Method Statement
Document Title:
A5
ARCC/EE/ ISSUE STATUS
TABLE OF CONTENTS
Page
1 PURPOSE 3
2 SCOPE 3
3 REFERENCE DOCUMENTS 3
4 MANPOWER 4
5 EQUIPMENT 4
7 QUALITY CONTROL 12
8 SAFETY PRECAUTIONS 12
9 ATTACHMENT 12
Notes:
1.0 The latest revised documents shall always be used.
2.0 Any conflict between this method statement and the CPL procedure, the CPL procedure shall
be followed.
1.0 PURPOSE
This method statement shall serve as guidelines for installation of piping around
equipment for United Ethylene Plant Project.
2.0 SCOPE
This method statement will cover installation of piping around static and rotating
equipment.
4.0 MANPOWER
Piping Superintendent will control the over-all activity for piping erection and installation
works. Basic manpower under him will basically include, but not limited to:
Piping Supervisors
Piping Foreman
Piping Leadman
Pipefitters
Welders
Crane Operators
Manlift Operators
Riggers
Helpers / Firewatchers
5.0 EQUIPMENT
Tools and equipment shall be made available to support continuous work. Tools and
equipment shall include but not limited to as follows:
5.2 Equipment
a) Mobile crane (telescopic type)
b) Welding machine
c) Air compressors
Method Statement for Installation of Piping Around Equipment Page 4 of 13
Method Statement No: A008-MS-PIP-014 Issue: A5
Al RushaidConstruction Co., Ltd.
d) Boom truck
e) Manlifts
f) Genset
6.1.1 Delivered spools, random length, pipe supports and other materials for
erection shall be inspected upon receipt from CPL and piping fabricators as
per A008-ITP-MR001 to verify following:
6.1.1.1 Piping materials meet acceptance criteria as per Spec No. P02-S01,
P02-S14, P03-S01 and P04-S01.
6.1.1.2 Alloy materials must have the proper markings as per Spec. No. 00-
P-0036 Sect. 6.1 para. 6.1.2. Related documents attesting PMI of the
alloy materials should also be available.
6.1.1.3 Pipe support materials delivered from ARCC Subcontractor are
coated according to Sect. 6.5 OF P01-E06.
6.1.1.4 Spool pieces have correct line number.
6.1.1.5 Piping materials are shipped according to the requirements of Spec.
No. 00-Z-004 Sect. 6.4.1, 6.4.2 and 6.4.3.
6.1.2 Review spool fabrication package and checked requirements for erection
including NDT, painting, heat treatment, cleaning, PMI documentation &
marking, etc.
6.1.4 Preservation of piping materials where needed shall be done following Item
5.4.12 of A008-MS-MECH-015.
6.2.1 Prior to piping erection works, ensure scaffoldings are sufficiently installed
for access of workers during fit-up, and fullwelding/bolting of pipe joints.
Install lifelines as needed.
6.2.2 Get ready and prepare manpower, tools, equipment and other logistics for
installation.
6.2.5 Check the area or location of the piping for possible obstruction before
erection.
6.3.1 Pipe supports and hangers shall be installed prior to connection of pipe
spools to equipment nozzles. In case where permanent supports are not
available, then temporary support shall be provided to avoid piping strain
applied to the equipment.
6.3.2 Installation of pipe supports shall be done using small capacity cranes
and/or chain blocks where applicable. Only nylon slings shall be used in
lifting supports to location.
6.4.1 After withdrawal of pipe spools from laydown yard and prior to erection,
conduct air blowing of pipe spools to ensure piping cleanliness as
required in Sect. 5.2 of P01-E27. Orifice flanges welded at site should be
internally flush after welding. Conduct flange face inspection on pipe &
equipment side.
6.4.2 Erection of pipe spools shall start from equipment nozzles where spool
flanges are fitted to equipment nozzle flanges.
6.4.3 Set-up pipe spool thru reference point such as Northing and Easting.
6.4.5.1 Fit-up spools using appropriate pipe clamps, check the gaps using
gap gauge.
6.4.5.2 Check for squareness and levelness using appropriate level and
steel square. Check plumbness (vertical pipes) using plumb bob.
6.4.5.3 Tack -weld directly on the bevel of pipes after checking. Tack
welding shall be done on four quadrants.
6.4.5.7 The welder’s ID, weld no., and line no. will be marked with metal
marker on the pipe next to the weld. Refer to P13-C02 Para. 6.1.
A5
6.4.5.8 The completed weld will be subjected to the required NDE as per
Spec. No. 00-W-0003 Sect. 2.4 and ASME 31.1 Chapter VI Sect.
Method Statement for Installation of Piping Around Equipment Page 8 of 13
Method Statement No: A008-MS-PIP-014 Issue: A5
Al RushaidConstruction Co., Ltd.
A5 6.4.5.9 Seal Welds shall be as per ASME B31.1 Chapter V Sect. 127.4
Para. 127.4.5 and 135.5.2/ ASME B31.3 Chapter V Sect. 335.3
Para. 335.3.2
A5
6.4.5.10 Post Weld Heat Treatment (as required) as per Spec. No. 00-W-
0001 Sect.2.5.7, Spec. No. 00-W-0003 Sect. 2.3.2 and ASME
B31.1 Chapter V Sect. 132/ ASME B31.3 Chapter V Sect. 331.
A5 6.4.6.2 Check type, materials of gaskets as specified in the ISO BM. Also
check bolt length and protruding threads. Temporary gaskets to be
used for pressuretest shall be dabbed with a spot of fluorescent red
paint in 4 spots (90 degrees equidistant). End points of temporary
bolts and nuts used for pressuretest shall be dabbed with a spot of
red fluorescent paint. Refer to Specs. No. 00-P-0033 Sect. 7.7.3
Para. d/ ASME B31.1 Chapter V Sect. 135.3 Para. 135.3.2/ ASME
B31.3 Chapter V Sect. 335.2 Para. 335.2.4 as applicable.
6.4.6.4 Using nylon sling, lift and set-up pipe spool thru reference point
such as Northing, Easting, columns, or beams.
6.4.6.7 Fit-up flanges using appropriate flange alignment tools and/or flange
bolts. Check alignment as follows:
6.5.3 Final piping connection to equipment will be done after the final
acceptance of pipe works (pressuretested, flushed, cleaned, and
inspected).
7.1 ARCC QC Inspector will be assigned to attend to the quality control and quality
assurance requirement of this work.
7.2 All documents attesting to the acceptability of the work will be produced by
ARCC QC Inspector and submit to CPL/United for review and approval.
8.1 Obtain the approval of the work permit from the concerned CPL/JUPC
Department before starting any work.
8.2 Fire watchers shall be at work area whenever there is hot work.
8.5 Provide warning sign and sufficient barricade on working area and only assigned
personnel will be allowed in the area.
8.6 Welding location shall be enclosed with wind barrier and provided with non-
asbestos fire blanket to prevent spread of any welding sparks.
8.7 Safety Officer shall monitor the work activities to help and to protect all assigned
workers ainst exposure to safety hazards. He shall ensure that Personnel
Protection Equipment (PPE’s) are supplied and used and comply with
CPL/JUPC applicable general instruction and standards.
8.8 Safety harness with double lanyards shall be used all the time when working at
elevated temporary platforms.
8.9 Manlift users shall be trained and certified to operate and use the equipment.
9.0 ATTACHMENTS