Y BASE PARA PILETA HºAº PZA 70.00 430.00 30,100.00
2 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 70.00 997.92 69,854.40
3 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 70.00 697.42 48,819.40
Costo Modulo 148,773.80
Módulo: IMPULSION POZO TANQUE
1 EXCAVACION M3 2.00 28.97 57.94
2 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 102.00 2.10 214.20
3 RELLENO COMPACTADO M3 1.50 34.02 51.03
4 PRUEBA HIDRAULICA D=4",8" ML 102.00 2.84 289.68
5 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 102.00 110.64 11,285.28
6 REPLANTEO DE LINEAS DE TUBERIA ML 102.00 3.36 342.72
7 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50
Costo Modulo 14,233.35
TOTAL GENERAL 600,883.11
Proyecto: AMPLIACION SIST. AGUA POTABLE COMUNIDAD VALLE HERMOSO (YAPACANI)

ACTIVIDA/ PRECIO PRECIO


DESCRIPCION UNID CANTIDAD
MODULO UNITARIO TOTAL
CONSTRUCCION NUEVA
1 Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
2 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 16,736.87
2 Módulo: MEDIDAS DE MITIGACION
1 CONSTRUCCION LETRINA SECA PZA 1.00 687.76 687.76
2 CONTENEDORES DE BASURA PZA 3.00 178.70 536.10
3 CINTA PLASTICA DE SEGURIDAD ML 100.00 0.75 75.00
4 SEÑALIZACION DE SEGURIDAD DE MADERA PZA 2.00 235.26 470.52
5 SEÑALIZACION DE SEGURIDAD DE PVC PZA 4.00 230.81 923.24
6 LIMPIEZA Y RETIRO DE ESCOMBROS GLB 1.00 1,856.36 1,856.36
Costo Modulo 4,548.98
3 Módulo: RED DE DISTRIBUCCION ###
1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2,633.90 3.36 8,849.90
2 EXCAVACION MANUAL M3 #REF! 37.88 #REF!
3 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 2,633.90 2.84 7,480.28
4 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 2,633.90 2.1 5,531.19
5 CAMARA DE LLAVES PZA 5.00 1177.81 5,889.05
6 ANCLAJE DE HªSª H-18 M3 2.00 1917.6 3,835.20
7 RELLENO Y COMPACTADO CON TIERRA COMUN M3 #REF! 34.02 #REF!
8 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 1187.04 1,187.04
9 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 2,633.90 39.24 103,354.24
Costo Modulo #REF!
4 Módulo: CONEXIONES DOMICILIARIAS ###
1 PEDESTAL Y BASE PARA PILETA HºAº PZA 20.00 430.00 8,600.00
2 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 20.00 997.92 19,958.40
3 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 20.00 697.42 13,948.40
Costo Modulo 42,506.80
5 Módulo: HIPOCLORADOR DE CARGA CONSTANTE
1 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31
Costo Modulo 2,908.31
TOTAL GENERAL #REF!
Proyecto: AMPLIACION SIST. AGUA POTABLE COMUNIDAD 9 DE ABRIL (YAPACANI)
ACTIVIDA/ PRECIO PRECIO
DESCRIPCION UNID CANTIDAD
MODULO UNITARIO TOTAL
CONSTRUCCION NUEVA
1 Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
2 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 16,736.87
2 Módulo: MEDIDAS DE MITIGACION
1 CONSTRUCCION LETRINA SECA PZA 1.00 687.76 687.76
2 CONTENEDORES DE BASURA PZA 3.00 178.70 536.10
3 CINTA PLASTICA DE SEGURIDAD ML 100.00 0.75 75.00
4 SEÑALIZACION DE SEGURIDAD DE MADERA PZA 2.00 235.26 470.52
5 SEÑALIZACION DE SEGURIDAD DE PVC PZA 4.00 230.81 923.24
6 LIMPIEZA Y RETIRO DE ESCOMBROS GLB 1.00 1,856.36 1,856.36
Costo Modulo 4,548.98
3 Módulo: RED DE DISTRIBUCCION
1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 4,414.75 3.36 14,833.56
2 EXCAVACION MANUAL M3 720.00 37.88 27,273.60
3 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 4,414.75 2.84 12,537.89
4 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 4,414.75 2.1 9,270.98
5 CAMARA DE LLAVES PZA 3.00 1177.81 3,533.43
6 ANCLAJE DE HªSª H-18 M3 2.00 1917.6 3,835.20
7 RELLENO Y COMPACTADO CON TIERRA COMUN M3 708.22 34.02 24,093.62
8 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 1187.04 1,187.04
9 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 4,414.75 39.24 173,234.79
Costo Modulo 269,800.11
4 Módulo: CONEXIONES DOMICILIARIAS
1 PEDESTAL Y BASE PARA PILETA HºAº PZA 25.00 430.00 10,750.00
2 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 25.00 997.92 24,948.00
3 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 25.00 697.42 17,435.50
Costo Modulo 53,133.50
5 Módulo: HIPOCLORADOR DE CARGA CONSTANTE
1 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31
Costo Modulo 2,908.31
TOTAL GENERAL 347,127.77

Proyecto: AMPLIACION SIST. AGUA POTABLE COMUNIDAD SANTA FE-15 DE JUNIO (YAPACANI)
ACTIVIDA/ PRECIO PRECIO
DESCRIPCION UNID CANTIDAD
MODULO UNITARIO TOTAL
CONSTRUCCION NUEVA
1 Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
2 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 16,736.87
2 Módulo: MEDIDAS DE MITIGACION
1 CONSTRUCCION LETRINA SECA PZA 1.00 687.76 687.76
2 CONTENEDORES DE BASURA PZA 3.00 178.70 536.10
3 CINTA PLASTICA DE SEGURIDAD ML 100.00 0.75 75.00
4 SEÑALIZACION DE SEGURIDAD DE MADERA PZA 2.00 235.26 470.52
5 SEÑALIZACION DE SEGURIDAD DE PVC PZA 4.00 230.81 923.24
6 LIMPIEZA Y RETIRO DE ESCOMBROS GLB 1.00 1,856.36 1,856.36
Costo Modulo 4,548.98
3 Módulo: RED DE DISTRIBUCCION
1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 7,132.47 3.36 23,965.10
2 EXCAVACION MANUAL M3 1,711.79 37.88 64,842.61
3 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 7,132.47 2.84 20,256.22
4 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 7,132.47 2.1 14,978.19
5 CAMARA DE LLAVES PZA 3.00 1177.81 3,533.43
6 ANCLAJE DE HªSª H-18 M3 2.00 1917.6 3,835.20
7 RELLENO Y COMPACTADO CON TIERRA COMUN M3 1,683.78 34.02 57,282.25
8 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 1187.04 1,187.04
9 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 7,132.47 39.24 279,878.16
Costo Modulo 469,758.20
4 Módulo: CONEXIONES DOMICILIARIAS
1 PEDESTAL Y BASE PARA PILETA HºAº PZA 57.00 430.00 24,510.00
2 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 57.00 997.92 56,881.44
3 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 57.00 697.42 39,752.94
Costo Modulo 121,144.38
5 Módulo: HIPOCLORADOR DE CARGA CONSTANTE
1 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31
Costo Modulo 2,908.31
TOTAL GENERAL 615,096.74
Proyecto: CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD PORVENIR (YAPACANI)
PRECIO PRECIO
ACTIVIDA/
DESCRIPCION UNID CANTIDAD UNITARIO TOTAL
MODULO
Bs Bs
CONSTRUCCION NUEVA
1 Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
2 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 16,736.87
2 Módulo: MEDIDAS DE MITIGACION
1 SEÑALIZACION GLB 1.00 5,253.63 5,253.63
2 LETRINA PZA 1.00 1,263.34 1,263.34
3 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80
4 SEÑALIZACION DE SEGURIDAD DE MADERA PZA 2.00 235.26 470.52
5 SEÑALIZACION DE SEGURIDAD DE PVC PZA 4.00 230.81 923.24
6 LIMPIEZA Y RETIRO DE ESCOMBROS GLB 1.00 1,856.36 1,856.36
Costo Modulo 8,903.77
3 Módulo: CASETA DE BOMBEO
1 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 13.80 7.47 103.09
2 EXCAVACION M3 2.38 95.68 227.72
3 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.38 66.44 158.13
4 CIMIENTO CORRIDO DE HªAª M3 2.38 3,862.52 9,192.80
5 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.72 2,122.80 1,528.42
6 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 24.22 127.27 3,082.48
7 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 21.02 126.30 2,654.83
8 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 21.25 422.84 8,985.35
9 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 3.22 654.75 2,108.30
10 PROVISION Y COLOCACION DE VENTANA METALICA M2 7.97 459.55 3,662.61
11 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74
12 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89
13 PINTURA LATEX M2 0.00 38.78 0.00
14 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33
15 INSTALACION ELECTRICA GLB 1.00 807.33 807.33
16 IMPERMEABILIZACION SOBRECIMIENTO ML 14.90 14.66 218.43
17 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.00 3,665.21 0.00
18 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08
19 REVOQUE CON MORTERO DE CEMENTO M2 0.00 62.97 0.00
20 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.22 148.50 3,596.67
21 COLUMNAS DE HORMIGON ARMADO M3 0.31 4,688.23 1,453.35
22 ZAPATAS DE HORMIGON ARMADO M3 0.10 3,626.70 362.67
Costo Modulo 44,076.22
4 TANQUE DE ALMACENAMIENTO
1 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 31.36 7.88 247.12
2 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 8.21 41.76 342.85
3 PROVISION Y COLOCACION ACCESORIOS TANQUE DE A GLB 1.00 2,758.86 2,758.86
4 REVOQUE INTERIOR CON SIKA DOSIF:1:3 E=2,5 CM M2 29.50 118.76 3,503.42
5 HORMIGON ARMADO 210 KG/CM2 M3 7.40 10,976.11 81,223.21
6 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUES M3 15.00 3.32 49.80
7 HIPOCLORADOR GLB 1.00 1,487.66 1,487.66
Costo Modulo 89,612.92
5 Módulo: CERCO MALLA OLIMPICA
1 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68
2 EXCAVACION M3 7.28 28.97 210.90
3 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.19 3,000.59 570.11
4 CIMIENTO CORRIDO DE HºCº M3 48.96 995.56 48,742.62
5 MURO DE LADRILLO ADOBITO M2 11.67 76.47 892.40
6 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.09 3,031.55 272.84
7 CERCO DE MALLA OLIMPICA ML 76.00 189.40 14,394.40
8 REPLANTEO CERCO PERIMETRAL ML 40.00 2.72 108.80
9 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88
10 COLUMNAS DE HºAº M3 26.00 130.00 3,380.00
Costo Modulo 76,290.63
6 Módulo: RED DE DISTRIBUCCION
1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,008.58 3.36 10,108.83
2 EXCAVACION MANUAL M3 1,440.00 37.88 54,547.20
3 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,008.58 2.84 8,544.37
4 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,008.58 2.1 6,318.02
5 CAMARA DE LLAVES PZA 3.00 1177.81 3,533.43
6 ANCLAJE DE HªSª H-18 M3 2.00 1917.6 3,835.20
7 RELLENO Y COMPACTADO CON TIERRA COMUN M3 1,416.44 34.02 48,187.25
8 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 1187.04 1,187.04
9 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,008.58 39.24 118,056.68
Costo Modulo 254,318.02
7 Módulo: CONEXIONES DOMICILIARIAS
1 PEDESTAL Y BASE PARA PILETA HºAº PZA 45.00 430.00 19,350.00
2 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 45.00 997.92 44,906.40
3 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 45.00 697.42 31,383.90
Costo Modulo 95,640.30
8 Módulo: IMPULSION POZO TANQUE
1 EXCAVACION M3 2.00 28.97 57.94
2 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 102.00 2.10 214.20
3 RELLENO COMPACTADO M3 1.50 34.02 51.03
4 PRUEBA HIDRAULICA D=4",8" ML 102.00 2.84 289.68
5 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 102.00 110.64 11,285.28
6 REPLANTEO DE LINEAS DE TUBERIA ML 102.00 3.36 342.72
7 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50
8 BOMBA SUMERGIBLE 2HP Y ACCESORIOS PZA 1.00 26,285.80 26,285.80
9 BOMBA DE IMPULSION 2HP Y ACCESORIOS PZA 2.00 12,500.00 25,000.00
Costo Modulo 65,519.15
TOTAL GENERAL 651,097.88
CONSTRUCCION SISTEMAS DE AGUA POTABLE EN YAPACANI

Proyecto: CONST. 7 SISTEMAS DE AGUA EN YAPACANI (YAPACANI) Fecha : 25/03/2012

Proyecto: CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD BARRIENTOS (YAPACANI)

