PERHITUNGAN VOLUME PEKERJAAN

NO SKETSA PERHITUNGAN VOLUME


1 Pekerjaan Persiapan
Pembersihan Lokasi
= p x l
= 16.50 6.00 = 99.00

Total Volume : 99.00 M2

Pasang Bouwplank/Pengukuran

= p x 2 sisi
= 16.50 x 2.00 = 33.00

= l x 2 sisi
= 6.00 x 2.00 = 12.00
Total Volume : 45.00 M1

2 Pekerjaan Struktur Bawah


Pekerjaan Tanah Pondasi Type 1
Galian Tanah
= p x l x t
= 43.00 x 0.80 x 1.50 = 51.60
Total Volume : 51.60 M3

Urugan Tanah Kembali Bekas Galian


= p x l x t
= 43.00 x 0.80 x 1.20 = 41.28

Total Volume : 41.28 M3

Urugan Pasir ( 5 cm )
= p x l x t
= 43.00 x 0.80 x 0.05 = 1.72
Total Volume : 1.72 M3

Anstampang
= p x l x t
= 43.00 x 0.80 x 0.15 = 5.16
Total Volume : 5.16 M3

Pekerjaan Tanah Pondasi Type 2


Galian Tanah
= p x l x t
= 43.00 x 0.80 x 1.50 = 51.60
Total Volume : 51.60 M3

Urugan Tanah Kembali Bekas Galian


= p x l x t
= 43.00 x 0.80 x 1.20 = 41.28
Urugan Pasir ( 5 cm )
= p x l x t
= 43.00 x 0.80 x 0.05 = 1.72
Total Volume : 1.72 M3

Anstampang
= p x l x t
= 43.00 x 0.80 x 0.15 = 5.16
Total Volume : 5.16 M3

Pekerjaan sloof
Beton K - 175
= p x l x t
= 43.00 x 0.15 x 0.25 = 1.61
Total Volume : 1.61 M3

3 Pekerjaan Beton Bertulang


Pekerjaan Kolom
Beton K - 175
= p x l x t x Jumlah
= 0.15 x 0.15 x 3.50 x 21.00 = 1.65
Total Volume : 1.65 M3
Pekerjaan Kolom Praktis
Beton K - 175
= p x l x t x Jumlah
= 0.15 x 0.15 x 4.00 x 1.00 = 0.09

Beton K - 175
= p x l x t x Jumlah
= 0.15 x 0.15 x 3.50 x 1.00 = 0.08

Total Volume : 0.17 M3


Pekerjaan Ring Balok
Beton K - 175
= p x l x t x Jumlah
= 43.00 x 0.15 x 0.20 x 1.00 = 1.29
Total Volume : 1.29 M3

4 Pekerjaan Pasangan Dan Plesteran


Pasangan batu bata 1:4 Tinggi Dinding = 3.50
= p x t
= 25.61 x 3.50 = 89.635

Tinggi Dinding = 4.00


= p x t
= 49.8 x 4.00 = 199.2

Tinggi Dinding = 2.50


= p x t
= 35.51 x 2.50 = 88.775

Luas Total = 377.61


Total Volume : 377.61 M2
Pasangan batu bata 1:2
Luas Trasraam
= p x t
= 5.8 x 2.20 = 12.76
Total Volume : 12.76 M2

plesteran dinding 1:4


Plesteran
= 89.635 x 2.00
= 89.64 x 2.00 = 179.27
Plesteran
= 199.2 x 2.00
= 199.20 x 2.00 = 398.4
Plesteran
= 88.775 x 2.00
= 88.78 x 2.00 = 177.55
Total Volume : 755.22 M2
plesteran dinding 1:2
Plesteran
= Luas Trasraam x 2.00
= 12.76 x 2.00 = 25.52
Total Volume : 25.52 M2

Plester Struktur 1:4


Kolom 15/15 = 17 Titik
Tinggi Kolom = 3.5
Keliling = 0.6
Luas = 3.5 x 0.6 = 2.1
Luas Total = 2.1 x 17 = 35.7
Kolom 15/15 = 4 Titik
Tinggi Kolom = 2.2
Keliling = 0.6
Luas = 2.2 x 0.6 = 1.32
Luas Total = 1.32 x 4 = 5.28
Total Plesteran struktur = 40.98
Total Volume : 40.98 M2

