Sei sulla pagina 1di 12

2: Procurement arrangement principles

2: Procurement principles:
Appendices

Heriot-Watt University
Paper
Challenges of post-tensioning in Dubai –
a designer’s perspective

Paul J. Mullett, BEng(Hons) CEng MICE

Gifford

Keywords: Dubai, United Arab Emirates, Construction industry, Post-tensioned concrete, Procurement,
Design, Floors, Risk, Subcontractors
Received: 01/09: Accepted: 02/09
© Paul J. Mullett

Synopsis
Fuelled by record prices of oil and the resulting high liquidity, the
Middle East, and the Gulf Cooperation Council (GCC) region in
particular, has in recent years seen a significant increase in
investment for both public and private infrastructure and
development projects. The epicentre of this boom has been Dubai
in the United Arab Emirates which, driven by the vision of HH
Sheikh Mohammed Bin Rashid Al Maktoum, has until very recently
1
continued to experience unprecedented levels of construction. The
high-profile projects in Dubai, including the iconic palm islands and
the colossal Burj Dubai, require no further introduction to structural
engineers throughout the world.
With a large proportion of fast-paced high-rise projects and in
situ concrete the preferred method of construction throughout the
region, the majority of building projects are specified with a post-
tensioned floor system. The post-tensioning business in the GCC,
and in particular Dubai, is therefore one of the most competitive in
the world.
The market is dominated by traditional procurement methods,
typically placing a high burden of risk on contractors with stiff
penalties for project overruns and rapidly increasing labour and
material costs. Employed by main contractors on a design and
build basis, post-tension sub-contractors and their specialist
designers are positioned to suffer the most from both technical
and contractual inadequacies. Combined with a highly competitive
and variable consultant market, the additional burden on specialist
post-tension designers can be significant. With such pressures,
issues of quality (technical, material and construction) are
prevalent.
This paper discusses some of the challenges facing the design
of post-tensioning in Dubai, although many of the issues are
applicable to the wider GCC region.
2
1 Dubai has witnessed construction on a
An introduction to the market massive scale
Construction markets across the GCC have been booming and 2 ‘The Address’ Downtown Dubai is an
none more so than Dubai in the United Arab Emirates (Fig 1). The example of the successful integration of
post-tensioning into high-rise construction
race to invest, build and reap financial returns from available local
liquidity, has driven the extreme pace of construction projects. The
result has been an extremely competitive construction market will therefore continue to show significant growth, with markets in
across all sectors, characterised by extravagant high-rise projects certain localities maturing significantly. The region is not, however,
and freedom of architectural expression. immune to market forces and reduced investor confidence and
With large increases in land and property prices apparent in access to credit will temper the pace of development in many
many of the region’s cities, local markets have recently shown areas for some time to come. Dubai itself has, in recent months,
signs of maturity with many new projects more investor focused, seen a more pronounced slow down with many projects being put
demonstrating a greater balance of capital and whole life costs. A on hold until market confidence returns.
demonstration of this is the decree by HH Sheikh Mohammed Bin
Rashid Al Maktoum in 2007 that all new construction projects Post-tensioning in Dubai
should adhere to the minimum LEED1 certification requirements. The principles and benefits of post-tensioning are well
Long-term strategic development plans have been developed documented2 and are particularly relevant for high-rise
for many of the major cities in the region on a scale unrivalled construction. Post-tensioning is therefore widely used in the GCC
elsewhere in the world and, despite global economic woes, many countries and is the preferred form of construction for most high-
of these schemes remain underway. The signs are that the region rise projects in Dubai (see Fig 2).

The Structural Engineer 87 (12) 16 June 2009 21


Typical advantages include the following:
– faster formwork striking times resulting in a reduced floor casting
cycle;
– reduced concrete mass leading to material savings in vertical
elements and foundations;
– reduced passive reinforcement increasing speed of construction
and making significant cost savings;
– thinner structural elements leading to a reduced storey height;
either providing additional valuable floor space for a given height
or reducing the building volume/envelope giving rise to reduced
material and operating costs;
– longer floor spans and provision for ‘soft-zones’ increasing
future flexibility;
– improved deflection performance.

