Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Introduction
A complete mix activated sludge process is a secondary treatment system which basically constitutes of three
major components. Aeration tank, clarifier and recycle system build up the activated sludge system.
Aeration tank, which is the first unit of an activated sludge system, is a reactor in which the microorganisms
used for the treatment of waste is kept in suspension and aerated. The next unit is the clarifier, where liquid –
solid separation is carried out, usually in a sedimentation tank. This unit is also called settling tank and most of
the time it is called secondary clarifier/settling tank as wastewater undergone a primary sedimentation step is
fed to the most activated sludge treatment plants. In primary sedimentation step, settle able solids in
wastewater are removed.
Part of the solids (sludge) removed from bottom of secondary clarifier is returned back to the aeration tank
and called as ‘return activated sludge’. The third component of an activated sludge process, the recycle system
is used to transport this return activated sludge. The rest of the sludge from secondary clarifier is removed as
waste and it is known as ‘waste activated sludge’.
The activated sludge process is a biological process which is used for removing soluble, colloidal and
particulate organic substances as well as biological nitrification and denitrification and biological phosphate
removal.
In this design, an activated sludge system for only BOD removal and an activated sludge system for BOD
removal with nitrification were considered.
Secondary Clarifier
Q + QR Qe
Q X Xe
Aeration Tank
QR
QW
XR
XW
1
2. Design Problem
A wastewater treatment plant receives wastewater at a rate of 35000 m3/day, having BOD5 of 250 mg/l and
COD of 350 mg/l. Primary treatment removes 25% of the BOD. An activated sludge system is to be used for
secondary treatment of this municipal wastewater. After secondary clarification, it is desired to have not
more than 25 mg/l of soluble BOD and 100 mg/l soluble COD in the effluent. The total solid content and the
volatile solid content of the wastewater are found as 70 mg/l and 60 mg/l respectively. A completely mixed
activated sludge system is to be used, and pilot plant analysis has established the following kinetic values;
Y = 0.5 kg/kg
kd = 0.05 l/day
Wastewater Characteristics
Following wastewater characteristics were assumed for the design of the complete-mix activated sludge
process.
Assumptions
2
3. Design of Complete - Mix Activated Sludge Process for BOD
Removal without Nitrification
In the primary treatment, 25% of the BOD in the municipal wastewater is removed. Therefore in the secondary
treatment, the rest of the BOD is removed to the desired level.
BOD of the wastewater fed into the secondary = Input wastewater BOD × 75%
treatment =250 × 75%
=187.5 mg/l
But,
0.862
8.257
Table 3.1: Wastewater Characteristics Developed
Characteristic Value
bCOD 300
nbCOD 50
sCODe 20
nbVSS 8.257
3
3.2 Design of Suspended Growth System
To develop the kinetics for the suspended growth system, first the activated sludge kinetic coefficients are
estimated at the design temperature. (25 0C)
Following are the equations that are used to estimate the kinetic coefficients of activated sludge systems at
different temperatures.
µm,25 = µmθt-20
=6×1.0725-20
=8.415 g VSS/g VSS.d
Ks,25 = Ks θt-20
=20×125-20
=20 g bCOD/m3
Following is the summary of the kinetic coefficient values used in the design.
The solid retention time (SRT) for BOD removal only, is assumed to be 5 days.
S – Substrate concentration
SRT – Solid retention time
4
0.487 g bCOD/m3
The biomass production rate for BOD removal only is given by,
Where,
Q – Wastewater flowrate
S0 – Input substrate concentration
S – Substrate concentration in the mixed liquor
TSS0 – Input total suspended solids
VSS0 – Input volatile suspended soilds
Q =35000 m3/day
S0 =input bCOD
=300 g bCOD/m3
TSS0 =70 g/m3
VSS0 =60 g/m3
= 4193.183 kg VSS/d
=157.244 kg VSS/d
D =Q(nbVSS)
=35000 × 8.257 × 10-3
=288.991 kg nbVSS/d
=A+B+D
=4193.183 + 157.244 + 288.991
=4639.419 kg VSS/d
5
=A/0.85 + B/0.85 + D + Q(TSS0 – VSS0)
=(4193.183+157.244)/0.85+288.991+35000×(70–60)×10-3
=5757.141 kg TSS/d
3.3 Determination of Mass of MLVSS and Mass of MLTSS in the Aeration Tank
The mass of VSS and TSS in the aeration tank can be determined using,
Therefore,
Mass of MLVSS =
=4639.419 × 5
=23197.093 kg MLVSS
Mass of MLTSS =
=5757.141 × 5
=28785.706 kg MLVSS
The mass of TSS in the aeration tank can also be determined using following relationship.
