Quotation 05/07/2017
Client: Sahel Erbil co.
Project: Detergent factory
Location: IRAQ-Erbil

We provide to you the offer for providing material, manufacturing and erecting the supper structure
of the factory warehouses as the following table:
ITEM DISCRPITION UNIT Estimated unit TOTAL
Quantity price $ PRICE $
1.two plants warehouses
Steel work: manufacturing, primer painting,
transporting and erecting all steel elements of the
1.1 warehouse using steel grade s275/s235 the elements m2 4740 29.30 $ 138,882.00 $
consist of roof purlins, frames, columns, bracings, with
all plates and flanges needed.
Roof cladding: Providing and erecting 5 cm good
1.2 quality sandwich panel with its flashing and m2 5010 $12.35 61,873.50 $
accessories.
Exterior Wall cladding: Providing and erecting 5 cm
1.3 good quality sandwich panel with its flashing, and m2 2090 $16.35 34,171.50 $
accessories.
Total Cost of two plants warehouses 234,927.00 $
2.concrete roof for offices and stores attaches to the plants
Steel work: manufacturing, primer painting,
2.1 transporting and erecting all steel elements of the roof m2 1210 53.40 $ 64,614.00 $
using steel grade s275/s235 the elements consist of roof
frames, columns, with all plates and flanges needed.
Roof concrete work: providing and installing deck
2.2 metal corrugated metal sheets 0.9 MM, laying BRC m2 1210 $20.00 24,200.50 $
wire mesh, and casting concrete grade C25.
Total Cost of. concrete roof for offices and stores 88,814.50 $
3. RAW AND MANUFACTURED MATERIALS STORAGE'S
Steel work: manufacturing, primer painting,
transporting
3.1 and erecting all steel elements of the warehouse using
steel m2 4117 47.15 $ 194,116.55 $
grade s275/s235 the elements consist of roof purlins,
frames, columns, bracings, with all plates and flanges
needed.
Roof cladding: Providing and erecting 5 cm good
3.2 quality sandwich panel with its flashing and m2 4345 $12.35 53,660.75 $
accessories.
3.3 Exterior Wall cladding: Providing and erecting 5 cm
good quality sandwich panel with its flashing, and m2 1185 $16.35 19,375.74 $
accessories.
Total Cost of RAW AND MANUFACTURED MATERIALS STORAGE'S 267,153.00 $
Notes:
 The structure designed against to the dead, live, and wind loads according to UFC and ASCE
STANDARD. And we can provide to you the shop drawings and structural calculations after
signing the contract.
 The price calculated for the present row material prices.
 We can provide data sheets and technical information after the bid awarded.
 You can see in the attachments the 3rd concept drawings of the warehouses.
 The estimated duration for the work is about 150 days for manufacturing and erecting.
 This quotation includes only the items that mentioned above so the other items which is not
mentioned (such as down water pvc pipes electrical works …) should be added.
 The main contractor should prepare the civil works and the site to let the work go without
obstacles.
 The erection of the j-anchor bolts should be upon the civil work responsibilities but the
manufacturing of the bolts is our responsibilities.
 Payment will be as the following:
o 30 % in advance.
o 30% when the steel structure elements start arriving to the site.
o 30 % after completing the erecting of the total steel structure elements and after the
sandwich panel raw materials reaches to the site.
o 10% after finishing the erecting of the sandwich panel.