Due to the general efficiency of post-tension design solutions


3
and the criticality of correct design intent, the performance of post- 3 A screenshot from typical post-tension
tension floors is particularly sensitive to the quality of design and design software
construction. Given the highly aggressive exposure conditions and
variability of design and construction quality, this is a particularly the main contractor which is passed directly to the post-tensioning
important issue for the GCC region. sub-contractor and their specialist designers. The risk to post-
All the main specialist post-tensioning players are active in the tensioning subcontractors is significant and limiting risk exposure
region, supported by either in-house or contracted third party and liability is extremely important to consultants engaged in such
design teams. The benefits and nuances of the various systems work.
available are beyond the scope of this paper, however due to the Despite this confrontational approach litigation has not been
particular requirements of the market, bonded post-tensioning widespread and disputes are generally settled (relatively) amicably
systems are generally preferred over unbonded systems. and without loss of face, often by offsetting losses against the
Due to the popularity of post-tensioning in the region many promise of future work. With both the consequences of delays and
smaller, less experienced design and installation companies have commercial pressures increasing, there is however, a real concern
recently joined the list of post-tensioning specialists operating in that litigation will increase.
the market. This has raised the pressure in what is already a highly The significant benefits that can be realised through alternative,
competitive design and installation market and has increased the less confrontational methods of procurement and earlier
challenge of maintaining standards at an acceptable level. involvement of supply chain members, as encouraged by the
Latham3 and Egan4 reports in the UK, are regrettably uncommon
Contracts and procurement in Dubai and the wider region. Best value is still equated with
Methods of procurement in the GCC are generally traditional, with lowest capital cost and hence a substantial shift is required in the
clients appointing architectural and structural consultants to market to provide structures that truly offer better value for money
complete detailed designs in advance of inviting tenders from main and achieve the stipulated LEED requirements. In this respect,
contractors. In turn, post-tensioning works are usually procured by post-tension sub-contractors and specialist designers have a great
the main contractor on a design and build basis, either through a deal to offer to ensure that floor schemes are achievable, efficient
competitive tender, direct appointment or occasionally through a and buildable from the outset.
nomination by the client or main consultant. Main contracts and
sub-contracts are usually based on the standard FIDIC forms Post-tension design challenges
incorporating a combination of lump-sum and re-measured Post-tension design is currently typically undertaken in accordance
components, although post-tensioning sub-contract works are with BS 81105,6 and associated good practice guidance, such as
invariably lump-sum contracts. the Concrete Society Technical Report 43 (1st Edition)7. Designs in
The sheer number and scale of tenders and the minimal time accordance with the ACI 3188 code are also common and may
available to adequately assess projects can make bidding take preference once the existing British Standards are
extremely hazardous for post-tensioning sub-contractors. With discontinued.
many post-tension projects tendered on inadequate or poorly Designs are usually produced using industry standard Finite
considered scheme designs, and with highly variable costs for Element software such as ADAPT Builder EX9 or RAM Concept10.
passive reinforcement and post-tensioning strand, the post- As with any such design software, it is easy to produce designs,
tensioning sub-contractor can carry a significant financial burden if but it does not guarantee an understanding of structural concepts,
the final material quantities are substantially more than that detailed practical design issues or the influence of modelling assumptions
in the accepted bid. (see Fig 3). A significant amount of experience is therefore required
Regrettably the fine details of contractual arrangements are to produce safe, efficient and buildable post-tension solutions and
often not sufficiently defined and can leave many hidden problems the involvement of specialist post-tension designers at an early
that only surface late into the project. Problems typically include stage is highly recommended.