PRESUPUESTO GENERAL

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD UNITARIO TOTAL
Bs Bs
CONSTRUCCION NUEVA
Módulo: ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 16,736.87
Módulo: MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80
Costo Modulo 8,903.77
Módulo: CASETA DE BOMBEO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 13.80 7.47 103.09
02FB005 EXCAVACION M3 2.38 95.68 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.38 66.44 158.13
09AA001 CIMIENTO CORRIDO DE HªAª M3 2.38 3,862.52 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.72 2,122.80 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 24.22 127.27 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 21.02 126.30 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 21.25 422.84 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 3.22 654.75 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 7.97 459.55 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89
93GB025 PINTURA LATEX M2 0.00 38.78 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 14.90 14.66 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.00 3,665.21 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 0.00 62.97 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.22 148.50 3,596.67
COLUMNAS DE HORMIGON ARMADO M3 0.31 4,688.23 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 0.10 3,626.70 362.67
Costo Modulo 44,076.22
Módulo: TANQUE ELEVADO
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68
31AD002 ESCALERA CON GUARDACUERPOS ML 12.10 576.99 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 20.00 23.14 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24
93GB349 HªAª H21 CUBA M3 10.36 4,720.33 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 3.30 4,688.23 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.80 4,743.52 18,025.38
96CA010 ZAPATAS DE HªAª M3 8.00 3,626.70 29,013.60
96DC132 CARPETA DE Hº POBRE M3 0.80 1,351.77 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 47.24 80.80 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86
Costo Modulo 142,699.29
Módulo: CERCO MALLA OLIMPICA
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68
02FB001 EXCAVACION M3 0.56 95.68 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.22 3,000.59 660.13
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43
Costo Modulo 26,278.67
Módulo: RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 5,500.00 2.86 15,730.00
93GC035 EXCAVACION MANUAL M3 493.84 90.36 44,623.38
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 5,500.00 1.78 9,790.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 5,500.00 2.92 16,060.00
42BC008 CAMARA DE LLAVES PZA 5.00 653.37 3,266.85
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 485.76 26.58 12,911.50
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2526.69 2,526.69
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 5,500.00 17.17 94,435.00
Costo Modulo 200,748.46
Módulo: CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 58.00 829.14 48,090.12
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 58.00 997.92 57,879.36
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 58.00 1,260.53 73,110.74
Costo Modulo 179,080.22
Módulo: IMPULSION POZO TANQUE
01AB001 EXCAVACION M3 2.00 95.68 191.36
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 102.00 2.92 297.84
40JA001 RELLENO COMPACTADO M3 1.50 66.44 99.66
93AD562 PRUEBA HIDRAULICA D=4",8" ML 102.00 1.78 181.56
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 102.00 96.05 9,797.10
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 102.00 2.86 291.72
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50
Costo Modulo 12,851.74
TOTAL GENERAL 631,375.24
Proyecto: AMPLIACION SIST. AGUA POTABLE COMUNIDAD VALLE HERMOSO (YAPACANI)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 14,982.82
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 3.00 1,193.40 3,580.20
Costo Modulo 10,097.20
Módulo: MDL070002 RED DE DISTRIBUCCION ###
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2,500.00 2.86 7,150.00
93GC035 EXCAVACION MANUAL M3 #REF! 90.36 #REF!
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 2,500.00 1.78 4,450.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 2,500.00 2.92 7,300.00
42BC008 CAMARA DE LLAVES PZA 5.00 653.37 3,266.85
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 #REF! 26.58 #REF!
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2526.69 2,526.69
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 2,500.00 17.17 42,925.00
Costo Modulo #REF!
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 20.00 829.14 16,582.80
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 20.00 997.92 19,958.40
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 20.00 805.29 16,105.80
Costo Modulo 52,647.00
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31
Costo Modulo 2,908.31
TOTAL GENERAL #REF!
Proyecto: AMPLIACION SIST. AGUA POTABLE COMUNIDAD 9 DE ABRIL (YAPACANI)
PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 14,982.82
Módulo: MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 3.00 1,193.40 3,580.20
Costo Modulo 10,097.20
Módulo: RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,000.00 2.86 8,580.00
93GC035 EXCAVACION MANUAL M3 720.00 90.36 65,059.20
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,000.00 1.78 5,340.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,000.00 2.92 8,760.00
42BC008 CAMARA DE LLAVES PZA 3.00 653.37 1,960.11
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 708.22 26.58 18,824.47
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2526.69 2,526.69
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,000.00 17.17 51,510.00
Costo Modulo 163,965.51
Módulo: CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 25.00 829.14 20,728.50
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 25.00 997.92 24,948.00
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 25.00 805.29 20,132.25
Costo Modulo 65,808.75
Módulo: HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31
Costo Modulo 2,908.31
TOTAL GENERAL 257,762.59

Proyecto: AMPLIACION SIST. AGUA POTABLE COMUNIDAD SANTA FE-15 DE JUNIO (YAPACANI)
PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 14,982.82
Módulo: MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 3.00 1,193.40 3,580.20
Costo Modulo 10,097.20
Módulo: RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 7,598.00 2.86 21,730.28
93GC035 EXCAVACION MANUAL M3 1,711.79 90.36 154,677.34
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 7,598.00 1.78 13,524.44
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 7,598.00 2.92 22,186.16
42BC008 CAMARA DE LLAVES PZA 3.00 653.37 1,960.11
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 1,683.78 26.58 44,754.92
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2526.69 2,526.69
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 7,598.00 17.17 130,457.66
Costo Modulo 393,222.64
Módulo: CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 57.00 829.14 47,260.98
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 57.00 997.92 56,881.44
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 57.00 805.29 45,901.53
Costo Modulo 150,043.95
Módulo: HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31
Costo Modulo 2,908.31
TOTAL GENERAL 571,254.92
Proyecto: CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD PORVENIR (YAPACANI)
PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD UNITARIO TOTAL
Bs Bs
CONSTRUCCION NUEVA
Módulo: ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 16,736.87
Módulo: MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80
Costo Modulo 8,903.77
Módulo: CASETA DE BOMBEO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 13.80 7.47 103.09
02FB005 EXCAVACION M3 2.38 95.68 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.38 66.44 158.13
09AA001 CIMIENTO CORRIDO DE HªAª M3 2.38 3,862.52 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.72 2,122.80 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 24.22 127.27 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 21.02 126.30 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 21.25 422.84 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 3.22 654.75 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 7.97 459.55 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89
93GB025 PINTURA LATEX M2 0.00 38.78 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 14.90 14.66 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.00 3,665.21 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 0.00 62.97 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.22 148.50 3,596.67
COLUMNAS DE HORMIGON ARMADO M3 0.31 4,688.23 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 0.10 3,626.70 362.67
Costo Modulo 44,076.22
TANQUE DE ALMACENAMIENTO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 31.36 7.88 247.12
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 8.21 41.76 342.85
41DE001 PROVISION Y COLOCACION ACCESORIOS TANQUE DE A GLB 1.00 2,758.86 2,758.86
93BC678 REVOQUE INTERIOR CON SIKA DOSIF:1:3 E=2,5 CM M2 29.50 118.76 3,503.42
93CC103 HORMIGON ARMADO 210 KG/CM2 M3 7.40 10,976.11 81,223.21
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUES M3 15.00 3.32 49.80
Z93BC506 HIPOCLORADOR GLB 1.00 1,487.66 1,487.66
Costo Modulo 89,612.92

Módulo: CERCO MALLA OLIMPICA


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68
02FB001 EXCAVACION M3 0.56 95.68 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.22 3,000.59 660.13
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43
Costo Modulo 26,278.67
Módulo: RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 6,000.00 2.86 17,160.00
93GC035 EXCAVACION MANUAL M3 1,440.00 90.36 130,118.40
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 6,000.00 1.78 10,680.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 6,000.00 2.92 17,520.00
42BC008 CAMARA DE LLAVES PZA 3.00 653.37 1,960.11
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 1,416.44 26.58 37,648.94
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2526.69 2,526.69
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 6,000.00 17.17 103,020.00
Costo Modulo 322,039.18
Módulo: CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 45.00 829.14 37,311.30
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 45.00 997.92 44,906.40
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 45.00 805.29 36,238.05
Costo Modulo 118,455.75
Módulo: IMPULSION POZO TANQUE
01AB001 EXCAVACION M3 2.00 95.68 191.36
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 102.00 2.92 297.84
40JA001 RELLENO COMPACTADO M3 1.50 66.44 99.66
93AD562 PRUEBA HIDRAULICA D=4",8" ML 102.00 1.78 181.56
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 102.00 96.05 9,797.10
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 102.00 2.86 291.72
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50
93GG036 BOMBA SUMERGIBLE 2HP Y ACCESORIOS PZA 1.00 26,285.80 26,285.80
93GG037 BOMBA DE IMPULSION 2HP Y ACCESORIOS PZA 2.00 12,500.00 25,000.00
Costo Modulo 64,137.54
TOTAL GENERAL 690,240.92

Proyecto: CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CASCABEL (YAPACANI)


VOLUMENES DE OBRA CONTRACTUALMENTE AUTORIZADOS
PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD UNITARIO TOTAL
Bs Bs
CONSTRUCCION NUEVA
Módulo: ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73
Costo Modulo 16,736.87
Módulo: MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80
Costo Modulo 8,903.77
Módulo: CASETA DE BOMBEO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 13.80 7.47 103.09
02FB005 EXCAVACION M3 2.38 95.68 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.38 66.44 158.13
09AA001 CIMIENTO CORRIDO DE HªAª M3 2.38 3,862.52 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.72 2,122.80 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 24.22 127.27 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 21.02 126.30 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 21.25 422.84 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 3.22 654.75 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 7.97 459.55 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89
93GB025 PINTURA LATEX M2 0.00 38.78 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 14.90 14.66 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.00 3,665.21 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 0.00 62.97 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.22 148.50 3,596.67
COLUMNAS DE HORMIGON ARMADO M3 0.31 4,688.23 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 0.10 3,626.70 362.67
Costo Modulo 44,076.22
Módulo: TANQUE ELEVADO
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68
31AD002 ESCALERA CON GUARDACUERPOS ML 12.10 576.99 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 20.00 23.14 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24
93GB349 HªAª H21 CUBA M3 10.36 4,720.33 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 3.30 4,688.23 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.80 4,743.52 18,025.38
96CA010 ZAPATAS DE HªAª M3 8.00 3,626.70 29,013.60
96DC132 CARPETA DE Hº POBRE M3 0.80 1,351.77 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 47.24 80.80 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86
Costo Modulo 142,699.29
Módulo: CERCO MALLA OLIMPICA
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68
02FB001 EXCAVACION M3 0.56 95.68 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.22 3,000.59 660.13
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43
Costo Modulo 26,278.67
Módulo: RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,000.00 2.86 8,580.00
93GC035 EXCAVACION MANUAL M3 720.00 90.36 65,059.20
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,000.00 1.78 5,340.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,000.00 2.92 8,760.00
42BC008 CAMARA DE LLAVES PZA 5.00 653.37 3,266.85
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 708.22 26.58 18,824.47
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2526.69 2,526.69
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,000.00 17.17 51,510.00
Costo Modulo 165,272.25
Módulo: CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 40.00 829.14 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 40.00 997.92 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 40.00 805.29 32,211.60
Costo Modulo 105,294.00
Módulo: IMPULSION POZO TANQUE
01AB001 EXCAVACION M3 2.00 95.68 191.36
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 102.00 2.92 297.84
40JA001 RELLENO COMPACTADO M3 1.50 66.44 99.66
93AD562 PRUEBA HIDRAULICA D=4",8" ML 102.00 1.78 181.56
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 102.00 96.05 9,797.10
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 102.00 2.86 291.72
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50
Costo Modulo 12,851.74
TOTAL GENERAL 522,112.81
CONTRATO MODIFICATORIO Nº1

Proyecto: CONST. 7 SISTEMAS DE AGUA EN COTOCA (COTOCA) Fecha : 25/03/2012


Supervisor : EDGAR MORAN FLORES Empresa: SITECO Moneda : US BS

Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA)

VOLUMENES DE OBRA CONTRACTUALMENTE AUTORIZADOS CONTRATO MODIFICATORIO


PRECIO PRECIO INCREMENTOS DECREMENTOS
PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD UNITARIO TOTAL CANTIDAD
CANT. P. PARCIAL CANT. P. PARCIAL TOTAL
Bs Bs
CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 -2.60 -172.74 0.00 0.00
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,496.44 43,918.09

ACTIVIDAD DE CREACION NUEVA COLUMNAS


COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02
Módulo: MSCZ0053 TANQUE ELEVADO
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.66 1,402.67 40.66 3,890.35
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,009.81

02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -144.00 -1,147.68 0.00 0.00
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.22 3,000.59 660.13 -0.03 -90.02 0.19 570.11
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -9.83 -1,241.53 11.67 1,473.92
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 33.00 6,250.20 76.00 14,394.40
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -3.00 -8.16 40.00 108.80
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.76 3,285.19 1.00 4,322.62
Costo Modulo 26,308.33 26,722.74
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,137.81 251,591.55
Proyecto: FPS-07-00003600 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD 15 DE ABRIL (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,496.44 44,090.83
ACTIVIDAD DE CREACION NUEVA COLUMNAS
COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,005.98
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.98 1,149.12 -64.00 -430.38 80.00 638.40
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 2.60 492.44 45.60 8,636.64
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 26,309.77 21,605.61
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,139.25 246,643.33
Proyecto: FPS-07-00003599 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD VILLA NUEVA (COTOCA) ###
###

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,456.33 1,456.33 1.00 1,456.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,487.44 44,081.83
ACTIVIDAD DE CREACION NUEVA COLUMNAS
COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02

