TABLE OF CONTENTS
1 PURPOSE
2 SCOPE OF WORKS
4 STEP OF WORKS
7 ATTACHMENT
1. PURPOSE
The purpose of this Work Method Statement for Toilet Partition of Building is to outline and
describe in detail the procedure such as setting and lay-out plan on actual location, installation of
panels and all other related activity. Inform all concerned supervisor including workers the value
and importance of this activity prior to implementation. This activity should be performed with
strict compliance and implementation of Safety Requirements & Procedure and project
specifications to complete the work both for toilet partition of building.
2. SCOPE OF WORKS
The scope of this Method Statement covers the works in any Project
Mark the center line for the U-profiles. Clearance from the floor to the bottom of U-profile +/-
160mm. Copy the height of the U-profiles on the wall. Mark the holes from the U-profiles. Drill
holes and fix the U-profile to the wall with plugs, washer and screw.
Drill holes (+/- 28mm) for the legs according to the drawing. Put the panels into the top of the
profiles. Put the front panels onto the partition panels. Adjust the head rail to the front length
and fix with screws 4.8 x 50. Apply pre-drill using 4.30mm diameter. Put the plastic end cap on
the end of the head rail.
After putting the doors in place, level all panels so the doors are closing properly.
Fix the walls with the screws of 3.5mm diameter x 11. Apply pre-drill using the 3.1mm diameter.
Mix the component A with Component B and pour it into the hole for the legs. Fill until the floor
levels and after 24 hours later, checked if it is properly cured then removed the temporary
support.
Mount the lower (plastic) shield with screws 3.5 x 16. Apply pre-drill with 3.1mm diameter.
Mount the upper (aluminium) shield (with a click) and put the door handles together.
Mount the anti-theft bolt into the hinge.
6. QA/QC – INSPECTION
7. ATTACHMENTS