design scope interfaces and the division of responsibility between As with most design consultancy, the quality of the output is
the main consultant and post-tension sub-contractor’s designer. dependant on the availability of time, skills and information.
Examples of issues that can cause problems are consideration of Unfortunately all three of these factors are under pressure in a fast-
thermal and shrinkage effects, design of key elements such as paced competitive market. The following sections discuss some of
transfer structures and the design of connections for forces due to the current market inadequacies and the challenges they present
lateral loads (i.e. wind and seismic). Poorly considered, or simply to post-tension sub-contractors and their specialist designers in
unachievable, scheme designs also serve to raise the pressure on particular.
post-tension sub-contractors once the project has commenced.
The overall result is a very high risk commercial environment Quality of scheme (tender) design
which has created an increasing tendency for parties to offload risk Many of the consultancies engaged in the local market provide
to others, often to those not necessarily best placed to manage it. clients with a combined architectural, structural and M & E
Extremely demanding project programmes, rising labour and consultancy service. Due to the normal fee structures and available
material costs, contractual vagaries and inherent (but often skill base, often this service is heavily focused on the architectural
avoidable) technical difficulties all place a large burden of risk on aspects of the building. The resulting structural schemes used for

22 The Structural Engineer 87 (12) 16 June 2009


&RQWHQWV

3DJH 1HZV
,QWURGXFWLRQ
7KLVLVVXHORRNVDWVRPHRIWKHLGHDVDQG
WRROVVPDUWEXVLQHVVHVDUHXVLQJWRGHOLYHU
VXFFHVVIXOSURJUDPPHVDQGSURMHFWV

PRUH« $IWHUWKHFUHGLWFUXQFK
7KHGRZQWXUQDQGLWVDIWHUPDWKKDYHKDGDKXJHHIIHFWRQFRQVWUXFWLRQ
3DJHV±
$XVWUDOLDSUHIHUULQJSDUWQHUVKLS
SURMHFWVZRUOGZLGH%XWWKRXJKZHJHQHUDOO\VSHDNRIDµJOREDO¶
GRZQWXUQWKHHIIHFWKDVQRWEHHQXQLIRUPDQGDWWLWXGHVWRSURFXUHPHQW ,Q$XVWUDOLDKRZHYHUWKHVNLOOVKRUWDJH
3URFXUHPHQW DUHVKDSHGDVPXFKE\FXOWXUHDVE\WKHHFRQRPLFHQYLURQPHQW 'DYH/LGGOH RYHUWKHSDVWGHFDGHKDVUHVXOWHGLQD
+RZGRHVDUHJLRQ¶VFXOWXUHGULYH 'LUHFWRU'DYH PRUHFROODERUDWLYHFXOWXUHVD\V'DYH
VXSSO\FKDLQVWUDWHJLHVDQGKDVWKH $UHFHQW7XUQHU 7RZQVHQGURXQGWDEOHDOORZHGXVWRH[SORUHWKHFXOWXUDODQG /LGGOHVSHFLDOLVHV /LGGOH³7KHUH¶VDUHFRJQLWLRQWKDWWKHUH
FUHGLWFUXQFKFKDQJHGWKHLUDSSURDFK" UHJLRQDOIDFWRUVDIIHFWLQJWKHVXSSO\FKDLQLQRXUSURMHFWV$NH\TXHVWLRQZDV LQFRVWSODQQLQJ DUHYHU\IHZSHRSOHLQWKHPDUNHWDQG
KRZWKHFXOWXUHRIUHVSHFWLYHUHJLRQVXVXDOO\GULYHVVXSSO\FKDLQVWUDWHJLHV± DQGYDOXH \RX¶YHJRWWRZRUNWRJHWKHUWRGHOLYHUIRU
PRUH«
DQGZKHWKHU DQGKRZ WKHFUHGLWFUXQFKKDVFKDQJHGWKHDSSURDFK HQJLQHHULQJPDMRU WKHFOLHQWRQFRPSOH[MREVSDUWLFXODUO\
SURMHFWVDQGLVUHVSRQVLEOHIRU LQELJJHUPDUNHWVVXFKDVRLODQGJDV
DOOFRVWPDQDJHPHQWVHUYLFHV PLQLQJDQGLQIUDVWUXFWXUHSURMHFWV7KDW¶V
3DJHV± 0LGGOH(DVWUHWXUQLQJWRWUDGLWLRQ GHOLYHUHGLQ4XHHQVODQGDQG ZKHUHZHDUHVHHLQJDWHQGHQF\WRZDUGV
:HVWHUQ$XVWUDOLD DOOLDQFHVDQGSDUWQHULQJ±EHFDXVHWKDW¶V
&RQVWUXFWLRQSURMHFWVLQWKH0LGGOH
(IILFLHQF\ GDYHOLGGOH#WXUQWRZQFRP WKHZD\WREULQJWRJHWKHUWKHVNLOOV
$ODQ7DODEDQL (DVWDUHJHQHUDOO\WUDQVDFWLRQDO
+ROLVWLFWKLQNLQJFDQFXWFDSLWDOFRVWV
'LUHFWRU$ODQ7DODEDQL EXWWKHEXLOGLQJIUHQ]\LQ'XEDL
ZKLOHVWLOOGHOLYHULQJWKHDVVHWV\RXQHHG ³7RDQH[WHQWZH¶YHVXIIHUHGOHVVIURP
KHDGVRXU8$(WHDP SDUWLFXODUO\FKDOOHQJHGWKLVPRGHO
,QWHJUDWHGV\VWHPVZLOOJLYH\RX WKHFUHGLWFUXQFK±$XVWUDOLDKDVDYRLGHG
DQGLVUHVSRQVLEOH ³7KHVKHHUYROXPHRIZRUNGXULQJ
JUHDWHUFRQWURO DµWHFKQLFDO¶UHFHVVLRQDQGWKHEDQNVKDYHVWD\HGUHDVRQDEO\VROLG±EXWPXFKRI
IRUWKHSURYLVLRQ WKHERRPIRUFHGSDUWLHVLQWRDPRUH
PRUH« WKHPRQH\FRPHVIURPRYHUVHDVVRZH¶YHGHILQLWHO\KDGDGRZQWXUQ
RI3URMHFWDQG FROODERUDWLYHZD\RIZRUNLQJWR
&RPPHUFLDO0DQDJHPHQWVHUYLFHV HQVXUHSURMHFWVZHUHFRPSOHWHG´
³,QWKLVHQYLURQPHQWZH¶YHKHOSHGFOLHQWVJHWDEHWWHUSULFHLQWKHPDUNHWE\
WKHUH+HLVDOVRWKHIUDPHZRUN VD\V$ODQ7DODEDQL³:KLOH'XEDL¶V
DGYLVLQJWKHPWRIXOO\GRFXPHQWWKHLUSURMHFWV±ZHKHOSHGRQHRIRXUPDMRU
PDQDJHUIRUWKHSURYLVLRQRIFRVW \HDURQ\HDUFRQVWUXFWLRQFRVW
3DJHV± FOLHQWVVDYH$8'PLOOLRQE\FKDQJLQJWROXPSVXPSURFXUHPHQW±DQGZH¶G
FRQVXOWDQF\VHUYLFHVWRDPDMRU8$( LQIODWLRQPD\KDYHEHHQEHDUDEOHLQ
H[SHFWWKLVDSSURDFKWRHQGXUHIRUD\HDURUWZR´
JRYHUQPHQWFOLHQWRQWKHLUFDSLWDO DQRYHUKHDWHGPDUNHWWKHVTXHH]H
1HZV H[SHQGLWXUHSURJUDPPH KDVVHHQSDUWLHVUHWXUQWRDPRUH
(QHUJ\LQ,QGLD5HWDLOLQ&KLQD&RDO 7XUQHU 7RZQVHQGRIILFHV±-XQH
WUDGLWLRQDOWUDQVDFWLRQDODSSURDFK´
6HDP*DVLQ$XVWUDOLD0RWRUZD\VLQ DODQWDODEDQL#WXUQWRZQFRP
%ULWDLQ333LQ8JDQGD([SDQVLRQLQ
&DQDGDDQG.D]DNKVWDQ ³2QWKHRWKHUKDQGUHODWLRQVKLSV
DUHDOVRLPSRUWDQWKHUH:HKDYH
PRUH« ZLWQHVVHGVFHQDULRVZKHUHWKH
WHQGHUSURFHVVLVXVHGWRPHUHO\
GHWHUPLQHWKHSULFHDQGQRW
3DJH QHFHVVDULO\WKHVXFFHVVIXOELGGHU´