Módulo: MSCZ0053 TANQUE ELEVADO ###


01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,005.98

02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -64.00 -430.38 80.00 637.60
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 2.60 492.44 45.60 8,636.64
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 26,308.33 21,604.81
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,128.81 246,633.53
Proyecto: FPS-07-00003617 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD ARROYITO (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MCBB0342 TRABAJOS COMPLEMENTARIOS
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
41HA001 HIPOCLORADOR COMPLETO (SG/DETALLE); ENVASE PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
93FB042 CASETA PARA HIPOCLORADOR PZA 1.00 3,075.29 3,075.29 1.00 3,075.29
93GB187 PROV. Y COLOC. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 20,966.42 20,966.42
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 1,500.00 2.86 4,290.00 1,690.00 4,833.40 3,190.00 9,123.40
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 360.00 95.68 34,444.80 118.50 11,338.08 0.00 478.50 45,782.88
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 150.00 66.44 9,966.00 -150.00 -9,966.00 0.00 0.00
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 210.00 53.15 11,161.50 262.03 13,927.14 472.03 25,088.64
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 1,500.00 1.78 2,670.00 1,690.00 3,008.20 3,190.00 5,678.20
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 1,500.00 2.92 4,380.00 1,690.00 3,190.00 9,314.80
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93DC693 LIMPIEZA GENERAL GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93IB0015 ANCLAJE DE HªSª H-18 M3 6.00 702.52 4,215.12 6.00 4,215.12
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 1,500.00 17.17 25,755.00 1,690.00 3,190.00 54,772.30
Costo Modulo 105,083.38 162,176.30
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 360.00 95.68 34,444.80 118.50 11,338.08 -478.50 -45,782.88
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 210.00 53.15 11,161.50 262.03 13,927.14 -472.03 -25,088.64

Módulo: MPTS1029 MEDIDAS DE MITIGACION


93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 3.00 1,193.40 3,580.20 3.00 3,580.20
Costo Modulo 10,097.17 10,097.17
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 2,617.98 9,948.32 -1.42 2.38 6,230.79
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 1,937.67 1,453.25 -0.03 0.72 1,395.12
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 77.99 1,793.77 1.22 95.15 24.22 1,888.92
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 377.03 6,786.54 3.25 1,225.35 21.25 8,011.89
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 27.09 1,408.68 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,408.21 1,874.52 -0.55 0.00 0.00
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 39,274.00 35,181.42
ACTIVIDAD DE CREACION NUEVA COLUMNAS
COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,592.56 19,518.38 -0.95 -4,362.93 3.30 15,155.45
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,371.57 13,149.12 4.10 13,823.44 8.00 26,972.56
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 121,104.00 141,649.23

02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -64.00 -430.38 80.00 637.60
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 138.87 5,971.41 2.60 492.44 45.60 6,332.47
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 24,135.54 19,300.64
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 30.00 829.14 24,874.20 6.00 115.70 36.00 29,849.04
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 30.00 997.92 29,937.60 6.00 115.70 36.00 35,925.12
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 30.00 805.29 24,158.70 6.00 115.70 36.00 28,990.44
Costo Modulo 78,970.50 94,764.60
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 93.13 7,347.96 78.90 7,347.96
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,112.99 92,788.07 -21,888.80 11,112.99
TOTAL GENERAL 410,744.00 420,490.73
Proyecto: FPS-07-00003613 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CUMAVI (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION 893.92
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,000.00 2.86 8,580.00 200.00 572.00 3,200.00 9,152.00
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 840.00 79.73 66,973.20 120.00 9,567.60 960.00 76,540.80
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 300.00 53.15 15,945.00 -300.00 -15,945.00 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,000.00 1.78 5,340.00 200.00 356.00 3,200.00 5,696.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,000.00 2.92 8,760.00 200.00 584.00 3,200.00 9,344.00
42BC008 CAMARA DE LLAVES PZA 5.00 653.37 3,266.85 5.00 3,266.85
93AD562 RELLENO COMUN COMPACTADO M3 540.00 26.58 14,353.20 402.31 10,693.40 942.31 25,046.60
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93IB0015 ANCLAJE DE HªSª H-18 M3 1.50 1,289.66 1,934.49 1.50 1,934.49
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,000.00 16.29 48,870.00 200.00 3,258.00 3,200.00 52,128.00
Costo Modulo 176,549.43 185,635.43
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 713.07 34,940.43 -24.00 25.00 17,826.75
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 928.45 45,494.05 -24.00 25.00 23,211.25
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 576.73 28,259.77 -24.00 25.00 14,418.25
Costo Modulo 108,694.25 55,456.25
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
TOTAL GENERAL 309,130.30 264,978.30

Proyecto: FPS-07-00003614 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD LA CRUCEÑA (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION 3,900.00 ###
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 3,500.00 10,010.00
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 3,500.00 6,230.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 3,500.00 10,220.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 552.91 14,696.25 1,042.91 27,720.45
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 90.36 75,902.40 202.91 18,334.61 1,042.91 94,237.01
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 400.00 6,868.00 3,900.00 66,963.00
Costo Modulo 201,936.05 223,232.41
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 45.00 829.14 37,311.30 -5.00 40.00 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 45.00 997.92 44,906.40 -5.00 40.00 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 45.00 805.29 36,238.05 -5.00 40.00 32,211.60
Costo Modulo 118,455.75 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
ACTIVIDAD DE CREACION NUEVA BOMBA SUMERGIBLE 3HP
BOMBA SUMERGIBLE 2HP Y ACCESORIOS PZA 26,285.80 1.00 26,285.80 1.00 26,285.80
Costo Modulo 26,285.80
TOTAL GENERAL 347,186.73 381,607.14
Proyecto: FPS-07-00003615 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD NUEVO AMANECER (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 -600.00 -1,716.00 2,900.00 8,294.00
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 -600.00 -1,068.00 2,900.00 5,162.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 -600.00 2,900.00 8,468.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 374.12 9,944.11 864.12 22,968.31
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 82.39 69,207.60 30.00 2,471.70 870.00 71,679.30
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 -600.00 2,900.00 49,793.00
Costo Modulo 195,241.25 174,216.56
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 829.14 40,627.86 -9.00 40.00 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 997.92 48,898.08 -9.00 40.00 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 805.29 39,459.21 -9.00 40.00 32,211.60
Costo Modulo 128,985.15 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
ACTIVIDAD DE CREACION NUEVA BOMBA SUMERGIBLE 3HP
BOMBA SUMERGIBLE 2HP Y ACCESORIOS PZA 26,285.80 1.00 26,285.80 1.00 26,285.80
Costo Modulo 26,285.80
TOTAL GENERAL 351,021.33 332,591.29
CONTRATO MODIFICATORIO Nº1

Proyecto: CONST. 7 SISTEMAS DE AGUA EN COTOCA (COTOCA) Fecha : 25/03/2012


Supervisor : EDGAR MORAN FLORES Empresa: SITECO Moneda : US BS

Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA)

VOLUMENES DE OBRA CONTRACTUALMENTE AUTORIZADOS CONTRATO MODIFICATORIO


PRECIO PRECIO INCREMENTOS DECREMENTOS
PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD UNITARIO TOTAL CANTIDAD
CANT. P. PARCIAL CANT. P. PARCIAL TOTAL
Bs Bs
CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 -2.60 -172.74 0.00 0.00
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,496.44 #REF!
Módulo: MSCZ0053 TANQUE ELEVADO
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.66 1,402.67 40.66 3,890.35
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,009.81
Módulo: MSCZ0057 CERCO MALLA OLIMPICA
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -144.00 -1,147.68 0.00 0.00
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.22 3,000.59 660.13 -0.03 -90.02 0.19 570.11
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -9.83 -1,241.53 11.67 1,473.92
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 33.00 6,250.20 76.00 14,394.40
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -3.00 -8.16 40.00 108.80
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.76 3,285.19 1.00 4,322.62
Costo Modulo 26,308.33 26,722.74
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,137.81 #REF!
Proyecto: FPS-07-00003600 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD 15 DE ABRIL (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,496.44 #REF!
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,005.98

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.98 1,149.12 -64.00 -430.38 80.00 638.40
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 2.60 492.44 45.60 8,636.64
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 26,309.77 21,605.61
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,139.25 #REF!
Proyecto: FPS-07-00003599 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD VILLA NUEVA (COTOCA) ###
###

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,456.33 1,456.33 1.00 1,456.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,487.44 #REF!

Módulo: MSCZ0053 TANQUE ELEVADO ###


01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,005.98
Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###
02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -64.00 -430.38 80.00 637.60
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 2.60 492.44 45.60 8,636.64
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 26,308.33 21,604.81
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,128.81 #REF!
Proyecto: FPS-07-00003617 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD ARROYITO (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MCBB0342 TRABAJOS COMPLEMENTARIOS
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
41HA001 HIPOCLORADOR COMPLETO (SG/DETALLE); ENVASE PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
93FB042 CASETA PARA HIPOCLORADOR PZA 1.00 3,075.29 3,075.29 1.00 3,075.29
93GB187 PROV. Y COLOC. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 20,966.42 20,966.42
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 1,500.00 2.86 4,290.00 #REF! #REF! #REF! #REF!
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 360.00 95.68 34,444.80 118.50 11,338.08 0.00 478.50 45,782.88
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 150.00 66.44 9,966.00 -150.00 -9,966.00 0.00 0.00
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 210.00 53.15 11,161.50 #REF! #REF! #REF! #REF!
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 1,500.00 1.78 2,670.00 #REF! #REF! #REF! #REF!
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 1,500.00 2.92 4,380.00 #REF! #REF! #REF!
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93DC693 LIMPIEZA GENERAL GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93IB0015 ANCLAJE DE HªSª H-18 M3 6.00 702.52 4,215.12 6.00 4,215.12
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 1,500.00 17.17 25,755.00 #REF! #REF! #REF!
Costo Modulo 105,083.38 #REF!

Módulo: MPTS1029 MEDIDAS DE MITIGACION


93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 3.00 1,193.40 3,580.20 3.00 3,580.20
Costo Modulo 10,097.17 10,097.17
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 2,617.98 9,948.32 -1.42 2.38 6,230.79
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 1,937.67 1,453.25 -0.03 0.72 1,395.12
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 77.99 1,793.77 1.22 95.15 24.22 1,888.92
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 377.03 6,786.54 3.25 1,225.35 21.25 8,011.89
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 27.09 1,408.68 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,408.21 1,874.52 -0.55 0.00 0.00
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 39,274.00 #REF!
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,592.56 19,518.38 -0.95 -4,362.93 3.30 15,155.45
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,371.57 13,149.12 4.10 13,823.44 8.00 26,972.56
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 121,104.00 141,649.23

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -64.00 -430.38 80.00 637.60
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 138.87 5,971.41 2.60 492.44 45.60 6,332.47
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 24,135.54 19,300.64
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 30.00 829.14 24,874.20 6.00 115.70 36.00 29,849.04
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 30.00 997.92 29,937.60 6.00 115.70 36.00 35,925.12
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 30.00 805.29 24,158.70 6.00 115.70 36.00 28,990.44
Costo Modulo 78,970.50 94,764.60
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 93.13 7,347.96 78.90 7,347.96
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,112.99 #REF! #REF! 11,112.99
TOTAL GENERAL 410,744.00 #REF!
Proyecto: FPS-07-00003613 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CUMAVI (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION 893.92
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,000.00 2.86 8,580.00 0.00 3,000.00 8,580.00
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 840.00 79.73 66,973.20 120.00 9,567.60 960.00 76,540.80
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 300.00 53.15 15,945.00 -300.00 -15,945.00 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,000.00 1.78 5,340.00 0.00 0.00 3,000.00 5,340.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,000.00 2.92 8,760.00 0.00 0.00 3,000.00 8,760.00
42BC008 CAMARA DE LLAVES PZA 5.00 653.37 3,266.85 5.00 3,266.85
93AD562 RELLENO COMUN COMPACTADO M3 540.00 26.58 14,353.20 402.31 10,693.40 942.31 25,046.60
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93IB0015 ANCLAJE DE HªSª H-18 M3 1.50 1,289.66 1,934.49 1.50 1,934.49
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,000.00 16.29 48,870.00 0.00 0.00 3,000.00 48,870.00
Costo Modulo 176,549.43 180,865.43
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 713.07 34,940.43 -30.00 19.00 13,548.33
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 928.45 45,494.05 -30.00 19.00 17,640.55
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 576.73 28,259.77 -30.00 19.00 10,957.87
Costo Modulo 108,694.25 42,146.75
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
TOTAL GENERAL 309,130.30 246,898.80

Proyecto: FPS-07-00003614 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD LA CRUCEÑA (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION 3,900.00 ###
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 3,500.00 10,010.00
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 3,500.00 6,230.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 3,500.00 10,220.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 #REF! #REF! #REF! #REF!
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 90.36 75,902.40 #REF! #REF! #REF! #REF!
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 400.00 6,868.00 3,900.00 66,963.00
Costo Modulo 201,936.05 #REF!
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 45.00 829.14 37,311.30 -5.00 40.00 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 45.00 997.92 44,906.40 -5.00 40.00 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 45.00 805.29 36,238.05 -5.00 40.00 32,211.60
Costo Modulo 118,455.75 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
TOTAL GENERAL 347,186.73 #REF!
Proyecto: FPS-07-00003615 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD NUEVO AMANECER (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 -600.00 -1,716.00 2,900.00 8,294.00
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 -600.00 -1,068.00 2,900.00 5,162.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 -600.00 2,900.00 8,468.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 374.12 9,944.11 864.12 22,968.31
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 82.39 69,207.60 30.00 2,471.70 870.00 71,679.30
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 -600.00 2,900.00 49,793.00
Costo Modulo 195,241.25 174,216.56
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 829.14 40,627.86 -9.00 40.00 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 997.92 48,898.08 -9.00 40.00 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 805.29 39,459.21 -9.00 40.00 32,211.60
Costo Modulo 128,985.15 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
TOTAL GENERAL 351,021.33 #REF!
CONTRATO MODIFICATORIO Nº1

