Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
: ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 1/8
Scope of Work Design (●), Fabrication (●), Installation ( ), Commissioning (○), Supervising (○)
1. PROJECT GENERAL
2. GENERAL TERMS AND CONDITION
3. PERFORMANCE GUARANTEE
4. SCOPE OF WORK
5. TECHNICAL REQUIREMENT
5.1 DESIGN CODE AND STANDARD
5.1 DESIGN DATA
5.3 GENERAL REQUIREMENT
6. PAINT SPECIFICATION
7. PACKING AND DELIVERY
8. SPARE PARTS & SPECIAL TOOL
HYUNDAI ROTEM
Doc. No. : ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 2/8
1. PROJECT GENERAL
1-1. Project Description
This specification states the conditions and requirements for Fabrication, assembly, packing and
delivering of Steel Structure for BETA COAL TERMINAL PROJECT in Indonesia complete with
accessories and with related equipment herein after described.
3. PERFORMANCE GUARANTEE
3-1 Guarantee and Warranty
The warranty period for the Goods shall be twenty four (24) months after issuance of Final Acceptance
Certificate (Mechanical Completion) by the End User.
If any trouble or defect in the design, Goods, Work, workmanship, operating characteristics or
performance of any part of the Goods and / or Work arises or is in danger of arising, at any time up to
the warranty period, and the Supplier is notified thereof, the Supplier shall, at its own cost and expense
and as promptly as possible thereafter, make all alterations, repairs and replacements as may be
necessary to permit the Goods and / or Work to function in accordance with the contract and to fulfill
the foregoing warranties.
HYUNDAI ROTEM
Doc. No. : ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 3/8
4. SCOPE OF WORK
4-1 Division of Scope of Supply
Work Scope
Item Remarks
Purchaser Supplier
Design ● -
Material Procurement ●
Manufacture ●
Painting ●
Inspection & Test ●
Packing ●
Installation ●
Commissioning ●
Site Supervision (Erection &
○ Option
Commissioning)
2 Year Warranty ●
Spare parts - -
5. TECHNICAL REQUIREMENT
5-1 Design Codes and Standards
HYUNDAI ROTEM
Doc. No. : ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 4/8
The plants shall be designed, manufactured, erected, and tested in accordance with
requirements and standard practice which set forth in the employer’s requirement. When
no specific requirement is stated in the employer requirements, the most relevant
regulation, standard and code of latest revision shall be applied.
In the event of any conflict between the specification in the employer’s requirement and
standard code, the most stringent requirement’s shall be applied unless otherwise be
approved by the engineer.
The following internationally recognized standard and code shall be acceptable
HYUNDAI ROTEM
Doc. No. : ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 5/8
- SNI 03-3985-2000 Indonesian Code for Detector and fire alarm system planning,
- SNI 03-6574-2001 Indonesian Code for Procedures for the design of emergency
- SNI 03-6575-2001 Indonesian Code for Procedures for planning artificial lighting
systems in buildings.
HYUNDAI ROTEM
Doc. No. : ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 6/8
5-2-3. Rainfall
Mean annual precipitation : over 2,000 mm
Mean number of days with precipitation : 175 days per year
Maximum recorded rainfall in 24 hour period : 118 – 310 mm
Wettest months: November to December typically more than 350mm rainfall per month.
Driest month: May through July with typically less than 200mm rainfall per month.
