Sei sulla pagina 1di 3

Quality Procedure: Document Number:

IN-QA-FORM-02
Armstrong Engineering Change Owner:
Management Design
AS Plant: Revision:
Engineering Change Request
India 00

1. Purpose

1.1 Purpose

ECR is submitted to the Design department to initialize engineering change process.

2. Format:

2.1 Format
ECR No
Date
Drawing No
Description
Requisitioner
Department
Reason/ Rationale/
Benefit of change

Estimated Need
Date
Change Description

Cost of implementation (Heads – New capital investment, change in process, inventory at DC (obsolete
or modification), training, inspection and others):

Date: 12/08/14 1 of 3
Quality Procedure: Document Number:
IN-QA-FORM-02
Armstrong Engineering Change Owner:
Management Design
AS Plant: Revision:
Engineering Change Request
India 00

Capital & one-time cost:

Head Value (INR)


Capital Investment
Cost for modifying inventory(One time)
Cost of obsolescence
Training
Other one-time costs (Specify the head)
Total
Recurring Cost:
Head Value/UoM (INR)
Supplementary accessories
Process change
Total

3. Approvals:

3.1 Approvals
Requisitioner
Manufacturing
Design
Quality
Vendor Management
Supply Chain
Head of Department - AS

4. Related Documents:

4.1 Related Documents

5. Document Approval

5.1 Document Approval

Date: 12/08/14 2 of 3
Quality Procedure: Document Number:
IN-QA-FORM-02
Armstrong Engineering Change Owner:
Management Design
AS Plant: Revision:
Engineering Change Request
India 00

Section Name, Department Date Signature

Prepare Navin K, VD. 7/11/2014

Review

Approve

6. Document Control

6.0 Document Revisions

Section Release/Amendment summary Issue Date

x.0

x.0

Date: 12/08/14 3 of 3