Sei sulla pagina 1di 2

Progress work

Owner : Linde Engineering North America INC. Progress No. : 2

Client : VPE at Khao Hin Sorn Period : 1- 15 Dec-17

Main Contractor : S.P. Mechanical Engineering Date: B16-Dec-17

Construction Drawing Internal Progress Report


Item Last period This period Accumulate Remark
No Heater no. Description Material type Q'ty Unit
back-up Hot face Q'ty Q'ty Q'ty

VPE Job: P549010 ผลงานคคุณฉงครรับ


(Linde Project)
F-10201 Convection Module # 5 Sparlite 50 16.00 m3 - 8.00 8.00 vertical position
F-10201 Convection Module # 6 Sparlite 50 20.53 m3 - 20.53 20.53 vertical position
F-10201 Convection Module # 7 Sparlite 50 11.59 m3 11.57 0.02 11.59 vertical position
F-10201 Convection Module # 8 Sparlite 50 15.42 m3 - - -
F-10201 Breeching Sparlite 51 6.67 m3 - - -
F-10201 End Tube sheet 1 Furnance Sparlite 50 12.60 m3 - - -

- - -
Grand Total 82.81 m3 11.57 28.55 40.12

Prepare By:……………………………….. Checked By:............................................

(………………………………..) ( Vittaya Anma )


Supervisor

Date: .................................... Date: ....................................