Proyecto: CONST. 7 SISTEMAS DE AGUA EN COTOCA (COTOCA) Fecha : 25/03/2012


Supervisor : EDGAR MORAN FLORES Empresa: SITECO Moneda : US BS

Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA)

VOLUMENES DE OBRA CONTRACTUALMENTE AUTORIZADOS CONTRATO MODIFICATORIO


PRECIO PRECIO INCREMENTOS DECREMENTOS
PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD UNITARIO TOTAL CANTIDAD
CANT. P. PARCIAL CANT. P. PARCIAL TOTAL
Bs Bs
CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 -2.60 -172.74 0.00 0.00
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,496.44 43,918.09

ACTIVIDAD DE CREACION NUEVA COLUMNAS


COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02
Módulo: MSCZ0053 TANQUE ELEVADO
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.66 1,402.67 40.66 3,890.35
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,009.81

02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -144.00 -1,147.68 0.00 0.00
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3 0.22 3,000.59 660.13 -0.03 -90.02 0.19 570.11
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -9.83 -1,241.53 11.67 1,473.92
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 33.00 6,250.20 76.00 14,394.40
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -3.00 -8.16 40.00 108.80
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.76 3,285.19 1.00 4,322.62
Costo Modulo 26,308.33 26,722.74
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,137.81 251,591.55
Proyecto: FPS-07-00003600 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD 15 DE ABRIL (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,496.44 44,090.83
ACTIVIDAD DE CREACION NUEVA COLUMNAS
COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,005.98
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.98 1,149.12 -64.00 -430.38 80.00 638.40
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 2.60 492.44 45.60 8,636.64
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 26,309.77 21,605.61
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,139.25 246,643.33
Proyecto: FPS-07-00003599 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD VILLA NUEVA (COTOCA) ###
###

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MPTS1029 MEDIDAS DE MITIGACION ###
93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.77 8,903.77
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 3,862.52 14,677.58 -1.42 2.38 9,192.80
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 2,122.80 1,592.10 -0.03 0.72 1,528.42
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 127.27 2,927.21 1.22 155.27 24.22 3,082.48
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 422.84 7,611.12 3.25 1,374.23 21.25 8,985.35
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 38.78 2,016.56 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,456.33 1,456.33 1.00 1,456.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,665.21 2,015.87 -0.55 0.00 0.00
96AB016 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 3,647.08 3,647.08 1.00 3,647.08
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 -2,770.68 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 50,487.44 44,081.83
ACTIVIDAD DE CREACION NUEVA COLUMNAS
COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02

Módulo: MSCZ0053 TANQUE ELEVADO ###


01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,688.23 19,924.98 -0.95 -4,453.82 3.30 15,471.16
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,626.70 14,144.13 4.10 14,869.47 8.00 29,013.60
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 122,505.61 144,005.98

02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -64.00 -430.38 80.00 637.60
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 189.40 8,144.20 2.60 492.44 45.60 8,636.64
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 26,308.33 21,604.81
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
01AB002 REPLANTEO Y CONTROL DE TUBERIAS ML 12.00 2.86 34.32 12.00 34.32
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 3.84 95.68 367.41 3.84 367.41
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 1.20 66.44 79.73 1.20 79.73
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 2.64 53.15 140.32 2.64 140.32
40DA037 PROV. Y TENDIDO TUBERIA PVC 3 PULG - CLASE 9 ML 12.00 44.88 538.56 12.00 538.56
40IA001 PRUEBA HIDRAULICA - TUBERIAS HASTA 4 PULG. ML 12.00 1.78 21.36 12.00 21.36
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 12.00 2.92 35.04 12.00 35.04
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 1.00 829.14 829.14 1.00 829.14
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 1.00 992.24 992.24 1.00 992.24
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00 805.29 805.29 1.00 805.29
Costo Modulo 3,843.41 3,843.41
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 96.05 7,578.35 78.90 7,578.35
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,343.38 11,343.38
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB032 MOVILIZACION Y DESMOVILIZACION GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 16,736.87 16,736.87
TOTAL GENERAL 240,128.81 246,633.53
Proyecto: FPS-07-00003617 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD ARROYITO (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MCBB0342 TRABAJOS COMPLEMENTARIOS
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
41HA001 HIPOCLORADOR COMPLETO (SG/DETALLE); ENVASE PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
93FB042 CASETA PARA HIPOCLORADOR PZA 1.00 3,075.29 3,075.29 1.00 3,075.29
93GB187 PROV. Y COLOC. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 20,966.42 20,966.42
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 1,500.00 2.86 4,290.00 #REF! #REF! #REF! #REF!
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 360.00 95.68 34,444.80 118.50 11,338.08 0.00 478.50 45,782.88
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 150.00 66.44 9,966.00 -150.00 -9,966.00 0.00 0.00
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 210.00 53.15 11,161.50 #REF! #REF! #REF! #REF!
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 1,500.00 1.78 2,670.00 #REF! #REF! #REF! #REF!
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 1,500.00 2.92 4,380.00 #REF! #REF! #REF!
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93DC693 LIMPIEZA GENERAL GLB 1.00 1,754.05 1,754.05 1.00 1,754.05
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93IB0015 ANCLAJE DE HªSª H-18 M3 6.00 702.52 4,215.12 6.00 4,215.12
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 1,500.00 17.17 25,755.00 #REF! #REF! #REF!
Costo Modulo 105,083.38 #REF!
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 360.00 95.68 34,444.80 118.50 11,338.08 -478.50 -45,782.88
03CA003 RELLENO Y COMPACTADO (TIERRA COMUN) M3 210.00 53.15 11,161.50 262.03 13,927.14 -472.03 -25,088.64

Módulo: MPTS1029 MEDIDAS DE MITIGACION


93CC100 SEÑALIZACION GLB 1.00 5,253.63 5,253.63 1.00 5,253.63
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 3.00 1,193.40 3,580.20 3.00 3,580.20
Costo Modulo 10,097.17 10,097.17
Módulo: MSCZ0009 CASETA DE BOMBEO ###
01AC001 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 25.00 7.47 186.75 -11.20 13.80 103.09
02FB005 EXCAVACION M3 3.80 95.68 363.58 -1.42 2.38 227.72
03CB002 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3 2.60 66.44 172.74 2.60 172.74
09AA001 CIMIENTO CORRIDO DE HªAª M3 3.80 2,617.98 9,948.32 -1.42 2.38 6,230.79
09BB001 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.75 1,937.67 1,453.25 -0.03 0.72 1,395.12
09CA001 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 23.00 77.99 1,793.77 1.22 95.15 24.22 1,888.92
10AB009 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 28.00 126.30 3,536.40 -6.98 21.02 2,654.83
15BC002 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 18.00 377.03 6,786.54 3.25 1,225.35 21.25 8,011.89
31BA002 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2 1.80 654.75 1,178.55 1.42 929.75 3.22 2,108.30
31BB001 PROVISION Y COLOCACION DE VENTANA METALICA M2 2.00 459.55 919.10 5.97 2,743.51 7.97 3,662.61
52FA001 ACOMETIDA ELECTRICIDAD GLB 1.00 404.74 404.74 1.00 404.74
93CD092 PROV. Y COLOC. TABLERO DE CONTROL PZA 1.00 416.89 416.89 1.00 416.89
93GB025 PINTURA LATEX M2 52.00 27.09 1,408.68 -52.00 -2,016.56 0.00 0.00
93GB197 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB 1.00 1,465.33 1,465.33 1.00 1,465.33
93GC026 INSTALACION ELECTRICA GLB 1.00 807.33 807.33 1.00 807.33
93GC028 IMPERMEABILIZACION SOBRECIMIENTO ML 15.20 14.66 222.83 -0.30 14.90 218.43
93GC051 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.55 3,408.21 1,874.52 -0.55 0.00 0.00
96FC203 REVOQUE CON MORTERO DE CEMENTO M2 44.00 62.97 2,770.68 -44.00 0.00 0.00
96FC563 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 24.00 148.50 3,564.00 0.22 32.67 24.22 3,596.67
Costo Modulo 39,274.00 35,181.42
ACTIVIDAD DE CREACION NUEVA COLUMNAS
COLUMNAS DE HORMIGON ARMADO M3 4,688.23 0.31 1,453.35 0.31 1,453.35
ZAPATAS DE HORMIGON ARMADO M3 3,626.70 0.10 362.67 0.10 362.67
Costo Modulo 1,816.02
Módulo: MSCZ0053 TANQUE ELEVADO ###
01AC003 RELLENO DE ESTRUCTURAS GBL 1.00 570.30 570.30 1.00 570.30
02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 40.62 3,886.52
31AD002 ESCALERA CON GUARDACUERPOS ML 17.50 576.99 10,097.33 -5.40 -3,115.75 12.10 6,981.58
31BD002 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML 2.00 460.77 921.54 -0.20 -92.15 1.80 829.39
93AB407 TAPA METALICA DE 70X70 CM PZA 1.00 690.14 690.14 1.00 690.14
93AD562 RELLENO COMPACTADO COMUN M3 20.00 66.44 1,328.80 20.00 1,328.80
93BB056 CAMARA DE VALCULAS GLB 1.00 770.31 770.31 1.00 770.31
93BC677 ACCESORIA DE TANQUE M3 1.00 2,463.56 2,463.56 1.00 2,463.56
93GB012 MEDIDOR DE NIVELES TANQUES DE H20 M2 1.00 430.31 430.31 1.00 430.31
93GB013 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2 15.00 23.14 347.10 5.00 115.70 20.00 462.80
93GB025 PINTURA LATEX M3 150.00 24.92 3,738.00 150.00 3,738.00
93GB20001 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3 46.00 28.94 1,331.24 46.00 1,331.24
93GB349 HªAª H21 CUBA M3 7.60 4,720.33 35,874.51 2.76 13,028.11 10.36 48,902.62
96BC014 HªAª COLUMNAS (TANQUE ELEVADO) M3 4.25 4,592.56 19,518.38 -0.95 -4,362.93 3.30 15,155.45
96BC015 HªAª VIGA (TANQUE ELEVADO) M3 3.70 4,743.52 17,551.02 0.10 474.35 3.80 18,025.38
96CA010 ZAPATAS DE HªAª M3 3.90 3,371.57 13,149.12 4.10 13,823.44 8.00 26,972.56
96DC132 CARPETA DE Hº POBRE M3 1.41 1,351.77 1,906.00 -0.61 -824.58 0.80 1,081.42
96EC258 REVOQUE CON SIKA IMPERMEABILIZANTE M2 46.00 80.80 3,716.80 1.24 100.19 47.24 3,816.99
96FC524 BARANDA METALICA DE PROTECCION GLB 1.00 4,211.86 4,211.86 1.00 4,211.86
Costo Modulo 121,104.00 141,649.23

02FB005 EXCAVACION M3 26.00 95.68 2,487.68 14.62 1,398.84 -40.62 -3,886.52

Módulo: MSCZ0057 CERCO MALLA OLIMPICA ###


02EB001 LIMPIEZA DE TERRENO Y DESHIERBE M2 144.00 7.97 1,147.68 -64.00 -430.38 80.00 637.60
02FB001 EXCAVACION M3 0.87 95.68 83.24 -0.31 -29.66 0.56 53.58
06BC001 HORMIGON ARMADO - ZAPATAS (ESTRCUTURAS) M3 0.22 3,000.59 660.13 -0.13 -390.08 0.09 270.05
09AA0025 CIMIENTO CORRIDO DE HºCº M3 2.58 1,496.84 3,861.85 2.58 3,861.85
10AB012 MURO DE LADRILLO ADOBITO M2 21.50 126.30 2,715.45 -14.88 -1,879.34 6.62 836.11
93AB105 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.65 3,031.55 1,970.51 -0.56 -1,697.67 0.09 272.84
93AB128 CERCO DE MALLA OLIMPICA ML 43.00 138.87 5,971.41 2.60 492.44 45.60 6,332.47
93DB127 REPLANTEO CERCO PERIMETRAL ML 43.00 2.72 116.96 -7.00 -19.04 36.00 97.92
93FB163 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 8.25 796.47 6,570.88 -6.16 -4,906.26 2.09 1,664.62
93IB0056 COLUMNAS DE HºAº M3 0.24 4,322.62 1,037.43 0.98 4,236.17 1.22 5,273.60
Costo Modulo 24,135.54 19,300.64
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 30.00 829.14 24,874.20 6.00 115.70 36.00 29,849.04
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 30.00 997.92 29,937.60 6.00 115.70 36.00 35,925.12
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 30.00 805.29 24,158.70 6.00 115.70 36.00 28,990.44
Costo Modulo 78,970.50 94,764.60
Módulo: MSCZ181 IMPULSION POZO TANQUE ###
01AB001 EXCAVACION M3 9.60 95.68 918.53 9.60 918.53
40IA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML 20.00 2.92 58.40 20.00 58.40
40JA001 RELLENO COMPACTADO M3 9.00 66.44 597.96 9.00 597.96
93AD562 PRUEBA HIDRAULICA D=4",8" ML 78.90 1.78 140.44 78.90 140.44
93BC693 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML 78.90 93.13 7,347.96 78.90 7,347.96
93BC961 REPLANTEO DE LINEAS DE TUBERIA ML 20.00 2.86 57.20 20.00 57.20
93GG035 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB 1.00 1,992.50 1,992.50 1.00 1,992.50
Costo Modulo 11,112.99 #REF! #REF! 11,112.99
TOTAL GENERAL 410,744.00 #REF!
Proyecto: FPS-07-00003613 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CUMAVI (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION 893.92
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,000.00 2.86 8,580.00 0.00 3,000.00 8,580.00
02AC001 EXCAVACION DE 0-2 M SUELO SEMIDURO M3 840.00 79.73 66,973.20 120.00 9,567.60 960.00 76,540.80
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 300.00 53.15 15,945.00 -300.00 -15,945.00 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,000.00 1.78 5,340.00 0.00 0.00 3,000.00 5,340.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,000.00 2.92 8,760.00 0.00 0.00 3,000.00 8,760.00
42BC008 CAMARA DE LLAVES PZA 5.00 653.37 3,266.85 5.00 3,266.85
93AD562 RELLENO COMUN COMPACTADO M3 540.00 26.58 14,353.20 402.31 10,693.40 942.31 25,046.60
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93IB0015 ANCLAJE DE HªSª H-18 M3 1.50 1,289.66 1,934.49 1.50 1,934.49
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,000.00 16.29 48,870.00 0.00 0.00 3,000.00 48,870.00
Costo Modulo 176,549.43 180,865.43
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 713.07 34,940.43 -30.00 19.00 13,548.33
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 928.45 45,494.05 -30.00 19.00 17,640.55
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 576.73 28,259.77 -30.00 19.00 10,957.87
Costo Modulo 108,694.25 42,146.75
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES ###
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
TOTAL GENERAL 309,130.30 246,898.80

