Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
ENGG CERT
DESCRIPTION
6600036980
UPGRADE JU’AYMAH SHOPS
MAINTENANCE SHOPS NORTHERN AREA
BI-10-01545
JO/EWO
DATE
DISCIPLINE
ENGINEER
DATE:
PROJECT
ENGINEER
PREPARED BY:
DATE:
CERTIFIED
DATE:
CONSTRUCTION
AGENCY
SAS SYSTEMS ENGINEERING
DATE:
OPERATIONS
DATE:
CONTROL NUMBER
VERIFICATION
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
Rev. date Description of Revision Prepared By: Checked By: Approved By:
(DCC) NO. _____________________
pr Pipe Lay-Up Procedure DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
REVISION
TABLE OF CONTENT
1 Purpose ............................................................................................................................................. 4
2 Scope ................................................................................................................................................. 4
3 References ........................................................................................................................................ 4
4 Definition .......................................................................................................................................... 5
5 Responsibilities ................................................................................................................................. 5
6 Operatives ......................................................................................................................................... 6
7 Lay Up Procedure .............................................................................................................................. 6
8 General Procedure- Dry Lay-Up ........................................................................................................ 7
9 Documentation ................................................................................................................................. 8
10 Attachments...................................................................................................................................... 8
Doc. Ref. No.
UPGRADE JU’AYMAH SHOPS PROJECT
UJS-CON-E-30138
Revision: 00
PIPE LAY-UP PROCEDURE
Page No.: Page 4 of 8
Date: 31-OCT-2018
Contract No. 6600036980 BI-10-01545
1 Purpose
2 Scope
3 References
The current editions of the following documents have been referenced in the
preparation of this procedure and shall be considered a part of this
procedure as applicable.
4 Definition
5 Responsibilities
6 Operatives
6.4 Scaffolders
7 Lay Up Procedure
Equipment and Piping must be laid-up after hydrotesting unless it can be
ensured that it will be returned to service within 30 days from the first
introduction of hydrotest water to the system.
at a positive pressure of at least 30 PSI. The dew point at the final lay-
up pressure must be lower than -1°C.
9 Documentation
This document is distributed by the Site QC Inspector to all the involved site
personnel. The original issue of this procedure will be kept by the Quality
Assurance Department.
10 Attachments
• SATIP-A-004-02; Hydrostatic Testing of On-Plot Piping
• SAIC-A-2007; Review Procedure - Lay-up of Piping Systems or Vessels
1.0 DOC REVIEW SPECIAL PROCESS (PRESSURE TESTING) REQUIRES BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS.
1.1 Hydrostatic Testing Procedure SAIC-A-2001 SAIC-A-2001 RH RH Submit Sample Test Pkg & Procedure together
3.0 APPLICATION
INSPECTION RESPONSIBILITY
4.0 POST- TEST
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
For Test Package Preparation & review on large projects, each new system designed for testing is thoroughly reviewed & approved. All subsequent packages within a given system shall be built
6 following the "Copy & Paste" theme for Test Package efficiency and then R1 (Contractor) & R2 (Company Sample Review of documents) Inspection may be performed.
LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements
Lay-Up Procedure or Method Statement shall be project specific and
Sch Q,
A1 identified in Project Quality Plan. (SPECIAL CONSTR. PROCESS).
Para. 3.1
Note Significant changes to SAES-A-007 (July 2012)
Procedure identifies lay-up methods selected and use one of the lay-
up methods detailed in the Attachments:
A) Wet Lay-up (Attachment 2) SAES-A-007,
B3 B) Dry Lay-up (Attachment 3) Paras. 5.2.2/
C) Inert Gas Lay-up (Attachment 4) 5.2.3/ 5.2.4/ 5.2.5
D) Ambient Lay-up (Attachment 4)
E) Other Approved Lay-up Methods (Attachment 4)
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
C SPECIFIC & SPECIAL LAY-UP REQUIREMENTS (Specific Applications)
Tank requirements are listed in applicable procedures: Carbon steel
open-roof, floating-roof, or API atmospheric cone
roof tanks not designed for service above atmospheric pressure, SAES-A-007,
C1
do not require treatment of hydrostatic water. Immediately after Para 7.1
completion of the hydrostatic test, drain and remove all traces of visible
water. Cleaning shall consider any coating operations.
Dry Gas & Refined Hydrocarbon Product Pipelines & Piping. See SAES-A-007,
C3
Attachment 5. Section 7.3
SAES-A-007,
C4 Sour Gas & Sour Oil Pipelines. See Attachment 5.
Section 7.4
PLANT SYSTEMS (PIPING & EQUIPMENT) SHALL BE LAYED UP SAES-A-007,
C5
PER ATTACHMENT 6. Inspectors are familiar with these reqmts. Section 7.5
D STAINLESS STEEL PRESSURE PIPING SYSTEM & EQUIPMENT (P-No. 6 & above) LAY-UP (INCLUDING NEW VALVE REQMTS)
Type 300-series stainless steel systems* shall be tested only with water
having maximum allowable chloride concentration of 50 ppm. Quality of
SAES-A-007,
D1 water shall be per Attachment 1. Para. 4.2 in entirety.
Para. 6.1
CS system with 300 Series SS trim valve is not a SS "system".
WATER QUALITY IS TESTED & CERTIFIED (SATR-A-2014)
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
3. The lay up procedures need to be approved before hydrotesting begins. PID does not have the authority to approve Lay Up procedures. Procedure
shall be approved by concern department as mentioned in SAES-A-007 PARA 5.2.1.
ATTACHMENTS:
Attachment 1 - SAES-A-007 (24 July 2012 ) GENERAL SYSTEM REQMTS
Attachment 2 - LAY-UP FOR CARBON STEEL SYSTEMS (WET METHOD)
Attachment 3 - LAY-UP FOR CARBON STEEL SYSTEMS (DRY METHOD)
Attachment 4 - LAY-UP FOR CARBON STEEL SYSTEMS (INERT GAS, AMBIENT & OTHER METHODS)
Attachment 5 - SPECIAL LAY UP PROCEDURES (Dry Gas & Refined Hydrocarbon Product Pipelines & Piping, Sour Gas & Sour Oil Pipelines)
Attachment 6 - SPECIAL LAY UP PROCEDURES (Plant Applications, Piping Systems & Equipment)
Attachment 7 - LAY UP PROCEDURE (STAINLESS STEEL SYSTEMS & EQUIPMENT)
REFERENCE DOCUMENTS:
1. SAES-A-007, Hydrostatic Testing Fluids and Lay-Up Procedures, (24 July 2012 )
THE END
THE END