Sei sulla pagina 1di 7

Design Ripper Excavator Back Hoe

On Overburde Stripping For Coal


Mine
Small-Scale
Sumar Hadi1, Muhammad Nur Irfan2
Department of Mechanical Engineering, Diponegoro University, Indonesia
sumarhs.undip@gmail.com

ABSTRACT: Bulldozer Ripper is a tool that serves to rake rock hard. The use of a ripper on
the stripping of overburden to increase production, minimize operating costs, especially for
fossil fuel use, and maintenance costs and unloading digging tools. Stripping of overburden
without carded first cause "cycle time" digging tools fit larger load capacity "bucket" (Fill
Factor) is very small, ie between 75% - 85%, "tooth bucket" more rapid wear and tear, and
the use of fuel oil more. Using a "ripper" on stripping overburden to increase production,
reduce the use of fuel oil, and directly minimizing operational costs.

KEYWORDS: Ripper, Bulldozer, overburden, Cycle Time.

I. PRELIMINARY Demolition by means of explosives,


requires substantial funds and require special
Region of East Kalimantan has the handling, besides causing various effects in
potential of coal is quite large and evenly its use as vibration blasting and toxic gases.
distributed almost all areas, so in the spirit of To achieve the production target of stripping
regional autonomy and supported by the of overburden without blasting is by using a
demand of coal for various industries, both "ripper" that serves as the rake before
domestically and abroad that encourages excavated and published by Excavator Back
local entrepreneurs to turn to coal mining Hoe.
activities with small scale up medium.
II. THEORETICAL BASIS
Mining companies are small to
medium bersekala have difficulty in Ripper consists of several types that
achieving production targets, due to can be classified as follows:
overburden material is very compact, solid,
and keras.Kekerasan material can be a. Multi-shank Rippers (Rigid type),
classified as follows: soft or easy digging, Ripper has three shank rippers are
medium hard digging, digging hard, very arranged in parallel. Multi-shank
hard digging or rock. Classification of rock rippers is very efficient for use in
types very hard digging before excavated areas that have a soft material for the
must first be detonated. The rock types corner digging (digging angel)
dominate the overburden in coal mines, ripper can be optimum. Rippers
especially in the East Kalimantan region, so Multi-Shank image can be seen in
that companies have difficulty in Figure 1.
pembongaran and stripping. Alternative
made in the achievement of production is by
means of explosives.

1
digger (excavator Back Hoe PC 200 PC 400),
drag the tool (Bulldozer D85-D375), and
Conveyance (dump truck with 6 wheels - 10
wheels).

2. Working hours
As coal mining company in general,
the number of working days mines
(production) accounted for 300 days per year,
Figure 1 Multi-shank Rippers with a planned holiday is Hari Raya ldul Fitr,
(Rochmanhadi, 1992) the Feast ldul Adha, Christmas, New Year,
and Sunday as well as other big day. While
b. Multi-shank Rippers (Variable working hours per day from 7 hours to 15
type), Ripper has three ripper point hours.
hydraulically angle can be varied
according to the conditions of 3. Hours of operation tool
material dug .. Picture Rippers Based on observations at several
Multi-shank can be seen in Figure 2. coal mining company, that the tool working
hours is influenced by several factors, among
others: the weather, the willingness of the
tool, and its effectiveness. The value of each
factor is estimated as follows:
a. weather factors
Weather factors affecting the
production of calculators by using the
formula:
Figure 2 Multi-shank Rippers
𝑇𝑅
(Rochmanhadi, 1992) 𝐹𝑐 = 1 − ( )
𝑊
c. Giant Rippers (Variable type)
Where:
Giant rippers are designed
Fc = Factors weather
specifically to break the rock
TR = Hours lost per year
material hard enough. Ripper Ripper
W = Hours
has a point that can be set
(adjustable) in order to conform
Total hours lost are calculated using
with the excavated material. Rippers
rusumus:
Giant image can be seen in Figure 3.
𝑇𝑅 = 𝑅 𝑥 (𝑅ℎ + 𝑇ℎ)

Where:
TR = Hours lost per year
R = Average days of rain per
year
rh = Hours hujan every day
th = Clock every day cleaning
mud rain
Figure 3 Giant Rippers (Rochmanhadi,
1992)
b. Factors willingness tool
Production equipment is calculated (Mechanical Availability, MA)
drngan attention to the factors that affect, The availability of tools is a factor
among others: that is used to indicate the readiness of a
device to work, where ketidaksiapannya is a
1. The type and capacity of equipment result of the repair and maintenance (repair
The type of equipment used for and maintenance). The availability of tools is
small-scale mining activities are: Equipment determined from the ratio between the