3HRSOH
.H\DSSRLQWPHQWVDW([HFXWLYH%RDUG
0DQDJLQJ'LUHFWRUDQG'LUHFWRUOHYHOV
3URERQRVHUYLFHVVXSSRUWRXU&65
FRPPLWPHQW
&RQWLQXHVRYHUOHDI 
!

PRUH«

‹7XUQHU 7RZQVHQGSOF-XQH PDNLQJWKHGLIIHUHQFH 


!

!
&RQWHQWV

3DJH 1HZV
,QWURGXFWLRQ
7KLVLVVXHORRNVDWVRPHRIWKHLGHDVDQG
WRROVVPDUWEXVLQHVVHVDUHXVLQJWRGHOLYHU
VXFFHVVIXOSURJUDPPHVDQGSURMHFWV

PRUH« $IWHUWKHFUHGLWFUXQFK FRQW

3DJHV±
8.EXLOGLQJEHWWHUUHODWLRQVKLSV (XURSHUHDVVHVVLQJWKHPDUNHWV
7KH8.KDVEHHQFRQVFLRXVO\PRYLQJ 3DUWVRI(XURSHKDYHEHHQKHDYLO\
3URFXUHPHQW -RKQ%RXOWZRRG DZD\IURPWUDQVDFWLRQDOSURFXUHPHQW -DPHV'DQG DIIHFWHGE\WKHFUDVK-DPHV'DQG
+RZGRHVDUHJLRQ¶VFXOWXUHGULYH /RQGRQEDVHG WRDPRUHUHODWLRQVKLSEDVHGDSSURDFK $VVRFLDWH'LUHFWRU UHSRUWVWKDWZKLOHWKHFUHGLWFUXQFK
VXSSO\FKDLQVWUDWHJLHVDQGKDVWKH 'LUHFWRU-RKQ IRURYHU\HDUV-RKQ%RXOWZRRG -DPHV'DQGLVDNH\ KDVQ¶WFUHDWHGDVKLIWWRZDUGV
FUHGLWFUXQFKFKDQJHGWKHLUDSSURDFK" %RXOWZRRG VHHVWZRPDLQGULYHUVRIWKLVFXOWXUDO PDQDJHUZLWKLQRXU DOWHUQDWLYHSURFXUHPHQWURXWHV
PDQDJHVRXU VKLIW³)LUVWWKHUHZDVDPRYHWRZDUGV $PVWHUGDP2IILFH LWKDVKDGDVLJQLILFDQWHIIHFWRQ
PRUH«
&RQWUDFW6HUYLFHV DIRUPRIFRQWUDFWLQZKLFKZHVSOLW UHVSRQVLEOHIRU KRZSHRSOHRSHUDWHZLWKLQWKHLU
WHDPRIIHULQJVSHFLDOLVWDGYLFH SURMHFWPDQDJHPHQWDZD\IURP OHDGLQJFRVWPDQDJHPHQWWHDPV UHFRJQLVHGIUDPHZRUNV³%LGGLQJ
RQSURFXUHPHQWVWUDWHJLHV GHVLJQZKLFKFKDQJHGWKHZD\ZH RQSURMHFWVDFURVVPDQ\SDUWV WUHQGVWKURXJKRXWWKHVXSSO\FKDLQ
3DJHV± FRQWUDFWDGPLQLVWUDWLRQGLVSXWH PDQDJHULVNLQWKH8.6HFRQGQHZ RI(XURSH-DPHVKDVZRUNHG LQFRXQWULHVOLNH,UHODQGDUHQRW
UHVROXWLRQDQGOLWLJDWLRQVXSSRUW OHJLVODWLRQHQIRUFHGSURPSWSD\PHQW H[WHQVLYHO\LQWKHFRPPHUFLDORIILFH VXVWDLQDEOHDWFXUUHQWOHYHOV7KHUH
(IILFLHQF\ +HUHJXODUO\SURYLGHVH[SHUW DQGVZLIWDGMXGLFDWLRQSURWHFWLQJ KRWHOVOHLVXUHUHVLGHQWLDODQG LVUHDOQHUYRXVQHVVDERXWZKRLV
WHVWLPRQ\UHJDUGLQJFODLPVDURXQG FRQWUDFWLQJSDUWLHVDQGUHGXFLQJ LQGXVWULDOVHFWRUVDQGLVFXUUHQWO\ JRLQJWREHDURXQGLQVL[PRQWKV¶
+ROLVWLFWKLQNLQJFDQFXWFDSLWDOFRVWV
ZKLOHVWLOOGHOLYHULQJWKHDVVHWV\RXQHHG
WKHZRUOG+HKDVH[SHULHQFH GLVSXWHV´ UHVSRQVLEOHIRUPDQDJLQJRQHRI WLPHDQGWKLVLVDVLJQLILFDQWEDUULHU
,QWHJUDWHGV\VWHPVZLOOJLYH\RX RIPDMRUSURJUDPPHVDQG RXUNH\JOREDODFFRXQWVLQWKH WRLQWHJUDWLRQ,Q5XVVLDZHDUH
JUHDWHUFRQWURO VWUDWHJLFSURFXUHPHQWLQPDMRU $VXUYH\LQWKHVGHVFULEHG DJULFKHPLFDOVVHFWRU QRZVHHLQJFOLHQWVUHDVVHVVLQJWKH
8.LQIUDVWUXFWXUHUDLODYLDWLRQ RI8.FRQVWUXFWLRQSURMHFWVDV FRQWUDFWLQJPDUNHWXQGHUWDNLQJZLGHU
PRUH« MDPHVGDQG#WXUQWRZQFRP
LQFOXGLQJ7 DQGQRQ8.SURFHVV DGYHUVDULDO7HQ\HDUVODWHUDIROORZXS SUHTXDOLILFDWLRQVDQGLQVRPHFDVHV
SODQWVDQGWKHHQHUJ\VHFWRU UHSRUWHGWKLVILJXUHKDGUHGXFHGWR DWWUDFWLQJWHQGHUOLVWVZLWKRUPRUH
MRKQERXOWZRRG#WXUQWRZQFRP  -RKQGRHVQ¶WVHHWKHFUHGLW ELGGHUV7KHHPSKDVLVRQORZHVWSULFHLVOHDGLQJWKHµKLJKFRVWKLJKTXDOLW\¶
3DJHV± FUXQFKPRYLQJ%ULWLVKLQGXVWU\EDFNLQ LQWHUQDWLRQDOFRQWUDFWRUVWRH[LWWKHPDUNHW´
WKHRWKHUGLUHFWLRQ³,QWKH8.ZH¶YH
1HZV VHHQFOLHQWVSXWWKHVTXHH]HRQWKHLUVXSSO\FKDLQEXWWKH\¶UHQRWPRYLQJIXOO\ 2QWKHRWKHUKDQGVRPHSDUWVRI(XURSHGHPRQVWUDWHVWURQJH[DPSOHVRI
(QHUJ\LQ,QGLD5HWDLOLQ&KLQD&RDO EDFNWRDWUDQVDFWLRQDODSSURDFK &RQVWUXFWLQJ([FHOOHQFHVXUYH\V VXSSO\FKDLQLQWHJUDWLRQ2QHLV6\QJHQWDLQ6ZLW]HUODQGZKLFKKDVWDNHQD
6HDP*DVLQ$XVWUDOLD0RWRUZD\VLQ PDUNHWOHDGLQJDSSURDFKZKHUHE\WRWDOVXSSO\FKDLQDOOLDQFHVDUHIRUPHGDQG
%ULWDLQ333LQ8JDQGD([SDQVLRQLQ ³7KDWVDLGLWPD\EHRQHRIISURFXUHUVZKRWDNHDGYDQWDJHRIWKHPDUNHW±EXW LWVPHPEHUVDUHUHPXQHUDWHGRQWKHEDVLVRIWKHRYHUDOOVXFFHVVRIWKHSURMHFW
&DQDGDDQG.D]DNKVWDQ ZKHQSUHVVXUHLVSDVVHGGRZQWKHVXSSO\FKDLQWKHRUJDQLVDWLRQWKDWFDQ¶WFRSH -DPHVVHHVWKLVDVDFKDUDFWHULVWLFRIVSHFLDOLVHGVHFWRUVZKHUHWKHUHDUHIHZHU
PRUH« ZLWKWKHGHDOPDGHDERYHLWLQWKHFKDLQLVDWVHULRXVULVN±DVLVWKHSURMHFW SOD\HUVDQGFOLHQWVKDYHWRWKLQNPRUHLQWHOOLJHQWO\DERXWKRZWRLQIOXHQFHDQG
LWVHOI´ LQFHQWLYLVHWKHLUVXSSO\FKDLQWRZRUNLQDFROODERUDWLYHZD\³7RPDNHLWZRUN\RX
QHHGDOLJQPHQWRIJRDOVORQJHYLW\RIUHODWLRQVKLSDQGDUHDOXQGHUVWDQGLQJRI
HDFKRWKHU´
3DJH

3HRSOH
.H\DSSRLQWPHQWVDW([HFXWLYH%RDUG
0DQDJLQJ'LUHFWRUDQG'LUHFWRUOHYHOV
3URERQRVHUYLFHVVXSSRUWRXU&65
FRPPLWPHQW
&RQWLQXHVRYHUOHDI 
!