Therefore,
V =
=28785.706 × 1000/3000
=9595.235 m3
τ - Detention time
τ =V/Q
=9595.235×24/35000
=6.580 h
The concentration of the MLVSS in the aeration tank can be calculated by,
F/M =QS0/XV
=35000×300/(2417.564×9595.235)
=0.453 kg/kg.d
BOD =QS0/V
=35000×300/9595.235
=1.094 kg/m3.d
The O2 demand for the aeration tank for BOD removal only, can be calculated by,
Where,
=
=35000×(300-0.487)×10-3 - 1.42×(4193.183 + 157.244)
=4528.638 kg/d
AOTR =R0/24
=4528.638/24
=188.693 kg/h
7
3.8 Fine bubble aeration design
The actual oxygen transfer rate under field condition is given by,
̅
( )
Where,
̅ is given by,
̅ ( )
First, the DO concentration at the operating temperature is found using the data tables.
But above value is the DO concentration at mean sea level and the DO concentration should be corrected for
altitude as it is assumed that the treatment facility is located at 500 m elevation. Therefore the correction of
concentration could be achieved by means of relative pressure at 500 m elevation.
[ ]
M =28.97 kg/kmol
R =8314 kJ/kmol.K
=exp* +
8
=exp* +
=0.944
Atmospheric pressure at an elevation of 500 m =Atmospheric pressure at mean sea level × Pb/Pa
=101.325 × 0.944
=95.680 kN/m2
As the point of air release is 0.5 above the tank bottom, pressure at the depth of air release
̅
= ( )
=7.781 × 1/2 (14.186/9.786 + 19/21)
=9.160 mg/l
0
At 20 C, DO concentration in water is 9.08 mg/l and the DO concentration in the aeration tank is 2 mg/l.
When α=0.50, β=0.95 and diffuser fouling factor, F=0.9,
SOTR
=AOTR[ ](1.02420-t)
=188.693× 1.02420-25
=504.603 kg/h
Here, the nitrification rate will control the system as nitrifying organisms grow more slowly than the
heterotrophic organisms that remove organic carbon. Therefore the specific growth rate of nitrifying
organisms should be estimated and first nitrification kinetic coefficients are estimated at the design
temperature. (25 0C)
Following are the equations that are used to estimate the kinetic coefficients of nitrification at different
temperatures.
Kn,25 = Kn θt-20
=0.74×1.05325-20
=0.572 g NH4-N/m3
Following is the summary of the kinetic coefficient values used in the design.
10
The specific growth rate for nitrifying organisms is given by,
( )( )
=( )( )
=( )( )
=0.134 g/g.d
S – Substrate concentration
SRT – Solid retention time
0.336 g bCOD/m3
The biomass production rate for BOD removal with nitrification is given by,
Where,
11
The VSS production rate is given by,
Where,
As nitrogen balance cannot be performed yet, first an assumed value for NOx (80% of TKN) was taken and the
calculations were done. Later when doing the nitrogen balance, the initial value taken for NOx was changed as
the error between the assumed and calculated values would be minimum. Thus the value obtained for NOx is
98.53% of TKN.
Q =35000 m3/day
S0 =input bCOD
=300 g bCOD/m3
= 3360.907 kg VSS/d
=282.481 kg VSS/d
=83.391kg VSS/d
D =Q(nbVSS)
=35000 × 8.257 × 10-3
=288.991 kg nbVSS/d
=A+B+C
=3360.907 + 282.481 + 83.391
=3726.779 kg VSS/d
12
=A+B+C+D
=4193.183 + 157.244 + 288.991
=4015.769 kg VSS/d
The amount of nitrogen oxidized to nitrate can be found by performing nitrogen balance using following
equation,
NOx = ⁄
3
=35 – 0.5 - 3726.779×10 /35000
=34.487 g/m3
Error
= ×100%
=(34.487 – 34.486)/34.486 × 100%
=0.005%
As the error is negligible, the calculations were continued with the assumed NOx value.