5-2-4. Humidity
Minimum humidity : 60%
Maximum humidity : 95%
Average : 85%
5-2-5. Material Handled
Material conveyed : Crushed coal
Maximum lump size : -50mm
Size distribution : 95% minus 50mm with minimum fine
Bulk density
For volume and handling rate calculation : 0.8 t/m³
For load, power, and structural calculation : 1.1 t/m³
Repose angle : 37°
Material conveying surcharge angle : 15°
Total moisture : 40.4%
Inherent moisture : 17.1%
Ash content : 4.2%
Volatile matter : 42%
Fixed carbon : 36.7%
Total sulphur : 0.77%
Grindability (HGI) : 39 min – 56 max (45 average)
Air temperature : 23 °C (min) - 40°C (max)
5-2-6. Noise Level : Below 85 dB (A) (1m next to machine)
5-2-7. Design life time : 25 years
5-2-8. System voltage and equipment rating
System Voltage at No Load Equipment Rating
Distribution Line(by PLN) 20kV or 11kV, 3 phase 20kV or 11kV, 3 phase
Motor (6.6kV, 3 phase)
MV System 6.9kV, 3 phase
Non-Motor (6.6kV, 3 phase)
Motor (380V, 3 phase)
LV System for Power 400V, 3 phase
Non-Motor (400V, 3 phase)
Lighting & Small Power 400V/230V, 3 phase 4 wires 400V/230V, 3 phase 4 wires
Welding Receptacle 400V, 3 phase 380V, 3 phase
UPS System 230V, 1 phase 230V, 1 phase
HYUNDAI ROTEM
Doc. No. : ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 7/8
6. PAINT SPECIFICATION
The cleaning and painting for all the equipment shall be made suitably for use under the
Atlantic saline environment close to the sea at the site.
The relative humidity of 95% shall be applied for protection of equipment for mechanical
and electrical equipment such as material selection, painting and electrical clearance.
The painting specification with final colors and identification system for the equipment shall
be approved by the EPC Contractor.
Areas within 100 mm of field welds shall not be primer coated.
Weld ends shall be coated with a product such as deoxaluminate paint or an alternate
acceptable to the Contractor, unless otherwise specified.
All machined surfaces, except weld ends, shall be coated with suitable protective material to
prevent corrosion. The use of greases or oil, other than light grade mineral oil, for corrosion
protection shall be prohibited.
All manufacturing waste, such as metal clips and fillings, welding rods and studs, waste, rags,
debris, etc., shall be removed from the interior of the unit. All loose mill scale, rust, oil,
grease, chalk, crayon paint marks and other deleterious material shall be removed from the
interior and exterior surface.
Final paint color : To be later
Coating procedure
Surface Application
Application Work
Prep. Remarks
Condition No. of Coat Paint Type DFT(㎛) Scope
(SSPC)
Zinc rich epoxy
1st Coat 50
primer
Steel surface
exposed to 2nd Coat Epoxy mastic 150
coastal SP-10 Polyurethane Shop
Environment Enamel
below93℃ 3rd Coat Topcoat or HS 50
Acrylic
Polyurethane
HYUNDAI ROTEM
Doc. No. : ASI-RFQ-005
Request for Quotation Rev. Date. : 02-Oct. 2018
for
Rev. No. : Rev. 0
Conveyor Belt
Page : 8/8
Prior to shipment, the equipment shall be completely drained and thoroughly dry. When
such draining requires removal of plugs, drain valves, etc., the Supplier shall make sure that
these parts are reinserted or reassembled prior to shipment.
All openings, nozzles, flanged, threaded and weld-end connections shall be provided with
protection to prevent damage, corrosion and entrance of foreign matter during shipment
and storage.
All openings shall be provided with substantial wooden or metal closure.
Flanged connections shall be protected by a 12mm or thicker plywood disc bolted to the
face of the flange.
Threaded connections shall be protected with screwed or snap-in (snap-on) type plastic
protectors.
Metal straps, fasteners or covers shall not be tag-welded to any manufactured part.
All electric and electronic equipment shall be packed to ensure against physical damage
during shipment and storage, and shall be wrapped to protest against humidity and contact
with water.
All exterior parts of the unit except for machined surfaces shall be painted in accordance
with the specification.
Equipment shall be adequately supported for shipment. All loose parts shall be crated or
boxed for shipment. Each box shall be approximately marked for identification purposes.
Where shipment is braced internally, it shall be marked conspicuously, “Remove internal
braces before testing and operating”.
Spare parts shall be packed for long term storage.
The Supplier shall make suitable treatment for prevention of the rust and corrosion on the
surfaces of the equipment and components during the sea transportation.
11. ATTATCHMENT
A1. Owner’s Structural Technical Specification
A2. Information of Steel structure weight
A3. Reference fabrication drawing
A4. Deviation Code & Standard
HYUNDAI ROTEM