Proyecto: FPS-07-00003614 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD LA CRUCEÑA (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL
CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION 3,900.00 ###
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 3,500.00 10,010.00
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 3,500.00 6,230.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 3,500.00 10,220.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 #REF! #REF! #REF! #REF!
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 90.36 75,902.40 #REF! #REF! #REF! #REF!
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 400.00 6,868.00 3,900.00 66,963.00
Costo Modulo 201,936.05 #REF!
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS ###
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 45.00 829.14 37,311.30 -5.00 40.00 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 45.00 997.92 44,906.40 -5.00 40.00 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 45.00 805.29 36,238.05 -5.00 40.00 32,211.60
Costo Modulo 118,455.75 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
ACTIVIDAD DE CREACION NUEVA BOMBA SUMERGIBLE 3HP
BOMBA SUMERGIBLE 2HP Y ACCESORIOS PZA 26,285.80 1.00 26,285.80 1.00 26,285.80
Costo Modulo 26,285.80
TOTAL GENERAL 347,186.73 #REF!
Proyecto: FPS-07-00003615 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD NUEVO AMANECER (COTOCA)

PRECIO PRECIO
ACTIVIDAD DESCRIPCION UNID CANTIDAD CANT. P. PARCIAL CANT. P. PARCIAL CANTIDAD PRECIO
UNITARIO TOTAL

CONSTRUCCION NUEVA
Módulo: MDL070002 RED DE DISTRIBUCCION
01AB001 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,500.00 2.86 10,010.00 -600.00 -1,716.00 2,900.00 8,294.00
03BA010 RELLENO MANUAL CON TIERRA CERNIDA (SIN MATERIAL M3 350.00 53.15 18,602.50 -350.00 -18,602.50 0.00 0.00
40IA001 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML 3,500.00 1.78 6,230.00 -600.00 -1,068.00 2,900.00 5,162.00
40JA001 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML 3,500.00 2.92 10,220.00 -600.00 2,900.00 8,468.00
42BC008 CAMARA DE LLAVES PZA 6.00 653.37 3,920.22 6.00 3,920.22
93IB0015 ANCLAJE DE HªSª H-18 M3 2.00 702.52 1,405.04 2.00 1,405.04
93CB400 RELLENO Y COMPACTADO CON TIERRA COMUN M3 490.00 26.58 13,024.20 374.12 9,944.11 864.12 22,968.31
93GB201 ACCESORIOS DE RED SEGÚN DISEÑO GLB 1.00 2,526.69 2,526.69 1.00 2,526.69
93GC035 EXCAVACION MANUAL M3 840.00 82.39 69,207.60 30.00 2,471.70 870.00 71,679.30
96GS001 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML 3,500.00 17.17 60,095.00 -600.00 2,900.00 49,793.00
Costo Modulo 195,241.25 174,216.56
Módulo: MPTS1029 MEDIDAS DE MITIGACION
93CC100 SEÑALIZACION GLB 1.00 5,253.66 5,253.66 1.00 5,253.66
93FA047 LETRINA PZA 1.00 1,263.34 1,263.34 1.00 1,263.34
S36A389 CONTENEDORES DE BASURA PZA 2.00 1,193.40 2,386.80 2.00 2,386.80
Costo Modulo 8,903.80 8,903.80
Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS
41BC025 PEDESTAL Y BASE PARA PILETA HºAº PZA 49.00 829.14 40,627.86 -9.00 40.00 33,165.60
93FB395 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA 49.00 997.92 48,898.08 -9.00 40.00 39,916.80
93GB309 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 49.00 805.29 39,459.21 -9.00 40.00 32,211.60
Costo Modulo 128,985.15 105,294.00
Módulo: MSCZ645 ACTIVIDADES PRELIMINARES
01FA003 INSTALACION DE FAENAS GLB 1.00 6,527.63 6,527.63 1.00 6,527.63
93GB187 PROV. Y COLO. PLACA DE ENTREGA FPS PZA 1.00 2,223.46 2,223.46 1.00 2,223.46
93GB70006 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA 1.00 6,231.73 6,231.73 1.00 6,231.73
Costo Modulo 14,982.82 14,982.82
Módulo: MTRJ476 HIPOCLORADOR DE CARGA CONSTANTE
01FA003 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA 1.00 2,908.31 2,908.31 1.00 2,908.31
Costo Modulo 2,908.31 2,908.31
ACTIVIDAD DE CREACION NUEVA BOMBA SUMERGIBLE 3HP
BOMBA SUMERGIBLE 2HP Y ACCESORIOS PZA 26,285.80 1.00 26,285.80 1.00 26,285.80
Costo Modulo 26,285.80
TOTAL GENERAL 351,021.33 332,591.29
COMPUTOS METRICOS - BALANCE ECONOMICO
Proyecto: CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD BARRIENTOS (YAPACANI)

Dimensiones Volumenes
ITEM DESCRIPCION Unid. GRAFICO
ancho largo alto Nº Veces Parcial Total
Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB
Instalacion de faenas 1.00 1.00
1.00
2 MOVILIZACION Y DESMOVILIZACION GLB
Movilizacion y desmovilizacion 1.00 1.00
1.00
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA
Prov. Y coloc placa de entrega FPS 1.00 1.00
1.00

4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA


Letrero Muro pintado 1.00 1.00
1.00

Módulo: MPTS1029 MEDIDAS DE MITIGACION


5 SEÑALIZACION GLB
Señalizacion 1.00 1.00
5.00
6 LETRINA PZA
Letrina 1.00 1.00
1.00
7 CONTENEDORES DE BASURA PZA
Contenedores de Basura 2.00 2.00
O I
2.00

Módulo: MSCZ0009 CASETA DE BOMBEO


4 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 3.45
Replanteo de estructura y edificaciones 4.00 3.45 4.00 1.00 13.80
13.80
5 EXCAVACION M3
Excavacion 0.40 3.45 0.40 2.00 1.10
0.40 4.00 0.40 2.00 1.28
2.38
6 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3
Relleno compactado manual-no incluye material 2.60 2.60

0.40 2.60
7 CIMIENTO CORRIDO DE HªAª M3 0.40 3.45 0.40 3.45 2.00 1.10
Cimiento corrido de HºAº 0.40 4.00 0.40 0.40 2.00 1.28
4.00
0.30 2.38
8 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.15 3.45 0.30 3.45 3.00 0.47
Sobreciemiento de Hormigon ciclopeo FC=210 0.15 4.00 0.30 0.30 4.00 0.72
4.00 0.72
9 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 3.30
Contrapiso de piedra y cemento 1:3:4 3.30 3.85 3.85 1.00 12.71
0.62 4.98 2.00 6.18
0.62 4.30 2.00 5.33
24.22
10 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 4.20

Muro de ladrillo de Adobito visto 15 cm 4.20 1.00 1.00 2.00 8.40


3.65 2.70 2.70 1.00 9.86
3.65 0.54 0.54 1.00 0.99
1.77 1.00 1.00 1.77
1.77 21.02
11 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 4.60

Cubieta placa ondulada fibrocemento 2.31 4.60 2.31 2.00 21.25


21.25
12 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2
Prov. Y colocado puerta metalica y malla olimp 1.20 2.68 1.00 3.22
3.22
13 PROVISION Y COLOCACION DE VENTANA METALICA M2
Provision y colocacion de ventana metalica 1.64 1.62 3.00 7.97
7.97
14 ACOMETIDA ELECTRICIDAD GLB
Acometida elctricidad 1.00 1.00
1.00
15 PROV. Y COLOC. TABLERO DE CONTROL PZA
Prov y coloc. Tablero de control 1.00 1.00
1.00
16 PINTURA LATEX M2
Pintura latex 52.00 52.00
52.00
17 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB
Pilastra de ladrillo visto para medidor 1.00 1.00
1.00
18 INSTALACION ELECTRICA GLB
instalacion electrica 1.00 1.00
1.00
19 IMPERMEABILIZACION SOBRECIMIENTO ML 3.45 2.00 6.90
impermeabilizacion sobrecimiento 4.00 2.00 8.00
14.90
20 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3 0.20 3.45 0.30 2.00 0.21
Viga HºAº encadenado nivel cubierta 0.20 4.00 0.30 2.00 0.24
0.89
21 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA
Hipoclorador completo según diseño 1.00 1.00
1.00
22 REVOQUE CON MORTERO DE CEMENTO M2
Revoque con mortero y cemento 44.00 44.00
44.00
23 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 3.30 3.85 1.00 12.71
Piso de cemento frotachado sin contrapiso 0.62 4.98 2.00 6.18
0.62 4.30 2.00 5.33
24.22
COLUMNA DE HORMIGON ARMADO M3
Columna de Hormigon Armado 0.20 0.12 3.20 4.00 0.31
0.31
ZAPATAS DE HORMIGON ARMADO M3
Zapatas de Hormigon Armado 0.50 0.50 0.10 4.00 0.10
0.10

Módulo: MSCZ0053 TANQUE ELEVADO


REPLANTEO DE ESTRUCTURA Ml
Replanteo de estructuras 4.40 4.40 4.40 2.00 8.80
17.60
4.40

24 RELLENO DE ESTRUCTURAS GBL 1.00 1.00


Relleno de Estructuras 1.00
25 EXCAVACION M3 2.20
Excavacion 2.20 2.20 2.10 2.20 4.00 40.66
2.10 40.66
26 ESCALERA CON GUARDACUERPOS ML
Escalera con guardacuerpos 12.10 12.10
12.10
27 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML
Prov. Y coloca de Escaleras metalica interior 1.80 1.80
1.80
28 TAPA METALICA DE 70X70 CM PZA 0.70 0.70 0.70
Tapa metalica de 70x70 cm 0.70 1.00 1.00
1.00
29 RELLENO COMPACTADO COMUN M3
Relleno compactado comun 20.00 20.00
20.00
30 CAMARA DE VALCULAS GLB
Camara de valvulas 1.00 1.00
1.00
31 ACCESORIA DE TANQUE M3
Accsorios de tanque 1.00 1.00
1.00
32 MEDIDOR DE NIVELES TANQUES DE H20 M2
Medidor de niveles tanques de H20 1.00 1.00
1.00
33 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2
Prueba de estanquiedad y desinfeccion de tanque 20.00 20.00
20.00
34 PINTURA LATEX M3
Pintura latex 150.00 150.00
150.00
35 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3
Impermeabilizacion de tanque Muros tanque 4.40 1.50 2.00 13.20
1.50 13.20

4.00
4.00 1.50 2.00 12.00
1.50 12.00

Losa de fondo 4.40


4.40 4.40 1.00 19.36
4.40 19.36

Total de Revoque con sika M3 44.56


36 HªAª H21 CUBA M3 4.40
HºAº h21 Cuba Muros tanque 0.20 4.40 1.50 2.00 2.64
1.50 2.64
0.20
4.00
0.20 4.00 1.50 2.00 2.40
1.50 2.40
0.20
Losa de fondo 4.40
4.40 4.40 0.20 1.00 3.87
0.20 3.87
4.40
Losa Tapa 4.40
4.40 4.40 0.10 1.00 1.94
Tapa metalica 0.70 0.70 0.10 1.00 0.49
4.40 1.45
Total Cuba M3 10.36
37 HªAª COLUMNAS (TANQUE ELEVADO) M3
HºAª Columnas 0.25 0.25 13.20 4.00 3.30
3.30

