Sei sulla pagina 1di 5

Technical Article

www.ijoss.org
Steel Structures 8 (2008) 67-71

Steel Bridge System with Simple Girder for Dead Load and
Continuous Girder for Live Load: Economic Advantages
Atorod Azizinamini¹ and Dae-Yong Lee² * ,

¹Professor, Civil Engineering Department, University of Nebraska, Lincoln, Nebraska, USA


²Senior Research Engineer, RIST Steel Structure Research Center, Republic of Korea

Abstract
The National Bridge Research Organization (NaBRO) has developed a competitive steel bridge system known as “steel
bridge system with simple girder for dead load and continuous girder for live load” In the proposed system, the girders are
designed as simply supported to resist construction loads and as continuous after hardening of the concrete. We investigated
in this paper the cost-benefit of the new steel bridge system as compared with that of the conventional system. In this study,
two girder bridges (one for I-girder bridge and one for box girder bridge) that have been already constructed in the U.S. are
selected and then the bridges are designed using two methods: the conventional method and the newly proposed concept.
Changes in steel girder weights, costs, and construction schedules are mainly discussed.
Keywords: Steel Bridge, Simple for Dead and Continuous for Live, I-Girder Bridge, Box Girder Bridge, Cost

1. Introduction

An 11-year overview of the National Bridge Inventory


(FHWA, 2003) data obtained from the Federal Highway
Administration (FHWA) for fifty states is shown in Fig.
1. The data are categorized according to the material of
bridge construction. The results in Fig. 1 clearly show
that the construction of steel and timber bridges in this
period is declining, whereas concrete and prestressed
concrete bridge construction is increasing. To identify
trends in the use of bridge materials in the mid-west
region of the U.S., a detailed market analysis was carried
out by Lampe (2001). Based on the trends identified
through the market analysis for the time period from 1911 Figure 1. Number of bridges in the U.S.
to 1998, it has been concluded that steel bridge
construction in all span lengths has either remained
steady or decreased in number in the last two decades, of simple construction methods. For this reason, the
whereas that of prestressed concrete has extended its National Bridge Research Organization (NaBRO), in its
presence as the construction material of choice across all effort to find an innovative construction method, finally
span lengths. The major factors for the diminishing developed a competitive method known as “steel bridge
competitiveness of steel bridges in the bridge market can system with simple girder for dead load and continuous
be attributed to steel material price, labor, and the girder for live load” In the new proposed method, the
excessive use of complicated details and equipment. girders of each span are designed as simply supported to
Traditionally, the material cost had been more important resist construction loads, such as weight of the concrete
in the estimation of the total cost of a bridge project, but slab and girders. However, the girders are connected
now the least labor generally results in the least cost. through a concrete diaphragm on the pier location to be
Labor cost can be substantially reduced through the use continuous after the hardening of concrete for the applied
live loads such as traffic weight. In this case, the
*Corresponding author connection over the pier is simple during the slab
Tel: +82-31-370-9582; Fax: +82-31-370-9599 concrete pouring and continuous during the bridge’s
E-mail: dylee@rist.re.kr service life. This requires designing a pseudo-continuous
68 Atorod Azizinamini and Dae-Yong Lee

connection over the pier that connects two adjacent


girders.
In this article, the cost-benefit of the “steel bridge
system with simple girder for dead load and continuous
girder for live load” is discussed in comparison with the
cost of the conventional steel bridge construction method.
For the comparison, two girder bridges (one for the I-
girder bridge and one for the box girder bridge) are
selected and then the bridges are designed using two
methods: first as a continuous beam for dead, live, and
superimposed loads (conventional method) and second as
two simple beams for dead load and continuous for live
load according to the new proposed concept.

