FiPER INDONESIA
FABRICATION & SHELTER GENSET
PT. ANUGERAH MEGA ENERGI
Stasiun Gas Kompressor
Komplek PLTGU Muara Karang - Jakarta

ID Task Name Duration Start Finish October 2018


26 29 2 5 8 11 14
1 PEKERJAAN PERSIAPAN 1 day Mon 1/10/18 Mon 1/10/18
2 1.1. Pek. Persiapan & Pengukuran Ulang 1 day Mon 1/10/18 Mon 1/10/18
3 1.2. Pek. Setting Bowplang 1 day Mon 1/10/18 Mon 1/10/18
4
5 PEKERJAAN FABRIKASI KONSTRUKSI SHELTER 11 days Tue 2/10/18 Fri 12/10/18
6 2.1. Pek. Fabrikasi Komponen Struktur Shelter Genset 7 days Tue 2/10/18 Mon 8/10/18
7 2.2. Pek. Finishing (Painting/ Hot Dip Galvanize) 3 days Tue 9/10/18 Thu 11/10/18
8 2.3. Pek. Mobilisasi Material & Tools 1 day Fri 12/10/18 Fri 12/10/18
9
10 Pekerjaan Tanah & Pondasi 5 days Tue 2/10/18 Sat 6/10/18
11 3.1. Pek. Galian Tanah Pondasi & Sloof 2 days Tue 2/10/18 Wed 3/10/18
12 3.2. Pek. Setting Pembesian Pondasi & Sloof 1 day Thu 4/10/18 Thu 4/10/18
13 3.3. Pek. Setting Anchor Bolt 1 day Fri 5/10/18 Fri 5/10/18
14 3.4. Pek. Pengecoran Pondasi & Sloop 1 day Sat 6/10/18 Sat 6/10/18
15 3.5. Pek. Pembuangan Tanah Ex. Galian Keluar 1 day Sat 6/10/18 Sat 6/10/18
16
17 PEKERJAAN ERECTION/ INSTALASI 3 days Sun 7/10/18 Tue 9/10/18
18 4.1. Pek. Pemasangan/ Instalasi Struktur Shelter Genset 2 days Sun 7/10/18 Mon 8/10/18
19 4.2. Pek. Finishing (Top Copping) & Cleaning 1 day Tue 9/10/18 Tue 9/10/18
20 4.3. Final Cleaning & Finish 1 day Tue 9/10/18 Tue 9/10/18

FABRICATION & INSTALATION of SHELTER Task Progress Summary External Tasks Deadline
PT. ANUGERAH MEGA ENERGI - Jakarta
Project Plan Schedule Split Milestone Project Summary External Milestone