38 HªAª VIGA (TANQUE ELEVADO) M3 0.25 3.80 0.25 3.80 16.00 3.80
HºAª Viga 0.25 ### 3.80

2.00
39 ZAPATAS DE HªAª M3 2.00 2.00 0.50 4.00 8.00
Zapata de HªAª 2.00 8.00
0.50
40 CARPETA DE Hº POBRE M3 2.00
Carpeta de Hº Pobre 2.00 2.00 0.05 4.00 0.80
2.00 0.80
41 REVOQUE CON SIKA IMPERMEABILIZANTE M2 0.05
Revoque con sika impermeabil Muros tanque 4.40 1.50 2.00 13.20
1.50 13.20

4.00
4.00 1.50 2.00 12.00
1.50 12.00

Losa de fondo 4.40


4.40 4.40 1.00 19.36
4.40 19.36

Total de Revoque con sika M2 44.56


42 BARANDA METALICA DE PROTECCION GLB 1.00 1.00
Baranda Metalica de Proteccion 1.00
Módulo: MSCZ0057 CERCO MALLA OLIMPICA
43 LIMPIEZA DE TERRENO Y DESHIERBE M2
Limpieza de terreno y deshierve 12.00 12.00 12.00 1.00 144.00
12.00 144.00

44 EXCAVACION M3
Excavacion zapatas 0.40 0.26 0.60 0.40 9.00 0.56
0.26 0.56
0.60
Excavacion cimiento M3 0.40 40.00 0.42 1.00 6.72
6.72
Total 7.28
45 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3
Hormigon armado - zapatas (Estructura) 0.40 0.26 0.10 0.40 18.00 0.19
0.26
0.10 0.19

46 CIMIENTO CORRIDO DE HºCº M3


Cimiento corrido de HºCª 0.40 40.00 0.26 9.00 37.44
0.20 40.00 0.16 40.00 9.00 11.52
0.26 48.96
0.40
47 MURO DE LADRILLO ADOBITO M2 10.00
Muro de Ladrillo adovito 10.00 0.30 ### 4.00 12.00
1.10 0.30 1.10 1.00 -0.33
### 11.67
48 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.20
Anclajes y zapatas de HºCº 0.20 0.30 0.16 0.30 9.00 0.09
0.16 0.09

49 CERCO DE MALLA OLIMPICA ML 10.00 1.90 10.00 4.00 76.00


Cerco de Malla Olimpica 1.90 76.00

50 REPLANTEO CERCO PERIMETRAL ML 10.00 10.00 10.00 2.00 40.00


replanteo cerco perimetral 10.00 40.00

51 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 1.10 1.90 1.10 1.00 2.09
Puerta de Malla olimpica para cerco perimetral 1.90 2.09

52 COLUMNAS DE HºAº Pza


Columnas de HºAº 26.00 1.00
2.70 1.00

Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS


15 PEDESTAL Y BASE PARA PILETA HºAº PZA
Pedestal y Base para Pileta Hª Aª 58.00 58.00
58.00
16 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA
Conexión Dom. c/ medidor 58.00 58.00
58.00

17 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00


Pozo de infiltracion 1 m3 1.00 1.00 1.00 1.00 58.00 1.00
1.00 58.00
Módulo: MSCZ181 IMPULSION POZO TANQUE
63 EXCAVACION M3 23.00 23.00
Excavancion 23.00

64 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML


Desinfeccion de tuberias (hasta D=4 pulg) 20.00 20.00 20.00 20.00
20.00
65 RELLENO COMPACTADO M3
Relleno compactado 9.00 9.00
9.00
66 PRUEBA HIDRAULICA D=4",8" ML
Prueba hidraulica D=4,8 78.90 78.90 78.90 78.90
78.90
67 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML
prov y coloc. Tuberia fg 2" con coplas 78.90 78.90 78.90 78.90
78.90
68 REPLANTEO DE LINEAS DE TUBERIA ML
Replanteo de lineas de tuberia 20.00 20.00 20.00 20.00
20.00
69 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB
Prov e instalacion de accesorios impusion de 2" 1.00 1.00
1.00

Módulo: RED DE DISTRIBUCCION


1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2,057.66 2057.66 1 2,057.66
Replanteo y control de lineas de tuberia 2,057.66
2" 11/2" 1"

2 EXCAVACION MANUAL M3 0.4 2057.66 0.6 0.4 1 493.84


Excavacion de 0-2 m suelo semiduro 2057.66 493.84
0.6

4 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML


Prueba hidraulica 2057.66 2057.66 1 2,057.66
2,057.66
2" 11/2" 1"
5 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML
Desinfeccion de tuberias 2057.66 2057.66 1 2,057.66
2,057.66
2" 11/2" 1"
6 CAMARA DE LLAVES PZA 5 1 5.00
Camara de llaves 5.00

7 ANCLAJE DE HªSª H-18 M3 2.00 1 2.00


Anclajes de HºSº 2.00

8 RELLENO Y COMPACTADO CON TIERRA COMUN M3


Relleno y compactado con tierra comun 0.4 2057.66 0.6 0.4 1 493.84
2" 2057.66 2057.66 8.0801736 485.76
0.6
9 ACCESORIOS DE RED SEGÚN DISEÑO GLB
Accesorios de red según diseño 1.00 1 1.00
1.00

11 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML


prov tendido tuebria pvc2 2057.66 2057.66 1 2,057.66
2,057.66
2"
COMPUTOS METRICOS
AMPLIACION SISTEMA DE AGUA POTABLE COMUNIDAD SIND. TRES CRUCES (YAPACANI)
Dimensiones Volumenes
ITEM DESCRIPCION Unid. GRAFICO
ancho largo alto Nº Veces Parcial Total
ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB
Instalacion de faenas 1.00 1.00
1.00
2 MOVILIZACION Y DESMOVILIZACION GLB
Movilizacion y desmovilizacion 1.00 1.00
1.00
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA
Prov. Y coloc placa de entrega FPS 1.00 1.00
1.00

4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) PZA


Letrero Muro pintado 1.00 1.00
1.00

MEDIDAS DE MITIGACION
1 LETRINA PZA
Letrina 1.00 1.00
1.00
2 Contenedores de Basura PZA
Contenedores de Basura 3.00 3.00
O I 3.00
3 CINTA PLASTICA DE SEGURIDAD ML
Letrina 100.00 100.00
100.00
4 SEÑALIZACION DE SEGURIDAD DE MADERA PZA
Señalizacion 2.00 2.00
2.00
5 SEÑALIZACION DE SEGURIDAD DE MADERA PZA
Señalizacion 4.00 4.00
4.00
6 LIMPIEZA Y RETIRO DE ESCOMBROS GLB
Limpieza y Retiro de Escombros 1.00 1.00
1.00
RED DE DISTRIBUCCION
1 REPLANTEO Y CONTROL DE LINEA DE TUBERIA ML 4,000 4000 1 4,000.00
Replanteo y control de lineas de tuberia 4,000.00
2" 1/2" 1"
2 EXCAVACION MANUAL M3 0.4 4000 0.6 0.4 1 960.00
Excavacion de 0-0,60 m suelo semiduro 4000 960.00
0.6
3 PRUEBA HIDRAULICA ML
Prueba hidraulica 4000 4000 1 4,000.00
4,000.00
2"
4 DESINFECCION DE TUBERIAS ML
Desinfeccion de tuberias 4000 4000 1 4,000.00
4,000.00
2"
5 CAMARA DE LLAVES PZA 5 1 5.00
Camara de llaves 5.00

6 ANCLAJE DE H°S° H-18 M3 2.00 1 2.00


Anclajes de HºSº 2.00
7 RELLENO COMPACTADO CON TIERRA COMUN M3
Relleno y compactado con tierra comun 0.4 4000 0.6 0.4 1 960.00
2" 4000 4000 15.7075 944.29
0.6
8 ACCESORIOS DE RED SEGÚN DISEÑO GLB
Accesorios de red según diseño 1.00 1 1.00 1.00
9 PROV. TENDIDO TUBERIA PVC 2"-C9-JR ML
prov tendido tuebria pvc2 4000 4000 1 4,000.00
4,000.00
2"
CONEXIONES DOMICILIARIAS
1 PEDESTAL Y BASE PARA PILETA H°A° PZA
Pedestal y Base para Pileta Hª Aª 16.00 16.00
16.00
2 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA
Conexión Dom. c/ medidor 16.00 16.00
16.00

3 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00


Pozo de infiltracion 1 m3 1.00 1.00 1.00 1.00 16.00 1.00
1.00 16.00
COMPUTOS METRICOS - BALANCE ECONOMICO
Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA)
FINANCIAMIENTO:FPS PROVINCIA: IBAÑEZ CONTRATISTA: CITECO
MUNICIPIO: G.A.M.COTOCA DEPARTAMENTO: SANTA CRUZ SUPERVISOR: DAVID ANGULO CRUZ

Dimensiones Volumenes
ITEM DESCRIPCION Unid. GRAFICO
ancho largo alto Nº Veces Parcial Total
Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB
Instalacion de faenas 1.00 1.00
1.00
2 MOVILIZACION Y DESMOVILIZACION GLB
Movilizacion y desmovilizacion 1.00 1.00
1.00
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA
Prov. Y coloc placa de entrega FPS 1.00 1.00
1.00

4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA


Letrero Muro pintado 1.00 1.00
1.00

Módulo: MPTS1029 MEDIDAS DE MITIGACION


5 SEÑALIZACION GLB
Señalizacion 1.00 1.00
5.00
6 LETRINA PZA
Letrina 1.00 1.00
1.00
7 CONTENEDORES DE BASURA PZA
Contenedores de Basura 2.00 2.00
O I
2.00

Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS


15 PEDESTAL Y BASE PARA PILETA HºAº PZA
Pedestal y Base para Pileta Hª Aª 20.00 20.00
20.00
16 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA
Conexión Dom. c/ medidor 20.00 20.00
20.00

17 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00


Pozo de infiltracion 1 m3 1.00 1.00 1.00 1.00 20.00 1.00
1.00 20.00

Módulo: RED DE DISTRIBUCCION


1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3,000 3000 1 3,000.00
Replanteo y control de lineas de tuberia 3,000.00
2" 11/2" 1"

2 EXCAVACION MANUAL M3 0.4 3000 0.6 0.4 1 720.00


Excavacion de 0-2 m suelo semiduro 3000 720.00
0.6

4 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML


Prueba hidraulica 3000 3000 1 3,000.00
3,000.00
2" 11/2" 1"
5 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML
Desinfeccion de tuberias 3000 3000 1 3,000.00
3,000.00
2" 11/2" 1"
6 CAMARA DE LLAVES PZA 3 1 3.00
Camara de llaves 3.00

7 ANCLAJE DE HªSª H-18 M3 2.00 1 2.00


Anclajes de HºSº 2.00

8 RELLENO Y COMPACTADO CON TIERRA COMUN M3


Relleno y compactado con tierra comun 0.4 3000 0.6 0.4 1 720.00
2" 3000 3000 11.780625 708.22
0.6
9 ACCESORIOS DE RED SEGÚN DISEÑO GLB
Accesorios de red según diseño 1.00 1 1.00
1.00

11 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML


prov tendido tuebria pvc2 3000 3000 1 3,000.00
3,000.00
2"
COMPUTOS METRICOS - BALANCE ECONOMICO
Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA)
FINANCIAMIENTO:FPS PROVINCIA: IBAÑEZ CONTRATISTA: CITECO
MUNICIPIO: G.A.M.COTOCA DEPARTAMENTO: SANTA CRUZ SUPERVISOR: DAVID ANGULO CRUZ

Dimensiones Volumenes
ITEM DESCRIPCION Unid. GRAFICO
ancho largo alto Nº Veces Parcial Total
Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB
Instalacion de faenas 1.00 1.00
1.00
2 MOVILIZACION Y DESMOVILIZACION GLB
Movilizacion y desmovilizacion 1.00 1.00
1.00
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA
Prov. Y coloc placa de entrega FPS 1.00 1.00
1.00

4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA


Letrero Muro pintado 1.00 1.00
1.00

Módulo: MPTS1029 MEDIDAS DE MITIGACION


5 SEÑALIZACION GLB
Señalizacion 1.00 1.00
5.00
6 LETRINA PZA
Letrina 1.00 1.00
1.00
7 CONTENEDORES DE BASURA PZA
Contenedores de Basura 2.00 2.00
O I
2.00

Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS


15 PEDESTAL Y BASE PARA PILETA HºAº PZA
Pedestal y Base para Pileta Hª Aª 20.00 20.00
20.00
16 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA
Conexión Dom. c/ medidor 20.00 20.00
20.00

17 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00


Pozo de infiltracion 1 m3 1.00 1.00 1.00 1.00 20.00 1.00
1.00 20.00

Módulo: RED DE DISTRIBUCCION


1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 7,132 7132.471 1 7,132.47
Replanteo y control de lineas de tuberia 7,132.47
2" 11/2" 1"

2 EXCAVACION MANUAL M3 0.4 7132.471 0.6 0.4 1 1,711.79


Excavacion de 0-2 m suelo semiduro 7132.471 1,711.79
0.6

4 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML


Prueba hidraulica 7132.471 7132.471 1 7,132.47
7,132.47
2" 11/2" 1"
5 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML
Desinfeccion de tuberias 7132.471 7132.471 1 7,132.47
7,132.47
2" 11/2" 1"
6 CAMARA DE LLAVES PZA 3 1 3.00
Camara de llaves 3.00

