GROUP THREE

ADETUBERU JOSEPH IPS/MSC/PPD/2017/296


AJAYI OLAWALE IPS/MSC/PPD/2017/297
AMUAH FREDA IPS/MSC/PPD/2017/299
ATEMIE-HART KELVIN IPS/MSC/PPD/2017/301
IBEH GLORY IPS/MSC/PPD/2017/304
ACKNOWLEDGEMENT

Our gratitude goes to God Almighty for making this project a success.

We also wish to acknowledge Mr. Francis Fusier and all lecturers of IPS for the knowledge impacted
to us, their patience and dedication towards us have brought us thus far. To the Management and Staff
of the Institute of Petroleum Studies (IPS), we say thank you.

Our appreciation goes to all the team members for their contribution to the success of the project.

i
EXECUTIVE SUMMARY

The report contains an elaborate and detailed design and specifications for well COD SE 1A a deviated
development well which aims to produce 1,200,000 stm3/D of gas per day in the COD field in the
Norwegian side of the North Sea, Norway. The water depth is 72 meters and the rig proposed and
eventually selected as adequate for the purpose is the Maersk Gallant Jackup Rig.
Formation data was obtained from the appraisal well 10/30-6 drilled previously in same field. Pore
pressures, Leak-Off pressures and formations to be encountered are already known. H2S is not present
in this location. There is also no expectation of shallow gas. The gas production would be channelled
to the COD central production station (12 kms away).
The design was carried out based on the use of a 4-1/2” Liner which has an hydraulically set packer for
completions, a Tubing conveyed Perforation method was used Underbalanced to perforate. Choice of
completion equipment was selected based on an expected flow rate of 1,200,000stm3/D. The casings
to be used to complete this project are 20” 106.5# surface casing to a depth of 610mTVD, 13-3/8”
68# Intermediate casing one to a depth of 1500mTVD, 9-5/8” 43.5#intermediate casing two to a
depth of 2500mTVD and a production casing of 7”29# to a 3250mTVD.
This report contains the Wells’ architecture, mud, cement and casing design, the operational drilling
program, the completion design with running procedures and intervention methods (if required in the
late life of the well) for both the vertical and directional wells and the forecasted progress charts for the
wells until the end of completion. All possible justifications and assumptions made during the course
of the study were also highlighted.
The project will be executed and completed in 44 days asides and unforeseen conditions and the cost
would be about 3,054,754.31 USD.
It is noteworthy to state that the project is HSE compliant.

ii
LIST OF FIGURES

Figure 1.1: Map of the COD field ........................................................................................................... 2


Figure 2.1:- Lithology of COD S-E 1A .................................................................................................. 8
Figure 4.1:-Casing Design (Source: Trans ocean Casing Design document) ....................................... 19
Figure 4.2:- Determination of casing depth using EMW ...................................................................... 20
Figure 4.3:- Determination of casing depth using Fracture pressure .................................................... 21
Figure 4.4:- Casing Architecture........................................................................................................... 22
Figure 5.1:-Proposed Well Trajectory .................................................................................................. 32
Figure 5.2:- Target Depth ..................................................................................................................... 33
Figure 6.1:- Drilling string schematics for phase one ........................................................................... 43
Figure 6.2:- Drilling string schematics for phase two........................................................................... 58
Figure 6.3:- Drilling string schematics for phase three......................................................................... 70
Figure 6.4:- Drilling string schematics phase four................................................................................ 83
Figure 7.1:- Completion diagram .......................................................................................................... 94
Figure 7.2:- Wellhead to be used for the CODSE 1A........................................................................... 97
Figure 7.3:- Gnatt chart showing project timeline .............................................................................. 102
Figure 7.4:- Gnatt chart showing project timeline cont’d ................................................................... 102

iii
LIST OF TABLES

Table 1.1:- LOT for appraisal well ......................................................................................................... 9


Table 3.1:- Risk register for the drilling operation ............................................................................... 14
Table 4.1:- Tubing Selection................................................................................................................. 29
Table 4.2:- Summary of casing design ................................................................................................. 30
Table 4.2:- Summary of casing design and architecture ....................................................................... 30
Table 5.1:- Depth of various sections ................................................................................................... 31
Table 5.2:- Kick off............................................................................................................................... 33
Table 5.3:- Well trajectory .................................................................................................................... 33
Table 6.1:- Drilling Phases and Intervals (Referenced to MSL) .......................................................... 37
Table6.2:- Basic Information of the Surface Casing ............................................................................ 38
Table 6.3: Summary of Drilling String Parameters for Phase 2 ........................................................... 39
Table 6.4:- Drilling Parameters (Bit Type) ........................................................................................... 40
Table 6.5:- Showing the calculation of the drill string weight ............................................................. 42
Table 6.6:- Showing the Pressure loss calculation................................................................................ 44
Table 6.7:- 26” Hole: Result of Mud Calculations .............................................................................. 48
Table 6.8:- 26” Hole: Principal Additives for Sea Water and Spud Mud........................................... 49
Table 6.9:- Typical Properties of the Inhibitive Gypsum Polymer Mud .............................................. 49
Table 6.10:- Summary of slurry calculations ........................................................................................ 51
Table 6.11:- Component and Additives of cement slurry ..................................................................... 51
Table 6.12:- Basic Information of the First Intermediate Casing ......................................................... 52
Table 6.13:- Summary of Drilling String Parameters for Phase 2 ........................................................ 54
Table 6.14:- Drilling Parameters (Bit Type) ......................................................................................... 54
Table 6.15:- Showing the calculation of the drill string weight ........................................................... 56
Table 6.16:- Showing the Pressure loss calculation.............................................................................. 59
Table 6.17:- 13 3/8 ” Hole: Results of Mud Volume Calculations ...................................................... 63
Table 6.18:- 13 3/8 ” Hole: Principal Additives for Inhibitive Gypsum Polymer Mud ..................... 63
Table 6.19:- Typical Properties of the Inhibitive Gypsum Polymer Mud ............................................ 64
Table 6.20:- Summary of cement calculations ..................................................................................... 64
Table 6.21:- Component and Additives of the cement slurry ............................................................... 65
Table 6.22:- Basic Information of the Second Intermediate Casing ..................................................... 66
Table 6.23: Summary of Drilling String Parameters for Phase 4 ......................................................... 67
Table 6.24:- Drilling Parameters (Bit Type) ......................................................................................... 68
Table 6.25:- Showing the calculation of the drill string weight ........................................................... 69
Table 6.26:- Showing the Pressure Loss calculation ............................................................................ 71
Table 6.27:- 9 5/8 ” Hole: Results of Mud Volume Calculations ........................................................ 75
Table 6.28:- 9 5/8 ”Hole: Principal Additives for Inhibitive Gypsum Polymer Mud ......................... 76
Table 6.29:- Typical Properties of the Inhibitive Gypsum Polymer Mud ............................................ 77

iv
Table 6.30:- Summary of cement calculations ..................................................................................... 77
Table 6.31:- Component and Additives of the cement slurry ............................................................... 77
Table 6.32: Basic Information of the Production Casing ..................................................................... 78
Table 6.33:- Summary of Drilling String Parameters for Phase 4 ........................................................ 79
Table 6.34:- Drilling Parameters (Bit Type) ......................................................................................... 80
Table 6.35:- Showing the calculation of the drill string weight ........................................................... 81
Table 6.36: Showing the Pressure Loss calculation.............................................................................. 84
Table 6.37:- Production Casing: Results of Mud Volume Calculations .............................................. 88
Table 6.38: 8 1/2” Hole: Principal Additives for Saturated Salt Mud .............................................. 89
Table 6.39:- Typical Properties of the Saturated Salt Mud .................................................................. 89
Table 6.40:- Summary of cement calculations ..................................................................................... 89
Table 6.41:- Additives for cement slurry .............................................................................................. 90
Table 6.42:- Cost estimation of the project ......................................................................................... 102
Table C-1: Summary of Results- Mud calculations a) Surface casing b) Intermediate Casing 1 c)
Intermediate Casing 2 d) Production Casing ..................................................................................... 119
Table C-2:- Mud Pump Requirement a) Surface casing b) Intermediate Casing 1 c) Intermediate
Casing 2 d) Production Casing .......................................................................................................... 123

v
TABLE OF CONTENTS

ACKNOWLEDGEMENT ....................................................................................................................... i
EXECUTIVE SUMMARY ....................................................................................................................ii
LIST OF FIGURES ...............................................................................................................................iii
LIST OF TABLES ................................................................................................................................. iv
TABLE OF CONTENTS ....................................................................................................................... vi
CHAPTER 1 ........................................................................................................................................... 1
GENERAL DATA .................................................................................................................................. 1
1.1 Data about the block & license ..................................................................................................... 1
1.2 Field Development Concepts ........................................................................................................ 1
1.3 Location Map ................................................................................................................................ 2
CHAPTER 2 ........................................................................................................................................... 3
GEOLOGICAL PROGRAMME ............................................................................................................ 3
2.1 Purpose of the wells ...................................................................................................................... 3
2.1.1 Objectives .............................................................................................................................. 3
2.1.2 Results of appraisal wells....................................................................................................... 3
2.1.3 Structure ................................................................................................................................. 4
2.1.4 Reservoir ................................................................................................................................ 4
2.1.5 Stratigraphic Prognosis Description ...................................................................................... 4
2.1.6 Pressure prognosis data: Formation pressure and fracture gradients ..................................... 9
2.1.7 Formation Temperature Prognosis ....................................................................................... 10
2.2 Formation Evaluation Programme .............................................................................................. 10
2.2.1 Conventional mud logging ................................................................................................... 10
2.2.2 MWD ................................................................................................................................... 11
2.2.3 Cuttings analysis and Coring ............................................................................................... 11
2.2.4 Wire Line Logging ............................................................................................................... 11
2.2.5 DST ...................................................................................................................................... 11
CHAPTER 3 ......................................................................................................................................... 12

vi
DRILLING HAZARDS ........................................................................................................................ 12
3.1 Environment And Waste Management ....................................................................................... 12
CHAPTER 4 ......................................................................................................................................... 19
WELL DESIGN .................................................................................................................................... 19
4.1 Well Architecture with Casing’s Design .................................................................................... 19
4.2 General Considerations ............................................................................................................... 22
4.3 Recap of Rules for Casing Design .............................................................................................. 23
4.4 Casing Calculations .................................................................................................................... 25
4.5 Tubing Design ............................................................................................................................. 29
CHAPTER 5 ......................................................................................................................................... 31
WELL TRAJECTORY ......................................................................................................................... 31
5.1 Planned trajectory to meet target ................................................................................................ 31
5.2 Measured Depth Estimation ........................................................................................................ 33
5.3 Trajectory Control ....................................................................................................................... 34
CHAPTER 6 ......................................................................................................................................... 37
DRILLING OPERATIONS .................................................................................................................. 37
6.1 Phase 1 – Conductor Casing (30”) .............................................................................................. 37
6.2 Phase 2 – Surface Casing (26” Hole Section) ............................................................................. 37
6.2.1 Purpose of this phase ........................................................................................................... 38
6.2.2 Possible Challenges ............................................................................................................. 38
6.2.3 Barriers ................................................................................................................................. 38
6.2.4 Drilling Procedure ................................................................................................................ 38
6.2.5 Kick-off Procedure............................................................................................................... 39
6.2.6 Drill Strings .......................................................................................................................... 39
6.2.7 Drilling Parameters .............................................................................................................. 39
6.2.8 Power Requirement .............................................................................................................. 43
6.2.9 Drilling Fluids ...................................................................................................................... 47
6.2.10 Fast line Tension ................................................................................................................ 50
6.2.11 Cementing .......................................................................................................................... 51
6.3 Phase 3 – Intermediate Casing 1 (17-1/2” Hole Section) ........................................................... 52
vii
6.3.1 Purpose of this phase ........................................................................................................... 52
6.3.2 Possible Challenges ............................................................................................................. 53
6.3.3 Barriers ................................................................................................................................. 53
6.3.4 Drilling Procedure ................................................................................................................ 53
6.3.5 Kick-off Procedure............................................................................................................... 53
6.3.6 Drill Strings .......................................................................................................................... 54
6.3.7 Drilling Parameters .............................................................................................................. 54
6.3.8 Power Requirement .............................................................................................................. 57
6.3.9 Drilling Lines ....................................................................................................................... 62
6.3.10 Drilling Fluids .................................................................................................................... 62
6.3.11 Cementing Procedure ......................................................................................................... 64
6.4 Phase 4 – Intermediate Casing 2 (12-1/4” Hole Section) ........................................................... 66
6.4.1 Purpose of this phase ........................................................................................................... 66
6.4.2 Possible Challenges ............................................................................................................. 66
6.4.3 Barriers ................................................................................................................................. 66
6.4.4 Drilling Procedure ................................................................................................................ 66
6.4.5 Kick-off Procedure............................................................................................................... 67
6.4.6 Drill Strings .......................................................................................................................... 67
6.4.7 Drilling Parameters .............................................................................................................. 67
6.4.8 Power Requirement .............................................................................................................. 70
6.4.9 Drilling Fluids ...................................................................................................................... 75
6.4.10 Cementing Programme ...................................................................................................... 77
6.5 Phase 4 –Production Casing 2 (8-1/2” Hole Section) ................................................................. 78
6.5.1 Purpose of this phase ........................................................................................................... 79
6.5.2 Possible Challenges ............................................................................................................. 79
6.5.3 Barriers ................................................................................................................................. 79
6.5.4 Drilling Procedure ................................................................................................................ 79
6.5.5 Kick-off Procedure............................................................................................................... 79
6.5.6 Drill Strings .......................................................................................................................... 79
6.5.7 Drilling Parameters .............................................................................................................. 80
viii
6.5.8 Power Requirement .............................................................................................................. 82
6.5.9 Drilling Lines ....................................................................................................................... 87
6.5.10 Power Requirement at end of Phase .................................................................................. 88
6.5.11 Drilling Fluids .................................................................................................................... 88
6.5.12 Cementing Programme ...................................................................................................... 89
CHAPTER 7 ......................................................................................................................................... 91
WELL COMPLETIONS ...................................................................................................................... 91
7.1 Overview ..................................................................................................................................... 91
7.1.1 Running and Testing Procedure ........................................................................................... 92
7.2 Perforation Strategy .................................................................................................................... 95
7.2.1 Completion and Packer fluid ............................................................................................... 95
7.3 Wellhead type and rating ............................................................................................................ 96
7.4 Running and Testing Procedure .................................................................................................. 97
7.4.1 The following checks should be carried out on all threaded joints of the tube ................... 97
7.4.2 The following procedures should be carried out on the wellbore before running the tubing
....................................................................................................................................................... 97
7.4.3 The following techniques and equipment should be used in running the tube to the correct
depth .............................................................................................................................................. 98
7.4.4 Installing the Christmas tree ................................................................................................ 98
7.4.5 Well clean up ....................................................................................................................... 99
7.4.6 Perforation............................................................................................................................ 99
7.4.7 Cleaning the well after perforation ...................................................................................... 99
7.5 Future Interventions .................................................................................................................. 100
7.6 Project timing and costing ........................................................................................................ 102
APPENDIX A : CASING DESIGN ................................................................................................... 106
Surface Casing ................................................................................................................................ 106
Intermediate Casing 1 ..................................................................................................................... 106
Intermediate casing 2 ...................................................................................................................... 107
Production casing ............................................................................................................................ 107
APPENDIX B: DRILL STRING CALCULATIONS ........................................................................ 108

ix
APPENDIX C: MUD CALCULATIONS .......................................................................................... 118
APPENDIX D: CEMENTING PROGRAMME ................................................................................ 126
30” and 20” Casing Section (Surface Casing): Cementing to the mudline ................................ 126
20” and 13 3/8” Casing Section (Intermediate Casing I): ........................................................... 129
13 3/8” and 9 5/8” Casing Section (Intermediate Casing II): ..................................................... 133
9 5/8” and 7” Casing Section (Production Casing):.................................................................... 137

x
CHAPTER 1

GENERAL DATA

The COD field is situated in the Norwegian side of the North Sea, in block 10/30 at 150 km South
West of Stavanger (Norway). Water depth is 72 meters. The reservoir situated in the late Palaeocene
Forties Fan System. Gas and Condensate have already been produced from the COD Field.

1.1 Data about the block & license


• Field Name: COD field
• Location: Norwegian side of the North Sea
• Block Description: Block 10/30
• Well identification: Gas Well
• Drilling rig: Jack up
• Position of Jacket: Co-ordinate (x; y) is (480,285.00; 6 310,909.00)
• Water depth: 72m
• Drilling depth objective: forties formation
• Estimated Top of Reservoir: 3080 m TVD MSL
• Total Depth: 3245m TVD MSL

1.2 Field Development Concepts


The COD S-E extension will be developed using a Steel Jacket of 8 conductor pipes for an initial
programme of 6 gas producers. Each producing well will be designed for a flow rate of 1,200,000
stm3/D
The Jacket will include only wellheads, as the gas production will be piped to the COD central
production station (12 kms away). The Jack-up rig will be a cantilever type positioned on top of the
wellhead jacket.
The proposed Jack-up is the “Maerskk Gallant”
Position of the Jacket:
Block 10/30
X = 480,285.00

1
Y = 6 310,909.00
Water depth = 72 meters
Height of jacket upper deck: 15.0 m above sea level.
Estimated distance MSL-RKB = 55 m
Conductor pipes OD 30” (ID = 28.75 “) will be driven and fully cemented at depth of 160 m MSL after
jacket installation (before rig positioning)

1.3 Location Map

Figure 1.1: Map of the COD field

2
CHAPTER 2

GEOLOGICAL PROGRAMME

2.1 Purpose of the wells


The purpose of drilling well COD S-E 1A is to safely produce gas from the COD Field through a 4-1/2
inch tubing.

2.1.1 Objectives
The appraisal wells drilled in the COD Field had the following objectives:
• To primarily explore the reservoir extent.
• To refine the reservoir characteristics, heterogeneity and quality and other reservoir features.
• To accurately determine the reservoir interval and thickness.
• To enhance knowledge of the reservoir structure.
• To obtain reservoir fluids for analysis and tests.
The well COD S-E 1A is a deviated well (J well) to produce gas from the forties formation. Its objective
is to be optimized to produce 1,200,000 stm3/D of gas.

Basic PVT parameters:


Gas Gravity: 0.74
Reservoir temperature: 98 oC
Estimated top of reservoir: 3080 m TVD MSL
Estimated reservoir thickness: 115 m (Gross)
A minimum of 50 meters (TVD) should be drilled in the Lista formation below the reservoir.

2.1.2 Results of appraisal wells


The first appraisal well drilled to analyse the South-East extension of the COD field gave the following
results:

Results of the appraisal well 10/30-6

3
Appraisal well 10/30-6 encountered the top of the Forties reservoir sands at 2 890 m MSL and drilled
85 m of gross sand thickness. After RFT measurements, the well was found gas bearing (fluid gradient
of 0.35 g/cc) down to the base of the reservoir at 2957 m and no hydrocarbon to water contact was
observed.
Two DST were performed and DST 2 flowed at a rate of 1.500 000 Sm3/d of gas associated with 153
Sm3/d of condensate through a 40/64" choke. The reservoir pressure is 376 bars at 2 912 m MSL, giving
a gradient of 1.30 EMW. This gradient is considered constant on all the structure.
The reservoir consists of thin sand bodies (1 to 3 m) inter-bedded with thin shale stringers (0,5 to 1 m).
Some of the reservoir layers are stacked and constitute more massive sandy units (up to 12 m). Electrical
logging shows that the so-called "thin beds" effect is influencing the reading of the tools, particularly
for the resistivity measurement. Those sands are fine to medium grained, and well sorted. Core
descriptions and electrical log patterns, where typical fining upward Bouma sequences can be seen,
clearly indicate that the reservoir bodies have been deposited as distal lobes of a turbiditic system. The
petrophysical characteristics show relatively low average porosity (16 %) and permeability (20 to 30
mD) associated with a 50 % net/gross. Both N/G and porosity are in the range of what is usually found
in very distal turbidites. This is consistent with the location of the well close to the pinch-out area where
the reservoir starts.

2.1.3 Structure
COD gas condensate field lies in the southern area of the Norwegian sector of the North Sea, in block
7/11, 280km southwest of the Norwegian coast. The field is also situated in the North Sea Central
graben, 46mi (75km) north-northwest of the giant Ekofisk field (rank 98, after Carmalt and St. Johns,
1986) and a half mile (1km) east of the median line between the English and Norwegian sectors. The
water depth in the area is 230ft (70 m). COD was discovered in 1968, and the plan for development
and operation (PDO) was approved in 1973.

2.1.4 Reservoir
The COD field produces gas and condensate from the upper Paleocene sandstone of deep marine distal
turbiditic origin, located at a depth of 9400ft (2870m) subsea. The deposit has a complex structure with
several separate reservoirs at the depth of 3,000 metres. It is expected to produce more than 280 bcf of
gas and 17 million barrels of condensate. It can be further described in the table below:

2.1.5 Stratigraphic Prognosis Description


Depth are from MSL
4
The proposed lithology is based on data from wells in the surrounding area.

The lithological prognosis for the shallow part of the wells will be adjusted / corrected in accordance
with the results of the site survey.

Cuttings will be sampled as soon as return is established.

72 m – 620 m Pleistocene – Holocene Nodland Group

72 m – 122 m : Soft silty clay overlain by thin sand layer of less than 1 meter.
122 m – 220 m : Fine sand interbedded with stiff to firm clay.
220 m – 250 m: Stiff clay.
250 m – 512 m : Consolidated stiff clay with minor sand layers. Possible coarser material at the base
of the unit (base of channel).
512 m – 620 m: Hard sandy clay with layers of sand and silt.

620 m – 1 615 m (+15 m) Miocene – Pliocene Nordland group

620 m – 780 m: Sandy clay with interbeds of sand.


780 m – 922 m: Claystone with minor sand interbeds.
922 m – 962 m: Clay, silty-sandy.
962 m – 1 615 m: Claystone, greenish, slightly silty, thin stringers of limestones, traces of pyrite.

1 615 ( 15 m) – 3 010 m ( 20 m) Eocene – Oligocene – Miocene Hordaland Group


1615 m – 1 854 m: Claystone, brown-greyish, moderate silty, stringers of limestones.
1 854 m – 1 950 m: Claystone/siltstone, light grey – brown moderate silty, sand, very fine-fine.
1 950 m – 2992 m: Claystone, light-dark brown, moderate silty, stringers of dolomite, limestones and
sand, traces of mica, organic material, pyrite and microfossils.

3 010 ( 20 m) – 3 310 m ( 40 m) Paleocene – EarlyEocene Rogaland Group

5
3 010 m – 3 025m: Balder Fm. Claystone, varicoloured, dominantly medium – dark grey greenish and
brownish, silty, traces of tuff.
3 025 m – 3 085 m: Sele Fm. Claystone, grey - greenish grey, stringers of limestone, traces of sandstone.
3085 m – 3195 m: Forties Fm. Sandstone, light grey – light brown, very fine-fine, subangular, well
sorted, thin beds/stringers of shale, light grey, silty, sandy traces of lignite.
3195 m – 3275 m Lista Fm. Claystone, grey – becoming green - greenish grey, occasionally brick red,
stringers of sandstone.
3275m – 3 310 m (3 275 msec): Vâle Fm. Interbedded limestone, muddy, chalky, locally silty,
claystone, grey, very calcareous and marl grey.

3310 – 3 355 m (TD), Danian Shetland Group

3310 m – 3355 m (TD): Ekofisk Fm. Limestone, chalky-mudstone, off-white-cream, silty,


argillaceous.

