Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
www.ijoss.org
Steel Structures 8 (2008) 67-71
Steel Bridge System with Simple Girder for Dead Load and
Continuous Girder for Live Load: Economic Advantages
Atorod Azizinamini¹ and Dae-Yong Lee² * ,
Abstract
The National Bridge Research Organization (NaBRO) has developed a competitive steel bridge system known as “steel
bridge system with simple girder for dead load and continuous girder for live load” In the proposed system, the girders are
designed as simply supported to resist construction loads and as continuous after hardening of the concrete. We investigated
in this paper the cost-benefit of the new steel bridge system as compared with that of the conventional system. In this study,
two girder bridges (one for I-girder bridge and one for box girder bridge) that have been already constructed in the U.S. are
selected and then the bridges are designed using two methods: the conventional method and the newly proposed concept.
Changes in steel girder weights, costs, and construction schedules are mainly discussed.
Keywords: Steel Bridge, Simple for Dead and Continuous for Live, I-Girder Bridge, Box Girder Bridge, Cost
1. Introduction
Figure 4. Erection of the first span of sprague street bridge Figure 5. Erection of the N-2 box girder bridge over the
over the I-680. I-80.
about 3 percent for the I-girder and 4 percent for the box splice costs about $2,000 for each I-girder. It is shown
girder. that the additional field splice adds approximately 13
percent to the total cost of each steel I-girder, whereas
4. Cost-Benefit Analysis employing the new technique increases the steel material
cost only by 6 percent. Therefore, there is a 7 percent
The average bid unit price of fabrication and erection savings with the use of the new method of construction.
of each steel girder is listed in Table 2. The unit price is Another splice detail is designed for the box girder and
derived from the assumption that the girders have been the cost is estimated by the same method as described for
fabricated following the conventional method. As the the I-girder. The cost of each field splice is about $6400,
weight of the girders designed based on the new technique which represents 11 percent of the total cost of a box
is greater than the conventional method, the total price of girder. The increase in cost due to the extra weight is
each steel girder is also greater. The increase in the cost about 4 percent. Therefore, by using the new method, the
of materials by utilizing the new concept is $923 for the contractor can save up to 7 percent for each box girder.
I-girder and $2381 for the box girder, as given in Table 2. In this study, the extra time required for the fabrication
The cost of fabrication and installation of each field and erection of each splice is also evaluated in consideration
splice needs to be estimated in order to determine the of a crew consisting of two steel workers for fabrication
extra cost of each girder when designed using the and installation, one crane operator, and one inspector.
conventional method as opposed to the new concept. The The total estimated time for the field splice of the I-girder
cost of fabrication and erection of one field splice for is about 10 hours. This will extend the project time for
each girder consists of the cost of bolts, holes, plates, an more than one day. The time estimation for the box girder
extra crane, steel workers for installation, and inspection. case indicates that employing field splices can extend the
The unit price and required time for each item is obtained project time for more than 4 days.
from the RS Means Open Shop Building Construction
Cost Data (2003). A 55 percent surplus is added to the 5. New Concept in Practice
total cost of material, equipment, and labor to consider
the overhead, profit, and indirect costs of the contractor. The Sprague Street over the I-680 and the N-2 over the
The typical field splice designed for the I-girder bridge is I-80 Bridges were constructed using the new construction
shown in Fig. 6. The fabrication and erection of each technique in Nebraska in 2003 and 2004, respectively.
The I-girder bridge was made of a rolled shape section
with a uniform section across the length and thus did not
need any change in the cross-section. The only additional
detail was the end bearing plates welded to both ends of
the girder in the shop. The cross-section of the box girder
was also uniform across the span length; therefore, plate
waste was minimized. The additional end bearing plates
were welded to the ends to improve the stability of the
box girder and continuity of the bridge system after
pouring the concrete.
The girders of the first span of Sprague Street Bridge
were set independently without erecting the second span
girder. Therefore, the traffic under the second span did
not need to be interrupted. The independence of the
girders setting in two spans is not possible with the current
method of practice, as the girders must be continuous
over the pier. The girders of the first span were erected at
night in order to minimize disruption to traffic, as the I-
680 below had to be closed during that time. The cost for
Figure 6. I-girder field splice details. in-place erected steel for the Sprague Street Bridge was
Steel Bridge System with Simple Girder for Dead Load and Continuous Girder for Live Load: Economic Advantages 71
approximately $0.52/lb. This compares to the rule-of- comparison are summarized in the following:
thumb value of engineering estimates of $0.75/lb for • The application of the new construction method may
erected rolled steel bridges with conventional bolted field result in a slight increase in the weight of the steel
splices (Azizinamini and Vander Veen, 2004). Project girder. The comparison in Table 1 shows about a 3
duration was about 6 calendar months. The elimination of percent additional weight of steel for the I-girder and
field splices could have shortened the project schedule by 4 percent for the box girder.
about 1 day, which represents approximately 1 percent of • However, the Sprague Street Bridge and N-2 Bridge
the total project duration. projects show that the application of the new method
The erection of the 139 ft box girder was carried out by can make cost savings of up to 7 percent by
two crawler cranes without any temporary shoring. The eliminating field splices in spite of the material cost
placement of each girder from the semi-trailer on the increase of up to 6 percent.
abutment and pier took about 20 minutes. As it was • Also found from the cost-benefit analysis is that the
pointed out earlier, the installation of a box girder with elimination of field splices can shorten the project
the traditional construction method could exceed 4 days schedule by up to 3 percent of the total project
considering the time needed for setting the temporary duration.
shoring and fastening of the field splices. The construction
period for this bridge was also about 6 calendar months. References
The time savings estimated by eliminating the field splice
based on the time calculation presented in the previous AASHTO (1998). “AASHTO LRFD Bridge Design
section is about 3 days, which represents approximately 3 Specifications,” Second Edition (w/2001 interims),
percent of the total project time. American Association of State Highway Transportation
Officials, Washington D.C.
6. Summary and Conclusion Azizinamini, A. and Vender Veen, L. (2004). “Simple-Made-
Continuous,” Steel Bridge News, 5(4), pp. 6-7.
In order to investigate the cost-benefit of the “steel Federal Highway Administration (FHWA) (2003). “National
bridge system with simple girder for dead load and Bridge Inventory.” URL http://www.fhwa.dot.gov/bridge/
nbi.htm (Accessed to This Website on December 22,
continuous girder for live load” proposed by the National 2007)
Bridge Research Organization (NaBRO), two girder Lampe, N. (2001). “Steel Girder Bridges Enhancing the
bridges (one for the I-girder bridge and one for the box Economy,” Master Thesis, University of Nebraska,
girder bridge) are selected and design of the bridges are Lincoln, Nebraska.
carried out using two methods: the conventional method RS Means (2003). “Open Shop Building Construction Cost
and the newly proposed concept. Major findings from the Data,” RS Means Company.