PRUH«

‹7XUQHU 7RZQVHQGSOF-XQH PDNLQJWKHGLIIHUHQFH 


!

!
&RQWHQWV

3DJH 1HZV
,QWURGXFWLRQ
7KLVLVVXHORRNVDWVRPHRIWKHLGHDVDQG
WRROVVPDUWEXVLQHVVHVDUHXVLQJWRGHOLYHU
VXFFHVVIXOSURJUDPPHVDQGSURMHFWV

PRUH« $IWHUWKHFUHGLWFUXQFK FRQW

3DJHV±
86$UHO\LQJRQWKHODZ\HUV $VLDVWLFNLQJWRWKHFRQWUDFW
,QWKH863HWHU:DONHUKDV $VLDQEXVLQHVVHVSUHVHQWD
3URFXUHPHQW 3HWHU:DONHU H[SHULHQFHGDQHPSKDVLVRQ 6WHSKHQ*LEVRQ FRPSOHWHO\GLIIHUHQWPRGHO$V
+RZGRHVDUHJLRQ¶VFXOWXUHGULYH 3HWHULVD6HQLRU UHODWLRQVKLSVLQWKHSULYDWHVHFWRU 'LUHFWRU6WHSKHQ*LEVRQ 6WHSKHQ*LEVRQLQ.RUHDQRWHV
VXSSO\FKDLQVWUDWHJLHVDQGKDVWKH 9LFH3UHVLGHQWRI ZKLOHILQGLQJWKHSXEOLFVHFWRU LVEDVHGLQ6HRXOZLWK PDQ\RIWKHFOLHQWRUJDQLVDWLRQV
FUHGLWFUXQFKFKDQJHGWKHLUDSSURDFK" 7XUQHU 7RZQVHQG PRUHWUDQVDFWLRQRULHQWHGODUJHO\ RXU.RUHDQMRLQWYHQWXUH DUHFRQJORPHUDWHVZLWKWKHLU
LQWKH86EDVHG GXHWRWKHULJRURXVHQIRUFHPHQW IROORZLQJSHULRGVLQWKH RZQFRQWUDFWLQJEXVLQHVVHV
PRUH«
LQ6DQ)UDQFLVFR RISURFXUHPHQWUHJXODWLRQ%XWKH 8$(DQG8.+HKDV $GGLWLRQDOO\WUDQVDFWLRQV
ZKHUHKHOHDGVWKHGHYHORSPHQW VD\VWKHNH\FXOWXUDOGLIIHUHQFHOLHV SDUWLFXODUVNLOOVLQYDOXHPDQDJHPHQW DUHYHU\UHODWLRQVKLSEDVHG
RIRXU86SURMHFWPDQDJHPHQW LQDWWLWXGHVWRODZ\HUV³:KDW¶V DQGULVNPDQDJHPHQWSURFHVVHVDQG FRQWUDFWRUVJLYHDSULFHYHU\
3DJHV± EXVLQHVV+HKDVOHGWHDPV SDUWLFXODUDERXWSURFXUHPHQWKHUHLV H[WHQVLYHH[SHULHQFHLQSURFXUHPHQW HDUO\RQDQGDEVRUEWKHULVN
RQDZLGHUDQJHRIEXVLQHVV WKHHPSKDVLVRQWKHOHJDODVSHFW± V\VWHPVLQFOXGLQJ3),SDUWQHULQJ ³,W¶VDOPRVWDQRQRWRJR
(IILFLHQF\ FRQVXOWLQJVWUDWHJLFSODQQLQJ PXFKPRUHVWURQJO\WKDQDQ\ZKHUH FRQVWUXFWLRQPDQDJHPHQWPDQDJHPHQW EDFNODWHUDQGVD\µFDQ,KDYH
FRPPHUFLDODQGLQIUDVWUXFWXUH HOVHSHRSOHHVWDEOLVKWKHLUUHODWLRQVKLS FRQWUDFWLQJLQFHQWLYLVHGWDUJHWFRVW PRUHFDVK"¶&ODLPVDUHDOPRVW
+ROLVWLFWKLQNLQJFDQFXWFDSLWDOFRVWV
ZKLOHVWLOOGHOLYHULQJWKHDVVHWV\RXQHHG SURMHFWVLQWKHSXEOLFDQGSULYDWH WKURXJKDVWURQJDQGRIWHQEHVSRNH JXDUDQWHHGPD[LPXPSULFHOXPSVXP XQKHDUGRI±WKHFRQWUDFWLV
,QWHJUDWHGV\VWHPVZLOOJLYH\RX VHFWRUV+LVH[SHULHQFHLQFOXGHV OHJDODJUHHPHQW$QGDVVRRQDV DQGFRQWUDFWRUGHVLJQ SUHWW\PXFKOHIWLQDGUDZHU
JUHDWHUFRQWURO DVVLJQPHQWVLQWKH8QLWHG6WDWHV WKHUHLVDQLVVXHWKH\VD\µVKDOOZH RQFHLW¶VVLJQHG´
VWHSKHQJLEVRQ#WXUQWRZQFRP
6RXWK$IULFD=LPEDEZH0DODZL JHWFRXQVHOLQ"¶:KLOHHDFKRIWKH
PRUH«
8QLWHG.LQJGRP%ULWLVK&ROXPELD VWDWHVKDVH[SHULHQFHGWKHGRZQWXUQ
*KDQD6DXGL$UDELDDQGWKH GLIIHUHQWO\ZHILQGWKLVFXOWXUDO
6XOWDQDWHRI2PDQ DSSURDFKDFURVVWKHFRXQWU\´
3DJHV± SHWHUZDONHU#WXUQWRZQFRP