6
7
Figure 1.1:- Lithology of COD S-E 1A

8
2.1.6 Pressure prognosis data: Formation pressure and fracture gradients
The prognosis is based on results from the discovery well 10/30-6. The prognosed gradients are quoted
in SG units of EMW, and are presented in figure 1.3 (reference level is MSL).
Nordland Group (72- 1 615 m)MSL
From seabed down to approximately 1420 m normal pressure conditions are expected. The lower part
of Nordland Group, from approx. 1420 – 1615 m is most likely representing the upper part of an
approximately 1 000 m thick undercompacted zone. The pressure gradient at base Nordland is
prognosed to be 1.40 g.cc EMW.
Hordaland Group (1615 - 3010 m)
The undercompacted zone, starting at approximately 1 466 m in Nordland Group, extends down to
about 2424 m. Maximum of undercompaction is expected between 1760 and 1860 m. In this interval,
the pressure gradient is prognosed to be in the range 1.50 – 1.55 g/cc EMW (maximum pressure
gradient: 1.57 g/cc EMW, minimum pressure gradient: 1.45 g/cc EMW).
From 1860 m down to base Hordaland, the pressure gradient should gradually drop to 1.30 – 1.35 g/cc
EMW.
Rogaland Group (3010- 3310 m)
Maximum pressure gradient at the top of the Forties reservoir should be 1.30 g/cc EMW (1.33 g/cc
EMW subsea), assuming a water gradient through the reservoir. Minimum pressure gradient at top
reservoir should be 1.30 g/cc EMW (1.31 g/cc EMW subsea) assuming the same gas-condensate
gradient as in well 10/30-6; 0.038 bar/m.
At base Rogaland Group, the pressure gradient is expected to be in the range 1.29 –1.32 g/cc EMW.
Shetland Group (3310 – 3355 m)
Pressure gradient is expected to be same as for base of Rogaland Group: 1.29 – 1.30 g/cc EM
Frac Pressure
The following LOT were made during exploration and appraisal phases:-
Table 1.1:- LOT for appraisal well

Depth: (MSL) LOT (EMW)


920 m 1.63
1550 m 1.75
2298 m 1.84
2850 m 1.93

9
3040 m 1.95
3120 m 1.96

2.1.7 Formation Temperature Prognosis


The temperature gradient for this formation is shown below. This gives an insight into the expected
evolution of temperature as the wells are being drilled enabling these variation or changes to be taken
into consideration as the design of mud and other drilling considerations are being carried out.
Expected reservoir temperature: 98 oC

2.2 Formation Evaluation Programme


2.2.1 Conventional mud logging
Mud logging is the creation of a detailed record of the borehole by examining rock cuttings brought to
the surface by the drilling mud. It provides information about the lithology and fluid content of the
borehole while drilling.
Mud logging is necessary in order to obtain the following information about the formation:
a) Drilling parameters
b) Mud flow
c) Mud density
d) Mud losses and gains
e) Cuttings sampling
f) Gas detection and analysis of gas brought up in the mud by surface gas detectors
Mud logging is carried out by a mobile mud logging unit situated on the offshore drilling platform. It
contains the following:
a) A hotwire or total gas detector
b) A gas chromatograph
c) A rate of penetration recorder
d) Pump stroke counters
e) Pit volume indicators
f) Carbon dioxide detectors
g) Mud resistivity recorders

10
2.2.2 MWD
MWD with GR/Resistivity/Directional will be used after piling in the 30”Conductor Pipe down to
160m. In the reservoir, LWD will be considered depending of borehole conditions.

2.2.3 Cuttings analysis and Coring


The purpose of coring is to enable better visualization of the formation (as seen on the log) and
hence to draw inferences on the likely behaviour of the actual rock mass. Only parameters which are
significant to the rock behaviour or which enable correlations between boreholes to be made or give a
better understanding of the general geology of the site are recorded.
Core samples are taken at predetermined intervals. Samples here were taken at 10 and 5 meters
intervals depending on drilling penetration rate.
The reservoir was cored from the top. Core analysis comprises routine measurements (Ø, Kh, Kv
etc) and special analysis (Resistivity Index, cappillary pressure, rock consolidation, etc).

2.2.4 Wire Line Logging


The formation will logged after drilling using openhole logs. The following basic logs will be run:
-Resistivity logs: Dual Laterolog/Micro SFL/Gamma Ray
-Porosity logs: Density/Neutron Porosity/Natural Gamma Ray
- Caliper/Gamma Ray
This should only take about a few hours (6).
A Cement Bond Log(CBL), Variabe Density Log (VDL) or Cement Evaluation Tool (CET) will be run
on all casings to test the integrity of the cement job as from the 24” intermediate section

2.2.5 DST
A drill stem test (DST) is a procedure for isolating and testing the pressure, permeability and productive
capacity of a geological formation during the drilling of a well. It is a key method of obtaining
information on the formation fluid and establishing whether a well has found a commercial
hydrocarbon reservoir.

11
CHAPTER 3

DRILLING HAZARDS

This chapter present potential hazards that may be encountered during while drilling through the
formation from the surface to the desired depth. The hazards are determined by dividing the formation
into zones. Each zone is considered a node. Hazards relating to each node are listed. The identified
nodes comprise:
• Node 1: Pleistocene – Holocene Nodland Group (72 m – 620 m)–
• Node 2: Miocene – Pliocene Nodland Group (620 m – 1 615 m)
• Node 3: Eocene – Oligocene – Miocene Hordaland Group: 1 615 (+/-15 m) – 3 010 m (+/-20
m)
• Node 4: Rogaland Group: 3 010 (+/-20 m) – 3 310 m (+/-40 m)
The risk register in table 3.1 contains the identified causes, consequences and proposed barriers
associated with each hazard scenario.

3.1 Environment And Waste Management


Drill cuttings, drilling fluids and drilling wastes will be handled, stored and disposed of pursuant to the
requirements the International Convention for the Prevention of Pollution from Ships (MARPOL,
1973/78) and These include specific conventions and agreements relating to particular maritime
regions, such as the Oslo and Paris Commission for the North-East Atlantic (OSPAR) for North Sea
region.
However, waste from the solids-control equipment are either:
 offshore discharge – fluids and/or cuttings are discharged overbroad from the drilling platform
after undergoing treatment by solids control equipment designed to remove solids and recover
fluids,
 offshore downhole injection –cuttings are ground to fine particle sizes and disposed of, along
with entrained fluids, by injection into permeable subsurface formations,

12
 Onshore disposal – cuttings and the associated fluids are collected and transported for
treatment if necessary and final disposal.

13
Table 3.1:- Risk register for the drilling operation

Hazard Events Description of Node Causes Consequences Controls


Node 1: Pleistocene – Holocene Nodland Group (72 m – 620 m)
72 m – 122 m: Soft silty clay • Release of gas through
overlain by thin sand layer of less near surface faults from
Release of shallow gas than 1 meter. deeper gas zone
while drilling and installing 122 m – 220 m: Fine sand • Potential release of gas • Collapse of jack-up • Appropriate mud
1
conductor and surface interbedded with stiff to firm clay. while drilling through high and drilling rigs system
casing holes. 220 m – 250 m: Stiff clay. porosity sand units in the • Blowout and fire if • Diverter unit and/
250 m – 512 m: Consolidated stiff section between 450 and ignited or BOP
clay with minor sand layers. 550 m MSL. • Damage to • Soil integrity
Possible coarser material at the • Drilling through high equipment check before
base of the unit (base of channel). porosity sand units in the • Injury to personnel installing and
2 Mud losses
512 m – 620 m: Hard sandy clay section between 450 and • Environmental spill positioning rig.
with layers of sand and silt. 550 m MSL.
Failure of jack-up drilling Normal pressure conditions are • Collapse of the soft silty
3
rigs expected. clay at the sea bed.
Node 2: Miocene – Pliocene Nodland Group (620 m – 1 615 m)

14
Hazard Events Description of Node Causes Consequences Controls
620 m – 780 m: Sandy clay with
interbeds of sand.
780 m – 922 m: Claystone with
minor sand interbeds.
4 Formation collapse
922 m – 962 m: Clay, silty-sandy. • Using appropriate
• Loss of tools
962 m – 1 615 m: Claystone, • Incompatibility of drilling mud.
• Damage to
greenish, slightly silty, thin shale/clay with drilling • Consistent
equipment
stringers of limestones, traces of mud, under compacted cuttings sampling.
• Injury to personnel
pyrite. zones, etc • Adopting best
• Environmental spill
620 m – 1 420 m: Normal pressure drilling practices.
Mud losses in under conditions are expected.
5
compacted zones 1 420 m - 2 410 m: Expected
under compacted shale section
(1.45 – 1.6 g/cc EMW) .
Node 3: Eocene – Oligocene – Miocene Hordaland Group: 1 615 (+/-15 m) – 3 010 m ( +/-20 m)

15
Hazard Events Description of Node Causes Consequences Controls
1615 m – 1 854 m: Claystone,
brown-greyish, moderate silty,
stringers of limestones.
1 854 m – 1 950 m:
Claystone/siltstone, light grey –
brown moderate silty, sand, very
fine-fine.
• Using
1 950 m – 2992 m: Claystone,
• Loss of tools appropriate
light-dark brown, moderate silty, • Incompatibility of
• Damage to drilling mud.
stringers of dolomite, limestones shale/clay with drilling
6 Formation collapse equipment • Consistent
and sand, traces of mica, organic mud, under compacted
• Injury to personnel cuttings sampling.
material, pyrite and microfossils. zones, etc
• Environmental spill • Adopting best
1760m - 1860 m: under
drilling practices.
compaction is expected (1.45g/cc -
1.57 g/cc EMW)
1860 m - 2992 m: 1.30 – 1.35 g/cc
EMW.
1 420 m - 2 410 m: Expected
under compacted shale section
(1.45 – 1.6 g/cc EMW) .

16
Hazard Events Description of Node Causes Consequences Controls
Mud losses in under
7
compacted zones
Node 4: Rogaland Group: 3 010 (+/-20 m) – 3 310 m (+/-40 m)
3010 m – 3025m: Balder Fm.
Claystone, varicoloured,
• Incompatibility of
dominantly medium – dark grey
8 Damage of payzone shale/clay with drilling
greenish and brownish, silty, traces
mud, etc
of tuff. • Install and testing
3025 m – 3085 m: Sele Fm. • Loss of reservoir BOP.
Claystone, grey - greenish grey, • Blowout and fire if •Using appropriate
Uncontrolled release of stringers of limestone, traces of ignited drilling mud.
9 • High formation pressure
hydrocarbon (gas or oil) sandstone. • Damage to • Install and testing
3085 m – 3195 m: Forties Fm. equipment BOP.
Sandstone, light grey to light • Injury/ death to • Consistent
brown, very fine-fine, subangular, personnel cuttings sampling.
well sorted, thin beds/stringers of • Balling of bits due to • Environmental spill • Adopting best
shale, light grey, silty, sandy traces sticky clay. drilling practices.
10 Drilling equipment failure
of lignite. • Differential sticking of
3195 m – 3275 m Lista Fm. drill string.
Claystone, grey – becoming green -
greenish grey, occasionally brick

17
Hazard Events Description of Node Causes Consequences Controls
red, stringers of sandstone.
3275m – 3 310 m (3 275 msec):
Vâle Fm. Interbedded limestone,
muddy, chalky, locally silty,
claystone, grey, very calcareous
and marl grey.
At base Rogaland Group, the
pressure gradient is expected to be
in the range 1.29 – 1.32 g/cc
EMW.

Note: H2S have not been encountered during exploration and appraisal. C02 level is expected to be very low (Less than 0.2%
volume). Hence, safety precautions against should be taken such as the use of gas detectors while drilling.

18
CHAPTER 4

WELL DESIGN

4.1 Well Architecture with Casing’s Design


The essence of proper casing size, type and shoe depth selection cannot be overemphasized in well
architecture. It is important so as to provide reliable well construction at a minimum cost and also
ensure good well mechanical integrity by providing proper design plan that accounts for all the
anticipated loads that can be encountered during the life of the well.

Figure 4.1:-Casing Design (Source: Trans ocean Casing Design document)

The well COD SE-1A is a vertical well optimized to produce gas at a rate of 1200000 Sm3/day
from the forties formation, based on the information obtained from the appraisal wells; Casing
shoe depths were selected based on the lithological constraints as shown and in obedience to the
casing design rules. Casing is tubing that is set inside the drilled well to protect and support the
wellstream (Rigzone, 2014).

19
Depth vsEMW
0 0.5 1 1.5 2 2.5
0

500

1000

Pore pressure
1500
frac pressure
Swab pressure
Surge pressure
2000 Mud Weight

2500

3000

3500

Figure 4.2:- Determination of casing depth using EMW

20
0 100 200 300 400 500 600 700
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
Pore Pressure
1600
1700 Frac Pressure
1800 swab margin
1900 surge margin
2000
hydrostatic pressure
2100
2200
2300
2400
2500
2600
2700
2800
2900
3000
3100
3200
3300
3400
3500
3600
3700

Figure 4.3:- Determination of casing depth using Fracture pressure

21
The size of the tubing with the capacity to produce 1200000 Sm3/day of gas was selected first and
informed the choice of the production casing. Hence casing selection was done from down
upwards and the schematic is shown in Figure 4.2 below.
The type of casing (linear weight, diameter, grade, connection) was selected based on technical
considerations.

Figure 2.4:- Casing Architecture

4.2 General Considerations


The casing programme was designed with regards to best leak off test at casing shoe. The drilling
mud programme includes water based mud (WBM) for the surface casing while non-aqueous
based mud (NABM) is selected for the remaining casings.
The following considerations were taken into account for the casing design:
• Determination of casing setting depths based on geological constraints.

22
• Determination of optimum casing size at various intervals to ensure that the required tubing
size is feasible.
• Calculations of maximum pressure constraints (burst, collapse and tensile) on the casing
during operations and selection of casings accordingly.
For the platform wells, the Conductor Casing (30” welded) will be driven while installing the
jacket. Drilling/Completion department indicated the type of Casing (steel, thickness..) with
minimum position of Conductor Casing extremity.
It is very important to control the verticality of the Conductor Casing.

4.3 Recap of Rules for Casing Design


Rule 1: Surface casing shall protect all shallow fresh water levels and shall be cemented up to
surface or mud line.
Surface casing shall be set before entering the first shallow hydrocarbon structure which requests
the use of a blow-out preventer (BOP); in such a case, surface casing shall be designed like a
technical casing.

Rule 2: With the exception of deep water wells, the casing point on intermediate casings shall be
designed for the following assumptions:
“Well full of gas”:
On exploration/appraisal wells as fluid, pressures, and formation weak points are not well known,
On development gas wells which can be temporarily abandoned with possible alteration of the
hydraulic barrier (for example, subsea wells or wells drilled from jack-up or platform rigs with
possible crew evacuation due to hurricanes): over time, fluid could replace mud in the hole leading
to a cross flow situation.
On shallow development gas wells: open-hole volumes are small and no more compatible with
standard admissible kick volume.
“Unlimited kick”:
On all development wells except those mentioned above (if in accordance with local legislation).

23
Rule 3: Minimum limited kick to be considered for casing design shall be 10 m3 on fixed
installations; this minimum value should be increased in the event of downgraded conditions or in
sensitive areas.

Rule 4: With respect to the above, the collapse design factor is set at:
1.125 for surface, intermediate and test casings,
1.125 for cemented part of these casing,
1.125 for production casing, cemented or not.
Load lines to be considered include:
• Cementing operations.
• Floated casing while running.
• Partial evacuation.
• Full evacuation.
• Perforation blockage conditions.

Rule 5: For the above reasons, the burst design factor is set at 1.10.
Load lines to be considered include:
• Bullheading a well full of gas.
• Limited oil and gas kick.
• Bullheading over a surface tubing leak.
• Artificial lift.
• Thermal expansion of trapped fluid.

Rule 6: The axial design factor is set at 1.30.

Rule 7: The triaxial design factor is set at 1.25; collapse shall be checked separately.

Rule 8: On HT wells (bottom hole temperature > 150°C) and/or if safety factors are close to design
factors, a derating on the minimum yield (relating to 20°C) must be applied.
A derating factor of 0.07 %/°C above 20°C on yield is a mean value for all steel grades. If necessary
more accurate figures can be supplied by equipment manufacturers.

24
4.4 Casing Calculations
1) 30’’ Conductor Pipe/Casing
No calculations were made for this phase as the conductor pipe was driven when installing the
platform to refusal to a depth of 160m.
Purpose
• To set the 30” CP at refusal depth.
• Protection of subsequent casings and isolation from seawater.
• Seal off unconsolidated formations at shallow depths.
• Stop washouts under the drilling rig.
• Protection of fresh water sands.
• To provide a good base and support for the next string of casing.
The 24” casing design follows thereafter.
2) 20’’ Surface Casing at 610m
Purpose
• Support other casings
• Protection of portable water aquifer
• Support the wellhead and BOP equipment’s
• Case unconsolidated formations
Collapse study
Worst case: During Cementing
Differential pressure at 610m = 43.03bar
Safety factor = 1.125
Final collapse constraint = 48.41 bar
Burst study
Worst case: After cementing mud weight increases
Pore pressure at 610m = 72 bar
Pore pressure at the shoe =86.12bar
Safety factor = 1.3
Final burst constraint = 18.36bar

Selected casing

25
The selected casing based on the burst and collapse calculations:
20”, 106.5 lb/ft, K55, Drift diameter=18.8” Coupling type Buttress Standard

Tension study
Casing shoe depth 1500m, mud density for the next phase 1.44
Tmax (Buttress standard) = 749KdaN
𝑇=𝑛𝑜𝑟𝑚𝑖𝑛𝑎𝑙 𝑤𝑒𝑖𝑔ℎ𝑡 ×𝑏𝑢𝑜𝑦𝑎𝑛𝑐𝑦 𝑓𝑎𝑐𝑡𝑜𝑟 ×𝑙𝑒𝑛𝑔ℎ𝑡
0.85 × 155.4 × 610
𝑊𝑚 = = 80.57𝐾𝑑𝑎𝑁
1000
Maximum pull=(𝑇𝑚𝑎𝑥⁄𝑊𝑚) > 1.6 :- 749⁄80.57 = 9.296
Tension: Safety Factor= 9.296 > 1.6 Satisfied.
3) 13-3/8’’ Intermediate Casing
Purpose
• Seal off weaker zones.
• Protect previous casing strings from higher Burst Pressure

Collapse study
Worst case: Partial emptying due to thief zone
Differential pressure at top of mud column, 975.6m = 118bar
Safety factor = 1.125
Final collapse constraint = 132.75 bar

Burst study
Worst case: Well full of gas and bull heading
Gas SG = 0.2g/cc3
Pore pressure at 1500m = 202 bar
Hydrostatic column of gas=49bar
Bull heading pressure = 35 bar
Safety factor = 1.3
Final burst constraint = 410.8 bar

Selected casing

26
The selected casing based on the burst and collapse calculations:
13-3/8”, 68 lb/ft, RT95, Drift diameter=12.27” Coupling type Buttress Standard

Tension study
Casing shoe depth 1500m, mud density for the next phase 1.44
Tmax (Buttress standard) = 788KdaN
Wm=95.14Kda𝑁
Maximum pull=(𝑇𝑚𝑎𝑥⁄𝑊𝑚) > 1.6 :- 788⁄95.14 = 8.28
Tension: Safety Factor= 8.28 > 1.6 Satisfied.
4) 9-5/8 ‘’ Intermediate Casing
Purpose
• Seal off weaker zones.
• Protect previous casing strings from higher Burst Pressure

Collapse study
Worst case: Partial emptying due to thief zone
Differential pressure at top of mud column, 860.3m = 138.323bar
Safety factor = 1.125
Final collapse constraint = 155.613 bar

Burst study
Worst case: Well full of gas and bull heading
Gas SG = 0.20g/cc3
Pore pressure at 3250m = 330 bar
Hydrostatic column of gas=63.7bar
Bull heading pressure = 35 bar
Safety factor = 1.3
Final burst constraint = 391.7 bar

Selected casing
The selected casing based on the burst and collapse calculations:
9-5/8’’, 43.5 lb/ft, L80, Drift diameter=8.6” Coupling type Vallourec VAM TOP

27
Tension study
Casing shoe depth 2500m, mud density for the next phase 1.64
Tmax (Buttress standard) = 447KdaN
Wm=86.4𝐾𝑑𝑎𝑁
Maximum pull=(𝑇𝑚𝑎𝑥⁄𝑊𝑚) > 1.6 :- 447⁄86.4 = 5.18
Tension: Safety Factor= 5.18 > 1.6 Satisfied.
5) 7” Production Casing
Purpose
• To drill through the payzone.
Collapse study
Worst case: Complete emptying below the packer
Pore pressure at 3250m = 418 bar
Safety factor = 1.125
Final collapse constraint = 470.3 bar

Burst study
Worst case: Well full of gas and tubing leak
Gas SG = 0.20g/cc3
Pore pressure at 3250m = 418 bar
Hydrostatic column of gas=63.7bar
Bull heading pressure = 35 bar
Safety factor = 1.3
Final burst constraint = 506.1bar
Selected casing
The selected casing based on the burst and collapse calculations:
7’’, 29 lb/ft, L80, Drift diameter=6.1” Vallourec VAM TOP

Tension study
Casing shoe depth 3250m, mud density for the next phase 1.36
Tmax (Buttress standard) = 301KdaN
Wm=70.29𝐾𝑑𝑎𝑁

28
Maximum pull=(𝑇𝑚𝑎𝑥⁄𝑊𝑚) > 1.6 :- 301⁄70.29 = 4.282
Tension: Safety Factor= 4.282 > 1.6 Satisfied.

4.5 Tubing Design


The 4 ½”, 12.6# tubing was selected based on the expected flow rate of the well which is
1,200,000stm3/day as shown:

Table 4.1:- Tubing Selection

Since our production casing is 7” with a drift ID=6.1” we resorted to using a WRSCSSSV (OD=5.748”)
as against TRSCSSSV (OD=6.92”) and a Baker SSD Circulating Valve (3.75”ID) was used as well.
Collapse Constraint = 295 bar
Tubing length = 3050m
Tension safety factor = 1.6
Tubing estimated maximum tension
=3050m x 18.39daN/m x 1.6 = 89.7kdaN
This tension can be handled by Grade N80 tubing
• Nominal tubing diameter: 4 ½”.
• Nominal Weight: 12.6lb/ft.

29
• Inside diameter: 3.958”.
• Drift: 3.833

Coupling
Vallourec and Mannesmann VAM PRO
Efficiency: 100%
Make-up torque: 600 daN.m

Table 4.2:- Summary of casing design

Type OD Length (m) Tension Max allowable Safety factor


(inches) (kdaN) Tension (kdaN)
Conductor Pipe 30 160 NA NA NA
Surface Casing 20 610 80.57 749 9.296
Intermediate casing 1 13 3/8 1500 95.144 788 8.28
Intermediate casing 2 9 5/8 2500 86.4 447 5.176
Production casing 7 3250 70.29 301 4.282

Table 4.2:- Summary of casing design and architecture

LOT Pore
Shoe OD Drift Weig Tensio Top of at pressu
Burst Collapse
Casing Depth( (Inche ID Thread Grade ht n cement shoe re
(bar) (bar)
m MSL) s) (in) (lb/ft) (kdaN) (m) (EM (EMW
W) )
Surface 610 20 18.8 API K55 106.5 18.36 48.41 749 NA 1.54 1.18
casing
Intermediate 1500 13 12.25 Buttress RT95 68 410.8 132.75 788 472.4 1.74 1.44
casing 1 3/8
Intermediate 2500 9 5/8 8.6 Buttress L80 43.5 391.7 155.6 447 301.54 1.81 1.64
casing 2
Production 3250 7 6.1 Vallourec VAM L80 29 506.1 470.3 301 600 1.88 1.36
casing TOP
Tubing NA 4½ 3.83 Vallourec N80 12.6 499 295 89.7 NA NA NA

VAM PRO

30
CHAPTER 5

WELL TRAJECTORY

5.1 Planned trajectory to meet target


Proposed kick off Depth: 620m; 10m below the end of surface casing.
All depths are referenced from the Mean Sea Level.