7 ANCLAJE DE HªSª H-18 M3 2.00 1 2.00


Anclajes de HºSº 2.00

8 RELLENO Y COMPACTADO CON TIERRA COMUN M3


Relleno y compactado con tierra comun 0.4 7132.471 0.6 0.4 1 1,711.79
2" 7132.471 7132.471 28.008322 1,683.78
0.6
9 ACCESORIOS DE RED SEGÚN DISEÑO GLB
Accesorios de red según diseño 1.00 1 1.00
1.00

11 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML


prov tendido tuebria pvc2 7132.471 7132.471 1 7,132.47
7,132.47
2"
COMPUTOS METRICOS - BALANCE ECONOMICO
Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA)
FINANCIAMIENTO:FPS PROVINCIA: IBAÑEZ CONTRATISTA: CITECO
MUNICIPIO: G.A.M.COTOCA DEPARTAMENTO: SANTA CRUZ SUPERVISOR: DAVID ANGULO CRUZ

Dimensiones Volumenes
ITEM DESCRIPCION Unid. GRAFICO
ancho largo alto Nº Veces Parcial Total
Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB
Instalacion de faenas 1.00 1.00
1.00
2 MOVILIZACION Y DESMOVILIZACION GLB
Movilizacion y desmovilizacion 1.00 1.00
1.00
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA
Prov. Y coloc placa de entrega FPS 1.00 1.00
1.00

4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA


Letrero Muro pintado 1.00 1.00
1.00

Módulo: MPTS1029 MEDIDAS DE MITIGACION


5 SEÑALIZACION GLB
Señalizacion 1.00 1.00
5.00
6 LETRINA PZA
Letrina 1.00 1.00
1.00
7 CONTENEDORES DE BASURA PZA
Contenedores de Basura 2.00 2.00
O I
2.00

Módulo: MSCZ0009 CASETA DE BOMBEO


4 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 3.45
Replanteo de estructura y edificaciones 4.00 3.45 4.00 1.00 13.80
13.80
5 EXCAVACION M3
Excavacion 0.40 3.45 0.40 2.00 1.10
0.40 4.00 0.40 2.00 1.28
2.38
6 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3
Relleno compactado manual-no incluye material 2.60 2.60

0.40 2.60
7 CIMIENTO CORRIDO DE HªAª M3 0.40 3.45 0.40 3.45 2.00 1.10
Cimiento corrido de HºAº 0.40 4.00 0.40 0.40 2.00 1.28
4.00
0.30 2.38
8 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.15 3.45 0.30 3.45 3.00 0.47
Sobreciemiento de Hormigon ciclopeo FC=210 0.15 4.00 0.30 0.30 4.00 0.72
4.00 0.72
9 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 3.30
Contrapiso de piedra y cemento 1:3:4 3.30 3.85 3.85 1.00 12.71
0.62 4.98 2.00 6.18
0.62 4.30 2.00 5.33
24.22
10 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 4.20

Muro de ladrillo de Adobito visto 15 cm 4.20 1.00 1.00 2.00 8.40


3.65 2.70 2.70 1.00 9.86
3.65 0.54 0.54 1.00 0.99
1.77 1.00 1.00 1.77
1.77 21.02
11 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 4.60

Cubieta placa ondulada fibrocemento 2.31 4.60 2.31 2.00 21.25


21.25
12 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2
Prov. Y colocado puerta metalica y malla olimp 1.20 2.68 1.00 3.22
3.22
13 PROVISION Y COLOCACION DE VENTANA METALICA M2
Provision y colocacion de ventana metalica 1.64 1.62 3.00 7.97
7.97
14 ACOMETIDA ELECTRICIDAD GLB
Acometida elctricidad 1.00 1.00
1.00
15 PROV. Y COLOC. TABLERO DE CONTROL PZA
Prov y coloc. Tablero de control 1.00 1.00
1.00
16 PINTURA LATEX M2
Pintura latex 52.00 52.00
52.00
17 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB
Pilastra de ladrillo visto para medidor 1.00 1.00
1.00
18 INSTALACION ELECTRICA GLB
instalacion electrica 1.00 1.00
1.00
19 IMPERMEABILIZACION SOBRECIMIENTO ML 3.45 2.00 6.90
impermeabilizacion sobrecimiento 4.00 2.00 8.00
14.90
20 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3
Viga HºAº encadenado nivel cubierta 0.00 0.00
0.00
21 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA
Hipoclorador completo según diseño 1.00 1.00
1.00
22 REVOQUE CON MORTERO DE CEMENTO M2
Revoque con mortero y cemento 44.00 44.00
44.00
23 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 3.30 3.85 1.00 12.71
Piso de cemento frotachado sin contrapiso 0.62 4.98 2.00 6.18
0.62 4.30 2.00 5.33
24.22
COLUMNA DE HORMIGON ARMADO M3
Columna de Hormigon Armado 0.20 0.12 3.20 4.00 0.31
0.31
ZAPATAS DE HORMIGON ARMADO M3
Zapatas de Hormigon Armado 0.50 0.50 0.10 4.00 0.10
0.10

Módulo: MSCZ0053 TANQUE ELEVADO


24 RELLENO DE ESTRUCTURAS GBL 1.00 1.00
Relleno de Estructuras 1.00
25 EXCAVACION M3 2.20
Excavacion 2.20 2.20 2.10 2.20 4.00 40.66
2.10 40.66
26 ESCALERA CON GUARDACUERPOS ML
Escalera con guardacuerpos 12.10 12.10
12.10
27 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML
Prov. Y coloca de Escaleras metalica interior 1.80 1.80
1.80
28 TAPA METALICA DE 70X70 CM PZA 0.70 0.70 0.70
Tapa metalica de 70x70 cm 0.70 1.00 1.00
1.00
29 RELLENO COMPACTADO COMUN M3
Relleno compactado comun 20.00 20.00
20.00
30 CAMARA DE VALCULAS GLB
Camara de valvulas 1.00 1.00
1.00
31 ACCESORIA DE TANQUE M3
Accsorios de tanque 1.00 1.00
1.00
32 MEDIDOR DE NIVELES TANQUES DE H20 M2
Medidor de niveles tanques de H20 1.00 1.00
1.00
33 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2
Prueba de estanquiedad y desinfeccion de tanque 20.00 20.00
20.00
34 PINTURA LATEX M3
Pintura latex 150.00 150.00
150.00
35 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3
Impermeabilizacion de tanque Muros tanque 4.40 1.50 2.00 13.20
1.50 13.20

4.00
4.00 1.50 2.00 12.00
1.50 12.00

Losa de fondo 4.40


4.40 4.40 1.00 19.36
4.40 19.36

Total de Revoque con sika M3 44.56


36 HªAª H21 CUBA M3 4.40
HºAº h21 Cuba Muros tanque 0.20 4.40 1.50 2.00 2.64
1.50 2.64
0.20
4.00
0.20 4.00 1.50 2.00 2.40
1.50 2.40
0.20
Losa de fondo 4.40
4.40 4.40 0.20 1.00 3.87
0.20 3.87
4.40
Losa Tapa 4.40
4.40 4.40 0.10 1.00 1.94
Tapa metalica 0.70 0.70 0.10 1.00 0.49
4.40 1.45
Total Cuba M3 10.36
37 HªAª COLUMNAS (TANQUE ELEVADO) M3
HºAª Columnas 0.25 0.25 13.20 4.00 3.30
3.30

38 HªAª VIGA (TANQUE ELEVADO) M3 0.25 3.80 0.25 3.80 16.00 3.80
HºAª Viga 0.25 ### 3.80

2.00
39 ZAPATAS DE HªAª M3 2.00 2.00 0.50 4.00 8.00
Zapata de HªAª 2.00 8.00
0.50
40 CARPETA DE Hº POBRE M3 2.00
Carpeta de Hº Pobre 2.00 2.00 0.05 4.00 0.80
2.00 0.80
41 REVOQUE CON SIKA IMPERMEABILIZANTE M2 0.05
Revoque con sika impermeabil Muros tanque 4.40 1.50 2.00 13.20
1.50 13.20

4.00
4.00 1.50 2.00 12.00
1.50 12.00

Losa de fondo 4.40


4.40 4.40 1.00 19.36
4.40 19.36

Total de Revoque con sika M2 44.56


42 BARANDA METALICA DE PROTECCION GLB 1.00 1.00
Baranda Metalica de Proteccion 1.00
Módulo: MSCZ0057 CERCO MALLA OLIMPICA
43 LIMPIEZA DE TERRENO Y DESHIERBE M2
Limpieza de terreno y deshierve 10.00 8.00 10.00 1.00 80.00
8.00 80.00

44 EXCAVACION M3
Excavacion 0.40 0.26 0.60 0.40 9.00 0.56
0.26 0.56
0.60
45 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3
Hormigon armado - zapatas (Estructura) 0.40 0.26 0.10 0.40 9.00 0.09
0.26
0.10 0.09

46 CIMIENTO CORRIDO DE HºCº M3


Puerta de malla olimpica para cerco perimetral 0.40 0.60 0.26 9.00 0.56
0.20 0.30 0.16 0.60 9.00 0.09
0.26 0.65
0.40
47 MURO DE LADRILLO ADOBITO M2 2.90
Muro de Ladrillo adovito 2.90 0.30 ### 7.00 6.09
1.75 0.30 1.75 1.00 0.53
### 6.62
48 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.20
Anclajes y zapatas de HºCº 0.20 0.30 0.16 0.30 9.00 0.09
0.16 0.09

49 CERCO DE MALLA OLIMPICA ML 6.00 1.90 6.00 4.00 45.60


Cerco de Malla Olimpica 1.90 45.60

50 REPLANTEO CERCO PERIMETRAL ML 6.00 6.00 6.00 1.00 36.00


replanteo cerco perimetral 6.00 36.00

51 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 1.10 1.90 1.10 1.00 2.09
Puerta de Malla olimpica para cerco perimetral 1.90 2.09

52 COLUMNAS DE HºAº M3
Columnas de HºAº 0.05 0.05 2.70 9.00 1.22
2.70 1.22

Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS


15 PEDESTAL Y BASE PARA PILETA HºAº PZA
Pedestal y Base para Pileta Hª Aª 58.00 58.00
58.00
16 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA
Conexión Dom. c/ medidor 58.00 58.00
58.00

17 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00


Pozo de infiltracion 1 m3 1.00 1.00 1.00 1.00 58.00 1.00
1.00 58.00
Módulo: MSCZ181 IMPULSION POZO TANQUE
63 EXCAVACION M3 23.00 23.00
Excavancion 23.00

64 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML


Desinfeccion de tuberias (hasta D=4 pulg) 20.00 20.00 20.00 20.00
20.00
65 RELLENO COMPACTADO M3
Relleno compactado 9.00 9.00
9.00
66 PRUEBA HIDRAULICA D=4",8" ML
Prueba hidraulica D=4,8 78.90 78.90 78.90 78.90
78.90
67 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML
prov y coloc. Tuberia fg 2" con coplas 78.90 78.90 78.90 78.90
78.90
68 REPLANTEO DE LINEAS DE TUBERIA ML
Replanteo de lineas de tuberia 20.00 20.00 20.00 20.00
20.00
69 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB
Prov e instalacion de accesorios impusion de 2" 1.00 1.00
1.00

Módulo: RED DE DISTRIBUCCION


1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 6,000.00 6000 1 6,000.00
Replanteo y control de lineas de tuberia 6,000.00
2" 11/2" 1"

2 EXCAVACION MANUAL M3 0.4 6000 0.6 0.4 1 1,440.00


Excavacion de 0-2 m suelo semiduro 6000 1,440.00
0.6

4 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML


Prueba hidraulica 6000 6000 1 6,000.00
6,000.00
2" 11/2" 1"
5 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML
Desinfeccion de tuberias 6000 6000 1 6,000.00
6,000.00
2" 11/2" 1"
6 CAMARA DE LLAVES PZA 5 1 5.00
Camara de llaves 5.00

7 ANCLAJE DE HªSª H-18 M3 2.00 1 2.00


Anclajes de HºSº 2.00

8 RELLENO Y COMPACTADO CON TIERRA COMUN M3


Relleno y compactado con tierra comun 0.4 6000 0.6 0.4 1 1,440.00
2" 6000 6000 23.56125 1,416.44
0.6
9 ACCESORIOS DE RED SEGÚN DISEÑO GLB
Accesorios de red según diseño 1.00 1 1.00
1.00

11 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML


prov tendido tuebria pvc2 6000 6000 1 6,000.00
6,000.00
2"
COMPUTOS METRICOS - BALANCE ECONOMICO
Proyecto: FPS-07-00003618 CONSTRUCCION SIST. AGUA POTABLE COMUNIDAD CAMPANERO SUR (COTOCA)
FINANCIAMIENTO:FPS PROVINCIA: IBAÑEZ CONTRATISTA: CITECO
MUNICIPIO: G.A.M.COTOCA DEPARTAMENTO: SANTA CRUZ SUPERVISOR: DAVID ANGULO CRUZ