1HZV
(QHUJ\LQ,QGLD5HWDLOLQ&KLQD&RDO &RQFOXVLRQWUXVW\RXUSURYHQSDUWQHUV
6HDP*DVLQ$XVWUDOLD0RWRUZD\VLQ :KDWHYHUWKHJOREDOGLIIHUHQFHVDFRQVLVWHQWPHVVDJHFDPHWKURXJK
%ULWDLQ333LQ8JDQGD([SDQVLRQLQ 7KHFUHGLWFUXQFKKDVOHGFOLHQWVWRORRN IURPRXUGLVFXVVLRQ7KHFUHGLWFUXQFKKDVOHGFOLHQWVWRORRNKDUGDW
&DQDGDDQG.D]DNKVWDQ
FRVWVDQGWKH\DUHQRZTXLFNHUWRJRWRWKHPDUNHWIRUWKHEHVWSULFH
PRUH« KDUGDWFRVWV%XWWKH\DOVRUHFRJQLVH %XWWKH\DOVRUHFRJQLVHWKHLPSRUWDQFHRIUHODWLRQVKLSV±WKHPDUNHW
PD\UHYHDOWKHSULFHEXWEXVLQHVVHVZDQWWRZRUNZLWKSDUWQHUVZKR
WKHLPSRUWDQFHRIUHODWLRQVKLSV KDYHVHUYHGWKHPZHOOEHIRUH%LGGHUVZKRZLQWHQGHUVRQSULFHDFURVV
3DJH WKHZRUOGDUHILQGLQJFOLHQWVUHYHUWLQJWRWKHILUPVWKH\NQRZ±DWWKH
EHVWSULFHWKHPDUNHWFDQRIIHU
3HRSOH
.H\DSSRLQWPHQWVDW([HFXWLYH%RDUG
0DQDJLQJ'LUHFWRUDQG'LUHFWRUOHYHOV
3URERQRVHUYLFHVVXSSRUWRXU&65
FRPPLWPHQW

PRUH«

‹7XUQHU 7RZQVHQGSOF-XQH PDNLQJWKHGLIIHUHQFH 


!

!
62

ECONOMICS
Procurement Construction management
Even in these risk-averse days, some hands-on clients still prefer the construction management
route. But would more schemes benefit from the CM approach? And how should clients organise
themselves to get the best results? Simon Rawlinson of Davis Langdon reports

01 Introduction

Construction management (CM) sectors. In some cases, the client elements, such as retail fit-out or example, the cultivation of direct,
has been out of favour in recent and CM have not collectively been hotel fixtures and fittings, that long-term relationships with
years with only a select group of able to impose discipline on can be finished later without trade contractors to secure many
commercial clients continuing to design development, coordination affecting the overall programme; of the benefits more often
adopt the route. With the Fraser and timely decision-making – ■ Involvement of specialist trade associated with partnering.
enquiry into the Scottish and, although there have been contractors in design and Furthermore, by employing a
Parliament delays and high- resounding successes such as construction; construction manager who is able
profile court cases highlighting Tate Modern, there have also been ■ Creation of a less adversarial, to focus on the interests of the
the risks of CM, it is not disappointing results. Whether problem-solving project culture. project, rather than on its own
surprising that use of this form these projects would have fared Clients should always devise risk management, the client can
of procurement has fallen. better following other their procurement strategy on the be confident that its project
However, as the continuing procurement strategies is a moot basis of their project priorities, objectives will be shared by the
Wembley Stadium saga point, but it is clear that the use management capability and the rest of the team.
illustrates, no procurement route, of CM can in some circumstances extent of risk that they are This article summarises current
even with as low a client risk- expose existing weaknesses in prepared to accept. Clients in arts best practice with respect to
profile as design-and-build, can project management capability. organisations, a sector that used construction management. It
guarantee a successful outcome. So, given the higher risk CM extensively during the lottery will look at advantages and
CM’s reputation has shifted exposure that follows that boom, might not, for example, be disadvantages of the route and
from its high point in the 1980s, adoption of a construction best-equipped to take on the in particular at what steps can
when it was almost exclusively management strategy, what increased risk exposure and be taken to address the client’s
associated with well-managed additional benefits should the additional administrative role higher risk profile associated
and well resourced commercial client be seeking as associated with CM – and might with CM. A case study based on
projects such as Broadgate and compensation? Opportunities for not now be given funding without the Peter Jones refurbishment
Canary Wharf. Since then it has enhanced performance include: the security of a lump-sum identifies many of the key
been adopted, typically for speed ■ Acceleration of the overall contract. ingredients of the successful
or flexibility reasons, on a wider project programme; However, beyond the glare of application of CM and also
range of projects, including ■ Enhanced ability to incorporate publicity, a small but significant demonstrates how modifications
schemes from the arts, leisure change into the design; group of clients continue to use to the general approach can work
and public administration ■ Delayed completion of design CM to their advantage, using, for to the client’s advantage.

BUILDING MAGAZINE 01.09.2006


economics.procurement 63

This picture: The flexibility of construction


management was an advantage in the highly
complex Time and Space planetarium project
in Greenwich Park
Below left: London’s Tate Modern has been
hailed as one of the most successful recent
construction management projects

02 Construction management best practice

Construction management is perhaps best consultants and trade contractors. in connection with contractor selection and so
summed up as the procurement route whereby ■ The importance of coordination and on, the selection of CM also means that lack of
designers design, trade contractors detail and management at interfaces between different performance by the client, caused by
deliver their packages, and where the trade packages. indecision or delayed instruction, can have a
construction manager manages the process, CM is distinguished by the influence of the real effect on a project. Furthermore, the
leaving the client to lead and accept the risk client’s and construction manager’s consequences of ineffective management by
on a project for which they are ultimately management and leadership skills on the the construction manager will also directly
responsible. The key issues raised by this outcome of the project, and the potential affect the client , should delay or claims for
definition include: exposure of the client to loss should these additional payments to trade contractors
■ The central role of the construction capabilities not be in place. Problems related occur as a result.
manager in managing the project and in to co-ordination and timely decision-making Accordingly, the client must be sufficiently
providing administrative support to the are common to all construction projects, disciplined and resourced to provide its inputs
employer. and with CM as well as any alternative into the project as required by the agreed
■ No single point of responsibility related to procurement route, it is the performance information release schedules. They must also
the delivery of the project. of the team that is at the root of project ensure that they appoint a construction
■ The greater role of trade contractors in the success – not the procurement strategy manager with the appropriate resources and
completion of their design work and co- per se. experience and a positive approach – a task
ordination of their work with other packages. However, by providing the client with greater that is challenging for many clients, whether
■ The direct relationship between the client, influence over the project and more flexibility experienced or not.