Table 5.1:- Depth of various sections

True Vertical Depth Measured Depth Horizontal


Section
(mss) (m) Displacement (m)

Mudline 72 72 0
Kickoff 620 620 0
End of Build 932.1 950 92.44

End of Slant 1 (Top of


3080 3511.1 1487.3
Reservoir)

End of Slant 2
3195 3648.2 1561.98
(Bottom of Reservoir)

Target 3250 3713.78 1597.7

31
Horizontal Displacement (m)
-200 0 200 400 600 800 1000 1200 1400 1600 1800
0

500
True Vertical Depth (mss)

1000

1500

2000

2500

3000

3500

Figure 3.1:-Proposed Well Trajectory

Using the co-ordinates of the jacket and the target;


Jacket;
X = 480,285m
Y = 6,310,909m
Target;
X = 481,430m
Y= 6,311,860m

32
1000.000

800.000
Distance Northwards

600.000

400.000

200.000

0.000
-200.000 0.000 200.000 400.000 600.000 800.000 1000.000 1200.000
-200.000
Distance Eastwards

Figure 5.2:- Target Depth

5.2 Measured Depth Estimation


Horizontal displacement from the location of jacket to the top of target estimated as D =1488.4m.
Based on formation type and recommendation;

Table 5.2:- Kick off

Kick-off Depth 620 m


0
Build-up Gradient 1.0 /10m
Vertical Depth of Target 3080 m
Radius of Curvature 573 m
Angle of inclination 33.08 degrees

Table 5.3:- Well trajectory

True Vertical Depth Measured Horizontal


Section
(m MSL) Depth (m) Displacement (m)
Sea Level 0 0 0
Mudline 72 72 0
Surface Casing Shoe 610 610 0
IC1 Shoe 1500 1627.14 461.29

33
IC2 Shoe 2500 2819.5 1110.7
Target 3250 3713.78 1597.7

5.3 Trajectory Control


The well trajectory is of the J-trajectory, that is, Build and Hold type.
The kick-off trajectory is achieved with the use of a downhole motor comprising of the bent
housing, thereafter the normal rotary drilling is used to achieve better trajectory or shape for the
slant section.
The deviation has to be accurately monitored with MWD in order to place the casing shoes at the
right depth and formation. The inclination is maintained at 330.
Horizontal displacement;

951m

1145m

𝐷 = √11452 + 9512 = 1488.4m

Build-up gradient = 10/10m based on formation type and characteristics


Kick-off depth, ZK = 620m, 10m below the casing shoe
Vertical depth of target is given, Z = 3080m,
Radius of curvature, R= 573m
Angle of inclination;
𝑍 − 𝑍𝑘 𝑅 𝑍 − 𝑍𝑘
𝑖 = 180 − tan−1 ⌊ ⌋ − cos −1 ⌊ ⌋ sin tan−1 ⌊ ⌋
𝐷−𝑅 𝑍 − 𝑍𝑘 𝐷−𝑅
𝑖 = 33.060
Measured depth at end of deviation;
𝑇𝑉𝐷𝐸 = 𝑍𝐾 + 𝑅 sin 𝑖
𝑇𝑉𝐷𝐸 = 932.1𝑚

34
ΠiR
𝐿𝐸 = 𝑍𝐾 +
180
𝐿𝐸 = 950𝑚

Horizontal Displacement at End of Build;


𝐷𝐸 = 𝑅(1 − cos 𝑖)
𝐷𝐸 = 92.44𝑚

Measured depth at top of target; TVD = 3080m


ΠiR 𝑍 − 𝑍𝐾 − 𝑅 sin 𝑖
𝐿𝑇 = 𝑍𝐾 + +
180 cos 𝑖
𝐿𝑇 = 3511.1𝑚

Measured depth at bottom of target; TVD = 3195m


115
𝐿𝐵 = 𝐿𝑇 +
cos 𝑖
𝐿𝐵 = 3648.2𝑚
Horizontal Displacement at bottom of target;
𝐷2 = 𝐷 + 115 tan 330
𝐷2 = 1562𝑚
Measured depth at bottom of well; TVD = 3250m
55
𝐿𝑤 = 𝐿𝑇 +
cos 𝑖
𝐿𝑤 = 3713.8𝑚
Horizontal Displacement at bottom of well;
𝐷3 = 𝐷2 + 55 tan 330
𝐷3 = 1597.71𝑚
Measured depth calculation at Casing Shoes;
Surface Casing:
𝑇𝑉𝐷 = 610𝑚
𝑀𝐷 = 610𝑚
Intermediate Casing 1:

35
𝑇𝑉𝐷 = 1500𝑚
ΠiR (TVD − 𝑇𝑉𝐷𝐸 )
𝑀𝐷 = 𝑍𝐾 + +
180 cos 𝑖
𝑀𝐷 = 1627.14𝑚
Intermediate Casing 2:
𝑇𝑉𝐷 = 2500𝑚
ΠiR (TVD − 𝑇𝑉𝐷𝐸 )
𝑀𝐷 = 𝑍𝐾 + +
180 cos 𝑖
𝑀𝐷 = 2819.5𝑚
Production Casing:
𝑇𝑉𝐷 = 3250𝑚
ΠiR (TVD − 𝑇𝑉𝐷𝐸 )
𝑀𝐷 = 𝑍𝐾 + +
180 cos 𝑖
𝑀𝐷 = 3713.8𝑚

36
CHAPTER 6

DRILLING OPERATIONS

Drilling of wells require several operations which include planning and layout of procedures for
the drilling phases, hole sizes, weight on bit, drill strings, collars, bits selection, mud Pumping,
barriers used, casing and cementing.
The summary of the phases are highlighted in the table below.

Table 6.1:- Drilling Phases and Intervals (Referenced to MSL)

Depth
Hole Size Casing Size
Phase No Casing Name Interval
(in) (in)
(m) MSL
1 Conductor - 30 0 -160
2 Surface 26 20 160 - 610
3 Intermediate 1 17-1/2 13-3/8 610 - 1500
4 Intermediate 2 12-1/4 9-5/8 1500 - 2500
5 Production 8-1/2 7 2500 – 3250

Estimated reservoir top: 3080m TVD MSL


Estimated reservoir Thickness: 115m (Gross)

6.1 Phase 1 – Conductor Casing (30”)


The 30” conductor casing is already in position at the depth of 160m MSL and it was fully
cemented after the jacket installation before the positioning of the rig.
The conductor pipe is connected from the mud line to the surface wellhead at platform.

6.2 Phase 2 – Surface Casing (26” Hole Section)

37
Table6.2:- Basic Information of the Surface Casing

Interval 160 – 610 TVD MSL


Maximum Expected BHP 1.14 SG
Mud Weight 1.2 SG
Expected LOT 1.54 SG

6.2.1 Purpose of this phase


The purpose of this phase is to drill using Water based mud to the depth of 610m MSL and case-
off the hole safely. The hole will pass through the Pleistocene – Holocene formations.

6.2.2 Possible Challenges


• Likelihood of gas presence between 450m – 550m MSL.
• Bit dulling due to coarse sediments (250m – 512m)
• Hole cleaning challenges due to coarse materials.

6.2.3 Barriers
No BOP stack is needed to drill this phase. A Diverter should however be installed to handle the
high concentration of background gas that might be present within the 450 – 550m MSL interval.
Barriers needed are:
• Diverter
• Inside BOP
• Gray Valve

Note: Always ensure the driller is aware of the wind direction so the correct overboard line can be
lined up as necessary.

6.2.4 Drilling Procedure


• Drill directly with a 26" Roller cone bit to TD with reduced ROP (<15m/hr). Inclination to
be maintained below 1 degree.
• MWD (GR/Resistivity) will be used continuously while drilling the 26” hole. No wire line
logging of section is required
• A directional survey shall be taken each 100m.
• Cuttings will be taken at every 10m interval.

38
• No coring activity for this section

6.2.5 Kick-off Procedure


No Kick-off in this section

6.2.6 Drill Strings

Table 6.3: Summary of Drilling String Parameters for Phase 2

Linear OD OD ID Cumulative
Length
Element Grade Weight No Max Body Body Length
(m)
(Kg/m) (in) (in) (in) (m)
IADC
- 1 26 - - - -
Roller Cone Bit CODE: 525
Bit sub + Float
- - 1 - 9 - - -
Valve
Stabilizer - - 3 - 25.75 - - -
MWD - - 1 - - - - -
Non- Magnetic Drill
- 323.18 5 - 9-1/2 3 9.144 45.72
Collar
Drill Collar API SPEC 323.18 2 - 9-1/2 3 9.144 18.288
Hydraulic Jar API SPEC - 1 - 9-1/2 3 - -
Drill Collar API SPEC 218.77 1 - 8 3 9.144 9.144
HWDP NC 50 74.67 1 - 5 3 9.144 9.144
G105 NC 50
32.55 64 - 5 4.276 9.144 585.216
Drill Pipe (XH)

6.2.7 Drilling Parameters


The hole is to be drilled to the depth of 610m MSL. The parameters to be considered involve the
following:
• Bit type
• Nozzle Selection

39
• Maximum Overpull
• WOB

6.2.7.1 Bit type


The Bit selection is made based on the nature of the formations to be encountered. The drill bit
parameters are shown below

Table 6.4:- Drilling Parameters (Bit Type)

Roller Cone, Insert


Type of Bit
Tooth
Diameter 26"
IADC Code 135

6.2.7.2 Nozzle Selection


The basis of the calculation of the flow rate is the cutting settling velocity in the annulus. The
following rule is recommended:
● For soft formation annular velocity between 30 and 40 m/mim
● For hard formation annular velocity between 25 and 30 m/min
Annular Mud Velocity = 40 m/min
Annular Capacity OH – DP = 329.2 l/m
𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐹𝑙𝑜𝑤 𝑟𝑎𝑡𝑒, 𝑄 = 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦, 𝐶𝑎 × 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦, 𝑉𝑎
𝑙 𝑚 𝐿
∴ 𝑄 = 329.2 × 40 = 13,168
𝑚 𝑚𝑖𝑛 𝑚𝑖𝑛

The annular flow rate obtained is rather high.


The Maersk Gallant rig has 3 pumps (3 X LTV Emsco FC – 2200) single acting with a power of
2200HP rated for 7500psi.
Taking an overall pumping efficiency of 90% (η= 0.9)

Using
𝑃×𝑄 1
𝑃𝐻𝑃 = ×
450 
Where

40
P= Stand pipe pressure in bar = 7500psi = 517.098bar
Q= Flowrate in l/min
η = pumping efficiency (90%)

Making use of two pumps and allowing one to be on standby, the combined horsepower will be
4400hp.
Calculating the flowrate that will be achieved by the pump
𝑃𝐻𝑃 ∗ 450 ∗ 
𝑄=
𝑃
4400 ∗ 450 ∗ 0.9
𝑄=
517.098
𝑄 = 3446.155 𝑙/𝑚𝑖𝑛
The flowrate achieved by the pump is smaller than the required for good hole cleaning, therefore
we will have to stop at various intervals to clean the hole.
Using
𝐹𝑅
𝑉=
38.71 ∗ 𝑇𝐹𝐴
Where
FR= Flow rate in liters/min
V= Mud Velocity meters/sec
TFA = Total Flow area, 𝒊𝒏𝟐
Making use of a mud velocity of 120m/s
𝐹𝑅
𝑇𝐹𝐴 =
38.71 ∗ 𝑉
3446.155
𝑇𝐹𝐴 =
38.71 ∗ 120
𝑇𝐹𝐴 = 0.74187 𝒊𝒏𝟐
From DDH E11 we choose a drilling Bit of 3 (Three) nozzles 18/32 inch each, having a total area
of 0.7255 𝒊𝒏𝟐 . (18-18-18)

6.2.7.3 Maximum Overpull

41
Table 6.5:- Showing the calculation of the drill string weight

Linear
Length Total Weight
Weight Buoyancy Factor Total Weight (kg)
(m) (T)
(Kg/m)
Drill Collar 323.18 73.152 0.85 23641.26336 23.64126336
Drill Collar 218.77 9.144 0.85 2000.43288 2.00043288
HWDP 74.67 9.144 0.85 682.78248 0.68278248
Drill Pipe 32.55 585.216 0.85 19048.7808 19.0487808
Total = 45.37325952

Maximum Overpull (MOP)


MOP = Maximum Tension on DP – weight of Drill String
Weight of Drill String in mud = (DC weight + HWDP weight + DP weight) * buoyancy factor
Total Drillstem Weight =45.37T * 0.85= 38.6T
Tensile Yield Strength on DP = 193.8kdaN DDH B15
𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟 = 90%
≈ 0.9
𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 = 𝑇𝑒𝑠𝑖𝑙𝑒 𝑦𝑖𝑒𝑙𝑑 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ × 𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟
= 0.9 𝑥 193.8
= 174.42 𝑘𝑑𝑎𝑁
≈ 177.8𝑇
Maximum Overpull = 𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 − Total Drillstem Weight
= 177.8𝑇 − 38.6 𝑇
= 139.24𝑇

6.2.7.4 WOB
Since this phase is very soft
1
𝑊𝑂𝐵 ≈ 𝑎 𝑡𝑜𝑛 𝑝𝑒𝑟 𝑖𝑛𝑐ℎ 𝑜𝑓 𝑏𝑖𝑡 𝑖𝑛 𝑠𝑜𝑓𝑡 𝑓𝑜𝑟𝑚𝑎𝑡𝑖𝑜𝑛
2
0.5𝑡𝑜𝑛𝑠
→ 𝑊𝑂𝐵 = 26′′ × = 13𝑡𝑜𝑛𝑠
𝑖𝑛𝑐ℎ

42
𝑐𝑜𝑛𝑣𝑒𝑟𝑡𝑖𝑛𝑔 𝑡ℎ𝑒 𝑊𝑂𝐵 𝑡𝑜 𝑑𝑎𝑁;
𝑑𝑎𝑁
𝑊𝑂𝐵 = 13 × 0.981 × 1000
𝑘𝑔
∴ 𝑊𝑂𝐵 = 12,753𝑑𝑎𝑁 = 𝟏𝟐. 𝟕𝟓𝟑𝒌𝒅𝒂𝑵

6.2.8 Power Requirement


To determine the rig power requirement, the powers for the following systems are evaluated:
1. Hydraulic System – Hydraulic Power
2. Hoisting System – Hoisting Power
3. Rotary System – Rotary Power
Pressure loss calculation

DP – L2, L5

HWDP – L2’, L5’

DC – L3, L4

Figure 6.1:- Drilling string schematics for phase one

𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑
𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿′2 𝑁3 +𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿′5 𝑁5 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑
𝑃𝑑 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝 𝑖𝑛 𝑛𝑜𝑧𝑧𝑙𝑒𝑠 𝑓𝑜𝑟 𝑑 = 1, (𝑘𝑃𝑎)
𝑘𝑔⁄
𝑑 = 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑔𝑟𝑎𝑣𝑖𝑡𝑦, ( 𝑙)
𝑁1 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑒𝑞𝑢𝑖𝑚𝑒𝑛𝑡, (𝑘𝑃𝑎⁄100𝑚)

43
𝑁2 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁3 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟𝑠, (𝑘𝑃𝑎⁄100𝑚 )

𝑁4 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟 𝑎𝑛𝑛𝑢𝑙𝑢𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁5 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑎𝑛𝑛𝑢𝑙𝑢𝑠(𝑘𝑃𝑎⁄100𝑚)

𝐿2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)


𝐿′2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿3 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿4 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿′5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
Typically Plastic viscosity is about twice of mud weight in pounds per gallon
Therefore:
𝑃𝑉 = 2 × 1.2 × 8.33
𝑷𝑽 = 𝟏𝟗. 𝟗𝟗𝟐 𝑪𝒑

Table 6.6:- Showing the Pressure loss calculation

Parameters Units DDH

Nozzle 18-18-19
N1 426.1541 kPa/100m G30
N2 267.46 kPa/100m G41
N3 1324.3 kPa/100m G46

N4 1 kPa/100m G62
N5 1 kPa/100m G67
L2 585.216 m
L2' 9.144 m
L3 73.152 m
L4 73.152 m

44
L5' 9.144 m
L5 585.216 m
Pd 8000.3 Kpa G52
d 1.2
B 2.11 G24
Case: 3
Q 3446.155 l/min
Ptotal= 16115.82 Kpa

Pumping requirement:
• Assuming a volumetric efficiency ηv=0.97
• Assuming a mechanical efficiency ηm=0.90

6.2.8.1 Hydraulic Power

Hydraulic power =
𝑃×𝑄
𝑃𝐻𝑃 (ℎ𝑝) =
44750
16115.82 × 3446.155
𝑃𝐻𝑃 (ℎ𝑝) =
44750
𝑃𝐻𝑃 (ℎ𝑝) = 1241.1 ℎ𝑝

6.2.8.2 Mechanical Power

𝐻𝑦𝑑𝑟𝑎𝑢𝑙𝑖𝑐 𝑃𝑜𝑤𝑒𝑟
Mechanical Power= 𝜂𝑚

1241.1
=
0.9
= 1378.96 ℎ𝑝

6.2.8.3 Hoisting Power


The hoisting power is evaluated for each of the phases using the equation below.

45
𝐹×𝑉 1
𝑃𝐻𝑃 = ×
77.5 

Where:
F, Total Hoisted Weight (String + Block +Hook + Over pull)
V, Pulling up Speed, meters/sec
, Overall Hoisting Efficiency

Assumptions
Weight of 25 Tons for Block + Hook,
Speed of 0.3 meters/second
Using 12 lines and roller bearing, we obtain a reeving efficiency of 0.782 (DDH F3)
From previous calculations,
String load in air = 44.5 Tons
Margin of Over pull = 139.24𝑇

Therefore:
F = 45.4+25+139.24𝑇
F = 184.64 Tons (184.64 X103 kg)
184.64 × 103 × 0.3 1
𝑃𝐻𝑃 = ×
77.5 0.782
𝑃𝐻𝑃 = 913.7 𝐻𝑃

6.2.8 4 Rotation Power


The rotation power is evaluated for each of the phases using the equation below.
𝐶 × 𝑅𝑃𝑀 1
𝑃𝐻𝑃 = ×
712 
Where
C, Torque (daN.m)
, Rotating Efficiency (0.9)
𝐶 = 𝑆𝑎𝑓𝑒𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 × 𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑇𝑜𝑟𝑞𝑢𝑒
The minimum torque is obtained from DDH B22

46
Minimum Torque for a 5” X 4.276” Drill Pipe with nominal weight of 32.55 kg/m is (connection
= API, NC 50).
Minimum Make up Torque = 2,969 daN.m DDH B22
Using a safety factor of 80%,
𝐶 = 0.8 × 2969
𝐶 = 2375.2 𝑑𝑎𝑁. 𝑚

The Rotation per Minute (RPM) is assumed to be 150


The Rotation Power required is
2375.2 × 150 1
𝑃𝐻𝑃 = ×
712 0.9
𝑃𝐻𝑃 = 555.99 𝐻𝑃

6.2.8.5 Total Power Requirement

Total power = Pump power + Hoisting Power + Rotation Power


Total Power = 4400 + 913.7 + 555.99
Total Power = 5869.2 HP

6.2.8.6 Drilling Lines


We choose a 1.5” Wire diameter, 6 X 195 RR IWRC

6.2.9 Drilling Fluids


The most critical function that a drilling fluid performs is to minimize the concentration of cuttings
around the drill bit and throughout the well bore. Of course, in so doing, the fluid itself assumes
this cuttings burden, Table hold contains the mud types that have been selected for the drilling
process. The choice of mud types is based on the following:
a) Effectiveness of the mud in achieving its primary function
b) Cost
c) Regulations
d) Safety and environment
e) Waste disposal consideration

6.2.9.1 Surface hole


Mud type : sea water and spud mud

47
Depth : 160m – 610m measured depth
Section length drilled : 450m
Drilled well volume : 154,138.14 litres
Required total mud : 291,195.21litres
volume

6.2.9.2 Drilling fluid Characteristics and Operations


Drilling with seawater and sweeps of hi-vis mud is aimed at achieving good hole cleaning and
wellbore stability. Pre-hydrated Bentonite flocculated with lime will be diluted with seawater and
treated to the correct properties. A displacement slurry will be mixed and ready for pumping ahead
of cementing. Returns will be to seabed.

6.2.9.3 Mud Volume and Circulation Time


See Appendix for the detailed formula used in the mud calculations as well as the results obtained.
Table 6.7:- 26” Hole: Result of Mud Calculations

Measured Parameter 26” Hole


Volume
Total drill string volume (l) 5,648.77
Total Annular volume (l) 188,481.37
Total circulating volume (l) 194,130.14
Mud pit volume (l) @ 50% of total circulating volume 70,809.90
Total mud volume required (l) 291,195.21
Circulating Time- 2 pumps@ 50% each
Total pump output ((l/stroke) 39.40
Total pump circulation rate (l/min) 4,136.49
Total circulation time (min) 46.93

48
Table 6.8:- 26” Hole: Principal Additives for Sea Water and Spud Mud

Concentration, Quantity
Additive Function
lb/bbl Needed (kg)
Bentonite 30 Viscosity, filtration control 24,945.93
Seawater/freshwater 1 831.53
Lime 1 Flocculent 831.53
Caustic soda pH to 10.0
Source: Amoco Production Company drilling fluids manual

Table 6.9:- Typical Properties of the Inhibitive Gypsum Polymer Mud

Parameter Value
Mud weight 1.44
Plastic viscosity 16 – 18 cP
Yield point 10- 14 (lb/100 ft2)
API Filtrate 6-10 cm3
Funnel Viscosity 70 - 130 sec
Source: Amoco Production Company drilling fluids manual

6.2.9.4 Kick Control


As a contingency plan to when the diverter fails, a minimum of 70m kill mud at 1.4kg/l is stocked
while drilling through the surface without BOP stack installed.

6.2.9.5 Mud Pump


Three mud pumps are available for the given rig (Maersk Gallant). Two are used during the
drilling operation. The last pump will serve as backup. The pump specification is given below:

Pump output (l/stroke) = 0.0386𝑒𝐿𝐷2 (1)

Circulation flowrate (l/min) = 𝑛 × 𝑝𝑢𝑚𝑝 𝑜𝑢𝑡𝑝𝑢𝑡 (2)

Where;
𝐷 = liner diameter of stroke (in)

49
𝐿 = length of stroke (in)
𝑛 = maximum speed of pump (strokes/min)
𝑒 = efficiency of pump
Two pumps will be used to drill each phase. Each will run at 50% output. The third pump will
serve as backup for the rig.
Pump data (each):
Name - 3 X LTV Emsco FC-2200
Description - Single acting triplex driven by 2 each Hi-
torque DC motors
Maximum rated Horsepower
(hp) - 2,200
Length of stroke (in) - 10
Maximum liner diameter of
stroke (in) - 9
Strokes per minute
(strokes/min) - 150
Suction Connection (in) - 12
Discharge Connection - 5-1/8" 5,000 psi Flange
Gear Ratio - 3.512:1
Valve Pot: - API #8
Approximate Weight (ibs) - 64,815
Efficiency of pump - 0.90
Pump output @50% (l/stroke) 19.70
Pump circulation rate (l/min) 2,068.25

6.2.10 Fast line Tension


𝐹
𝑇𝑓𝑙 =
ηm ∗ N

Where;
F = Hook Load

50
N = Number of lines
ηm = reeving efficiency
165.3019
𝑇𝑓𝑙 =
0.782 ∗ 12
𝑇𝑓𝑙 = 17.6 𝑡𝑜𝑛𝑛𝑒𝑠

6.2.11 Cementing
Cemented Length in conductor casing = 160m MSL less water depth of 72m = 88m

Table 6.10:- Summary of slurry calculations

Total slurry volume 118.50 m3


Tail slurry volume 12.70 m3
Lead slurry volume 105.80 m3

Table 6.11:- Component and Additives of cement slurry

Lead Tail Total


Class G Cement 40.22 (943.2) 9.82 (230.4) 50.04 (1,173.5) Tons (sacks)
(2.5-4) % Pre-hydrated 3.49 0.24 3.74 Tons
Bentonite
Fresh water 91.71 9.49 101.2 m3
S.G. 1.28 1.54 - -
Mixing Time 2.77 0.17 2.94 Hours
Minimum Thickening - - 5.08 Hours
Time
Chemical Wash - - 3.18 m3
Spacer (46.25m) - - 10 m3
Total Required Water - - 127.80 m3
Antifoam (0.02gal/sk) 0.07 0.02 0.09 m3
Accelerator (2% BWOC) 18.86 4.61 23.47 Sacks
Cementing Procedure;
Annular Volume (Casing-Casing and Casing – open hole) – 113.47 m3
Volume from casing collar to shoe – 5.02 m3
The casing shall be cemented to the sea bed, i.e. 72 m MSL inside the 30” conductor casing.
Estimated quantity; 50% Excess in Open hole

51
After having run the 20 ‘’ casing, cementing procedure is;
• Pump 10 m3 of spacer of 1.23 S.G.
• Pump 105.80 m3 Class G lead slurry 1.28 S.G.
• Pump 12.70 m3 Class G Tail slurry 1.54 S.G.
• Displace cement with 93.44 m3 of 1.44 S.G. mud
Cement Composition: G cement + Chemical wash +Dispersant +Retarder +Bentonite+ FLAC
For Lead cement, 40.22 tons is mixed with 91.71m3 Fresh water with 4% pre-hydrated
Bentonite.
For Tail cement, 9.82 tons is used mixed with 9.49 m3 Fresh water with 2.5% pre-hydrated
Bentonite.

6.3 Phase 3 – Intermediate Casing 1 (17-1/2” Hole Section)

Table 6.11:- Basic Information of the First Intermediate Casing

Interval 610 – 1500 TVD MSL


Maximum Expected BHP 1.36 SG
Mud Weight 1.44 SG
Expected LOT 1.74 SG

6.3.1 Purpose of this phase


The purpose of this phase is to drill using Water based mud from the surface casing to the depth
of 1500m MSL and case-off the hole safely. The hole will pass through the Miocene - Pliocene
formations.

The section will involve directional drilling through the Nordland group, the section is planned to
have a build-up of 33.0ᵒ, having the kick-off point at 620m MSL. The casing shoe will be placed
at 1500m TVD MSL (1627.2m MD MSL).