2. Conventional System versus New System


Due to handling limitations, steel girders are usually
fabricated in the shop in several pieces, and then
transported to the site for assembly. The multi-span steel
bridges are connected together at the site to make the New method of steel bridge design and construction.
continuous beams. The construction sequence consists of
Figure 3.

placing the middle segment and connecting the two end


sections using a bolted or welded field splice. The location
of field splices due to structural design considerations is field, the contractor fixes them with a partial concrete
preferred to be somewhere between the piers rather than diaphragm at the pier. This technique greatly simplifies
on the piers. This type of construction usually requires the formation of continuous girders, which would otherwise
extra cranes or temporary shoring (see Fig. 2) for erection be bolted or welded together in the field. After placing
with a possible interrupting traffic. The connection of two each girder on the bearing pads, the concrete slab and the
steel girders while hanging in the air can also be remaining portion of the diaphragm are poured. The
hazardous for the steelworkers. Furthermore, the detailing concrete deck, diaphragm, and longitudinal reinforcing
and fabrication of splice holes require extra inspection provide the continuity of two adjacent steel girders for the
costs. In a series of discussions with designers, fabricators, traffic loads and superimposed dead loads as shown in
and contractors, two factors were identified to be Fig. 3(b). The advantages of this new system were
essential in improving the conventional system: investigated in a parametric study (Lampe, 2001) and are
• Elimination of field splices as follows:
• Simplification of the type of details at the pier location • The need for expensive field splices are completely
In the newly developed concept, designers specify steel eliminated for spans of up to 150 ft (as controlled by
girders in simple span configuration as shown in Fig. transportation considerations).
3(a); girders sit simply on the abutments and piers. In the • The contractor will need fewer cranes for installation.
The need for less installation equipment allows
smaller contractors to bid for jobs.
• A uniform cross-section can be utilized for the entire
span that reduces the fabrication effort.
• Girders can be placed over the support without
significant interruption to the ongoing traffic.
• Improves safety of steel workers.
• The placement of girders directly on the pier and
abutment reduces the erection time.
• Requires minimal detailing of the steel beams.
• Does not need temporary shoring.
Girders designed using the proposed concept can increase
the weight of steel material required because of the
simple span action of each girder under the construction
loads. However, the implementation of simpler details
enhances the overall economy of the bridge and this will
Figure 2. Conventional erection method of steel girders. be shown later in this article.
Steel Bridge System with Simple Girder for Dead Load and Continuous Girder for Live Load: Economic Advantages 69

Figure 4. Erection of the first span of sprague street bridge Figure 5. Erection of the N-2 box girder bridge over the
over the I-680. I-80.