BUILDING MAGAZINE 01.09.2006


03 The construction manager’s role

The construction manager’s administration and negotiation of relationships as an equivalent manager to be able to carry
roles and responsibilities go the tender process. main contractor. out all aspects of its pre-
well beyond the scope of ■ Managing, planning and Another area of contrast construction role.
work of a typical contractor controlling the work of trade between CM and conventional Finally, as the role is so
and require specialist contractors, including the contracting relates to the wide-ranging, there is
resources for successful administration of design identification and avoidance of potential for overlap with the
delivery. As an illustration approvals and inspections. problems before they occur. work of other consultants,
of the scope of the role, the ■ Monitoring and reporting on A solutions-based approach particularly project managers
following duties are typically overall progress, advising on such as this requires thorough and, to a lesser extent cost
found in a construction issues related to trade contractor planning and management and consultants. This potential for
manager appointment: performance and forecasting the as a result, significant resource. overlap needs to be dealt with
■ Programming of design impact of design changes or This is particularly the case directly, either via the clear
and construction activity, disruption to the progress of the in areas such as design co- drafting of schedules of services
including information release works. ordination and risk management, or through the adoption of a joint
programmes, approvals and ■ Managing financial aspects of both of which are often given team-based approach to work
reprogramming to meet overall the project, including trade lip service under other such as cost control.
completion dates. contract valuations, claims and procurement routes. Although the duties described
■ Advising on buildability administration of contra-charges. Effective project administration above might suggest that the
construction methodologies ■ Initiating action by the client is also an important aspect of construction manager role
and sequencing including and project team to mitigate CM, and the availability of a provides for considerable
assistance with the selection of delays or cost overrun. range of standard processes, authority with limited
materials or, in some instances, Beyond the letter of the CM documents, templates and responsibility, the agreements
the use of prefabrication. agreement, it is widely recognised databases will play an important and services under which
■ Commenting on and that the construction manager’s role in enabling the client to construction managers operate
monitoring the progress of soft skills can make a substantial discharge its responsibilities. can be very demanding. In
design development. contribution to the success All of these aspects of the CM addition, the judgement of the
■ Advising on requirements of the project. The case study service should be available to legal case associated with the
for preconstruction works, overleaf illustrates this well. clients on all projects, but there Great Eastern Hotel suggests
temporary works, mock-ups The separation of the continues to be considerable that the construction manager
and testing. construction manager from inconsistency in the standard role creates significant direct
■ Packaging up the works into direct contractual relationships of service and performance liabilities. In the Great Eastern
well co-ordinated and clearly with the trade contractors that is offered to clients. As a Hotel case, the judge found
demarcated trade contracts, places them a good position result, it is essential that the that deficiencies in the delivery
together with the definition to promote a collaborative construction manager’s ability of specific construction
of the transfer of design approach to project delivery. and track record in delivering management responsibilities
responsibility. An adversarial approach is across its full range of project such as the organisation of
■ Advising on the pre- usually less effective – partly responsibilities is carefully temporary works and the
qualification of trade contractors. as the client is unlikely to tested at appointment, and packaging up of work created
■ Preparing and collating pre- have the same commercial that this appointment takes liabilities for the construction
qualification and tender interest in the aggressive place at a sufficiently early manager for both delay and
documentation together with the management of subcontractor stage for the construction cost overrun.

BUILDING MAGAZINE 01.09.2006


Chiswick Park (pictured on this page and
opposite), Stanhope’s office and retail
scheme in West London, was construction
managed by Bovis Lend Lease

04 Advantages and disadvantages of CM

Construction management stands at the top end of the scale with therefore may not be secured by all clients following a CM strategy. As
respect to a client’s risk exposure but potentially offers substantial a result, careful consideration of these advantages and disadvantages
advantages. However, most of these benefits, set out in the table must be undertaken on a project and client-specific basis, to ensure
(below), are only secured by direct client engagement and action, and that they are relevant to a client’s decision making.

Advantages Disadvantages

Accelerated programme overlapping design and construction Design co-ordination risk and increased likelihood of design change

Ability to closely manage cost during design and procurement No cost certainty until all packages are let and no single point
lump-sum cost commitment

Proactive management of the design and construction process to Exposure to risk associated with construction manager and team
minimise impact of change and other causes of disruption performance. Reliance on the capability of construction manager
and project team to correctly forecast consequences of change.
Responsibility to fund solutions to problems should they occur

Hands-on involvement of the client on the project Increased administration role for the client of CM route

Professional team including the construction manager focused on CM and professional team owe duty of care liability only
meeting client’s needs. Integration of design and construction skills

Full control over design including incorporation of design by High degree of client ownership of risks associated with design
specialist contractors including impacts of late or incomplete and uncoordinated design

Early appointment of construction advisers and specialist trade


contractors

Ability of client to influence the selection of trade contractors. Added complexity of one to one contractual relationships of client
One-to-one contractual relationships with all team members

Management focus on programme, sequencing and buildability Reliance on management capability of construction manager

Client ownership of tendering and contractual arrangements Client position at centre of management requires effective
decision-making

Opportunity to package the work to suit the capability of the trade


contractors and to manage on-site interfaces

Ability to identify and act upon poor trade contractor performance Client exposure to performance risk and exposure to consequential
loss associated with trade contractor default.