A rotary steerable system will be used to drill this section to enable the kick-off at 620m MSL and
a building inclination of 1.0ᵒ/10m up to a depth of 932.078m TVD MSL (950m MD MSL), the

52
drilling thereafter will continue on a tangent (slant) to the section TD of 1500m TVD MSL
(1627.2m MD MSL). The section will be drilled with Synthetic based Mud (SBM).

6.3.2 Possible Challenges


• Inability to build inclination due to soft shallow formation of sandy clay with interbedded
sands.
• Down hole tool failures which can lead to tripping in and out the drill string
• Differential sticking of drill pipe for varying reasons such as mechanical sticking due to
presence of interbedded sand and shale in the NordLand group.
• Hole cleaning problems
• Well log data distortion due to the presence of pyrites (962m-1615m MSL).
• Formation collapse due to incompatibility of shale/clay with drilling mud.
• Expected mud losses in under compacted zones between 1 420 m - 2 410 m
• Risk of corrosion due to the presence of pyrite in the between 962 m and 1 615 m.

6.3.3 Barriers
The drilling fluid (1.44 SG, WBM) will be the primary control; A Blow out Preventer will be
installed to control the borehole pressure from the underlying formation.

6.3.4 Drilling Procedure


• Drill directly with a 17-1/2" Roller cone bit to TD of 1500m MSL with reduced ROP
(<15m/hr).
• The accepted angle of inclination in 33ᵒ and the maximum permissible angle of deviation
is (Bit Walk) is 36ᵒ
• MWD (GR/Resistivity/Density/Sonic) will be used continuously while drilling the 17-1/2"
hole. No wire line logging of section is required
• Cuttings will be taken at every 10m interval.
• No coring activity for this section

6.3.5 Kick-off Procedure


The kick-off will take place at depth 620m MSL and inclination will be less than 1ᵒ o this depth.
A GBU of 1ᵒ/10m will be used; Survey would be performed until magnetic interference from
preceding casing is off. Afterwards, MWD survey will be performed on every stand drilled.

53
6.3.6 Drill Strings

Table 6.13:- Summary of Drilling String Parameters for Phase 2

Linear OD OD ID Cumulative
Length
Element Grade Weight No Max Body Body Length
(m)
(Kg/m) (in) (in) (in) (m)
Roller Cone Bit IADC CODE: 535 - 1 17-1/2 - - - -
Motor/ Bit sub + Float
- - 1 - 9 - - -
Valve
Stabilizer - - 3 - 17.25 - - -
MWD - - 1 - - - - -
Non- Magnetic Drill
- 323.18 5 - 9-1/2 3 9.144 45.72
Collar
Drill Collar API SPEC 323.18 3 - 9-1/2 3 9.144 27.432
Hydraulic Jar API SPEC - 1 - 9-1/2 - -
Drill Collar API SPEC 218.77 1 - 8 3 9.144 9.144
HWDP NC 50 74.67 1 - 5 3 9.144 9.144
Drill Pipe G105 NC 50 (XH) 32.55 174 - 5 4.276 9.144 1591.056

6.3.7 Drilling Parameters


The hole is to be drilled to the depth of 1500m MSL. The parameters to be considered involve the
following:
• Bit type
• Nozzle Selection
• Maximum Overpull
• WOB

6.3.7.1 Bit type


The Bit selection is made based on the nature of the formations to be encountered. The drill bit
parameters are shown below:

Table 6.14:- Drilling Parameters (Bit Type)

Roller Cone, Insert


Type of Bit
Tooth
Diameter 17-1/2"

54
IADC Code 535

6.3.7.2 Nozzle Selection


The basis of the calculation of the flow rate is the cutting settling velocity in the annulus. The
following rule is recommended:
● For soft formation annular velocity between 30 and 40 m/mim
● For hard formation annular velocity between 25 and 30 m/min
Annular Mud Velocity = 35 m/min
Annular Capacity OH – DP = 141.9 l/m DDH D14
𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐹𝑙𝑜𝑤 𝑟𝑎𝑡𝑒, 𝑄 = 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦, 𝐶𝑎 × 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦, 𝑉𝑎
𝑙 𝑚 𝐿
∴ 𝑄 = 141.9 × 35 = 4966.5
𝑚 𝑚𝑖𝑛 𝑚𝑖𝑛

The annular flow rate obtained is rather high.


The Maersk Gallant rig has 3 pumps (3 X LTV Emsco FC – 2200) single acting with a power of
2200HP rated for 7500psi.
Taking an overall pumping efficiency of 90% (η= 0.9)

Using
𝑃×𝑄 1
𝑃𝐻𝑃 = ×
450 
Where
P= Stand pipe pressure in bar = 7500psi = 517.098bar
Q= Flowrate in l/min
η = pumping efficiency (90%)

Making use of two pumps and allowing one to be on standby, the combined horsepower will be
4400hp.
Calculating the flowrate that will be achieved by the pump
𝑃𝐻𝑃 ∗ 450 ∗ 
𝑄=
𝑃

55
4400 ∗ 450 ∗ 0.9
𝑄=
517.098
𝑄 = 3446.155 𝑙/𝑚𝑖𝑛
The flowrate achieved by the pump is smaller than the required for good hole cleaning; therefore
we will have to stop at various intervals to clean the hole.
Using
𝐹𝑅
𝑉=
38.71 ∗ 𝑇𝐹𝐴
Where
FR= Flow rate in liters/min
V= Mud Velocity meters/sec
TFA = Total Flow area, 𝒊𝒏𝟐
Making use of a mud velocity of 110m/s
𝐹𝑅
𝑇𝐹𝐴 =
38.71 ∗ 𝑉
3446.155
𝑇𝐹𝐴 =
38.71 ∗ 110
𝑇𝐹𝐴 = 0.8093 𝒊𝒏𝟐
From DDH G56 we choose a drilling Bit of 3 (Three) nozzles 18-19-19, having a total area of
0.8023 𝒊𝒏𝟐 .

6.3.7.3 Maximum Overpull

Table 6.15:- Showing the calculation of the drill string weight

Linear
Length Buoyancy Total Total Weight
Weight
(m) Factor Weight (kg) (T)
(Kg/m)
Drill Collar 323.18 82.296 0.817 26596.42128 26.59642128
Drill Collar 218.77 9.144 0.817 2000.43288 2.00043288
HWDP 74.67 9.144 0.817 682.78248 0.68278248
Drill Pipe 32.55 1591.056 0.817 51788.8728 51.7888728
Total = 81.06850944

Maximum Overpull (MOP)

56
MOP = Maximum Tension on DP – weight of Drill String
Weight of Drill String in mud = (DC weight + HWDP weight + DP weight) * buoyancy factor
Total Drill stem Weight =81.06 Tonnes
Weight of Drill String in mud = 81.06 Tonnes * 0.817 = 66.23Tonnes
Tensile Yield Strength on DP = 193.8kdaN DDH B15
𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟 = 90%
≈ 0.9
𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 = 𝑇𝑒𝑠𝑖𝑙𝑒 𝑦𝑖𝑒𝑙𝑑 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ × 𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟
= 0.9 𝑥 193.8
= 174.42 𝑘𝑑𝑎𝑁
≈ 177.8𝑇
Maximum Overpull = 𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 − Total Drillstem Weight
= 177.8𝑇 − 81.06 𝑇
= 96.74𝑇

Since this phase is soft


𝑊𝑂𝐵 ≈ 1 𝑡𝑜𝑛 𝑝𝑒𝑟 𝑖𝑛𝑐ℎ 𝑜𝑓 𝑏𝑖𝑡 𝑖𝑛 𝑠𝑜𝑓𝑡 𝑓𝑜𝑟𝑚𝑎𝑡𝑖𝑜𝑛
𝑡𝑜𝑛𝑠
→ 𝑊𝑂𝐵 = 17.5′′ × 1 𝑥 cos 33.06 = 14.67𝑡𝑜𝑛𝑠
𝑖𝑛𝑐ℎ
𝑐𝑜𝑛𝑣𝑒𝑟𝑡𝑖𝑛𝑔 𝑡ℎ𝑒 𝑊𝑂𝐵 𝑡𝑜 𝑑𝑎𝑁;
𝑑𝑎𝑁
𝑊𝑂𝐵 = 14.67 × 0.981 × 1000
𝑘𝑔
∴ 𝑊𝑂𝐵 = 14391.3𝑑𝑎𝑁 = 𝟏𝟒. 𝟑𝟗𝟏𝒌𝒅𝒂𝑵

6.3.8 Power Requirement


To determine the rig power requirement, the powers for the following systems are evaluated:
4. Hydraulic System – Hydraulic Power
5. Hoisting System – Hoisting Power
6. Rotary System – Rotary Power
Pressure loss calculation

57
DP – L2, L5

HWDP – L2’,
L5 ’

DC – L3, L4

Figure 6.2:- Drilling string schematics for phase two

𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑
𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿′2 𝑁3 +𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿′5 𝑁5 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑
𝑃𝑑 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝 𝑖𝑛 𝑛𝑜𝑧𝑧𝑙𝑒𝑠 𝑓𝑜𝑟 𝑑 = 1, (𝑘𝑃𝑎)
𝑘𝑔⁄
𝑑 = 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑔𝑟𝑎𝑣𝑖𝑡𝑦, ( 𝑙)
𝑁1 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑒𝑞𝑢𝑖𝑚𝑒𝑛𝑡, (𝑘𝑃𝑎⁄100𝑚)

𝑁2 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁3 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟𝑠, (𝑘𝑃𝑎⁄100𝑚 )

𝑁4 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟 𝑎𝑛𝑛𝑢𝑙𝑢𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁5 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑎𝑛𝑛𝑢𝑙𝑢𝑠(𝑘𝑃𝑎⁄100𝑚)

𝐿2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)


𝐿′2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)

58
𝐿3 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿4 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿′5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
Typically Plastic viscosity is about twice of mud weight in pounds per gallon
Therefore:
𝑃𝑉 = 2 × 1.44 × 8.33
𝑷𝑽 = 𝟐𝟑. 𝟗𝟗 𝑪𝒑

Table 6.16:- Showing the Pressure loss calculation

Parameters Units DDH

Nozzle 18-18-19
N1 426.1541 kPa/100m G30
N2 267.46 kPa/100m G41
N3 1324.3 kPa/100m G46
N4 1 kPa/100m G62
N5 1 kPa/100m G67
L2 1591.056 m
L2' 9.144 m
L3 82.296 m
L4 82.296 m
L5' 9.144 m
L5 1591.056 m
Pd 10779 Kpa G52
d 1.44
B 2.53 G24
Case: 3
Q 3446.155 l/min
Ptotal= 30472.43 Kpa

Pumping requirement:
• Assuming a volumetric efficiency ηv=0.97
• Assuming a mechanical efficiency ηm=0.90

59
6.3.8.1 Hydraulic Power

Hydraulic power =
𝑃×𝑄
𝑃𝐻𝑃 (ℎ𝑝) =
44750
30472.43 × 3446.155
𝑃𝐻𝑃 (ℎ𝑝) =
44750
𝑃𝐻𝑃 (ℎ𝑝) = 2346.65 ℎ𝑝
6.3.8.1.1 Mechanical Power

𝐻𝑦𝑑𝑟𝑎𝑢𝑙𝑖𝑐 𝑃𝑜𝑤𝑒𝑟
Mechanical Power= 𝜂𝑚

2346.65
=
0.9
= 2607.39 ℎ𝑝

6.3.8.2 Hoisting Power


The hoisting power is evaluated for each of the phases using the equation below.
𝐹×𝑉 1
𝑃𝐻𝑃 = ×
77.5 

Where:
F, Total Hoisted Weight (String + Block +Hook + Over pull)
V, Pulling up Speed, meters/sec
, Overall Hoisting Efficiency

Assumptions
Weight of 25 Tons for Block + Hook,
Speed of 0.3 meters/second
Using 12 lines and roller bearing, we obtain a reeving efficiency of 0.782 (DDH F3)
From previous calculations,
String load in air = 81.06 Tons
Margin of Over pull = 96.74 𝑇𝑜𝑛𝑛𝑒𝑠

60
Therefore:
F = 81.06+25+96.74
F = 202.8 Tons (202.8 X103 kg)
202.8 × 103 × 0.3 1
𝑃𝐻𝑃 = ×
77.5 0.782
𝑃𝐻𝑃 = 1003.9 𝐻𝑃

6.3.8.3 Rotation Power


The rotation power is evaluated for each of the phases using the equation below.
𝐶 × 𝑅𝑃𝑀 1
𝑃𝐻𝑃 = ×
712 

Where
C, Torque (daN.m)
, Rotating Efficiency (0.9)
𝐶 = 𝑆𝑎𝑓𝑒𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 × 𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑇𝑜𝑟𝑞𝑢𝑒
The minimum torque is obtained from DDH B22
Minimum Torque for a 5” X 4.276” Drill Pipe with nominal weight of 32.55 kg/m is (connection
= API, NC 50).
Minimum Make up Torque = 2,969 daN.m DDH B22
Using a safety factor of 80%,
𝐶 = 0.8 × 2969
𝐶 = 2375.2 𝑑𝑎𝑁. 𝑚

The Rotation per Minute (RPM) is assumed to be 130


The Rotation Power required is
2375.2 × 130 1
𝑃𝐻𝑃 = ×
712 0.9
𝑃𝐻𝑃 = 481.86 𝐻𝑃

61
6.3.8.4 Total Power Requirement

Total power = Pump power + Hoisting Power + Rotation Power


Total Power = 4400 + 1003.9 + 481.86
Total Power = 5885.76HP

6.3.9 Drilling Lines

We choose a 1.5” Wire diameter, 6 X 195 RR IWRC

6.3.9.1 Fast line Tension


𝐹
𝑇𝑓𝑙 =
ηm ∗ N
Where;
F = Hook Load
N = Number of lines
ηm = reeving efficiency
202.8 T
𝑇𝑓𝑙 =
0.782 ∗ 12
𝑻𝒇𝒍 = 𝟐𝟏. 𝟔 𝑻𝒐𝒏𝒏𝒆𝒔

6.3.10 Drilling Fluids


Hole size : 13 3/8”
Interval : 610m – 1627.2m measured depth
Mud type : Inhibitive gypsum polymer mud
Section length drilled : 1,017.2m
Drilled well volume : 157,845.92 litres
Required mud volume: 446,777.21 litres
Mud weight : 1.44

62
Table 6.17:- 13 3/8 ” Hole: Results of Mud Volume Calculations

Measured Parameter 26” Hole


Volume
Total drill string volume (l) 14,120.72
Total Annular volume (l) 283,689.70
Total circulating volume (l) 297,851.48
Mud pit volume (l) @ 50% of total circulating volume 148,925.74
Total mud volume required (l) 446,777.21
Circulating Time- 2 pumps@ 50% each
Total pump output ((l/stroke) 39.40
Total pump circulation rate (l/min) 4,136.49
Total circulation time (min) 71.68

6.3.10.1Drilling fluid Characteristics and Operations


The drilling fluid used for this section is aimed at achieving good cleaning capability, hole
stability and mud loss while maintaining inhibition for the clay/ shale sections. Gypsum provides
Ca++ ion for base exchange of clays from Na+ to Ca++ for inhibition.
Table 6.18:- 13 3/8 ” Hole: Principal Additives for Inhibitive Gypsum Polymer Mud

Quantity
Concentration,
Additive Function Needed
lb/bbl slurry
(kg)
Bentonite 20 Viscosity, filtration control 25,486.74
Lignosulfonate 4 Deflocculant 5,097.35
Gypsum 4 Inhibition, alkalinity control 5,097.35
Caustic Soda pH 9.5 - 11.0 Alkalinity control
Caustic Potash Inhibition, alkalinity control
DESCO (sulfonated tannin) Deflocculant 2,548.67
Starch 4 Filtration control 5,097.35

63
Viscosity (increase in yield 318.58
PAC 0.25
point), Filtration Control
Barite 190 Weighting agent 242,124.03
Source: Amoco Production Company drilling fluids manual

Table 6.19:- Typical Properties of the Inhibitive Gypsum Polymer Mud

Parameter Value
Mud weight 1.44
Plastic 15-20 cP
viscosity
Yield point 2-15 (lb/100 ft2)
API Filtrate 6-8 cm3
pH 2-3
Source: Amoco Production Company drilling fluids manual

6.3.10.2Kick Control
Kick is controlled by adopting the driller’s method;
𝑆𝐼𝐷𝑃𝑃×10.2 (3)
𝐾𝑖𝑙𝑙𝑀𝑢𝑑 𝑊𝑡. = 𝑃𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑚𝑢𝑑 𝑤𝑡 + +
𝑑

𝑜𝑣𝑒𝑟𝑘𝑖𝑙𝑙 𝑠𝑎𝑓𝑒𝑡𝑦 𝑚𝑎𝑟𝑔𝑖𝑛


Where;
𝑆𝐼𝐷𝑃𝑃 = shut-in drill pipe pressure (bar)
𝑑 = depth (m)
𝑜𝑣𝑒𝑟𝑘𝑖𝑙𝑙 𝑠𝑎𝑓𝑒𝑡𝑦 𝑚𝑎𝑟𝑔𝑖𝑛 = 6.89476 bar

6.3.11 Cementing Procedure


Cemented Length in Surface casing = 50m

Table 6.20:- Summary of cement calculations

Total slurry volume 104.98 m3


Tail slurry volume 5.69 m3
Lead slurry volume 99.29 m3

64
Table 6.21:- Component and Additives of the cement slurry

Lead Tail Total


Class G Cement 76.82 6.12 (145.53) 82.94 (1,945) Tons (sacks)
(1,801.5)
(0.75-2.5) % Pre- 1.90 0.05 1.95 Tons
hydrated Bentonite
Fresh water 74.19 3.72 77.91 m3
S.G. 1.54 1.74 - -
Mixing Time 2.60 0.07 2.67 Hours
Minimum Thickening - - 5.09 Hours
Time
Chemical Wash - - 3.18 m3
Spacer (108.3m) - - 10 m3
Retarder (0.1-0.5) % 0.08 0.03 0.11 Tons
BWOC
Loss Circulation 0.24 0.02 0.26 Tons
Additive (0.3-0.4) %
BWOC
Total Required Water - - 99.85 m3
Antifoam (0.01 – 0.02) 0.07 0.01 0.08 m3
gal/sk

Annular Volume (Casing-Casing and Casing – open hole) – 102.83 m3


Volume from casing collar to shoe – 2.14 m3
Cementing Procedure;
The casing shall be cemented to the 50m into the 20” surface casing, i.e. 560m MSL
Estimated quantity; 50% Excess in Open hole
After having run the 13 3/8” casing, cementing procedure is;
• Pump 10 m3 of spacer 0f 1.48 S.G.
• Pump 99.29 m3 Class G lead slurry 1.54 S.G.
• Pump 5.69 m3 Class G Tail slurry 1.74 S.G.
• Displace cement with 119.14 m3 of 1.64 S.G. mud
Cement Composition: G cement + Chemical wash +Dispersant +Retarder +Bentonite+ FLAC

65
For Lead cement, 76.82 tons is mixed with 74.19 m3 Fresh water with 2.5% pre-hydrated
Bentonite.
For Tail cement, 6.12 tons is mixed 3.79 m3 Fresh water with 0.75% pre-hydrated Bentonite.

6.4 Phase 4 – Intermediate Casing 2 (12-1/4” Hole Section)


Table 6.22:- Basic Information of the Second Intermediate Casing

Interval 1500 – 2500 TVD MSL


Maximum Expected BHP 1.58 SG
Mud Weight 1.64 SG
Expected LOT 1.868 SG

6.4.1 Purpose of this phase


The purpose of this phase is to drill using Water based mud from the first Intermediate casing to
the depth of 2500m MSL and case-off the hole safely. The hole will pass through the Eocene –
Oligocene- Miocene formations.

6.4.2 Possible Challenges


• Bit wear and tear due to increasing hardness of formation as we drill deeper
• Hole cleaning problems
• Well log data distortion due to the presence of pyrites (962m-1615m MSL).
• Differential sticking of drill pipe for varying reasons.
• Formation collapse due to incompatibility of shale/clay with drilling mud.
• Expected mud losses in under compacted zones.
• Risk of corrosion due to the presence of pyrite in the formation.

6.4.3 Barriers
The drilling fluid (1.64 SG, WBM) will be the primary control; A Blow out Preventer will be
installed to control the borehole pressure from the underlying formation.

6.4.4 Drilling Procedure


• Drill directly with a 12-1/4" string to TD of 2500m MSL with reduced ROP (<15m/hr).
• MWD (GR/Resistivity/Density/Sonic) will be used continuously while drilling the 12-1/4”
hole. No wire line logging of section is required
• Cuttings will be taken at every 10m interval.

66
• No coring activity for this section
• This is a slant section of the well, therefore we limit the deviation of the well to 1ᵒ from the
trajectory

6.4.5 Kick-off Procedure


No further Kick-off, we will maintain the angle generated by the GBU.

6.4.6 Drill Strings


Table 6.23: Summary of Drilling String Parameters for Phase 4

Linear OD ID Cumulative
OD Max Length
Element Grade Weight No Body Body Length
(in) (m)
(Kg/m) (in) (in) (m)
Roller Cone Bit IADC CODE: 725 - 1 12-1/4 - - - -
Bit sub + Float Valve - - 1 - 9 - - -
Stabilizer - - 3 - 12-1/4 - - -
MWD - - 1 - - - - -
Non- Magnetic Drill
- 323.18 5 - 9-1/2 3 9.144 45.72
Collar
Drill Collar API SPEC 323.18 6 - 9-1/2 3 9.144 54.864
Hydraulic Jar API SPEC - 1 - 7.75 - - -
Drill Collar API SPEC 323.18 1 - 8 3 9.144 9.144
HWDP NC 50 74.67 1 - 5 3 9.144 9.144
Drill Pipe G105 NC 50 (XH) 32.55 302 - 5 4.276 9.144 2761.488

6.4.7 Drilling Parameters


The hole is to be drilled to the depth of 2500m MSL. The parameters to be considered involve the
following:
• Bit type
• Nozzle Selection
• Maximum Overpull
• WOB

67
6.4.7.1 Bit type
The Bit selection is made based on the nature of the formations to be encountered. The drill bit
parameters are shown below

Table 6.24:- Drilling Parameters (Bit Type)

Type of Bit Roller Cone, Insert Tooth


Diameter 12-1/4"
IADC Code 725

6.4.7.2 Nozzle Selection


The basis of the calculation of the flow rate is the cutting settling velocity in the annulus. The
following rule is recommended:
● For soft formation annular velocity between 30 and 40 m/mim
● For hard formation annular velocity between 25 and 30 m/min
Annular Mud Velocity = 30 m/min
Annular Capacity OH – DP = 62.7 l/m DDH D14
𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐹𝑙𝑜𝑤 𝑟𝑎𝑡𝑒, 𝑄 = 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦, 𝐶𝑎 × 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦, 𝑉𝑎
𝑙 𝑚 𝐿
∴ 𝑄 = 62.7 × 30 = 1881
𝑚 𝑚𝑖𝑛 𝑚𝑖𝑛

Using
𝐹𝑅
𝑉=
38.71 ∗ 𝑇𝐹𝐴
Where
FR= Flow rate in liters/min
V= Mud Velocity meters/sec
TFA = Total Flow area, 𝒊𝒏𝟐
Making use of a mud velocity of 100m/s
1881
𝑇𝐹𝐴 =
38.71 ∗ 𝑉
1881
𝑇𝐹𝐴 =
38.71 ∗ 100
𝑇𝐹𝐴 = 0.48592 𝒊𝒏𝟐

68
From DDH G56 we choose a drilling Bit of 3 (Three) nozzles 14-14-15, having a total area of
0.4732 𝒊𝒏𝟐 .

6.4.7.3 Maximum Overpull

Table 6.25:- Showing the calculation of the drill string weight

Linear
Length Buoyancy Total Total Weight
Weight
(m) Factor Weight (kg) (T)
(Kg/m)
Drill Collar 323.18 100.584 0.791 32506.73712 32.50673712
Drill Collar 218.77 9.144 0.791 2000.43288 2.00043288
HWDP 74.67 9.144 0.791 682.78248 0.68278248
Drill Pipe 32.55 2761.488 0.791 89886.4344 89.8864344
Total = 125.0763869
Maximum Overpull (MOP)
MOP = Maximum Tension on DP – weight of Drill String
Weight of Drill String in mud = (DC weight + HWDP weight + DP weight) * buoyancy factor
Total Drill stem Weight =125.1 Tonnes
Weight of Drill String in mud = 125.1 Tonnes * 0.791 = 98.95 Tonnes
Tensile Yield Strength on DP = 193.8kdaN
𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟 = 90%
≈ 0.9
𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 = 𝑇𝑒𝑠𝑖𝑙𝑒 𝑦𝑖𝑒𝑙𝑑 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ × 𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟
= 0.9 𝑥 193.8
= 174.42 𝑘𝑑𝑎𝑁
≈ 177.8𝑇
Maximum Overpull = 𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 − Total Drillstem Weight
= 177.8𝑇 − 98.95 T
= 78.85𝑇