2
working hours of effective and effective Table 2 Job efficiency ripping
hours plus hours of maintenance / repair.
Operating conditions job Efficiency
𝑊 Good (Good) 0.75
𝑀𝐴 = 𝑥 100%
𝑊+𝑅 A verage (average) 0:58
Rather poor (rather ugly) 0:50
Where: Poor (ugly) 0:40
MA = mechanical availability
W = Working Hours
Actual production tool rake is
R = Repair
calculated using the following formula:
c. The effectiveness factor (Use of 𝑃𝑎 = 𝑃𝑠 𝑥 𝐽𝑒
Availibility, UA)
Effectiveness factors used to Where:
demonstrate the effectiveness of an operation, Pa = Actual production
in which the tools do not effectively work due ps = Standard production
to lack of coordination and adjustment. Je = job efficiency
Factors equipment effectiveness is
determined by the ratio between the hours of Figure 4 to Figure 7 Ripper in design
operation with total available working hours. using Solidworks.
𝑊
𝑈𝐴 = 𝑥 100%
𝑊+𝑅+𝑆
Where:
UA = Use of availability
W = Working hours
R = Repair
S = standby

The production capability of the tool


rake (ripper) to the specifications of each
instrument whose value is determined based
on the material hardness in wave velocity
Figure 4 design Rippers
values format (seismic wave velocity). The
ability of a standard production tool rake
Komatsu D 155 and 0375 in various
conditions of the material hardness is shown
in Table 1.

Table 1 Standard production tool rake (bcm /


hour)

Type Seismic Wave Velocitv (m / s)


Tool 500 750 1000 1250 1500 1750 2000
D155 705 520 388 286 203 133 72
D375 1383 1059 828 650 504 380 272
Figure 5 Rippers design looks aside
And based on Job Efficiency
Ripping who constitute the actual operation
penggaruan are affected by the conditions in
which the operating efficiency of the
appliance is not operating at full capacity in
one hour. Value Job Efficiency Ripping is
dlihat in Table 2.

3
In Figure 8 is a processing flow
chart of this research. The first step is
determining the dimensions do Ripper. In this
case the connection with data retrieval. Then
the survey material. Do overburde stripping
process that divided two, with and without the
Ripper Ripper. After the stripping process
overburde stripping and profit results
obtained between the two processes, select
the process more profitable results between
the two methods is seen from the time, money
Figure 6 Dimensional Rippers looks ahead and fuel.

5. RESULTS AND DISCUSSION

1. Production Ripper
Referring to the general conditions
of the overburden material in the region of
East Kalimantan which has fast propagation>
1000 m / s, then the existence of the tool rake
in principle is needed. Assuming a hard
material having a hardness value of
propagation of 1250 rn seconds, then the
production tool in the Job Efficiency rakes
Figure 7 Dimensional Rippers looks aside 0375 averages, are:
4. METHODOLOGY
𝑃 = 650 𝑥 0,58 = 377 𝑏𝑐𝑚/𝑗𝑎𝑚
This research workmanship step as
Of the large number of production
illustrated in Figure 8. Research methodology
shows that 377 bcm / hour uncovered
The research methodology is a step or
overburden material without blown up,
sequence and used as a researcher in
making it easier Excavator Back Hoe in
conducting research.
digging and loading.

2. Demolition without Ripper


Stripping of overburden without
raked in advance using ripper cause a "cycle
time" digging tools fit more especially when
digging and loading capacity "bucket" (Fill
Factor) is very small, ie between 75% - 85%
due excavated material in the form of chunks
large ,
Based on the observation of the
production target of between 245,000 bcm
overburden stripping - 350,000 bcm per
month using 3 units Excavator Back Hoe
Komatsu PC 300 as digging tools fit with the
conditions of the willingness of the tool 90%
indicated that the production target has never
been reached. This is due to a hard and tough
material uncovered, on the other hand use
more fuel and "tooth bucket" faster wear out.
From the calculation of production
stripping overburden at. Gema Coal Abadi is
a mining contractor PT. Insani Bara Perkasa
Figure 8 Research Flow Chart seen in Table 3.

4
Table 3 Production stripping overburden
2005

No. Month Production (bcm)


1 January 107,000
2 February 115,000
3 March 110,000
4 April 101,000
5 May 105.000 Figure 9 Ripping method of cross-maze
6 June 110,000
7 July 125 600 With this method, the rock would be
8 August 130.000 easily detached from the parent rock, making
9 September 125.000 excavation by Excavator Back Hoe easier and
10 October 109,000 use the time to dig a smaller (small cycle
11 November 110 200 time).
12 December 102,000
Based on observations at the same
location and different pit mine using a
And from data on the use of fuel oil "ripper" for demolition excavator overburden
for loading the third excavator is shown in and unloading by Cat 330 Excavator Back
Table 4. Hoe 2 units with the production condition of
80% is obtained as follows seen in Table 5.
Table 4 The use of fuel
Table 5 Production stripping overburden
material Hour
No. Month roasted Productive No. Month Production (Bcm)
(liter) (1am) 1 January 141 600
1 January 13125 477.50 2 February 148 000
2 February 12000 450.00 3 March 145 200
3 March 13275 425.00
4 April 143000
4 April 12 825 475.00
5 May 156 000
5 May 13050 492.50
6 June 160 100
6 June 12750 500.00
7 July 14850 507.50 7 July 192 500
8 August 15000 550,00 8 August 198000
9 September 14 925 475.00 9 September 193000
10 October 13200 495.00 10 October 151 000
11 November 13650 492.50 11 November -
12 December 13500 450.00 12 December -
3.Demolition of the Ripper From the production data show that
In general, the type used on the job using the Excavator Back Hoe two units with
Bulldozer ripping is Komatsu D 155 - the same capacity and aided by bulldozers to
Caterpillar D9N D378 or given area of Pit rip before excavation, production is greater
Mine to the production target of stripping than using Excavator Back Hoe 3 units
245,000 bcm - 350,000 bcm per month is not without ripping done first. And search data on
too large. the use of fuel oil both Excavator Back Hoe
unit and one unit Bulldozer show a decline in
Ripping methods that do are a cross- the use of fuel (see Table 6. This is due to the
cutting maze coating field rock or 45 ° see strength of the machine tool does not work
Figure 5. hard.