3. Case Studies The N-2 Bridge has been recently constructed at


Nebraska Highway 2 over the I-80 (see Fig. 5). The
In order to validate the economic advantage of the bridge structure consists of two 139-ft spans, and a three-
proposed concept, a parametric study was carried out. For box girder cross-section. The spacing between centerlines
the study, two recently constructed steel bridges (Sprague of the boxes is 16 feet-1 in. and supports a 46 feet-4 in.
Street Bridge and N-2 Bridge) based on the new concept clear roadway and a pedestrian sidewalk. The cast-in-
were selected. Sprague Street Bridge consists of the I- place deck thickness is 7.5 in. with 0.5 in. integral
girder cross-section, whereas the N-2 Bridge has the box wearing surface. The exterior girder overhang is 4 feet-1
section. These two bridges were designed based on the in. from the center of the exterior girder to the deck’s
conventional method and the proposed concept. AASHTO- edge. The box girders are fabricated with 100 ksi
LRFD Bridge Design Specification (1998) provisions weathering steel. The bridge was built using the proposed
were used for the steel bridge designs. construction method. This bridge was selected to examine
The Sprague Street Bridge over the I-680 is located in the new concept on the different cross-sections and its
Omaha, Nebraska and was opened to traffic in August practicality in the medium span length range.
2004. The erection of the first span of Sprague Street The above two bridges were designed using two methods:
Bridge over the I-680 is shown in Fig. 4. The bridge has the conventional method and the newly proposed concept.
two spans, each 97 ft long with four I-girder cross- A summary of the design results is provided in Table 1.
sections. The clear roadway width is 32 ft, with a 7-ft The variation of flange thickness is limited to two thicknesses
pedestrian sidewalk on the south side of the bridge. Cast- along the girder length to include practical fabrication
in-place deck thickness is 7.5 in. with 0.5 in. integral considerations. However, the obtained thickness is not
wearing surface. For the fabrication of the rolled I-girder, market-standard size. The web depth and thickness
50 ksi weathering steel was used. In this study, the remain constant in both methods to satisfy deflection
Sprague Street project was selected for two reasons. First, requirements. In weight calculations, the weights of
the 97-ft spans represent a common two-span bridge stiffeners and cross frames are ignored as they are similar
constructed in the U.S. in the short span range. Second, in both alternatives. The flange thickness is changed to
the project has been recently designed and erected and obtain a demand-to-strength ratio of the section close to
thus provides current cost estimates for economic 1.00. The results in Table 1 shows that for each case the
comparisons. weight of the additional steel by using the new concept is
Table 1. Comparison of the designed girders
I-Girder Box Girder
Conventional Method New Method Conventional Method New Method
Top Flange Sizes (in) (15.8 × 0.5) & (15.8 × 2.6) (15.8 × 0.5) & (15.8 × 2.6) (16 × 0.64) & (16 × 1.3) (16 × 0.7) & (16 × 0.8)
Web Sizes (in) (36.56 × 0.75) (36.56 × 0.75) (50 × 0.375) (50 × 0.375)
Bottom Flange Sizes (in) (15.8 × 0.5) & (15.8 × 2.6) (15.8 × 0.5) & (15.8 × 2.6) (72 × 0.64) & (72 × 1.3) (72 × 0.7) & (72 × 0.8)
Demand/Strength Ratio 1.00 1.00 1.00 1.00
Weight of 1 Girder (kips) 21.46 22.07 52.47 54.63
Weight Increase Percentage 2.82% 4.13%
70 Atorod Azizinamini and Dae-Yong Lee

Table 2. Steel girder cost comparison


I-Girder Box Girder
Conventional New Conventional New
Weathering steel unit price per lb $0.75 $0.75 $1.1 $1.1
Price of each steel girder $15,627 $16,551 $57,712 $60,093
Difference between the two methods $923 $2,381

about 3 percent for the I-girder and 4 percent for the box splice costs about $2,000 for each I-girder. It is shown
girder. that the additional field splice adds approximately 13
percent to the total cost of each steel I-girder, whereas
4. Cost-Benefit Analysis employing the new technique increases the steel material
cost only by 6 percent. Therefore, there is a 7 percent
The average bid unit price of fabrication and erection savings with the use of the new method of construction.
of each steel girder is listed in Table 2. The unit price is Another splice detail is designed for the box girder and
derived from the assumption that the girders have been the cost is estimated by the same method as described for
fabricated following the conventional method. As the the I-girder. The cost of each field splice is about $6400,
weight of the girders designed based on the new technique which represents 11 percent of the total cost of a box
is greater than the conventional method, the total price of girder. The increase in cost due to the extra weight is
each steel girder is also greater. The increase in the cost about 4 percent. Therefore, by using the new method, the
of materials by utilizing the new concept is $923 for the contractor can save up to 7 percent for each box girder.
I-girder and $2381 for the box girder, as given in Table 2. In this study, the extra time required for the fabrication
The cost of fabrication and installation of each field and erection of each splice is also evaluated in consideration
splice needs to be estimated in order to determine the of a crew consisting of two steel workers for fabrication
extra cost of each girder when designed using the and installation, one crane operator, and one inspector.
conventional method as opposed to the new concept. The The total estimated time for the field splice of the I-girder
cost of fabrication and erection of one field splice for is about 10 hours. This will extend the project time for
each girder consists of the cost of bolts, holes, plates, an more than one day. The time estimation for the box girder
extra crane, steel workers for installation, and inspection. case indicates that employing field splices can extend the
The unit price and required time for each item is obtained project time for more than 4 days.
from the RS Means Open Shop Building Construction
Cost Data (2003). A 55 percent surplus is added to the 5. New Concept in Practice
total cost of material, equipment, and labor to consider
the overhead, profit, and indirect costs of the contractor. The Sprague Street over the I-680 and the N-2 over the
The typical field splice designed for the I-girder bridge is I-80 Bridges were constructed using the new construction
shown in Fig. 6. The fabrication and erection of each technique in Nebraska in 2003 and 2004, respectively.
The I-girder bridge was made of a rolled shape section
with a uniform section across the length and thus did not
need any change in the cross-section. The only additional
detail was the end bearing plates welded to both ends of
the girder in the shop. The cross-section of the box girder
was also uniform across the span length; therefore, plate
waste was minimized. The additional end bearing plates
were welded to the ends to improve the stability of the
box girder and continuity of the bridge system after
pouring the concrete.
The girders of the first span of Sprague Street Bridge
were set independently without erecting the second span
girder. Therefore, the traffic under the second span did
not need to be interrupted. The independence of the
girders setting in two spans is not possible with the current
method of practice, as the girders must be continuous
over the pier. The girders of the first span were erected at
night in order to minimize disruption to traffic, as the I-
680 below had to be closed during that time. The cost for
Figure 6. I-girder field splice details. in-place erected steel for the Sprague Street Bridge was
Steel Bridge System with Simple Girder for Dead Load and Continuous Girder for Live Load: Economic Advantages 71