6.4.7.4 WOB

𝑊𝑂𝐵 ≈ 2 𝑡𝑜𝑛 𝑝𝑒𝑟 𝑖𝑛𝑐ℎ 𝑜𝑓 𝑏𝑖𝑡 𝑖𝑛 𝑠𝑜𝑓𝑡 𝑓𝑜𝑟𝑚𝑎𝑡𝑖𝑜𝑛

69
𝑡𝑜𝑛𝑠
→ 𝑊𝑂𝐵 = 12 − 1/4′′ × 2 𝑥 cos 33.06 = 20.53𝑡𝑜𝑛𝑠
𝑖𝑛𝑐ℎ
𝑐𝑜𝑛𝑣𝑒𝑟𝑡𝑖𝑛𝑔 𝑡ℎ𝑒 𝑊𝑂𝐵 𝑡𝑜 𝑑𝑎𝑁;
𝑑𝑎𝑁
𝑊𝑂𝐵 = 20.53 × 0.981 × 1000
𝑘𝑔
∴ 𝑊𝑂𝐵 = 20134𝑑𝑎𝑁 = 𝟐𝟎. 𝟏𝟑𝟒𝒌𝒅𝒂𝑵

6.4.8 Power Requirement


To determine the rig power requirement, the powers for the following systems are evaluated:
• Hydraulic System – Hydraulic Power
• Hoisting System – Hoisting Power
• Rotary System – Rotary Power
Pressure loss calculation

DP – L2, L5

HWDP – L2’, L5’

DC – L3, L4

Figure 6.3:- Drilling string schematics for phase three

𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑

70
𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿′2 𝑁3 +𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿′5 𝑁5 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑
𝑃𝑑 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝 𝑖𝑛 𝑛𝑜𝑧𝑧𝑙𝑒𝑠 𝑓𝑜𝑟 𝑑 = 1, (𝑘𝑃𝑎)
𝑘𝑔⁄
𝑑 = 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑔𝑟𝑎𝑣𝑖𝑡𝑦, ( 𝑙)
𝑁1 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑒𝑞𝑢𝑖𝑚𝑒𝑛𝑡, (𝑘𝑃𝑎⁄100𝑚)

𝑁2 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁3 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟𝑠, (𝑘𝑃𝑎⁄100𝑚 )

𝑁4 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟 𝑎𝑛𝑛𝑢𝑙𝑢𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁5 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑎𝑛𝑛𝑢𝑙𝑢𝑠(𝑘𝑃𝑎⁄100𝑚)

𝐿2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)


𝐿′2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿3 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿4 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿′5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
Typically Plastic viscosity is about twice of mud weight in pounds per gallon
Therefore:
𝑃𝑉 = 2 × 1.64 × 8.33
𝑷𝑽 = 𝟐𝟕. 𝟑 𝑪𝒑

Table 6.26:- Showing the Pressure Loss calculation

Parameters Units DDH

Nozzle 14-14-15
N1 136.34 kPa/100m G30
N2 90.1 kPa/100m G40
N3 445.02 kPa/100m G45
N4 36.24 kPa/100m G62
N5 2 kPa/100m G67
L2 2761.488 m
L2' 9.144 m

71
L3 109.728 m
L4 109.728 m
L5' 9.144 m
L5 2761.488 m
Pd 5917 Kpa G48
d 1.64
B 2.89 G26
Case: 3
Q 1881 l/min
Ptotal= 19092.40027 Kpa

Pumping requirement:
• Assuming a volumetric efficiency ηv=0.97
• Assuming a mechanical efficiency ηm=0.90

6.4.8.1 Pump Power

The Maersk Gallant rig has 3 pumps (3 X LTV Emsco FC – 2200) single acting with a power of
2200HP rated for 7500psi.
Taking an overall pumping efficiency of 90% (η= 0.9)

Using
𝑃×𝑄 1
𝑃𝐻𝑃 = ×
450 
Where
P= Stand pipe pressure in bar
Q= Flowrate in l/min
η = pumping efficiency (90%)

Standpipe pressure = 19092.40027 Kpa = 191 bar


191 × 1881 1
𝑃𝐻𝑃 = ×
450 0.9
𝑃𝐻𝑃 = 887.1 ℎ𝑝

72
6.3.8.2 Hydraulic Power

Hydraulic power =
𝑃×𝑄
𝑃𝐻𝑃 (ℎ𝑝) =
44750
19092.40027 × 1881
𝑃𝐻𝑃 (ℎ𝑝) =
44750
𝑃𝐻𝑃 (ℎ𝑝) = 802.52 ℎ𝑝

6.4.8.3 Mechanical Power

𝐻𝑦𝑑𝑟𝑎𝑢𝑙𝑖𝑐 𝑃𝑜𝑤𝑒𝑟
Mechanical Power= 𝜂𝑚

802.52
=
0.9
= 891.7 ℎ𝑝

6.4.8.4 Hoisting Power


The hoisting power is evaluated for each of the phases using the equation below.
𝐹×𝑉 1
𝑃𝐻𝑃 = ×
77.5 

Where:
F, Total Hoisted Weight (String + Block +Hook + Over pull)
V, Pulling up Speed, meters/sec
, Overall Hoisting Efficiency

Assumptions
Weight of 25 Tons for Block + Hook,
Speed of 0.3 meters/second
Using 12 lines and roller bearing, we obtain a reeving efficiency of 0.782 (DDH F3)
From previous calculations,
String load in air = 125.1 Tons
Margin of Over pull = 78.85 𝑇𝑜𝑛𝑛𝑒𝑠

73
Therefore:
F = 125.1 +25+78.85
F = 228.95 Tons (228.95 X103 kg)
230.054 × 103 × 0.3 1
𝑃𝐻𝑃 = ×
77.5 0.782
𝑃𝐻𝑃 = 1133.32 𝐻𝑃

6.4.8.5 Rotation Power


The rotation power is evaluated for each of the phases using the equation below.
𝐶 × 𝑅𝑃𝑀 1
𝑃𝐻𝑃 = ×
712 

Where
C, Torque (daN.m)
, Rotating Efficiency (0.9)
𝐶 = 𝑆𝑎𝑓𝑒𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 × 𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑇𝑜𝑟𝑞𝑢𝑒
The minimum torque is obtained from DDH B22
Minimum Torque for a 5” X 4.276” Drill Pipe with nominal weight of 32.55 kg/m is (connection
= API, NC 50).
Minimum Make up Torque = 2,969 daN.m DDH B22
Using a safety factor of 80%,
𝐶 = 0.8 × 2969
𝐶 = 2375.2 𝑑𝑎𝑁. 𝑚

The Rotation per Minute (RPM) is assumed to be 120


The Rotation Power required is
2375.2 × 120 1
𝑃𝐻𝑃 = ×
712 0.9
𝑃𝐻𝑃 = 444.79 𝐻𝑃

74
6.4.8.6 Total Power Requirement

Total power = Pump power + Hoisting Power + Rotation Power


Total Power = 887.1 + 1133.32 + 444.79
Total Power = 2465.2HP

6.4.8.7 Drilling Lines


We choose a 1.5” Wire diameter, 6 X 195 RR IWRC

6.4.8.8 Fast line Tension


𝐹
𝑇𝑓𝑙 =
ηm ∗ N
Where;
F = Hook Load
N = Number of lines
ηm = reeving efficiency
228.95
𝑇𝑓𝑙 =
0.782 ∗ 12
𝑻𝒇𝒍 = 𝟐𝟒. 𝟒 𝒕𝒐𝒏𝒏𝒆𝒔

6.4.9 Drilling Fluids


Mud type : Inhibitive gypsum polymer mud
Interval : 1627.2m - 2819.5m TVD MSL
Section length drilled : 1,192.3m
Drilled well volume : 90,658.52 litres
Required mud volume: 377,630.51 litres

Table 6.27:- 9 5/8 ” Hole: Results of Mud Volume Calculations

2nd Intermediate
Measured Parameter
Hole
Volume
Total drill string volume (l) 25,533.56.91
Total Annular volume (l) 226,220.11

75
Total circulating volume (l) 251,753.67
Mud pit volume @ 50% of total circulating volume (l) 125,876.84
Total volume needed (l) 377,630.51
Circulating Time- 2 pumps@ 50% each
Total pump output ((l/stroke) 39.40
Total pump circulation rate (l/min) 4,136.49
Total circulation time (min) 60.86

6.4.9.1 Drilling fluid Characteristics and Operations


The drilling fluid used for this section is aimed at achieving good cleaning capability, hole stability
and mud loss while maintaining inhibition for the clay/ shale sections. Gypsum provides Ca++ ion
for base exchange of clays from Na+ to Ca++ for inhibition.

Table 6.28:- 9 5/8 ”Hole: Principal Additives for Inhibitive Gypsum Polymer Mud

Quantity
Concentration,
Additive Function Needed
lb/bbl slurry
(kg)
Bentonite 20 Viscosity, filtration control 21,503.70
Lignosulfonate 4 Deflocculant 4,300.74
Gypsum 4 Inhibition, alkalinity control 4,300.74
Caustic Soda pH 9.5 - 11.0 Alkalinity control
Caustic Potash Inhibition, alkalinity control
DESCO (sulfonated
Deflocculant 2,150.37
tannin)
Starch 4 Filtration control 4,300.74
Viscosity (increase in yield
PAC 0.25 268.80
point), Filtration Control
As required for
Barite Weighting agent 263,420.36
density
Source: Amoco Production Company drilling fluids manual

76
Table 6.29:- Typical Properties of the Inhibitive Gypsum Polymer Mud

Parameter Value
Mud weight 1.64
Plastic 15-20 cP
viscosity
Yield point 2-15 (lb/100 ft2)
API Filtrate 6-8 cm3
pH 2-3
Source: Amoco Production Company drilling fluids manual

6.4.9.1 Kick Control


Kick is controlled by adopting the driller’s method as stated earlier.

6.4.10 Cementing Programme


Cemented Length in Intermediate Casing II = 30m

Table 6.30:- Summary of cement calculations

Total slurry volume 59.82 m3


Tail slurry volume 2.84 m3
Lead slurry volume 56.99 m3

Table 6.31:- Component and Additives of the cement slurry

Lead Tail Total


Class G Cement 61.34 3.60 (84.45) 64.94 (1,523) Tons (sacks)
(1,438.52)
(0.1-1) % Pre-hydrated 0.49 0.005 0.495 Tons
Bentonite
Fresh water 37.33 1.69 39.02 m3
S.G. 1.74 1.87 - -
Mixing Time 1.49 0.04 1.53 Hours
Minimum Thickening - - 3.81 Hours
Time

77
Chemical Wash - - 3.18 m3
Spacer (100m) - - 3.12 m3
Retarder (0.1-1.5) % 0.06 0.05 0.11 Tons
BWOC
Loss Circulation 0.18 0.01 0.19 Tons
Additive (0.3-0.4) %
BWOC
Total Required Water - - 53.18 m3
Antifoam (0.01 – 0.02) 0.05 0.01 0.06 m3
gal/sk

Annular Volume (Casing-Casing and Casing – open hole) – 58.76 m3


Volume from casing collar to shoe – 1.07 m3
Cementing Procedure;
The casing shall be cemented to the 30m into the 13 3/8” casing, i.e. 1654.1m MDMSL
Estimated quantity; 50% Excess in Open hole
After having run the 9 5/8” casing, cementing procedure is;
• Pump 3.12 m3 of spacer
• Pump 56.99 m3 Class G lead slurry 1.74 S.G.
• Pump 2.84 m3 Class G Tail slurry 1.87 S.G.
• Displace cement with 105.70 m3 of 1.44 S.G. mud
Cement Composition: G cement + Chemical wash +Dispersant +Retarder +Bentonite+ FLAC
For Lead cement, 76.82 tons is mixed with 74.19 m3 Fresh water with 1% pre-hydrated Bentonite.
For Tail cement, 6.12 tons is mixed with 3.79 m3 Fresh water with 0.1% pre-hydrated Bentonite.

6.5 Phase 4 –Production Casing 2 (8-1/2” Hole Section)

Table 6.32: Basic Information of the Production Casing

Interval 2,500 – 3,250 TVD MSL


Maximum Expected BHP 1.34 SG
Mud Weight 1.44 SG
Expected LOT 1.98 SG

78
6.5.1 Purpose of this phase
The purpose of this phase is to drill using Synthetic based mud (SBM) from the second
intermediate casing to the depth of 3250m MSL and case-off the hole safely. The hole will pass
through the Rogaland group and the Shetland group (Paleocene – Early Eocene and the Danian
Formations).
The hole section will be passing through the reservoir.

6.5.2 Possible Challenges


• Bit wear and tear due to increasing hardness of formation as we drill deeper
• Hole cleaning problems
• Differential sticking problems due to the presence of a chalky and muddy formation

6.5.3 Barriers
The drilling fluid (1.44 SG, SBM) will be the primary control; A Blow out Preventer will be
installed to control the borehole pressure from the underlying formation

6.5.4 Drilling Procedure


• Drill directly with an 8-1/2" PDC Bit to TD of 3250m MSL with reduced ROP (<15m/hr).
• MWD (GR/Resistivity/Density/Sonic) will be used continuously while drilling the 8-1/2”
hole. No wire line logging of section is required
• Cuttings will be taken at every 10m interval.
• Coring will be done from the depth of 2500m TVD MSL to 3250m TVD MSL
• This is a vertical section of the well, therefore we limit the deviation of the well to 1ᵒ from
the trajectory

6.5.5 Kick-off Procedure


No further Kick-off, we will maintain the angle generated by the GBU.

6.5.6 Drill Strings

Table 6.33:- Summary of Drilling String Parameters for Phase 4

Linear OD ID Cumulative
OD Max Length
Element Grade Weight No Body Body Length
(in) (m)
(Kg/m) (in) (in) (m)
IADC CODE:
- 1 8-1/2 - - - -
PDC Bit M432

79
Bit sub + Float
- - 1 - 6-3/4 - - -
Valve
Stabilizer - - 3 - 8-1/2 - - -
MWD - - 1 - - - - -
Non- Magnetic - 145.43 5 - 6-3/4 3 9.144 45.72
Drill Collar
Drill Collar API SPEC 145.43 12 - 6-3/4 3 9.144 109.728
Hydraulic Jar API SPEC - 1 - 6-3/4 - - -
HWDP NC 50 74.67 1 - 5 3 9.144 9.144
G105 NC 50
32.55 395 - 5 4.276 9.144 3611.88
Drill Pipe (XH)

6.5.7 Drilling Parameters


The hole is to be drilled to the depth of 3250m TVD MSL. The parameters to be considered involve
the following:
• Bit type
• Nozzle Selection
• Maximum Overpull
• WOB

6.5.7.1 Bit type


The Bit selection is made based on the nature of the formations to be encountered. The drill bit
parameters are shown below:

Table 6.34:- Drilling Parameters (Bit Type)

Matrix Body PDC with a cutter density of


Type of Bit 50 or more, ½” cutters and a size of
13.3mm for the cutters
Diameter 8-1/4"
IADC Code M432

6.5.7.2 Nozzle Selection


The basis of the calculation of the flow rate is the cutting settling velocity in the annulus. The
following rule is recommended:
● For soft formation annular velocity between 30 and 40 m/mim

80
● For hard formation annular velocity between 25 and 30 m/min
Annular Mud Velocity = 25 m/min
Annular Capacity OH – DP = 23.3 l/m DDH D14
𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐹𝑙𝑜𝑤 𝑟𝑎𝑡𝑒, 𝑄 = 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦, 𝐶𝑎 × 𝐴𝑛𝑛𝑢𝑙𝑎𝑟 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦, 𝑉𝑎
𝑙 𝑚 𝐿
∴ 𝑄 = 23.3 × 25 = 582.5
𝑚 𝑚𝑖𝑛 𝑚𝑖𝑛

Using
𝐹𝑅
𝑉=
38.71 ∗ 𝑇𝐹𝐴
Where
FR= Flow rate in liters/min
V= Mud Velocity meters/sec
TFA = Total Flow area, 𝒊𝒏𝟐
Making use of a mud velocity of 90m/s
𝑄
𝑇𝐹𝐴 =
38.71 ∗ 𝑉
582.5
𝑇𝐹𝐴 =
38.71 ∗ 90
𝑇𝐹𝐴 = 0.1672 𝒊𝒏𝟐
From DDH G56 we choose a drilling Bit of 3 (Three) nozzles 8-8-9, having a total area of
0.1603 𝒊𝒏𝟐 .

6.5.7.3 Maximum Overpull

Table 6.35:- Showing the calculation of the drill string weight

Linear
Length Buoyancy Total Weight Total Weight
Weight
(m) Factor (kg) (T)
(Kg/m)
Drill Collar 145.45 155.448 0.817 22609.9116 22.6099116
HWDP 74.67 9.144 0.817 682.78248 0.68278248
Drill Pipe 32.55 3611.88 0.817 117566.694 117.566694
Total = 140.8593881

Maximum Overpull (MOP)

81
MOP = Maximum Tension on DP – weight of Drill String
Weight of Drill String in mud = (DC weight + HWDP weight + DP weight) * buoyancy factor
Total Drill stem Weight =140.9 Tonnes
Weight of Drill String in mud = 140.9 Tonnes * 0.817 = 115.12 Tonnes
Tensile Yield Strength on DP = 193.8kdaN
𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟 = 90%
≈ 0.9
𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 = 𝑇𝑒𝑠𝑖𝑙𝑒 𝑦𝑖𝑒𝑙𝑑 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ × 𝑆𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟
= 0.9 𝑥 193.8
= 174.42𝑘𝑑𝑎𝑁
≈ 177.8 𝑇
Maximum Overpull = 𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 − Total Drillstem Weight
= 177.8 𝑇 − 140.9T
= 36.9 𝑇

6.5.7.4 WOB

𝑊𝑂𝐵 ≈ 2 𝑡𝑜𝑛 𝑝𝑒𝑟 𝑖𝑛𝑐ℎ 𝑜𝑓 𝑏𝑖𝑡 𝑖𝑛 𝑠𝑜𝑓𝑡 𝑓𝑜𝑟𝑚𝑎𝑡𝑖𝑜𝑛


𝑡𝑜𝑛𝑠
→ 𝑊𝑂𝐵 = 𝟖 − 𝟏/𝟒′′ × 2 𝑥 cos 33.06 = 14.24𝑡𝑜𝑛𝑠
𝑖𝑛𝑐ℎ
𝑐𝑜𝑛𝑣𝑒𝑟𝑡𝑖𝑛𝑔 𝑡ℎ𝑒 𝑊𝑂𝐵 𝑡𝑜 𝑑𝑎𝑁;
𝑑𝑎𝑁
𝑊𝑂𝐵 = 14.24 × 0.981 × 1000
𝑘𝑔
∴ 𝑊𝑂𝐵 = 13969.4𝑑𝑎𝑁 = 𝟏𝟑. 𝟗𝟔𝟗𝟒 𝒌𝒅𝒂𝑵

6.5.8 Power Requirement


To determine the rig power requirement, the powers for the following systems are evaluated:
• Hydraulic System – Hydraulic Power
• Hoisting System – Hoisting Power
• Rotary System – Rotary Power

Pressure loss calculation

82
DP – L2, L5

HWDP – L2’, L5’

DC – L3, L4

Figure 6.4:- Drilling string schematics phase four

𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑
𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝐿𝑜𝑠𝑠, Pr = (𝑁 + 𝐿2 𝑁2 + 𝐿′2 𝑁3 +𝐿3 𝑁3 + 𝐿4 𝑁4 + 𝐿′5 𝑁5 + 𝐿5 𝑁5 ) × 𝐵 + 𝑝𝑑 𝑑
𝑃𝑑 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝 𝑖𝑛 𝑛𝑜𝑧𝑧𝑙𝑒𝑠 𝑓𝑜𝑟 𝑑 = 1, (𝑘𝑃𝑎)
𝑘𝑔⁄
𝑑 = 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑔𝑟𝑎𝑣𝑖𝑡𝑦, ( 𝑙)
𝑁1 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑒𝑞𝑢𝑖𝑚𝑒𝑛𝑡, (𝑘𝑃𝑎⁄100𝑚)

𝑁2 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁3 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟𝑠, (𝑘𝑃𝑎⁄100𝑚 )

𝑁4 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟 𝑎𝑛𝑛𝑢𝑙𝑢𝑠, (𝑘𝑃𝑎⁄100𝑚)

𝑁5 = 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑙𝑜𝑠𝑠 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑖𝑛 ℎ𝑜𝑙𝑒 − 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑎𝑛𝑛𝑢𝑙𝑢𝑠(𝑘𝑃𝑎⁄100𝑚)

𝐿2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)


𝐿′2 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿3 = 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿4 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝐶 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
𝐿′5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐻𝑊𝐷𝑃 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)

83
𝐿5 = 𝐸𝑥𝑡𝑒𝑟𝑛𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐷𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 𝑠𝑒𝑐𝑡𝑖𝑜𝑛, (100𝑚)
Typically Plastic viscosity is about twice of mud weight in pounds per gallon
Therefore:
𝑃𝑉 = 2 × 1.44 × 8.33
𝑷𝑽 = 𝟐𝟒 𝑪𝒑

Table 6.36: Showing the Pressure Loss calculation

Parameters Units DDH

Nozzle 8-8-9
N1 17.3 kPa/100m G30
N2 11.3 kPa/100m G40
N3 54.2 kPa/100m G45

N4
15.95 kPa/100m G60
N5 3.65 kPa/100m G67
L2 3611.88 m
L2' 9.144 m
L3 155.448 m
L4 155.448 m
L5' 9.144 m
L5 3611.88 m

Pd
5917 Kpa G48
d 1.44
B 2.53 G26
Case: 3
Q 582.5 l/min
Ptotal= 10219.65997 Kpa

Pumping requirement:
• Assuming a volumetric efficiency ηv=0.97
• Assuming a mechanical efficiency ηm=0.90

84
6.5.8.1 Pump power

The Maersk Gallant rig has 3 pumps (3 X LTV Emsco FC – 2200) single acting with a power of
2200HP rated for 7500psi.
Taking an overall pumping efficiency of 90% (η= 0.9)

Using
𝑃×𝑄 1
𝑃𝐻𝑃 = ×
450 
Where
P= Stand pipe pressure in bar
Q= Flowrate in l/min
η = pumping efficiency (90%)

Standpipe pressure = 10219.65997Kpa = 102.2bar


102.2bar × 582.5 1
𝑃𝐻𝑃 = ×
450 0.9
𝑃𝐻𝑃 = 147.83 ℎ𝑝

6.5.8.2 Hydraulic Power

Hydraulic power =
𝑃×𝑄
𝑃𝐻𝑃 (ℎ𝑝) =
44750
10219.65997 × 582.5
𝑃𝐻𝑃 (ℎ𝑝) =
44750
𝑃𝐻𝑃 (ℎ𝑝) = 133.8 ℎ𝑝

6.5.8.3 Mechanical Power

𝐻𝑦𝑑𝑟𝑎𝑢𝑙𝑖𝑐 𝑃𝑜𝑤𝑒𝑟
Mechanical Power= 𝜂𝑚

133.8
=
0.9
= 144.66 ℎ𝑝

85
6.5.8.4 Hoisting Power
The hoisting power is evaluated for each of the phases using the equation below.
𝐹×𝑉 1
𝑃𝐻𝑃 = ×
77.5 

Where:
F, Total Hoisted Weight (String + Block +Hook + Over pull)
V, Pulling up Speed, meters/sec
, Overall Hoisting Efficiency

Assumptions
Weight of 25 Tons for Block + Hook,
Speed of 0.3 meters/second
Using 12 lines and roller bearing, we obtain a reeving efficiency of 0.782 (DDH F3)
From previous calculations,
String load in air = 140.9 Tons
Margin of Over pull = 36.9 𝑇𝑜𝑛𝑛𝑒𝑠
Therefore:
F = 140.9+25+36.9
F = 202.77 Tons (202.77 X103 kg)
202.77 × 103 × 0.3 1
𝑃𝐻𝑃 = ×
77.5 0.782
𝑃𝐻𝑃 = 1003.73 𝐻𝑃

6.5.8.5 Rotation Power


The rotation power is evaluated for each of the phases using the equation below.
𝐶 × 𝑅𝑃𝑀 1
𝑃𝐻𝑃 = ×
712 
Where
C, Torque (daN.m)

86
, Rotating Efficiency (0.9)
𝐶 = 𝑆𝑎𝑓𝑒𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 × 𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑇𝑜𝑟𝑞𝑢𝑒
The minimum torque is obtained from DDH B22
Minimum Torque for a 5” X 4.276” Drill Pipe with nominal weight of 32.55 kg/m is (connection
= API, NC 50).
Minimum Make up Torque = 2,969 daN.m DDH B22
Using a safety factor of 80%,
𝐶 = 0.8 × 2969
𝐶 = 2375.2 𝑑𝑎𝑁. 𝑚

The Rotation per Minute (RPM) is assumed to be 100


The Rotation Power required is
2375.2 × 100 1
𝑃𝐻𝑃 = ×
712 0.9
𝑃𝐻𝑃 = 370.66 𝐻𝑃

6.5.8.6 Total Power Requirement

Total power = Pump power + Hoisting Power + Rotation Power


Total Power = 147.83 + 1003.73 + 370.66
Total Power = 1522.22 HP

6.5.9 Drilling Lines

We choose a 1.5” Wire diameter, 6 X 195 RR IWRC

6.5.9.1 Fast line Tension


𝐹
𝑇𝑓𝑙 =
ηm ∗ N
Where;
F = Hook Load
N = Number of lines

87
ηm = reeving efficiency
202.77
𝑇𝑓𝑙 =
0.782 ∗ 12
𝑻𝒇𝒍 = 𝟐𝟏. 𝟔 𝒕𝒐𝒏𝒏𝒆𝒔

6.5.10 Power Requirement at end of Phase

6.5.11 Drilling Fluids


Interval : 2,819.5m – 3,714 m MSL measured depth
Mud type : Saturated salt mud
Section length drilled : 894.5m
Drilled well volume : 30,110.96 litres
Required mud volume: 265,585.73 litres

Table 6.37:- Production Casing: Results of Mud Volume Calculations

Production
Measured Parameter
Casing
Volume
Total drill string volume (l) 33,438.10
Total Annular volume (l) 144,028.03
Total circulating volume (l) 177,466.13
Mud pit volume (l) @ 50% of total circulating volume 88,528.58
Total volume of mud needed (l) 265,585.73
Circulating Time- 2 pumps @ 50% each
Total pump output ((l/stroke) 39.40
Total pump circulation rate (l/min) 4,136.49
Total circulation time (min) 42.90

6.5.11.1 Drilling Fluids Characteristics and Operations


The drilling fluid used for this section is aimed at achieving good cleaning capability, hole
stability and mud loss while maintaining inhibition for the clay/ shale sections. Gypsum
provides Ca++ ion for base exchange of clays from Na+ to Ca++ for inhibition.