5
Table 6 The use of fuel oil in 2006 the most red-colored area, and the parts that
have the smallest deformation is the most
Exacavator Bulldozer D375 ' blue (Hong-Kyu, 2018). Deformation
Month Hour Hour simulation results can be seen in the figure
BBM Productiv BBM Productiv below.
January 8531 358.13 e 75000 170.00e
February 7800 337.50 78000 165.00
March 8628 318.75 79600 182.00
April 8336 356.25 73200 175.00
May 8482 369.38 75200 186.00
June 8287 375.00 77400 183.00
July 9652 380.63 84000 204.00
August 9750 412.50 83000 210.40
September 9701 356.25 81000 191.20
October 8580 371.25 79 166.80
November - - -
800 -
December - - - -

Figure 11 The results of deformation


For the analysis of the storage tank analysis
2016. Analysis using Anysy analysis Ripper
style 1000 N when given as in the following Based on the above simulation
explanation. results, defromation greatest value is in the
red
a. Stress Analysis (Von Mises)
Voltage is set force (force) on an c. Strain analysis
object surface. The narrower area of the The strain is part of the deformation,
surface but the style remains, the greater the which is described as a relative change of the
stress. The voltage is indicated on the red particles in the body that is not a rigid body.
shades, the smallest is the most blue. While Another definition of strain may vary
the area with medium voltage areas are green- depending on the field of what term is used,
yellow-blue. (Indarniati and Frida, 2008) or from and to the point where the strain
occurred. (Hasbi, 2014).

Figure 10 The results of stress analysis Figure 12 Results strain analysis


Based on the above simulation In the above simulation,Ripper
results, Ripper declared safe because there declared safe because there are no red
are no red gradation. gradation.
b. AnalysisChanges Shape 6. CONCLUSION
(Deformasion)
deformationis the change in shape Production ripper on the overburden
on the body is subjected to force. Parts that material that has a value of propagation of
have the greatest deformation of this order is 1250 m / sec at 377 bcm / hour, thereby

6
extracting and loading using the Excavator Hasan, Hajuni. (2008). Use of Ripper in
Back Hoe Can more easily without detonated. Helping Backhoe Excavators on
Stripping Without Bursting
Stripping of overburden without Overburden at Small Scale Coal Mine.
raked first cause "cycle tirne" digging tools fit Alpika Journal, Volume 8 Number 1.
larger load capacity "bucket" (Fill Factor) is
very small, ie between 75% - 85%, "tooth Kim, Hong-Kyu, dkk. (2018). Deformation
bucket" more rapid wear and tear, and the use Criterion for Face-Centered-Cubic
of fuel oil more. Metal Nanowires. Department of
Materials Science and Engineering,
Using a "ripper" on stripping Korea University, Republik of Korea.
overburden to increase production, reduce the
use of fuel oil, and directly minimizing Mengler, Kew, Gilkes dan Koch. (2006).
operational costs. Using Instrumented Bulldozers to
Map Spatial Variation in the Strength
of Regolith for Bauxite Mine Floor
BIBLIOGRAPHY Rehabilitation.
Song, Bo dan Brett Sanbon. (2018).
Budi, Tri dan Edward. (2014). Rock Strength
Relationship of Compressive Stress-
Evaluation of Ripper Equipment PT.
Strain Response of Engineering
Kitadin Embalut Site, Tenggarong
Materials Obtained at Constant
District, opposite Kutai Kartanegara,
Engineering and True Strain Rates.
East Kalimantan Province. Mining
Sandia National Laboratories, United
Engineering Study Program, Kutai
States.
Kartanegara University.
Varges, Fonseca, Costa dan Naccache.
Fernandez. (2001). Materials Selection to
(2018). Exchange ßows between yield
Excavator Teeth in Mining Industry.
stress materials and Newtonian oils.
Volume 250, Issues 1-12.
Department of Mechanical
Engineering, Rio de Janeiro.

Potrebbero piacerti anche