approximately $0.52/lb. This compares to the rule-of- comparison are summarized in the following:
thumb value of engineering estimates of $0.75/lb for • The application of the new construction method may
erected rolled steel bridges with conventional bolted field result in a slight increase in the weight of the steel
splices (Azizinamini and Vander Veen, 2004). Project girder. The comparison in Table 1 shows about a 3
duration was about 6 calendar months. The elimination of percent additional weight of steel for the I-girder and
field splices could have shortened the project schedule by 4 percent for the box girder.
about 1 day, which represents approximately 1 percent of • However, the Sprague Street Bridge and N-2 Bridge
the total project duration. projects show that the application of the new method
The erection of the 139 ft box girder was carried out by can make cost savings of up to 7 percent by
two crawler cranes without any temporary shoring. The eliminating field splices in spite of the material cost
placement of each girder from the semi-trailer on the increase of up to 6 percent.
abutment and pier took about 20 minutes. As it was • Also found from the cost-benefit analysis is that the
pointed out earlier, the installation of a box girder with elimination of field splices can shorten the project
the traditional construction method could exceed 4 days schedule by up to 3 percent of the total project
considering the time needed for setting the temporary duration.
shoring and fastening of the field splices. The construction
period for this bridge was also about 6 calendar months. References
The time savings estimated by eliminating the field splice
based on the time calculation presented in the previous AASHTO (1998). “AASHTO LRFD Bridge Design
section is about 3 days, which represents approximately 3 Specifications,” Second Edition (w/2001 interims),
percent of the total project time. American Association of State Highway Transportation
Officials, Washington D.C.
6. Summary and Conclusion Azizinamini, A. and Vender Veen, L. (2004). “Simple-Made-
Continuous,” Steel Bridge News, 5(4), pp. 6-7.
In order to investigate the cost-benefit of the “steel Federal Highway Administration (FHWA) (2003). “National
bridge system with simple girder for dead load and Bridge Inventory.” URL http://www.fhwa.dot.gov/bridge/
nbi.htm (Accessed to This Website on December 22,
continuous girder for live load” proposed by the National 2007)
Bridge Research Organization (NaBRO), two girder Lampe, N. (2001). “Steel Girder Bridges Enhancing the
bridges (one for the I-girder bridge and one for the box Economy,” Master Thesis, University of Nebraska,
girder bridge) are selected and design of the bridges are Lincoln, Nebraska.
carried out using two methods: the conventional method RS Means (2003). “Open Shop Building Construction Cost
and the newly proposed concept. Major findings from the Data,” RS Means Company.

Potrebbero piacerti anche