Dimensiones Volumenes
ITEM DESCRIPCION Unid. GRAFICO
ancho largo alto Nº Veces Parcial Total
Módulo: ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB
Instalacion de faenas 1.00 1.00
1.00
2 MOVILIZACION Y DESMOVILIZACION GLB
Movilizacion y desmovilizacion 1.00 1.00
1.00
3 PROV. Y COLO. PLACA DE ENTREGA FPS PZA
Prov. Y coloc placa de entrega FPS 1.00 1.00
1.00

4 LETRERO MURO -PINTADO (L=2,6 M ; H = 2,05 M) S/G PZA


Letrero Muro pintado 1.00 1.00
1.00

Módulo: MPTS1029 MEDIDAS DE MITIGACION


5 SEÑALIZACION GLB
Señalizacion 1.00 1.00
5.00
6 LETRINA PZA
Letrina 1.00 1.00
1.00
7 CONTENEDORES DE BASURA PZA
Contenedores de Basura 2.00 2.00
O I
2.00

Módulo: MSCZ0009 CASETA DE BOMBEO


4 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 3.45
Replanteo de estructura y edificaciones 4.00 3.45 4.00 1.00 13.80
13.80
5 EXCAVACION M3
Excavacion 0.40 3.45 0.40 2.00 1.10
0.40 4.00 0.40 2.00 1.28
2.38
6 RELLENO COMPACTADO MANUAL-NO INCLUYE MA M3
Relleno compactado manual-no incluye material 2.60 2.60

0.40 2.60
7 CIMIENTO CORRIDO DE HªAª M3 0.40 3.45 0.40 3.45 2.00 1.10
Cimiento corrido de HºAº 0.40 4.00 0.40 0.40 2.00 1.28
4.00
0.30 2.38
8 SOBRECIMIENTO DE HORMIGON CICLOPEO FC=210 M3 0.15 3.45 0.30 3.45 3.00 0.47
Sobreciemiento de Hormigon ciclopeo FC=210 0.15 4.00 0.30 0.30 4.00 0.72
4.00 0.72
9 CONTRAPISO DE PIEDRA Y CEMENTO 1:3:4 M2 3.30
Contrapiso de piedra y cemento 1:3:4 3.30 3.85 3.85 1.00 12.71
0.62 4.98 2.00 6.18
0.62 4.30 2.00 5.33
24.22
10 MURO DE LADRILLO DE ADOBITO VISTO 15 CM M2 4.20

Muro de ladrillo de Adobito visto 15 cm 4.20 1.00 1.00 2.00 8.40


3.65 2.70 2.70 1.00 9.86
3.65 0.54 0.54 1.00 0.99
1.77 1.00 1.00 1.77
1.77 21.02
11 CUBIERTA PLACA ONDULADA FIBROCEMENTO M2 4.60

Cubieta placa ondulada fibrocemento 2.31 4.60 2.31 2.00 21.25


21.25
12 PROV. Y COLOC. PUERTA METALICA Y MALLA OLIMP M2
Prov. Y colocado puerta metalica y malla olimp 1.20 2.68 1.00 3.22
3.22
13 PROVISION Y COLOCACION DE VENTANA METALICA M2
Provision y colocacion de ventana metalica 1.64 1.62 3.00 7.97
7.97
14 ACOMETIDA ELECTRICIDAD GLB
Acometida elctricidad 1.00 1.00
1.00
15 PROV. Y COLOC. TABLERO DE CONTROL PZA
Prov y coloc. Tablero de control 1.00 1.00
1.00
16 PINTURA LATEX M2
Pintura latex 52.00 52.00
52.00
17 PILASTRA DE LADRILLO VISTO PARA MEDIDOR GLB
Pilastra de ladrillo visto para medidor 1.00 1.00
1.00
18 INSTALACION ELECTRICA GLB
instalacion electrica 1.00 1.00
1.00
19 IMPERMEABILIZACION SOBRECIMIENTO ML 3.45 2.00 6.90
impermeabilizacion sobrecimiento 4.00 2.00 8.00
14.90
20 VIGA HºAº ENCADENADO NIVEL CUBIERTA M3
Viga HºAº encadenado nivel cubierta 0.00 0.00
0.00
21 HIPOCLORADOR COMPLETO SEGÚN DISEÑO PZA
Hipoclorador completo según diseño 1.00 1.00
1.00
22 REVOQUE CON MORTERO DE CEMENTO M2
Revoque con mortero y cemento 44.00 44.00
44.00
23 PISO DE CEMENTO FROTACHADO SIN CONTRAPISO M2 3.30 3.85 1.00 12.71
Piso de cemento frotachado sin contrapiso 0.62 4.98 2.00 6.18
0.62 4.30 2.00 5.33
24.22
COLUMNA DE HORMIGON ARMADO M3
Columna de Hormigon Armado 0.20 0.12 3.20 4.00 0.31
0.31
ZAPATAS DE HORMIGON ARMADO M3
Zapatas de Hormigon Armado 0.50 0.50 0.10 4.00 0.10
0.10

Módulo: MSCZ0053 TANQUE ELEVADO


24 RELLENO DE ESTRUCTURAS GBL 1.00 1.00
Relleno de Estructuras 1.00
25 EXCAVACION M3 2.20
Excavacion 2.20 2.20 2.10 2.20 4.00 40.66
2.10 40.66
26 ESCALERA CON GUARDACUERPOS ML
Escalera con guardacuerpos 12.10 12.10
12.10
27 PROV. Y COLOC. DE ESCALERAS METALICA INTERIOR ML
Prov. Y coloca de Escaleras metalica interior 1.80 1.80
1.80
28 TAPA METALICA DE 70X70 CM PZA 0.70 0.70 0.70
Tapa metalica de 70x70 cm 0.70 1.00 1.00
1.00
29 RELLENO COMPACTADO COMUN M3
Relleno compactado comun 20.00 20.00
20.00
30 CAMARA DE VALCULAS GLB
Camara de valvulas 1.00 1.00
1.00
31 ACCESORIA DE TANQUE M3
Accsorios de tanque 1.00 1.00
1.00
32 MEDIDOR DE NIVELES TANQUES DE H20 M2
Medidor de niveles tanques de H20 1.00 1.00
1.00
33 PRUEBA DE ESTANQUEIDAD Y DESINFECCION TANQUE M2
Prueba de estanquiedad y desinfeccion de tanque 20.00 20.00
20.00
34 PINTURA LATEX M3
Pintura latex 150.00 150.00
150.00
35 IMPERMIABILIZACION DE TANQUE C/SIKA TOP M3
Impermeabilizacion de tanque Muros tanque 4.40 1.50 2.00 13.20
1.50 13.20

4.00
4.00 1.50 2.00 12.00
1.50 12.00

Losa de fondo 4.40


4.40 4.40 1.00 19.36
4.40 19.36

Total de Revoque con sika M3 44.56


36 HªAª H21 CUBA M3 4.40
HºAº h21 Cuba Muros tanque 0.20 4.40 1.50 2.00 2.64
1.50 2.64
0.20
4.00
0.20 4.00 1.50 2.00 2.40
1.50 2.40
0.20
Losa de fondo 4.40
4.40 4.40 0.20 1.00 3.87
0.20 3.87
4.40
Losa Tapa 4.40
4.40 4.40 0.10 1.00 1.94
Tapa metalica 0.70 0.70 0.10 1.00 0.49
4.40 1.45
Total Cuba M3 10.36
37 HªAª COLUMNAS (TANQUE ELEVADO) M3
HºAª Columnas 0.25 0.25 13.20 4.00 3.30
3.30

38 HªAª VIGA (TANQUE ELEVADO) M3 0.25 3.80 0.25 3.80 16.00 3.80
HºAª Viga 0.25 ### 3.80

2.00
39 ZAPATAS DE HªAª M3 2.00 2.00 0.50 4.00 8.00
Zapata de HªAª 2.00 8.00
0.50
40 CARPETA DE Hº POBRE M3 2.00
Carpeta de Hº Pobre 2.00 2.00 0.05 4.00 0.80
2.00 0.80
41 REVOQUE CON SIKA IMPERMEABILIZANTE M2 0.05
Revoque con sika impermeabil Muros tanque 4.40 1.50 2.00 13.20
1.50 13.20

4.00
4.00 1.50 2.00 12.00
1.50 12.00

Losa de fondo 4.40


4.40 4.40 1.00 19.36
4.40 19.36

Total de Revoque con sika M2 44.56


42 BARANDA METALICA DE PROTECCION GLB 1.00 1.00
Baranda Metalica de Proteccion 1.00
Módulo: MSCZ0057 CERCO MALLA OLIMPICA
43 LIMPIEZA DE TERRENO Y DESHIERBE M2
Limpieza de terreno y deshierve 10.00 8.00 10.00 1.00 80.00
8.00 80.00

44 EXCAVACION M3
Excavacion 0.40 0.26 0.60 0.40 9.00 0.56
0.26 0.56
0.60
45 HORMIGON ARMADO - ZAPATAS (ESTRUCTURAS) M3
Hormigon armado - zapatas (Estructura) 0.40 0.26 0.10 0.40 9.00 0.09
0.26
0.10 0.09

46 CIMIENTO CORRIDO DE HºCº M3


Puerta de malla olimpica para cerco perimetral 0.40 0.60 0.26 9.00 0.56
0.20 0.30 0.16 0.60 9.00 0.09
0.26 0.65
0.40
47 MURO DE LADRILLO ADOBITO M2 2.90
Muro de Ladrillo adovito 2.90 0.30 ### 7.00 6.09
1.75 0.30 1.75 1.00 0.53
### 6.62
48 ANCLAJES Y ZAPATAS DE HºCº 1:3:4 50% PIEDRA M3 0.20
Anclajes y zapatas de HºCº 0.20 0.30 0.16 0.30 9.00 0.09
0.16 0.09

49 CERCO DE MALLA OLIMPICA ML 6.00 1.90 6.00 4.00 45.60


Cerco de Malla Olimpica 1.90 45.60

50 REPLANTEO CERCO PERIMETRAL ML 6.00 6.00 6.00 1.00 36.00


replanteo cerco perimetral 6.00 36.00

51 PUERTADE MALLA OLIMPICA PARA CERCO PERIMETRAL M2 1.10 1.90 1.10 1.00 2.09
Puerta de Malla olimpica para cerco perimetral 1.90 2.09

52 COLUMNAS DE HºAº M3
Columnas de HºAº 0.05 0.05 2.70 9.00 1.22
2.70 1.22

Módulo: MSCZ0225 CONEXIONES DOMICILIARIAS


15 PEDESTAL Y BASE PARA PILETA HºAº PZA
Pedestal y Base para Pileta Hª Aª 58.00 58.00
58.00
16 CONEX. DOM. C/MEDIDOR (INCL. EXC. Y RELL) PZA
Conexión Dom. c/ medidor 58.00 58.00
58.00

17 POZO DE INFILTRACION 1 M3 (SEGÚN DISEÑO) PZA 1.00


Pozo de infiltracion 1 m3 1.00 1.00 1.00 1.00 58.00 1.00
1.00 58.00
Módulo: MSCZ181 IMPULSION POZO TANQUE
63 EXCAVACION M3 23.00 23.00
Excavancion 23.00

64 DESINFECCION DE TUBERIAS (HASTA D=4 PULG.) ML


Desinfeccion de tuberias (hasta D=4 pulg) 20.00 20.00 20.00 20.00
20.00
65 RELLENO COMPACTADO M3
Relleno compactado 9.00 9.00
9.00
66 PRUEBA HIDRAULICA D=4",8" ML
Prueba hidraulica D=4,8 78.90 78.90 78.90 78.90
78.90
67 PROV. Y COLOC TUBERIA FG 2" CON COPLAS ML
prov y coloc. Tuberia fg 2" con coplas 78.90 78.90 78.90 78.90
78.90
68 REPLANTEO DE LINEAS DE TUBERIA ML
Replanteo de lineas de tuberia 20.00 20.00 20.00 20.00
20.00
69 PROV. E INST. DE ACCESORIOS IMPULSION DE 2" GLB
Prov e instalacion de accesorios impusion de 2" 1.00 1.00
1.00

Módulo: RED DE DISTRIBUCCION


1 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3000 3000 1 3,000.00
Replanteo y control de lineas de tuberia 3,000.00
2" 11/2" 1"

2 EXCAVACION MANUAL M3 0.4 3000 0.6 0.4 1 720.00


Excavacion de 0-2 m suelo semiduro 3000 720.00
0.6

4 PRUEBA HIDRAULICA-TUBERIAS HASTA 4 PULG. ML


Prueba hidraulica 3000 3000 1 3,000.00
3,000.00
2" 11/2" 1"
5 DESINFECCION DE TUBERIAS (HASTA D=4 PULG) ML
Desinfeccion de tuberias 3000 3000 1 3,000.00
3,000.00
2" 11/2" 1"
6 CAMARA DE LLAVES PZA 5 1 5.00
Camara de llaves 5.00

7 ANCLAJE DE HªSª H-18 M3 2.00 1 2.00


Anclajes de HºSº 2.00

8 RELLENO Y COMPACTADO CON TIERRA COMUN M3


Relleno y compactado con tierra comun 0.4 3000 0.6 0.4 1 720.00
2" 3000 3000 11.780625 708.22
0.6
9 ACCESORIOS DE RED SEGÚN DISEÑO GLB
Accesorios de red según diseño 1.00 1 1.00
1.00

11 PROV. TENDIDO TUBERIA PVC 2" - C9 -JR ML


prov tendido tuebria pvc2 3000 3000 1 3,000.00
3,000.00
2"