5 Pekerjaan Lantai
Pek. Lantai Keramik 30 x 30 cm
Luas Lantai Keramik (30x30) = 30.00
Total Volume : 30.00 M2

Pek. Lantai Keramik 20 x 20 cm

Luas Lantai Keramik (20x20) = 7.14


Total Volume : 0.00 M2

6 Pekerjaan Atap dan Plafond


Rangka atap baja ringan
Luas Atap = Luas Bidang Teratap / Kemiringan
= 29.50 / 0.50
= 59.00
Total Volume : 59.00 M2

atap datar
luas atap datar = p x l x t
= 3.00 x 1.10 x 0.15
= 0.50
Total Volume : 0.50 M2
plafond gypsum 9mm
List Plafond
Dapur = 5.10
Ruang Tamu = 5.50
Kamar tidur 1 = 8.55
ruang makan = 7.50
kamar tidur 2 = 8.55
Wc = 3.30
Jumlah = 38.50
Total Volume : 38.50 M1
7 Pekerjaan Pintu Jendela
pek. Pintu
P1 = 1
Luas Pintu = 1.935
Luas = 1.935 x 1 = 1.935
Volume Pintu = 1.935

P2 = 3
Luas Pintu = 1.8275
Luas = 1.8275 x 3 = 5.4825
Volume Pintu = 5.4825

P3 = 1
Luas Pintu = 1.519
Luas = 1.519 x 1 = 1.519
Volume Pintu = 1.519

Luas Total = 8.9365


Volume total = 8.9365
Total Volume : 8.94 M2

pek. Jendela
J1 = 1 Unit
Luas Jendela = 2.22
Luas Daun Jendela = 2.22 x 1 = 2.22

J2 = 2 Unit
Luas Jendela = 1.30
Luas Daun Jendela = 1.30 x 2 = 2.59

J3 = 2 Unit
Luas Jendela = 1.16
Luas Daun Jendela = 1.16 x 2 = 2.32

J4 = 1 Unit
Luas Jendela = 0.91
Luas Daun Jendela = 0.91 x 1 = 0.91
Total Volume : 8.04 M2
pek. Cat pintu dan jendela
P1 = 1 Unit
Luas Daun = 1.94
Total Luas = 1.94 x 1 = 1.94

P2 = 3 Unit
Luas Daun = 1.83
Total Luas = 1.83 x 3 = 5.48

P3 = 1 Unit
Luas Daun = 1.52
Total Luas = 1.52 x 1 = 1.52

J1 = 1 Unit
Luas Daun = 2.22
Total Luas = 2.22 x 1 = 2.22

J2 = 2 Unit
Luas Daun = 1.30
Total Luas = 1.30 x 2 = 2.59

J3 = 2 Unit
Luas Daun = 1.16
Total Luas = 1.16 x 2 = 2.32

J4 = 1 Unit
Luas Daun = 0.91
Total Luas = 0.91 x 1 = 0.91
Total Volume : 16.98 M2

8 Pengerjaan Instalasi Listrik


lampu pijar
Total Volume : 8.00 ttk

sparing lamu taman


Total Volume : 4.00 ttk

stop kontak dinding


Total Volume : 5.00 ttk

saklar ganda
Total Volume : 2.00 ttk

saklar tunggal
Total Volume : 4.00 ttk

MCB listrik
Total Volume : 1.00 Bh
Meter listrik
Total Volume : 1.00 Bh
9 Pekerjaan Sanitasi
Pompa
Total Volume : 1.00 Bh

Shower
Total Volume : 1.00 Set

Jet Spray
Total Volume : 1.00 Set

Closet
Total Volume : 1.00 Set

kitchen sink
Total Volume : 1.00 Bh

kran taman
Total Volume : 2.00 Bh

Bak kontrol
Total Volume : 3.00 Unit

resapan
Total Volume : 1.00 Unit

floor drain
Total Volume : 1.00 Bh

pas pipa 3 inci + acseeoris


Total Volume : 3.00 Bh

pas pipa 4 inci + acseeoris


Total Volume : 4.00 Bh

septictank
Total Volume : 1.00 Unit