1. WORK METHOD FOR CABLE PULLING


1.1. Flow Chart

Preparation Work for Cable - DWG for Construction


Pulling - Tools & Consumable
- Works Permit
- Materials
Insulation & Continuity test of - Main Power
cable (Before Pulling Cable)

Inspection Letters
Submission

Marking & Installation of REPAIR


power cable (Pulling Cable)

Inspection of marking
installation Power cable
(Pulling Cable)

Inspection Letters
Submission

NO
Inspection Cable

FINISH
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.2. Safety Brieving


Before doing job activity we do toolbox meeting in the each of area, and supervisors must
ensure that:
1. All workers are fit and equipped with APD / PPE in accordance with the type of their work.
2. Work location and its components have been done "INTERFACE WITH OTHER DISCIPLINE.
3. All work equipment and work tools will be used in ready-to-use conditions.
4. Prepare“Drawing for Construction" for use in performing work.
5. Permit To Work (PTW) has been obtained and placed on site.

2|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.3. Prepare equipment and tools for cable pulling & termination
Before doing the work we must prepare all the necessary work tools and check the work tools to ensure
in good condition.
1. Materials
Materials required in accordance with the material listed in the above "STANDART DRAWING
TERMINATION".
2. Tools of Cable Pulling & Termination ( MV,LV and Control Cable )
a. Tools for Cable Pulling
 Crane
 Jack Drum Cable
 Cable Roller
 Winch Motor
 Pull Rope
 HeavyEquipment Jack Drum Cable
 Scaffolding
 Safety Tools for Cable Pulling

Cable Roller

SarungTangan

Wire Rope Body Harnes


Crane

Safety Tools Winch Motor


Skafolding

3|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.4. Insulation Test

1. Insulation Cable Test


Doing cable testing to measurethe cable isolation & continuity must be donebefore &After pull
cable aims to ensure that the cable is in good condition.
Insulation Test For MV. Cable :
1. Insulation Test (R-G)
2. Insulation Test (S-G)
3. Insulation Test (T-G)
4. Insulation Test (R-S)
5. Insulation Test (S-T)
6. Insulation Test (R-T)

4|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.5 Lifting Cable


When lifting cable, cable jack drum to be positioned track by using crane according to heavy equipment (
supervisedbysupervisor, foreman, rigging man, and safety officer

SAFETY SUPERVISOR

CRANE
80T

Hanging
Support Lifting
Cable Drum

Cable Drum

FOREMAN

RIGGING MAN
SUPERVISOR

Hanging Support
Lifting Cable Drum
Jack Drum Cable

5|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.6 Pulling Cable On Cable Tray


1.6.1 Moving Cable
Moving cable from stock yard to site use a trailler

1.6.2 Pulling Cable on Cable Tray

6|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.6.3 Dressing cable


Job last pulling cable on cable tray is Dressing cable manual, used a tie wripe

7|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.7 Pulling Cable Underground


1.7.1 Pulling Cable
Pulling cable do to the Winch motor, with tolls cable roll distance 5 meters.

Winch
Jack
Motor
Drum

Roller SAFETY SUPERVISOR


FOREMAN Cable SUPERVISOR

8|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.7.3 Crossing Road


Then pulling cable Crossing road, we use method crossing with duct bank or u-ditc.

9|Page
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.8 Spare Cable

Spare cable on the jack and drum cable.

10 | P a g e
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

Install Roller Cable Spare Cable Before Pulling If needed

Pulling Cable Pulling Cable

Cable Protection Tile Cable Protection Tile

11 | P a g e
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

Post Marker Existing


Install Pos Marker

12 | P a g e
Document No : Rev :
WORK METHODE FOR CABLE PULLING
Date : Page :

1.1.Inspection Test Plant (ITP )

13 | P a g e