88
Table 6.38: 8 1/2” Hole: Principal Additives for Saturated Salt Mud

Concentration, Quantity
Additive Function
lb/bbl slurry Needed (kg)
Viscosity, filtration
Pre-hydrated Bentonite 10 10,751.85
control
Caustic Soda pH 9 - 11.0 Alkalinity control 1,233
Inhibition, calcium
Soda ash 1 1,075.19
removal
Salt (NaCl) 125 Weight Material 134,398.14
Starch 4 Filtration control 4,300.74
Viscosity, Filtration
PAC 0.25 268.80
Control
Source: Amoco Production Company drilling fluids manual

Table 6.39:- Typical Properties of the Saturated Salt Mud

Parameter Value
Mud weight 1.44
Plastic viscosity 15-20 cP
Yield point 15 - 18 (lb/100 ft2)
API Filtrate 6-8 cm3
pH 2-3
Source: Amoco Production Company drilling fluids manual

6.5.11.2 Kick Control


Kick is controlled by adopting the driller’s method as stated earlier.

6.5.12 Cementing Programme


Cemented Length in Intermediate Casing II = 50m
Table 6.40:- Summary of cement calculations

Total slurry volume 55.62 m3

89
Table 6.41:- Additives for cement slurry

Class G Cement 20.12 (471.84) Tons (sacks)


Fresh water 8.85 m3
S.G. 1.90 -
Mixing Time 0.40 Hours
Minimum Thickening Time 2.32 Hours
Chemical Wash 3.18 m3
Spacer (150m) 2.10 m3
Retarder (0.05% BWOC) 0.01 Tons
Loss Circulation Additive (0.4% BWOC) 0.08 Tons
Total Required Water 53.18 m3
Antifoam (0.5 gal/sk) 0.89 m3

Annular Volume (Casing-Casing and Casing – open hole) – 14.71 m3


Volume from casing collar to shoe – 0.53 m3
Cementing Procedure;
The casing shall be cemented into the 9 5/8” casing, i.e. 3663.78m MDMSL
Estimated quantity; 50% Excess in Open hole
After having run the 7” casing, cementing procedure is;
• Pump 2.10 m3 of spacer
• Pump 55.62 m3 Class G slurry 1.90 S.G.
• Displace cement with 71.47 m3 of 1.45 S.G. mud
Cement Composition: G cement + Chemical wash +Dispersant +Retarder + FLAC + Antifoam
For cement, 20.09 tons is mixed with 8.86 m3 Fresh water. The cement is neat without bentonite.

90
CHAPTER 7

WELL COMPLETIONS

7.1 Overview
The successful production and depletion of a reservoir depends on the quality of the completion
operations applied to the well. Completion, in petroleum engineering, is the process of making a
well ready for production (or injection). This primarily involves preparing the bottom of the hole
to the required specifications, cementing the casing, running in the production tubing and it’s
associated down hole tools, perforating and stimulating as required. The wellbore provides the
only path from the reservoir to the surface. In most establishments, it is the production engineer’s
responsibility to design and supervise the completion operations.

The objectives of a well completion are to:


• Connect the reservoir to the surface so that fluids can be produced from or injected into
the reservoir.
• Provide a conduit for well stimulation treatments.
• Isolate the producing reservoir from other zones.
• Protect the integrity of the reservoir, especially in unconsolidated formations.
• Provide a conduit to measure the changes in flow rate and pressure needed to run a well
test.
The well is completed as a single string cased-hole completion with 41/2 ’’ production string. To
ensure the well safety during the entire completion period, at least two safety barriers must be
ensured on both the tubing and the annulus. Perforated liner completion will be used. Packer shall
be set within the 7” production casing at 3040ft to anchor the 41/2” production tubing, and also to
isolate the liner-tubing annulus from production. After CBL has confirmed the integrity of the
cement, the perforation tool shall be lowered through the tubing to selectively perforate the 41/2”
production liner at the interval of the pay zone suspected to be between the OWC and the GOC.

91
The completion program starts after the 7” casing was cemented. The well was filled up with the
1.36 SG drilling fluid (by design).
• Between the 30” and 20” casings: hardened set and a plastic seal.
• Between the 20” annulus and the 13 3/8” casing: set cement and plug.
• Between the 13 3/8” and 9 5/8" casings: set cement and pack-off.
• The well: cemented 9 5/8" casing, cemented 7” casing and 10,000 psi rated BOP in place.
Preparation are made to run the log twice, the reason for the first is to ensure good cement job, the
second, being after a remedial cementing this is done to achieve selectivity of fluids, and ensure
that water production is delayed and can be controlled in future by plugging and re-perforating as
well as prevention of early gas cusping. Areas of concentration are the casing supporting the
casing, the casing and the production zone itself. The production zone refers to the zones from the
top of the reservoir to the gas water level and proper cementation of this zone is essential.

7.1.1 Running and Testing Procedure


The following steps were taken to perforate underbalanced using Tubing Conveyed Perforation
system with a permanent packer.
1) Hole Conditioning
a) Ran in hole with bit and scraper to verify hole depth (depth of float collar), cleaned the
hole of cement debris and displaced mud with completion fluid (1.1 S.G).
b) Ran cement evaluation Log with GR-CCL (Gamma Ray-Casing Collar Locator) for
future depth correlation.
c) Cement evaluation was positive so remedial cementing was not necessary
2) Ran in hole with Drill Stem Test (DST) string and Tubing Conveyed Perforation (TCP) gun
assembly attached to tubing. 2 TCP guns were used (over the interval 3080 - 3130, 3144 –
3195m MSL) with a spacer of 14m between.
3) Packer positioning:
When DST inflatable packers were close to their setting depth, we stopped running in and
performed a GR-CCL logging inside the tubing to position the packer at the required depth.

4) Perforating:

92
After the packers were inflated, the well was perforated at the stated intervals with guns from
down to top.

5) Drill Stem Testing:


Carried out drill stem test and interpreted data after it was transmitted to surface.

6) Well Kill:
Well was killed with 1.1S.G completion fluid in preparation for running in hole with completion
assembly.

7) DST/TCP gun assembly Retrieval:


Pulled out of hole and laid down DST/TCP assembly. Retrieved recorded data and compared with
real time measurements.

8) Installing Permanent Packer:


Ran the tubing conveyed hydraulically set permanent packer at depth (3040m) equipped with below
packer extensions using wireline setting tool.

9) Completion assembly in hole:-The Figure is shown below


a) Anchor locator.
b) Landing Nipple Bottom No Go.
c) Perforated tail pipe.
d) Landing Nipple Top No Go.
e) Joints of tubing.
f) Sliding Side Door (SSD).
g) Circulating valve.
h) SCSSV (Surface Control Sub-Surface Safety Valve)

93
Figure 7.1:- Completion diagram

10) Tubing Space out:


Pulled out tubing to connect hydraulic line to SCSSV. Ran in hole with final tubing arrangement
including tubing hanger and engaged the tubing inside the packer as it was landed on the tubing
head spool.

11) Pressure Testing:


Pressure tested the tubing string by applying 5000psi in the annulus.

12) Well head Installation:


Removed BOP (Blow out Preventer) and installed production well head back pressure valve
(BPV) inside the tubing hanger after installing the well head.

94
13) Well Activation:
Opened Sliding Side Door (SSD) with slickline, and pumped in light completion fluid (1.1S.G)
inside the annulus to reduce hydrostatic. Confirmed well had started unloading, and then closed
Sliding Side Door (SSD).

14) Well Clean Up:


Cleaned up the well progressively by opening the choke.

15) SSSV Testing:


The SCSSV was wire line retrievable; ran SCSSV inside mandrel and tested.

16) Prepared completion report.

7.2 Perforation Strategy


Technique: Underbalanced perforation
Gun Type: Tubing Conveyed Perforating Gun System
Gun diameter: 2 ½”
No. of shot directions: 8
Explosive Load: 21g
Entrance hole: 0.36”
Penetration: 28.4”
Shot density: 12 shots per foot
Phasing: 60º
Perforation Intervals: 3080-3130m (MSL)
3144-3195m (MSL)

7.2.1 Completion and Packer fluid


The completion fluid will be solids free. The required density to apply 10bar overbalance is
about 1.33 SG at reservoir temperature 140ºC. CaCl2 solution of 1.39 S.G at 20ºC (surface
temperature) will be used for this purpose. The crystallization temperature of CaCl2 solution at

95
this concentration is about –15ºF. There is very little likelihood of solids precipitation since the
temperature at sea floor is 10ºC and increases with depth.
Filtered brine weighted with CaCO3.
Completion Fluid Brine I: 1.40g/cc mud weight
(Heavy completion fluid for displacing the drilling mud)
Completion Fluid Brine II: 1.10g/cc mud weight.
(Light completion fluid for displacing the heavy
completions fluid through the SSD, in order to activate the
well)
Packer Fluid Brine I: 1.40g/cc mud weight.

7.3 Wellhead type and rating


Casing Head: To provide support for the casing hanger, weight of the casing string, the load
from testing the wellhead connection.
Provides a seal to isolate the annulus between the inside of the bowl and outside of the casing.
Tubing Head: To provide support for the tubing and tubing hanger.
Tubing Hanger: To Support the tubing.
From casing string design, the maximum pressure expected at the wellhead when the well is full
of gas and bullheading is 506.1bar (7439.67psi).

Wellhead Type: Surface


Working Pressure: 5,000psi
Other wellhead accessories required are:
• Secondary Seal.
• Wear Bushing.
• Locking Flanges
The X-mass Tree (10,000psi WP).

96
Figure 7.2:- Wellhead to be used for the CODSE 1A

7.4 Running and Testing Procedure


7.4.1 The following checks should be carried out on all threaded joints of the tube:
• Inspect connection and drift check before running the tubing .
• Ensure that the correct thread dope was applied.
• Use adequate torque and avoid high make up speed.
• Ensure that all couplings, cross-over, and pop joints are made of the same tubular material

7.4.2 The following procedures should be carried out on the wellbore before running the tubing:
• Evaluate the cement job by GR/CCL/CBL-VDL/CET.
• Bit and Scrapper run for wellbore hole cleaning particularly at the packer setting depth.
• Use the brine (completion fluid CaCl2 of SG 1.4) to displace the drilling mud.
• Perform correlation log to obtain a proper reference point for the depth of packer and
perforations. The parker depth should be chosen so that the packer is set opposite a well-
cemented zone.
• Rig up the wire line well control equipment and the shooting nipple.
• Perforation gun assemble and at accurate interval.
▪ Conduct several runs of the tubing to ensure the perforation interval is covered.
▪ Observe well to ensure overbalance and not flowing before Pull-Out-Of-Hole.

97
▪ Ensure Pull-Out-Of-Hole is done at an adequate rate to avoid swabbing or formation
damage.

• Run-in-Hole the production tubing with accessories following the description on the
completions diagram.
• Land tubing with the tubing hanger in the tubing head spool and pressure test tubing.
• Set the Packer with the specified surface pressure and pressure test.
• Nipple down the landing joint and set Back-Pressure-Valve (BPV), nipple down the Blow-
out-Preventer (BOP) with tested appropriate rams.
• Nipple up the Christmas tree and pressure test the well

7.4.3 The following techniques and equipment should be used in running the tube to the correct
depth:
A hydraulically set retrievable packer was selected for this completions program, which is a tubing
conveyed packer. The equipment to be assembled on the tubing string includes:
• Landing nipple.
• Tubing retrievable surface controlled subsurface safety valve (TRSCSSV).
• Tubing

Procedure:
• Conduct visual examination of the assembly of equipments including the tubing based on the
running order.
• Screw the tubing to the landing nipple and tubing hanger and run in hole. Caution should be
taken when the tubing string approaches the top of the liner to avoid damaging the packer
setting mechanism.
• Pressure test tubing assembly above the packer while running in hole at 320bar.
• Set the packer.
• Land the tubing hanger on the tubing head spool.
• Test the tubing (production) string at 320bar.

7.4.4 Installing the Christmas tree


Installing the Christmas tree involves first uninstalling the blow out preventer (BOP) and replacing
with the Christmas tree. The procedure for replacing the BOP with the Christmas tree is as follow:
• Unbolt the BOP and skid it to one side.

98
• Mount the adaptor on the upper flange of the tubing head spool.
• Install the Christmas tree on top of the adaptor.
• Test the production wellhead.

Procedure:
• Test seal between the tubing hanger at 320bar.
• Test the surface controlled subsurface safety valve (SCSSV) control line.
• Replace the back-pressure valve with a two-way check valve and perform an overall
production wellhead test.
• Perform a valve-by-valve pressure test on the adapter plus Christmas tree assembly

7.4.5 Well clean up


In the annulus, the completion fluid must be replaced with the packer fluid and a cleanup fluid by
circulating through the sliding sleeve door. The following procedures are followed:
• Remove the two-way check valve from the wellhead and open the circulating valve by wire
line.
• Displace the completion fluid in the annulus and tubing by the use of light weight completion
fluid with SG of 1.1. This is done by reverse circulation through the sliding sleeve door. This
should activate the well.
• Nitrogen unloading may be required if the well is not activated.
• Close the circulating valve at bottoms up

7.4.6 Perforation
The perforation is carried out underbalanced using the CWOK process using the through tubing gun
technique on slickline after the completion equipment have been run. The Christmas tree installed
and the well is filled with inhibited water (Light weight completion fluid).

7.4.7 Cleaning the well after perforation


• Open the Christmas tree valves and allow the well to flow through the choke manifold and a
flow line connected to a flare for gas venting.
• All test ports must be fully opened.
• Flow the well until the effluent is considered to be clean enough.
• Put the well back in safe condition by closing the subsurface safety valve and Christmas tree
valves.

99
7.5 Future Interventions
Well intervention operations are carried out in order to extend the producing life of the well by either
improving its performance or providing access to addition/stranded hydrocarbon reserves
(AkerSolution, 2011). Well intervention operation could be heavyweight (HW) or light weight (LW)
depending on the objection of the operation and production state of the well. The heavy weight (HW)
operation requires the mobilization of a rig unit while the mobilization of a rig unit is not needed for
light weight (LW) intervention operations. Typical well intervention operations services include:

Replacement of all or part of the completion equipment above the packer. The completion
equipment that could be replaced above the packer are:
• Christmas tree/wellhead equipment (LW). Possible problems are:
▪ Valve leaks.
▪ Tubing hanger or tie down screws.
▪ Back pressure valve (BPV) seat.
▪ SCSSV control line outlet
• Leaks on circulating sleeve (LW)
• Stuck/faulty TRSCSSV (HW)
• Faulty control line (HW)
• Tubing repairs (HW)

Replacement of equipment below the packer or the packer itself. The possible equipments that
could be replaced are:
• Damaged/leaking retrievable packer (HW)
• Damaged/leaking slips joints and locators (HW)
• Accidentally unseated packer (HW)

Bottom hole data gathering. This includes temperature and pressure logging using the respective
gauges attached to a wireline using lubricator.

Perforation plugging and re-perforation in order to carry out water/gas shut off. Plugging and
re-perforating the perforation interval is performed in order to shut of water when production water
exceeds limit (water-oil-ratio) or shut off gas when the produced gas exceeds the limit (Gas-oil ratio).

100
A squeeze job is done by placing an inflatable bridge beneath the perforations and injecting slurry in
squeeze mode through a stinger under low pressure. The well is usually killed before carrying put a
squeeze job.

Well stimulation by acid job. A light weight operation using coiled tubing and skid-mounted pumps
should be used to inject chemicals downhole. Procedure are as follows:
• A coiled tubing is recommended to minimize tubing movement.
• A hydrochloric based acid is recommended.
• A pre flush of about 5% HCl is used to treat the reservoir zone
• Main treatment of about 1m3 mud acid/m reservoir height can be used
• An after flush of mineral oil can be used
• The well should be cleaned up immediately after the after flush has been pumped.

101
7.6 Project timing and costing

Figure 7.3:- Gnatt chart showing project timeline

Figure 7.4:- Gnatt chart showing project timeline cont’d

Table 6.42:- Cost estimation of the project

OPERATION PHASE WELL Drilled &


No Of Unit type Cost Per
PHASE S/SERVICES/ Comments TIME TIME Cased
Unit each Unit (USD)
EQUIPMENT (days) (days) (USD)

Rig Positioning Rig Positioning 50 Loads 3 3 3600 180,000

Prepare for 50,000 50,000


spudding

102
Bit Surface 2 each Bits Required 8.5 17 5000 10,000
Hole

26" HOLE - 20" Surface Mud 560 Cubic Meter Cost/m3Water 50 28,000
CSG and Chemicals out

Interval=610m Surface Casing 610 Meters C90 205 123,000


106.5lb/ft.

Attachment & 60 each Centralizers, 25 1,500


Accessories Scratchers,
etc.

Tongs 610 Meters Equipment 8 4,800

Cement 610 Meters Pumping, 30 18,000


&Services additives,
Tonnage

17 1/2" HOLE Bit Intermediate 7 each Bits Required 10 20 10,000 70,000


– 13-3/8” CSG Hole

Interval=1500 Intermediate 468.7 Cubic Cost/m3 475 222,632.5


Mud & Meter
Invert out
Chemical

Intermediate 1627.2 Meters RT95 250 377,570


Casing
117.8lb/ft.

Attachment & 1627.2 each Centralizers, 25 37,757


Accessories Scratchers,
etc.

Tongs 1627.2 Meters Equipment 5 7,551.4

Cement & 1627.2 Meters Pumping, 22 33,226.16


Services additives,
Tonnage

12 1/4" HOLE Bit Intermediate 9 each Bits Required 15 30 12,000 108,000


–9 5/8” CSG Hole

103
Interval=2500m Intermediate 227 Cubic Cost/m3 500 113,500
Mud & Metre
Invert out
Chemical

Intermediate 2819.5 Meters C90 300 862,047


Casing
47.0 lb/ft

Attachment & 2819.5 each Centralizers, 25 71,837


Accessories Scratchers,
etc.

Tongs 2819.5 Meters Equipment 5 14,367

Cement & 2819.5 Meters Pumping, 20 57,470


Services additives,
Tonnage

8 1/2" HOLE – Bit Production 4 each Bits Required 16 32 15,000 60,000


7” CSG Hole

Interval=3250 Production Mud 163 Cubic Cost/m3 900 146,700


& Chemical Meter
Invert out

Intermediate 3714 Meters L80 90 333,941


Casing
29.00 lb/ft

Attachment & 354 each Centralizers, 25 8,850


Accessories Scratchers,
etc.

Tongs 3714 Meters Equipment 6 22,263

Cement & 3714 Meters Pumping, 25 92,761.25


Services additives,
Tonnage

Completion Well Head 1 each Type and 5 10 30,000 30,000


Estimate Accessories

Tubing 3300 Meters C90 12.6 lb/ft 32 105,600

Packers, 1 each Anchors, 38,250 38,250


Plugs& Packers,
Retainers Nipples, etc

104
Perforation 1 TCP guns 25,500 25,500

TOTAL COST 3,054,754.31

105
APPENDIX A : CASING DESIGN

Surface Casing
Burst Pressure @Shoe
610 × 1.44
𝑃𝑖 = = 86.12𝑏𝑎𝑟
10.2
Pe=72bar
ΔP= 86.12-72=14.12bar
Collapse Pressure @ Shoe
610 × 1.18
𝑃𝑖 = = 70.6𝑏𝑎𝑟
10.2
610 × 1.9
𝑃𝑒 = = 113.63𝑏𝑎𝑟
10.2
ΔP= 113.63-70.6=43.03bar
Safety factor consideration
Burst pressure = 14.12 x 1.3 = 18.356bar= 1.8356MPa
Collapse pressure= 43.03 x 1.125 = 48.41bar= 4.841MPa
Intermediate Casing 1
Collapse Pressure (Partial emptying)
For height of mud in casing column :-
2500 × 1
𝑃𝑖 = = 245.1𝑏𝑎𝑟
10.2
245.1 × 10.2
ℎ= = 1524.4𝑚
1.64
Depth=2500-1524.4=975.61m
ℎ × 1.9 (1500 − ℎ) × 1.44
+ = 258𝑏𝑎𝑟
10.2 10.2
h=1027.6m
H (top of cement)=1500-1027.6=472.4m
ΔP @ mud level=118bar
(1500−975.6)×1.64
ΔP @ shoe=202- 10.2
= 117.68𝑏𝑎𝑟

Burst pressure (well full of gas)


2500×0.2
ΔP @ shoe=330- 10.2
+ 35 = 315.98𝑏𝑎𝑟

Safety factor consideration

106
Collapse pressure = 118 x 1.125 = 132.75bar = 13.3MPa
Burst pressure = 315.98 x 1.3 = 410.77bar = 41.1MPa
Intermediate casing 2
Collapse pressure (partial emptying)
For height of mud in casing column :-
3250 × 1
𝑃𝑖 = = 318.63𝑏𝑎𝑟
10.2
318.3 × 10.2
ℎ= = 2389.71𝑚
1.36
Depth=3250-2389.71=860.3m
ℎ × 1.9 (2500 − ℎ) × 1.64
+ = 458𝑏𝑎𝑟
10.2 10.2
h=2198.456m
H (top of cement)=2500-2198.456=301.54m
860.3 ×1.64
ΔP @ mud level= 10.2
= 138.32bar
(2500−860.3)×1.36
ΔP @ shoe=330- = 111.37𝑏𝑎𝑟
10.2

Burst pressure (well full of gas)


3250×0.2
ΔP @ shoe=330- 10.2
+ 35 = 301.275𝑏𝑎𝑟

Safety factor consideration


Collapse pressure = 138.323 x 1.125 = 155.613bar = 15.56MPa
Burst pressure = 301.275 x 1.3 = 391.66 bar= 39.17MPa
Production casing
Well empty
ΔP = 418bar
Well full of gas
3039 × 1
𝑃𝑖 = = 297.9𝑏𝑎𝑟
10.2
Pe = 395bar
ΔP = 395 – 297.9 = 97.1bar
Kick situation (unlimited kick)
3250 ×0.2
ΔP =418 - 10.2
+ 35 = 389.27𝑏𝑎𝑟

Safety factor consideration


Collapse pressure = 418 x 1.125 = 470.25bar = 47.03MPa
Burst pressure = 389.27 x 1.3 = 506.05 bar = 50.61MPa

107
APPENDIX B: DRILL STRING CALCULATIONS

26” OPEN HOLE (610m MSL)


Weight on bit
Weight on bit = 0.5 ton per inch for very soft formations
= 0.5 × 26 = 13 𝑇𝑜𝑛𝑛𝑒𝑠
Taking 80% of Drill collar weight to be on the bit
Therefore Drill collar weight in mud equals
13𝑇
=
0.8

Drill Collar Weight on Bit in mud is therefore = 16.25𝑇


= 16250𝑘𝑔 (16.25𝑇)

Mud Characteristics: 1.18S.G


Buoyancy Factor: DDH A27 = 0.850

Drill collar weight in air will be


16250𝑘𝑔
=
0.850
= 19117.6 𝑘𝑔
Choice of drill collars
A slick 9.5in (OD) 3in (ID) was chosen for this phase
Nominal weight = 323.18
= 323.18 𝑘𝑔/𝑚
Length of drill collars
19117.6 𝑘𝑔
=
323.18 𝑘𝑔/𝑚
= 59.15𝑚
Each length of Drill Collar is taken as 30ft = 9.144m
Number of drill collars required =

108
59.15 𝑚
=
9.144 𝑚

= 6.5 ≃ 7𝑝𝑐𝑠

For a good transmission of weight and maintaining the Section Modulus less than 5.5 a drill
collar with specification DC (8” X 3”) will incorporated in the drill String

• One Drill collar with specification DC (8” X 3”) ≃ 218.77 kg/m will be used.