4.5 Determination of Mass of MLVSS and Mass of MLTSS in the Aeration Tank
The mass of VSS and TSS in the aeration tank can be determined using,
Therefore,
Mass of MLVSS =
=4015.769 × 11.207
=45002.816 kg MLVSS
Mass of MLTSS =
=5023.436 × 11.207
= 56295.259 kg MLVSS
The mass of TSS in the aeration tank can also be determined using following relationship.
13
Therefore,
V =
=56295.259 × 1000/3000
=18765.086 m3
τ - Detention time
τ =V/Q
=18765.086×24/35000
=12.867 h
The concentration of the MLVSS (X)in the aeration tank can be calculated by,
F/M =QS0/XV
=35000×300/(2398.221×18765.086)
= 0.233 kg/kg.d
BOD =QS0/V
=35000×300/18765.086
=0.560 kg/m3.d
14
YObs,VSS =0.386 g VSS/g bCOD × 1.6 g bCOD/g BOD
= 0.613 g VSS/g BOD
The O2 demand for the aeration tank for BOD removal, can be calculated by,
=
=35000× (300-0.336)×10-3 - 1.42×3726.779+
4.33×35000×34.486
= 10422.736 kg/d
AOTR =R0/24
=10422.736/24
= 434.281kg/h
SOTR
=AOTR[ ](1.02420-t)
= 434.281 × 1.02420-25
=1161.352 kg/h
From section 1.8, the amount of oxygen per unit mass of air,
kg O2/ m3 air =0.259 kg/m3 air
4.11 Alkalinity
When nitrogen is oxidized to nitrate, the medium become acidic. But the medium should be maintained about
pH 7. Therefore by performing an alkalinity balance over aeration tank, the amount of alkalinity to be added to
maintain pH at 7 could be found.
15
Alkalinity used for nitrification = Amount of nitrogen converted to nitrate
× 7.14 g CaCO3 /g NH4-N
= 34.487 × 7.14
= 246.239 g/m3 as CaCO3
The residual alkalinity needed to maintain pH in the range of 6.8 – 7.0 is about 70 to 80 g/m3 as CaCO3. Taking
residual alkalinity needed as 80 g/m3 as CaCO3,
The alkalinity requirement is expressed in terms of sodium bicarbonate as, sodium bicarbonate is preferred
over lime for alkalinity addition due to ease of handling and less scaling.
⁄ ⁄ ⁄
For a well operating activated sludge process with an SRT ≥4 days, the effluent soluble BOD is usually less than
3 mg/l. With a proper secondary clarifier design and good settling sludge, the effluent suspended solids may
be in the range of 5 – 15 mg/l. Thus taking sBODe as 3 mg/l and effluent TSS as 10 mg/l,
16
5. Design of Secondary Clarifier
Secondary Clarifier
Q + QR Qe
Q X Xe
Aeration Tank
QR
QW
XR
XW
Assuming Xe is negligible,
(Q + QR) X = QRXR+ QWXW
Assuming waste sludge mass is insignificant,
(Q + QR) X = QRXR
QR (XR -X ) = QX
QR /Q = X/(XR -X )
R = X/(XR -X )
= 3000/(8000 – 3000)
= 0.6
The range of average flow for the secondary clarifier is 16 to 28 m3/m2.d. Therefore assuming a hydraulic
application rate to the secondary clarifier as 22 m3/m2.d ,
17
The solid loading to the secondary clarifier should be in the acceptable range of 4 to 6 kg/m2.h.
6. Summary
Table 6.1: Summary
Design Parameter Units BOD Removal Only BOD Removal and
Nitrification
Average wastewater flow m3/d 35000 35000
Aerobic SRT d 5.000 11.207
Hydraulic detention time h 6.580 12.867
MLSS g/m3 3000 3000
MLVSS g/m3 2417.564 2398.221
F/M g/g.d 0.453 0.233
BOD loading kg BOD/m3 d 1.094 0.560
Sludge production kg/d 5757.141 5023.436
Observed yield kg TSS/kg bCOD 0.879 0.766
kg VSS/kg BOD 0.708 0.613
Oxygen required kg/h 188.693 434.281
Air flow rate of average wastewater m3/min 92.703 213.357
flow
RAS ratio 0.6 0.6
Clarifier hydraulic application rate m3/m2d 22 22
Clarifiers Number 4 4
Diameter, m 22.6 22.6
References
Metcalf and Eddy Inc. (2003) Wastewater Engineering: Treatment and Reuse. Fourth edition. McGraw – Hill
Companies Inc.
18