BUILDING MAGAZINE 01.09.2006


66 economics.procurement

05 Client actions to reduce the risk of CM

Construction management of concern include: the use of impact on the associated interface management resources
involves no more or less co- consistent processes for design elements of the works will need by the construction manager and
ordination and organisation than review and coordination, trade to be reviewed on a consistent by trade contractors – not only to
any other procurement option. contractor pre-selection and so and thorough basis. save money, but also to ensure
However, as the client is involved on; the management of package ■ Management of the work as it that responsibility rests with a
alongside the construction interfaces, the capability to proceeds – providing sufficient single party.
manager in more aspects of predict the full outcome of on-site management resources ■ Ensuring that the procurement
project administration, it will change orders; and the overall to co-ordinate package of trade contractor packages is
inevitably make greater demands management of the project team. interfaces, to monitor progress based on sufficient information
on the client’s time and ■ Early determination of the and to implement corrective to define the full scope of work
resources. Although this is not an minimum level of cost certainty action as required. and all critical interfaces with
issue for experienced employers required ahead of start on site. ■ Management of contra- other packages. Design should be
with a dedicated management This typically ranges from 70 to changes – recording the basis of completed to a point whereby
resource, this could challenge the 80% of the anticipated issues that give rise to contra provisional sums are not required
capabilities of less well- construction cost. The timing of changes so that costs are borne in package tenders. Pricing
resourced, one-off clients. package procurement will by the responsible party rather documents should also be
In addition to making sure that determine the design programme. than by the client. prepared in sufficient detail to
their own house is in order, ■ Clear communication of areas ■ Establishing change control enable the project team to obtain
clients must make sure that the of responsibility. CM agreements processes that address the full enough price information to
construction manager is fully are often bespoke and impact of any change on a support cost reporting and the
engaged at all stages of the considerable negotiation may be package, associated trade negotiation of variation costs.
project. Key measures that can required in the agreement of a contractors and overall ■ Investment of time and effort
be put in place to create the construction manager’s scope of programme. Change control by the client and construction
conditions for success on a CM service and liability. Roles must should include procedures that manager into the development of
project include: be properly demarcated so that strictly define delegated powers relationships with trade
■ Early appointment of the the construction manager can and requirements for client sign- contractors, including the issue
construction manager. To be perform effectively in advance of off. Cost reporting processes that of instructions, administration
really effective, the construction the completion of the CM closely monitor the impact of of payment and problem solving.
manager needs to be on board agreement. instructed changes also need to In managing these relationships,
before the initial design, budget ■ Ensuring that management be in place, backed up by an the construction manager and
and programme are set. resources are applied at key actively administered risk client should aim to achieve a
Retrospective adoption of a CM stages of the project, including: management process. The scope balance between contractual
strategy is likely to result in the ■ Design – establishing and of progress reporting should also discipline and an appropriate
appointed construction manager monitoring the design be extended to include design level of flexibility, in order to
having limited influence, playing programme, and reviewing deliverables and information maintain the commitment and
catch-up throughout the project. design deliverables for release schedules. co-operation of trade contractors.
■ Appointment of the right CM completeness and coordination. ■ Allocating work to packages Investment in team-building
team. Clients and their advisers The construction manager will based on trade interfaces rather activities at all levels of the
must be absolutely vigorous in also need to enforce compliance than administrative convenience. project team also helps to focus
their selection and appointment with information release Clients should also monitor staff on the importance of the
of the CM team, ensuring that it schedules with respect to packages to avoid the duplicate client’s objectives and the
has the full range of skill sets completeness and timeliness. procurement of site successful completion of the
and processes required. Key areas Where change occurs, the establishment, plant and scheme.

BUILDING MAGAZINE 01.09.2006


economics.procurement 67

06 Case study: Peter Jones department store refurbishment


This case study, based on the Peter Jones based on the assumption of a CM route and The effect on the quality of information was
department store refurbishment, illustrates included realistic allowances for risk issues considerable – directly addressing one of the
the conditions for success required for the associated with the uncertain scope of work, major risks associated with CM. Risk
effective use of CM. It also underlines the key the building’s listed status, phasing and so on. management as a discrete project
role of the client and gives an example of how The client’s active involvement ensured that management activity was also taken very
CM can be adapted to provide a greater level its key issues, mostly focused on a very high seriously – aided by the successful
of certainty, but without undermining its key level of customer care and neighbourhood management of some major issues early in
features. liaison, together with the achievement of the the project – with monthly reviews and the
The refurbishment of the Peter Jones detailed design solution required by the formal management of the ownership and
department store in Chelsea, London, valued retailers, were always at the forefront. closedown of major risks.
at £100m and completed in summer 2004 is The project programme, devised after the One key to the success of the Peter Jones
one of the most complex and high-profile consideration of many options, was based on refurbishment was the quality of working
projects that the John Lewis Group has three major phases – “the three rooms” – relationships at all levels of the project, which
undertaken. The major issues for the client involving the complete reconstruction and led to a genuine understanding of the client’s
concerned delivery to budget and to an extension of large, discrete sections of the key issues – particularly the importance of
agreed programme aligned with key trading building. Package procurement really suited managing the impact of the project on
dates, and above all, the minimisation of the the project, particularly with respect to the customers. The client and CM were
impact of the project on customers and continuing involvement of trade contractors instrumental in establishing this way of
neighbours. in successive phases. working and in addressing the strengths and
The John Lewis management is naturally An unusual feature of the contractual weaknesses of CM procurement.
very focused on retailing as well as the arrangements for the project was Bovis’ That a project with such a high risk profile
management of its building projects, and as responsibility for the performance of the could be delivered so successfully – on time
construction clients have tended towards design team during the detailed design and and budget and to critical acclaim – is more as
risk-sharing procurement strategies that production information stages. The client a result of the efforts of the team, than the
best align risks with the party best placed to retained the design risk, but the arrangement, selection of a procurement route. However in
manage them. John Lewis’ general preference whereby the design team was managed and this instance, the adoption of CM, and the
is for lump-sum contracts where commercial paid by the CM, focused Bovis’ attention on client’s commitment to its discipline, gave the
risk is taken by the contractor. In the case of the co-ordination of the design and on the project the focus on end results that became
Peter Jones, the client was persuaded by the timing and content of information releases. the foundation of its success.
project team that, because of the extended
project timescale, the problems of working in
a trading store and above all, risks related to Previously …
an uncertain scope of work in an existing
building, it would not be possible to obtain a 4 August Cost model: Retail fit-out
realistic or secure lump-sum tender as the 11 August Small projects cost model:
basis for a traditional contract. Social housing
The construction manager – in this case, 25 August The tracker
Bovis Lend Lease – was appointed at an early
project stage, during RIBA stage C. At the Coming up …
same time the client made key internal
appointments, nominating the group deputy 8 September Cost update
chairman as project sponsor, and making the 15 September The tracker
existing Peter Jones MD a full-time project 22 September Whole-life costs: Basements
director. A huge effort was made by the client
in preplanning, liaison with third parties and in
understanding the potential impact of the Data toolkit
project on trading and on the reputation
of the business. This level of commitment Building’s database of cost data is an
had a profound impact on the motivation of essential resource for anyone in the
the project team. In time, the client team business of procuring buildings. There is an
co-located with the CM staff and other extensive archive of cost models, market
consultants, creating a project team that was forecasts, whole-life costings and much
fully focused on the client’s priorities and on more. See www.building.co.uk/datatoolkit
solving problems as they emerged.
Appointing Bovis early meant that detailed Cost model correction
programming options were considered from Because of a production error, the cost
the outset. The project budget was also breakdown in the retail fit-out cost model
published on 4 August contained some
incorrect units. The corrected model is now
Opposite and right: The £100m refurbishment available on www.building.co.uk and Davis
of the Peter Jones department store in London Langdon’s website www.davislangdon.com
is an example of good construction management

BUILDING MAGAZINE 01.09.2006

Potrebbero piacerti anche