Heavy Weight Drill Pipe (HWDP)

To ensure smooth transition from the rigid and compressed DC’s to the flexible and in tension
DPs, HWDP are used. This also acts as a safety such that the DP’s are never in compression as
the HWDP can with stand a considerable compression force. The section modulus of less than
5.5 is targeted between DC and HWDP and also between HWDP and DP
Section modulus
DC (9.5” X 3”) and DC (8” X 3”) = 1.69 <5.5 Okay
DC (8”X3”) and HWDP (5” X 3”) = 4.6 <5.5 Okay
HWDP (5” X 3”) and DP (5” X 4.276”) = 1.87 < 5.5 Okay

HWDP specifications
HWDP (5” X 3”) ≃ 74.67 kg/m

Drill Pipes (DP)


Total length of drill pipe required
= Depth MSL + Rig Height depth (55m) – Total length of DCs – Total length of HWDP
= 658.368m
Drill pipe length is taken as 30ft ≃ 𝟗. 𝟏𝟒𝟒𝒎
Total Number of Drill Pipes =
658.368m
=
9.144 𝑚

109
= 72 pcs

DP specification
5” X 4.276” 19.5 lb/ft,
Tool joint G105, NC50 (XH)
Approximate weight with tool joint = 32.55 kg/m

110
17.5” OPEN HOLE (1500m MSL)

Weight on bit
Weight on bit = 1 ton per inch for very soft formations
= 1 × 17.5 𝑥 cos 33.06 = 14.67 𝑇𝑜𝑛𝑛𝑒𝑠
Taking 80% of Drill collar weight to be on the bit
Therefore Drill collar weight in mud equals
14.67𝑇
=
0.8

Drill Collar Weight on Bit in mud is therefore = 18.333𝑇


= 18333𝑘𝑔 (18.333𝑇)

Mud Characteristics: 1.44S.G


Buoyancy Factor: DDH A27 = 0.817

Drill collar weight in air will be


18333𝑘𝑔
=
0.817
= 22440 𝑘𝑔
Choice of drill collars
A slick 9.5in (OD) 3in (ID) was chosen for this phase
Nominal weight = 323.18
= 323.18 𝑘𝑔/𝑚
Length of drill collars
22440 𝑘𝑔
=
323.18 𝑘𝑔/𝑚
= 69.43𝑚
Each length of Drill Collar is taken as 30ft = 9.144m
Number of drill collars required =
69.43 𝑚
=
9.144 𝑚

111
= 8𝑝𝑐𝑠
For a good transmission of weight and maintaining the Section Modulus less than 5.5 a drill
collar with specification DC (8” X 3”) will incorporated in the drill String

• One Drill collar with specification DC (8” X 3”) ≃ 218.77 kg/m will be used.

Heavy Weight Drill Pipe (HWDP)

To ensure smooth transition from the rigid and compressed DC’s to the flexible and in tension
DPs, HWDP are used. This also acts as a safety such that the DP’s are never in compression as
the HWDP can with stand a considerable compression force. The section modulus of less than
5.5 is targeted between DC and HWDP and also between HWDP and DP
Section modulus
DC (9.5” X 3”) and DC (8” X 3”) = 1.69 <5.5 Okay
DC (8”X3”) and HWDP (5” X 3”) = 4.6 <5.5 Okay
HWDP (5” X 3”) and DP (5” X 4.276”) = 1.87 < 5.5 Okay

HWDP specifications
HWDP (5” X 3”) ≃ 74.67 kg/m

• One length of HWDP (5” X 3”) ≃ 74.67 kg/m will be used

Drill Pipes (DP)


Total length of drill pipe required
= Depth MSL + Rig Height depth (55m) – Total length of DCs – Total length of HWDP

= 1591.056m
Drill pipe length is taken as 30ft ≃ 𝟗. 𝟏𝟒𝟒𝒎
Total Number of Drill Pipes =
1591.056m
=
9.144 𝑚

112
= 174 pcs

DP specification
5” X 4.276” 19.5 lb/ft,
Tool joint G105, NC50 (XH)
Approximate weight with tool joint = 32.55 kg/m

12.25” OPEN HOLE (2500m MSL)

Weight on bit
Weight on bit = 2 ton per inch for very soft formations
= 2 × 12.25 𝑋 cos 33.06 = 20.53 𝑇𝑜𝑛𝑛𝑒𝑠
Taking 80% of Drill collar weight to be on the bit
Therefore Drill collar weight in mud equals
20.53𝑇
=
0.8

Drill Collar Weight on Bit in mud is therefore = 25.6668 𝑇


= 25667𝑘𝑔 (25.67𝑇)

Mud Characteristics: 1.64S.G


Buoyancy Factor: DDH A27 = 0.791

Drill collar weight in air will be


25667𝑘𝑔
=
0.791
= 32448.8 𝑘𝑔
Choice of drill collars
A slick 9.5in (OD) 3in (ID) was chosen for this phase
Nominal weight = 323.18
= 323.18 𝑘𝑔/𝑚
Length of drill collars

113
32448.8 𝑘𝑔
=
323.18 𝑘𝑔/𝑚
= 100.4𝑚
Each length of Drill Collar is taken as 30ft = 9.144m
Number of drill collars required =
100.4 𝑚
=
9.144 𝑚

= 11 𝑝𝑐𝑠
For a good transmission of weight and maintaining the Section Modulus less than 5.5 a drill
collar with specification DC (8” X 3”) will incorporated in the drill String

• One Drill collar with specification DC (8” X 3”) ≃ 218.77 kg/m will be used.

Heavy Weight Drill Pipe (HWDP)

To ensure smooth transition from the rigid and compressed DC’s to the flexible and in tension
DPs, HWDP are used. This also acts as a safety such that the DP’s are never in compression as
the HWDP can with stand a considerable compression force. The section modulus of less than
5.5 is targeted between DC and HWDP and also between HWDP and DP
Section modulus
DC (9.5” X 3”) and DC (8” X 3”) = 1.69 <5.5 Okay
DC (8”X3”) and HWDP (5” X 3”) = 4.6 <5.5 Okay
HWDP (5” X 3”) and DP (5” X 4.276”) = 1.87 < 5.5 Okay

HWDP specifications
HWDP (5” X 3”) ≃ 74.67 kg/m

• One length of HWDP (5” X 3”) ≃ 74.67 kg/m will be used

Drill Pipes (DP)


Total length of drill pipe required

114
= Depth MSL + Rig Height depth (55m) – Total length of DCs – Total length of HWDP
= 2761.488 m
Drill pipe length is taken as 30ft ≃ 𝟗. 𝟏𝟒𝟒𝒎
Total Number of Drill Pipes =
2761.488 𝑚
=
9.144 𝑚

= 302pcs
DP specification
5” X 4.276” 19.5 lb/ft,
Tool joint G105, NC50 (XH)
Approximate weight with tool joint = 32.55 kg/m

115
8.5” OPEN HOLE (2500m MSL)

Weight on bit
Weight on bit = 2 ton per inch for very soft formations
= 2 × 8.5 𝑥 cos 33.06 = 14.24 𝑇𝑜𝑛𝑛𝑒𝑠
Taking 80% of Drill collar weight to be on the bit
Therefore Drill collar weight in mud equals
14.24𝑇
=
0.8

Drill Collar Weight on Bit in mud is therefore = 17.8 𝑇


= 17800𝑘𝑔 (17.8𝑇)

Mud Characteristics: 1.44S.G


Buoyancy Factor: DDH A27 = 0.817

Drill collar weight in air will be


17800𝑘𝑔
=
0.817
= 21787 𝑘𝑔
Choice of drill collars
A slick 6.75in (OD) 3in (ID) was chosen for this phase
Nominal weight = 145.43
= 145.43 𝑘𝑔/𝑚
Length of drill collars
21787 𝑘𝑔
=
145.43 𝑘𝑔/𝑚
= 149.8 𝑚
Each length of Drill Collar is taken as 30ft = 9.144m
Number of drill collars required =
149.8 𝑚
=
9.144 𝑚

116
= 16.3 𝑝𝑐𝑠 ≃ 𝟏𝟕𝒑𝒄𝒔

Heavy Weight Drill Pipe (HWDP)

To ensure smooth transition from the rigid and compressed DC’s to the flexible and in tension
DPs, HWDP are used. This also acts as a safety such that the DP’s are never in compression as
the HWDP can with stand a considerable compression force. The section modulus of less than
5.5 is targeted between DC and HWDP and also between HWDP and DP
Section modulus
DC (6.75” X 3”) and HWDP (5” X 3”) = 2.72 < 5.5 Okay
HWDP (5” X 3”) and DP (5” X 4.276”) = 1.87 < 5.5 Okay

HWDP specifications
HWDP (5” X 3”) ≃ 74.67 kg/m

• One length of HWDP (5” X 3”) ≃ 74.67 kg/m will be used

Drill Pipes (DP)


Total length of drill pipe required
= Depth MSL + Rig Height depth (55m) – Total length of DCs – Total length of HWDP
= 3611.88 m
Drill pipe length is taken as 30ft ≃ 𝟗. 𝟏𝟒𝟒𝒎
Total Number of Drill Pipes =
3611.88 𝑚
=
9.144 𝑚

= 395pcs
DP specification
5” X 4.276” 19.5 lb/ft,
Tool joint G105, NC50 (XH)
Approximate weight with tool joint = 32.55 kg/m

117
APPENDIX C: MUD CALCULATIONS

Mud Calculations, Mud Pump and Typical Mud Compositions


Mud Calculations
The following formula were used to calculate volumes. Results of mud calculations obtained
for each hole section is found in section 2.2.3.
1) Volume of Drill String
a) Capacity of drill pipe, HWDP or drill collar (litres⁄ metre);

= 0.5067 × 𝐷2 (4)

b) Total volume of drill pipe, HWDP or drill collar (litres);

= Capacity of drill string (l⁄𝑚) × 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑡𝑟𝑖𝑛𝑔 (𝑚) (5)

c) Total volume of drill string (litres);

= 𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑑𝑟𝑖𝑙𝑙 𝑝𝑖𝑝𝑒 + 𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐻𝑊𝐷𝑃 (6)


+ 𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑑𝑟𝑖𝑙𝑙 𝑐𝑜𝑙𝑙𝑎𝑟
Where;
Drill string is either drill pipe, HWDP or drill collar
𝐷 = Internal diameter of drill pipe, HWDP or drill collar respectively in metre
2) Annular Volume
a) Annular capacity: drill pipe and cased hole (litres⁄ metre);

= 0.5067 × [(𝑖𝑛𝑛𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝐶𝐻)2 (7)


− (𝑜𝑢𝑡𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝐷𝑃)2 ]
b) Annular capacity: drill pipe and open hole (litres⁄ metre);

= 0.5067 × [(𝑖𝑛𝑛𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑂𝐻)2 (8)


− (𝑜𝑢𝑡𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝐷𝑃)2 ]
c) Annular capacity: HWDP and open hole (litres⁄ metre)

= 0.5067 × [(𝑖𝑛𝑛𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑂𝐻)2 (9)


− (𝑜𝑢𝑡𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝐻𝑊𝐷𝑃)2 ]
d) Annular capacity: drill collar and open hole (litres⁄ metre)

= 0.5067 × [(𝑖𝑛𝑛𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑂𝐻)2 (10)


− (𝑜𝑢𝑡𝑒𝑟 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝐷𝐶)2 ]
e) Total annular volume of each section (litres⁄ metre);

= 𝑎𝑛𝑛𝑢𝑙𝑎𝑟 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 (11)


× 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑒𝑎𝑐ℎ 𝑟𝑒𝑠𝑝𝑒𝑐𝑡𝑖𝑣𝑒 𝑎𝑛𝑛𝑢𝑙𝑎𝑟 𝑠𝑒𝑐𝑡𝑖𝑜𝑛]]
f) Total annular volume (litres);

118
(12)
= ∑ (𝑡𝑜𝑡𝑎𝑙 𝑎𝑛𝑛𝑢𝑙𝑎𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑒𝑎𝑐ℎ 𝑠𝑒𝑐𝑡𝑖𝑜𝑛)

Where the depth of OH (open hole), CH (cased hole), HWDP (heavy weight drill pipe), DP
(drill pipe) and DC (drill collar) are in metres.
3) Total Circulating Volume
a) Total circulating volume (litres);

= 𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑑𝑟𝑖𝑙𝑙 𝑠𝑡𝑟𝑖𝑛𝑔 + 𝑡𝑜𝑡𝑎𝑙 𝑎𝑛𝑛𝑢𝑙𝑎𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 (13)

4) Mud Pit Volume


Mud pit volume was taken to be 50% of total of total circulating volume calculated for each phase of
drilling. Thus, mud pit volumes required can be found in table hold.
5) Total Circulating Time

𝑡𝑜𝑡𝑎𝑙 𝑐𝑖𝑟𝑐𝑢𝑙𝑎𝑡𝑖𝑛𝑔 𝑣𝑜𝑙𝑢𝑚𝑒 (14)


=
𝑡𝑜𝑡𝑎𝑙 𝑝𝑢𝑚𝑝 𝑜𝑢𝑡𝑝𝑢𝑡

Carrying capacity (assuming Cuttings carrying capacity= 1)


400000
𝐾=
𝑀𝑊 × 𝐴𝑉

Where,
𝐴𝑉 = annular velocity, ft/min,
𝑊 = mud weight, lb/gal,
𝐾 = viscosity (the cxonsistency, K, in the Power Law model), cP
SUMMARY OF RESULTS
Table C-1: Summary of Results- Mud calculations a) Surface casing b) Intermediate Casing 1 c) Intermediate Casing 2 d)
Production Casinga) Surface casing

Surface
Measured Parameter
Casing
Estimated distance MSL-RKB 55
Measured shoe depth (m) mud line 538
Outer diameter of Casing (in) 20
Inner diameter of Casing (in) 18.73
Outer diameter of drill pipe (in) 5
Internal diameter of drill pipe (in) 4.276
Length of drill pipe (m) 582.70
Outer diameter of HWDP (in) 5
Internal diameter of HWDP (in) 3
Length of each HWDP (m) 9.14
Number of HWDP used 1
Number of drill collar used 8
Outer diameter of 7 drill collar above jar from surface 1 (in) 9.5
Outer diameter of drill collar below jar from surface 2 (in) 8

119
Internal diameter of drill collar (in) 3
Length of drill collar (m) 9.14
Diameter of open hole (in) 26
Inner diameter of previous cased hole (in) 29
Volume
Capacity of drill pipe (l/m) 9.05
Capacity of each HWDP (l/m) 4.56
Capacity of drill collar 1 (l/m) 4.56
Capacity of drill collar 2 (l/m) 4.56
Volume of drill pipe (l) 5,273.47
Volume of HWDP (l) 41.70
Volume of drill collar (l) 333.60
Total drillstring volume (l) 5,648.77
Annular capacity: drill pipe and cased hole (l/m) 413.47
Annular capacity: (drill pipe + HWDP) and open hole (l/m) 329.86
Annular capacity: drill collar 1 and open hole (l/m) 296.80
Annular capacity: drill collar 2 and drill pipe (l/m) 310.10
Annular capacity: riser and drill pipe to RKB (l/m) 413.47
Annular volume: drill pipe and cased hole (l) 36,385.11
Annular volume: (drill pipe + HWDP) and open hole(l) 76,807.64
Annular volume: drill collar 1 and open hole (l) 18,997.54
Annular volume: drill collar 2 and open hole (l) 3,780.74
Annular volume: conductor pipe and drill pipe to RKB (l) 52,510.33
Total Annular volume (l) 188,481.37
Total circulating volume (l) 194,130.14
b) Intermediate Casing 1
1st Intermediate
Measured Parameter
Casing
Estimated distance MSL-RKB 55
Measured shoe depth (m) mud line 1,555.20
Outer diameter of Casing (in) 13.375
Inner diameter of Casing (in) 12.41
Outer diameter of drill pipe (in) 5
Internal diameter of drill pipe (in) 4.276
Length of drill pipe (m) 1,591.06
Outer diameter of HWDP (in) 5
Internal diameter of HWDP (in) 3
Length of each HWDP (m) 9.14
Number of HWDP used 1
Outer diameter of the 8 drill collar above jar from surface 1
(in) 9.5
Outer diameter of 1 drill collar below jar from surface 2 (in) 8
Internal diameter of drill collar (in) 3
Length of drill collar (m) 9.14

120
Diameter of open hole (in) 17.5
Inner diameter of previous cased hole (in) 18.73
Volume
Capacity of drill pipe (l/m) 9.05
Capacity of each HWDP (l/m) 4.56
Capacity of drill collar 1 (l/m) 4.56
Capacity of drill collar 2 (l/m) 4.56
Volume of drill pipe (l) 14,399.06
Volume of HWDP (l) 41.70
Volume of drill collar (l) 375.29
Total drill string volume (l) 14,816.05
Annular capacity: drill pipe and cased hole (l/m) 165.09
Annular capacity: (drill pipe + HWDP) and open hole (l/m) 142.51
Annular capacity: drill collar 1 and open hole (l/m) 109.45
Annular capacity: drill collar 2 and drill pipe (l/m) 122.75
Annular capacity: conductor pipe and drill pipe to RKB (l/m) 413.47
Annular volume: drill pipe and cased hole (l) 88,818.10
Annular volume: (drill pipe + HWDP) and open hole(l) 133,232.58
Annular volume: drill collar 1 and open hole (l) 8,006.28
Annular volume: drill collar 2 and open hole (l) 1,122.41
Annular volume: conductor pipe and drill pipe to RKB (l) 52,510.33
Total Annular volume (l) 283,689.70
Total circulating volume (l) 298,505.76

C) Intermediate Casing 2
2nd Intermediate
Measured Parameter
Casing
Estimated distance MSL-RKB 55
Measured shoe depth (m) mud line 2747.5
Outer diameter of Casing (in) 9.625
Inner diameter of Casing (in) 8.75
Outer diameter of drill pipe (in) 5
Internal diameter of drill pipe (in) 4.276
Length of drill pipe (m) 2,761.49
Outer diameter of HWDP (in) 5
Internal diameter of HWDP (in) 3
Length of each HWDP (m) 9.14
Number of HWDP used 1
Outer diameter of the 11 drill collars above jar from surface 1
(in) 9.5
Outer diameter of 1 drill collar below jar from surface 2 (in) 8
Internal diameter of drill collar (in) 3

121
Length of drill collar (m) 9.14
Diameter of open hole (in) 12.25
Inner diameter of previous cased hole (in) 12.41
Volume
Capacity of drill pipe (l/m) 9.05
Capacity of each HWDP (l/m) 4.56
Capacity of drill collar 1 (l/m) 4.56
Capacity of drill collar 2 (l/m) 4.56
Volume of drill pipe (l) 24,991.47
Volume of HWDP (l) 41.70
Volume of drill collar (l) 500.39
Total drill string volume (l) 25,533.56
Annular capacity: drill pipe and cased hole (l/m) 65.37
Annular capacity: (drill pipe + HWDP) and open hole (l/m) 63.37
Annular capacity: drill collar 1 and open hole (l/m) 30.31
Annular capacity: drill collar 2 and open hole (l/m) 43.61
Annular capacity: conductor pipe and drill pipe to RKB (l/m) 413.47
Annular volume: drill pipe and cased hole (l) 101,660.94
Annular volume: (drill pipe + HWDP) and open hole(l) 68,601.69
Annular volume: drill collar 1 and open hole (l) 3,048.40
Annular volume: drill collar 2 and open hole (l) 398.75
Annular volume: conductor pipe and drill pipe to RKB (l) 52,510.33
Total Annular volume (l) 226,220.11
Total circulating volume (l) 251,753.67

d) Production Casing
Production
Measured Parameter
Casing
Estimated distance MSL-RKB 55
Measured shoe depth (m) mud line 3642
Outer diameter of Casing (in) 7
Inner diameter of Casing (in) 6.18
Outer diameter of drill pipe (in) 5
Internal diameter of drill pipe (in) 4.276
Length of drill pipe (m) 3,611.88
Outer diameter of HWDP (in) 5
Internal diameter of HWDP (in) 3
Length of each HWDP (m) 9.14
Number of HWDP used 1
Outer diameter of the 17 drill collars (in) 6.75
Internal diameter of drill collar (in) 3
Length of drill collar (m) 9.14

122
Diameter of open hole (in) 8.5
Inner diameter of previous cased hole (in) 8.75
Volume
Capacity of drill pipe (l/m) 9.05
Capacity of each HWDP (l/m) 4.56
Capacity of drill collar 1 (l/m) 4.56
Volume of drill pipe (l) 32,687.51
Volume of HWDP (l) 41.70
Volume of drill collar (l) 708.89

Total drill string volume (l) 33,438.10


Annular capacity: drill pipe and cased hole (l/m) 26.13
Annular capacity: (drill pipe + HWDP) and open hole
(l/m) 23.94
Annular capacity: drill collar and open hole (l/m) 13.52
Annular capacity: conductor pipe and drill pipe to RKB
(l/m) 413.47
Annular volume: drill pipe and cased hole (l) 73,664.28
Annular volume: (drill pipe + HWDP) and open hole(l) 15,751.35
Annular volume: drill collar and open hole (l) 2,102.05
Annular volume: conductor pipe and drill pipe to RKB
(l) 52,510.33
Total Annular volume (l) 144,028.03
Total circulating volume (l) 177,466.13

Table C-2:- Mud Pump Requirement a) Surface casing b) Intermediate Casing 1 c) Intermediate Casing 2 d) Production
Casinga) Surface casing

Surface
Pump Data- Emsco F-2200 Parameter
Casing
Liner diameter of stroke (in) 9 Total pump output ((l/stroke) 39.40
Total pump circulation rate
Length of stroke (in) 14 (l/min) 4,136.49
Strokes per minute (strokes/min) 105 Total circulation time (min) 46.93
Number of pumps 2
Efficiency of pump 0.9
Pump output (l/stroke) @50% 19.70
Pump circulation rate (l/min) @50% 2,068.25
Total pump output ((l/stroke) 39.40
Total pump circulation rate (l/min) 4,136.49

b) Intermediate Casing 1

123
1st
Pump Data- Emsco F-2200- Intermediate
Parameter Intermediate
1
Casing
Total pump output
Liner diameter of stroke (in) 9 ((l/stroke) 39.40
Total pump circulation rate
Length of stroke (in) 14 (l/min) 4,136.49
Strokes per minute (strokes/min) 105 Total circulation time (min) 72.16
Number of pumps 2
Efficiency of pump 0.9
Pump output (l/stroke) @50% 19.70
Pump circulation rate (l/min)
@50% 2,068.25
Total pump output ((l/stroke) 39.40
Total pump circulation rate
(l/min) 4,136.49

c) Intermediate Casing 2

2nd
Pump Data- Emsco F-2200 Parameter Intermediate
Casing
Liner diameter of stroke (in) 9 Total pump output ((l/stroke) 39.40
Total pump circulation rate
Length of stroke (in) 14 (l/min) 4,136.49
Strokes per minute (strokes/min) 105 Total circulation time (min) 58.39
Number of pumps 2
Efficiency of pump 0.9
Pump output (l/stroke) @50% 19.70
Pump circulation rate (l/min)
@50% 2,068.25
Total pump output ((l/stroke) 39.40
Total pump circulation rate (l/min) 4,136.49

d) Production Casing
Pump Data- Emsco F-2200- Production Production
Parameter
Casing Casing
Liner diameter of stroke (in) 9 Total pump output ((l/stroke) 39.40
Total pump circulation rate
Length of stroke (in) 14 (l/min) 4,136.49
Strokes per minute (strokes/min) 105 Total circulation time (min) 42.90
Number of pumps 2
Efficiency of pump 0.9

124
Pump output (l/stroke) @50% 19.70
Pump circulation rate (l/min) @50% 2,068.25
Total pump output ((l/stroke) 39.40
Total pump circulation rate (l/min) 4,136.49

The cement calculations are done in sections.

125
APPENDIX D: CEMENTING PROGRAMME

30” and 20” Casing Section (Surface Casing): Cementing to the mudline
Volume Calculations

Casing – Casing Section


Internal Diameter (ID) of the 30” casing =28.75".
Outside Diameter (OD) of Surface Casing = 20”
Length = (160 – 72) m = 88m
From DDH D1
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 19.03𝑚3

Casing – Open Hole Section


Open hole size = 26”
Length = (610 – 160) = 450m
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 62.93𝑚3
Open hole excess = 50%
𝑉𝑜𝑙𝑢𝑚𝑒 = 94.45𝑚3

Inside 20” Casing Between Float Collar and Shoe


Length = 90ft = 27.43m
0.5067(𝐼𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 5.02 𝑚3
Total Slurry Volume = 118.50 m3
Calculating Lead and Tail Slurry Volume;
Lead Volume = (Casing – Casing Annular Volume) + (Casing – Top of Tail Volume) + Open Hole
Excess
𝐿𝑒𝑎𝑑 𝑉𝑜𝑙𝑢𝑚𝑒 = 105.80 𝑚3
Tail Volume = (Casing – Open Hole Volume + Open hole Excess) + (Inside 20” Casing Volume)
𝑇𝑎𝑖𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = 12.70 𝑚3

126
Lead Slurry S.G. = Mud Weight + 0.1 S.G.
Lead Slurry S.G. = 1.28
Tail Slurry S.G. = Fracture Gradient at Shoe
Tail Slurry S.G. = 1.44
Preparation of 1 m3 Class G cement:
Bentonite weight (kg);
𝑑
100 (1 − ) − (𝑑 − 1)𝑒
𝑏= 3.15
1
𝑑 ( + 𝑍) − (𝑍 + 1)
2.65
Water Volume (liters);
𝐸 = 𝑒 + 𝑧𝑏
Slurry Volume (liters);
100 𝑏
𝑣= + + 𝑒 + 𝑧𝑏
3.15 2.65

LEAD
For 100kg of Cement;
d = 1.28
e = 44liters
z = 21.2 for pre-hydrated bentonite
𝑏 = 8.86𝑘𝑔
𝐸 = 228 𝑙𝑖𝑡𝑒𝑟𝑠
𝑣 = 263.04 𝑙𝑖𝑡𝑒𝑟𝑠
If 100kg of cement = 263.04 liters of slurry,
Therefore105.80m3 of slurry = 40.22 Tons of Cement
Similarly,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 94𝑙𝑏 = 42.64𝐾𝑔
40.22Tons 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 943.2 𝑠𝑎𝑐𝑘𝑠
We thus require 943 sacks of cement for the lead.
Similarly,
100 𝐾𝑔 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑟𝑒𝑞𝑢𝑖𝑟𝑒 8.68 𝐾𝑔 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
𝑇ℎ𝑢𝑠 40.22 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 3.49 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒

127
Furthermore,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 𝑐𝑜𝑛𝑡𝑎𝑖𝑛𝑠 1𝑇𝑜𝑛
3.49 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 = 3.49 𝑠𝑎𝑐𝑘𝑠
We thus require 3.49 sacks of bentonite.
Similarly,
263.04 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑆𝑙𝑢𝑟𝑟𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑠 228.016 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
𝑇ℎ𝑢𝑠 105.80𝑚3 of slurry = 91.71𝑚3 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

TAIL
For 100kg of Cement;
d = 1.54
e = 44liters
z = 21.2 for pre-hydrated bentonite
𝑏 = 2.48𝑘𝑔
𝐸 = 96.57 𝑙𝑖𝑡𝑒𝑟𝑠
𝑣 = 129.26 𝑙𝑖𝑡𝑒𝑟𝑠
If 100kg of cement = 129.26 liters of slurry,
Therefore12.70 m3 of slurry = 9.82 Tons of Cement
Similarly,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 94𝑙𝑏 = 42.64𝐾𝑔
9.82Tons 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 230.37 𝑠𝑎𝑐𝑘𝑠
We thus require 231 sacks of cement for the tail.
Similarly,
100 𝐾𝑔 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑟𝑒𝑞𝑢𝑖𝑟𝑒 2.48 𝐾𝑔 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
𝑇ℎ𝑢𝑠 9.82 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 0.24 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
Furthermore,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 𝑐𝑜𝑛𝑡𝑎𝑖𝑛𝑠 1𝑇𝑜𝑛
0.24 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 = 0.24 𝑠𝑎𝑐𝑘𝑠
We thus require 0.24 sacks of bentonite.
Similarly,
129.26 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑆𝑙𝑢𝑟𝑟𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑠 96.57𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
𝑇ℎ𝑢𝑠 12.70𝑚3 of slurry = 9.49𝑚3 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

128
Spacer Volume
The spacer exists in the casing – casing annular section with a length of 46.25m, therefore:
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 10𝑚3
Total Water Required;
= 𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝑐𝑒𝑚𝑒𝑛𝑡 + 20% 𝑆𝑎𝑓𝑒𝑡𝑦 + 𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ
+ 20 𝐵𝑎𝑟𝑟𝑒𝑙𝑠 𝑚𝑖𝑛𝑖𝑚𝑢𝑚 (𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔
𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝐶𝑒𝑚𝑒𝑛𝑡 = 101.80 𝑚3
20% 𝑆𝑎𝑓𝑒𝑡𝑦 = 20.24𝑚3
𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ = 3.179𝑚3
20𝑏𝑏𝑙𝑠 𝑓𝑜𝑟 𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔 = 3.179𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐻2 𝑂 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 127.80𝑚3
Displacement
Volume from the float collar to the top of the casing:
𝑉𝑜𝑙𝑢𝑚𝑒 = 0.5067(𝐼𝐷2 ) × (538 − 90 ∗ 0.3048), 𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 = 93.44𝑚3

Minimum Thickening Time


Job time = Mixing time + Displacement time + 10minutes(to drop plugs)
Mixing Time
Assuming mixing time for the lead and tail are 4 bpm and 8 bpm respectively,
105799.3
Lead: = barrels : 4 bbls per min = 2.77 Hours
159
12696.82
Tail: = barrels ∶ 8 bbls per min = 0.17 Hours
159

Displacement Time
93440
Displacement: barrels : 10 bbls per min = 0.97 Hours
159

Job time = 2.77 + 0.17 + 0.97 + 10/60 = 4.08 Hours


To allow a safe margin for cement job, Time for cement to remain pumpable = 1 hour
Therefore, MINIMUM THICKENING TIME = 4.08 + 1= 5.08 Hours
MINIMUM THICKENING TIME = 5 hrs 5 mins

20” and 13 3/8” Casing Section (Intermediate Casing I):


Volume Calculations

Casing – Casing Section


Internal Diameter (ID) of the 20” casing =19".

129
Outside Diameter (OD) of Intermediate Casing I = 13 3/8”
Length = 50m into the previous casing
From DDH D1
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 4.62 𝑚3

Casing – Open Hole Section


Open hole size = 17.5”
Length = (1552.14 – 538) = 1014.14m
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 65.48𝑚3
Open hole excess = 50%
𝑉𝑜𝑙𝑢𝑚𝑒 = 98.22𝑚3

Inside 13 3/8” Casing Between Float Collar and Shoe


Length = 90ft = 27.43m
0.5067(𝐼𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 2.14 𝑚3
Total Slurry Volume = 104.98m3
Calculating Lead and Tail Slurry Volume;
Lead Volume = (Casing – Casing Annular Volume) + (Casing – Top of Tail Volume) + Open Hole
Excess
𝐿𝑒𝑎𝑑 𝑉𝑜𝑙𝑢𝑚𝑒 = 99.29 𝑚3
Tail Volume = (Casing – Open Hole Volume + Open hole Excess) + (Inside 20” Casing Volume)
𝑇𝑎𝑖𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = 5.69 𝑚3
Lead Slurry S.G. = Mud Weight + 0.1 S.G.
Lead Slurry S.G. = 1.54
Tail Slurry S.G. = Fracture Gradient at Shoe
Tail Slurry S.G. = 1.74
Preparation of 1 m3 Class G cement:
Bentonite weight (kg);

130
𝑑
100 (1 − ) − (𝑑 − 1)𝑒
𝑏= 3.15
1
𝑑 ( + 𝑍) − (𝑍 + 1)
2.65
Water Volume (liters);
𝐸 = 𝑒 + 𝑧𝑏
Slurry Volume (liters);
100 𝑏
𝑣= + + 𝑒 + 𝑧𝑏
3.15 2.65

LEAD
For 100kg of Cement;
d = 1.54
e = 44liters
z = 21.2 for pre-hydrated bentonite
𝑏 = 2.48 𝑘𝑔
𝐸 = 96.57 𝑙𝑖𝑡𝑒𝑟𝑠
𝑣 = 129.26 𝑙𝑖𝑡𝑒𝑟𝑠
If 100kg of cement = 129.26 liters of slurry,
Therefore, 99.29m3 of slurry = 76.82 Tons of Cement
Similarly,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 94𝑙𝑏 = 42.64𝐾𝑔
76.82 Tons 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 1081.53 𝑠𝑎𝑐𝑘𝑠
We thus require 1082 sacks of cement for the lead.
Similarly,
100 𝐾𝑔 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑟𝑒𝑞𝑢𝑖𝑟𝑒 2.48 𝐾𝑔 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
𝑇ℎ𝑢𝑠 76.82 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 1.90 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
Furthermore,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 𝑐𝑜𝑛𝑡𝑎𝑖𝑛𝑠 1𝑇𝑜𝑛
1.90 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 = 1.90 𝑠𝑎𝑐𝑘𝑠
We thus require 1.9 sacks of bentonite.
Similarly,
129.26 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑆𝑙𝑢𝑟𝑟𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑠 96.57 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

131
𝑇ℎ𝑢𝑠 99.29𝑚3 of slurry = 74.19𝑚3 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

TAIL
For 100kg of Cement;
d = 1.74
e = 44liters
z = 21.2 for pre-hydrated bentonite
𝑏 = 0.80𝑘𝑔
𝐸 = 60.85 𝑙𝑖𝑡𝑒𝑟𝑠
𝑣 = 92.9 𝑙𝑖𝑡𝑒𝑟𝑠
If 100kg of cement = 92.9 liters of slurry,
Therefore5.69m3 of slurry = 6.12 Tons of Cement
Similarly,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 94𝑙𝑏 = 42.64𝐾𝑔
6.12 Tons 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 143.53 𝑠𝑎𝑐𝑘𝑠
We thus require 144 sacks of cement for the tail.
Similarly,
100 𝐾𝑔 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑟𝑒𝑞𝑢𝑖𝑟𝑒 0.80 𝐾𝑔 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
𝑇ℎ𝑢𝑠 6.12 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 0.05 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
Furthermore,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 𝑐𝑜𝑛𝑡𝑎𝑖𝑛𝑠 1𝑇𝑜𝑛
0.05 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 = 0.05 𝑠𝑎𝑐𝑘𝑠
We thus require0.05 sacks of bentonite.
Similarly,
92.9 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑆𝑙𝑢𝑟𝑟𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑠 60.85 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
𝑇ℎ𝑢𝑠 5.69𝑚3 of slurry = 3.72 𝑚3 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

Spacer Volume
The spacer exists in the casing – casing annular section with a length of 108.3m, therefore:
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 10𝑚3
Total Water Required;

132
= 𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝑐𝑒𝑚𝑒𝑛𝑡 + 20% 𝑆𝑎𝑓𝑒𝑡𝑦 + 𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ
+ 20 𝐵𝑎𝑟𝑟𝑒𝑙𝑠 𝑚𝑖𝑛𝑖𝑚𝑢𝑚 (𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔
𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝐶𝑒𝑚𝑒𝑛𝑡 = 77.91 𝑚3
20% 𝑆𝑎𝑓𝑒𝑡𝑦 = 15.58 𝑚3
𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ = 3.179𝑚3
20𝑏𝑏𝑙𝑠 𝑓𝑜𝑟 𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔 = 3.179𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐻2 𝑂 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 99.85𝑚3
Displacement
Volume from the float collar to the top of the casing:
𝑉𝑜𝑙𝑢𝑚𝑒 = 0.5067(𝐼𝐷2 ) × (1552.14 − 90 ∗ 0.3048), 𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 = 119.14𝑚3

Minimum Thickening Time


Job time = Mixing time + Displacement time + 10minutes(to drop plugs)
Mixing Time
Assuming mixing time for the lead and tail are 4 bpm and 8 bpm respectively,
99290.76
Lead: = barrels : 4 bbls per min = 2.60 Hours
159
5685.77
Tail: = barrels ∶ 8 bbls per min = 0.07 Hours
159

Displacement Time
11940
Displacement: barrels : 10 bbls per min = 1.25 Hours
159

Job time = 2.60 + 0.07 + 1.25 + 10/60 = 4.09 Hours


To allow a safe margin for cement job, Time for cement to remain pumpable = 1 hour
Therefore, MINIMUM THICKENING TIME = 4.09 + 1= 5.09 Hours
MINIMUM THICKENING TIME = 5 hrs 6 mins

13 3/8” and 9 5/8” Casing Section (Intermediate Casing II):


Volume Calculations

Casing – Casing Section


Internal Diameter (ID) of the 13 3/8” casing =12.415".
Outside Diameter (OD) of Intermediate Casing I = 9 5/8”
Length = 30m into the previous casing
From DDH D1
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000

133
𝑉𝑜𝑙𝑢𝑚𝑒 = 0.94 𝑚3

Casing – Open Hole Section


Open hole size = 12.5”
Length = (2747.5 – 1552.14) = 1014.14m
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 38.55 𝑚3
Open hole excess = 50%
𝑉𝑜𝑙𝑢𝑚𝑒 = 58.72𝑚3

Inside 9 5/8” Casing Between Float Collar and Shoe


Length = 90ft = 27.43m
0.5067(𝐼𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 1.07 𝑚3
Total Slurry Volume = 59.82 m3
Calculating Lead and Tail Slurry Volume;
Lead Volume = (Casing – Casing Annular Volume) + (Casing – Top of Tail Volume) + Open Hole
Excess
𝐿𝑒𝑎𝑑 𝑉𝑜𝑙𝑢𝑚𝑒 = 56.99 𝑚3
Tail Volume = (Casing – Open Hole Volume + Open hole Excess) + (Inside 20” Casing Volume)
𝑇𝑎𝑖𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = 2.84 𝑚3
Lead Slurry S.G. = Mud Weight + 0.1 S.G.
Lead Slurry S.G. = 1.74
Tail Slurry S.G. = Fracture Gradient at Shoe
Tail Slurry S.G. = 1.87
Preparation of 1 m3 Class G cement:
Bentonite weight (kg);
𝑑
100 (1 − ) − (𝑑 − 1)𝑒
𝑏= 3.15
1
𝑑 ( + 𝑍) − (𝑍 + 1)
2.65
Water Volume (liters);
𝐸 = 𝑒 + 𝑧𝑏

134
Slurry Volume (liters);
100 𝑏
𝑣= + + 𝑒 + 𝑧𝑏
3.15 2.65

LEAD
For 100kg of Cement;
d = 1.74
e = 44liters
z = 21.2 for pre-hydrated bentonite
𝑏 = 0.80 𝑘𝑔
𝐸 = 60.85 𝑙𝑖𝑡𝑒𝑟𝑠
𝑣 = 92.90 𝑙𝑖𝑡𝑒𝑟𝑠
If 100kg of cement = 92.90 liters of slurry,
Therefore, 56.99 m3 of slurry = 61.34 Tons of Cement
Similarly,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 94𝑙𝑏 = 42.64𝐾𝑔
61.34 Tons 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 1438.52 𝑠𝑎𝑐𝑘𝑠
We thus require 1439 sacks of cement for the lead.
Similarly,
100 𝐾𝑔 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑟𝑒𝑞𝑢𝑖𝑟𝑒 0.80 𝐾𝑔 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
𝑇ℎ𝑢𝑠 61.34 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 0.49 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
Furthermore,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 𝑐𝑜𝑛𝑡𝑎𝑖𝑛𝑠 1𝑇𝑜𝑛
0.49 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 = 0.49 𝑠𝑎𝑐𝑘𝑠
We thus require 0.49 sacks of bentonite.
Similarly,
92.9 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑆𝑙𝑢𝑟𝑟𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑠 60.85 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
𝑇ℎ𝑢𝑠56.99 𝑚3 of slurry = 37.33 𝑚3 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

TAIL
For 100kg of Cement;
d = 1.87
e = 44liters

135
z = 21.2 for pre-hydrated bentonite
𝑏 = 0.14𝑘𝑔
𝐸 = 46.94 𝑙𝑖𝑡𝑒𝑟𝑠
𝑣 = 78.73 𝑙𝑖𝑡𝑒𝑟𝑠
If 100kg of cement = 78.73 liters of slurry,
Therefore, 2.84 m3 of slurry = 3.60 Tons of Cement
Similarly,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 94𝑙𝑏 = 42.64𝐾𝑔
3.60 Tons 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 84.45 𝑠𝑎𝑐𝑘𝑠
We thus require 85 sacks of cement for the tail.
Similarly,
100 𝐾𝑔 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑟𝑒𝑞𝑢𝑖𝑟𝑒 0.14 𝐾𝑔 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
𝑇ℎ𝑢𝑠 3.60 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 0.005 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒
Furthermore,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 𝑐𝑜𝑛𝑡𝑎𝑖𝑛𝑠 1𝑇𝑜𝑛
0.005 𝑇𝑜𝑛𝑠 𝑜𝑓 𝐵𝑒𝑛𝑡𝑜𝑛𝑖𝑡𝑒 = 0.005 𝑠𝑎𝑐𝑘𝑠
We thus require0.005 sacks of bentonite.
Similarly,
78.73 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑆𝑙𝑢𝑟𝑟𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑠 46.94 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
𝑇ℎ𝑢𝑠 2.84 𝑚3 of slurry = 1.69 𝑚3 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

Spacer Volume
The spacer exists in the casing – casing annular section with a length of 100m, therefore:
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 3.12𝑚3
Total Water Required;
= 𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝑐𝑒𝑚𝑒𝑛𝑡 + 20% 𝑆𝑎𝑓𝑒𝑡𝑦 + 𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ
+ 20 𝐵𝑎𝑟𝑟𝑒𝑙𝑠 𝑚𝑖𝑛𝑖𝑚𝑢𝑚 (𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔
𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝐶𝑒𝑚𝑒𝑛𝑡 = 39.02 𝑚3
20% 𝑆𝑎𝑓𝑒𝑡𝑦 = 7.80 𝑚3
𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ = 3.179𝑚3
20𝑏𝑏𝑙𝑠 𝑓𝑜𝑟 𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔 = 3.179𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐻2 𝑂 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 53.18𝑚3

136
Displacement
Volume from the float collar to the top of the casing:
𝑉𝑜𝑙𝑢𝑚𝑒 = 0.5067(𝐼𝐷2 ) × (2747.5 − 90 ∗ 0.3048), 𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 = 105.70 𝑚3

Minimum Thickening Time


Job time = Mixing time + Displacement time + 10minutes(to drop plugs)
Mixing Time
Assuming mixing time for the lead and tail are 4 bpm and 8 bpm respectively,
56985.6
Lead: = barrels : 4 bbls per min = 1.49 Hours
159
2835.14
Tail: = 159
barrels ∶ 8 bbls per min = 0.04 Hours

Displacement Time
105697
Displacement: barrels : 10 bbls per min = 1.11 Hours
159

Job time = 2.60 + 0.07 + 1.25 + 10/60 = 2.81 Hours


To allow a safe margin for cement job, Time for cement to remain pumpable = 1 hour
Therefore, MINIMUM THICKENING TIME = 2.81 + 1= 3.81 Hours
MINIMUM THICKENING TIME = 3 hrs 49 mins

9 5/8” and 7” Casing Section (Production Casing):


Volume Calculations

Casing – Casing Section


Internal Diameter (ID) of the 9 5/8” casing =8.755".
Outside Diameter (OD) of Production Casing = 7”
Length = 50m into the previous casing
From DDH D1
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 0.0270 𝑚3

Casing – Open Hole Section


Open hole size = 8.5”
Length = (3713.78 – 600) = 3113.78m
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000

137
𝑉𝑜𝑙𝑢𝑚𝑒 = 36.68 𝑚3
Open hole excess = 50%
𝑉𝑜𝑙𝑢𝑚𝑒 = 55.09𝑚3

Inside 7” Casing Between Float Collar and Shoe


Length = 90ft = 27.43m
0.5067(𝐼𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 0.53 𝑚3
Total Slurry Volume = 55.62 m3
Slurry S.G. = 1.90
Bentonite is not required due to the specific gravity of the cement required.
Preparation of 1 m3 Class G cement:
Water Volume (liters);
𝐸 = 44 𝑙𝑖𝑡𝑒𝑟𝑠
Slurry Volume (liters);
100
𝑣= +𝑒
3.15
For 100kg of Cement;
d = 1.90
e = 44liters
𝑏 = 0.80 𝑘𝑔
𝑣 = 75.74 𝑙𝑖𝑡𝑒𝑟𝑠
If 100kg of cement = 75.74 liters of slurry,
Therefore, 15.24 m3 of slurry = 20.12 Tons of Cement
Similarly,
1 𝑠𝑎𝑐𝑘 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 94𝑙𝑏 = 42.64𝐾𝑔
20.12 Tons 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 471.84 𝑠𝑎𝑐𝑘𝑠
We thus require 472 sacks of cement.
Furthermore,
Similarly,
75.74 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 𝑆𝑙𝑢𝑟𝑟𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑠 44 𝑙𝑖𝑡𝑟𝑒𝑠 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

138
𝑇ℎ𝑢𝑠 15.24 𝑚3 of slurry = 8.85 𝑚3 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟

Spacer Volume
The spacer exists in the casing – casing annular section with a length of 150m, therefore:
0.5067(𝐼𝐷2 − 𝑂𝐷2 )
𝑉𝑜𝑙𝑢𝑚𝑒 = × 𝐿𝑒𝑛𝑔𝑡ℎ (𝑚3 )
1000
𝑉𝑜𝑙𝑢𝑚𝑒 = 2.10 𝑚3
Total Water Required;
= 𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝑐𝑒𝑚𝑒𝑛𝑡 + 20% 𝑆𝑎𝑓𝑒𝑡𝑦 + 𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ
+ 20 𝐵𝑎𝑟𝑟𝑒𝑙𝑠 𝑚𝑖𝑛𝑖𝑚𝑢𝑚 (𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔
𝑀𝑖𝑥𝑒𝑑 𝐻2 𝑂 𝑓𝑜𝑟 𝐶𝑒𝑚𝑒𝑛𝑡 = 8.85 𝑚3
20% 𝑆𝑎𝑓𝑒𝑡𝑦 = 1.77 𝑚3
𝑊𝑎𝑡𝑒𝑟 𝑓𝑜𝑟 𝑐ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑤𝑎𝑠ℎ = 3.179𝑚3
20𝑏𝑏𝑙𝑠 𝑓𝑜𝑟 𝑝𝑟𝑖𝑚𝑖𝑛𝑔 𝑎𝑛𝑑 𝑤𝑎𝑠ℎ𝑖𝑛𝑔 = 3.179𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐻2 𝑂 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 16.98 𝑚3
Displacement
Volume from the float collar to the top of the casing:
𝑉𝑜𝑙𝑢𝑚𝑒 = 0.5067(𝐼𝐷2 ) × (3713.78 − 90 ∗ 0.3048), 𝑚3
𝑉𝑜𝑙𝑢𝑚𝑒 = 71.47 𝑚3

Minimum Thickening Time


Job time = Mixing time + Displacement time + 10minutes(to drop plugs)
Mixing Time
Assuming mixing time for is 4 bpm
71470
= barrels : 4 bbls per min = 0.40 Hours
159

Displacement Time
105697
Displacement: barrels : 10 bbls per min = 0.75 Hours
159

Job time = 0.40 + 0.75 + 10/60 = 1.32 Hours


To allow a safe margin for cement job, Time for cement to remain pumpable = 1 hour
Therefore, MINIMUM THICKENING TIME = 1.32 + 1= 2.32 Hours
MINIMUM THICKENING TIME = 2 hrs 34 mins

139