Sei sulla pagina 1di 22

OFFSHORE SERVICE SPECIFICATION

DNV-OSS-300

RISK BASED VERIFICATION


APRIL 2004

DET NORSKE VERITAS


FOREWORD
DET NORSKE VERITAS (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, prop-
erty and the environment, at sea and onshore. DNV undertakes classification, certification, and other verification and consultancy
services relating to quality of ships, offshore units and installations, and onshore industries worldwide, and carries out research
in relation to these functions.
DNV Offshore Codes consist of a three level hierarchy of documents:
— Offshore Service Specifications. Provide principles and procedures of DNV classification, certification, verification and con-
sultancy services.
— Offshore Standards. Provide technical provisions and acceptance criteria for general use by the offshore industry as well as
the technical basis for DNV offshore services.
— Recommended Practices. Provide proven technology and sound engineering practice as well as guidance for the higher level
Offshore Service Specifications and Offshore Standards.
DNV Offshore Codes are offered within the following areas:
A) Qualification, Quality and Safety Methodology
B) Materials Technology
C) Structures
D) Systems
E) Special Facilities
F) Pipelines and Risers
G) Asset Operation
H) Marine Operations

Amendments and Corrections


This document is valid until superseded by a new revision. Minor amendments and corrections will be published in a separate
document on the DNV web-site; normally updated twice per year (April and October). To access the web-site, select short-cut
options "Technology Services" and "Offshore Rules and Standards" at http://www.dnv.com/
The electronic web-versions of the DNV Offshore Codes will be regularly updated to include these amendments and corrections.

Comments may be sent by e-mail to rules@dnv.com


For subscription orders or information about subscription terms, please use distribution@dnv.com
Comprehensive information about DNV services, research and publications can be found at http://www.dnv.com, or can be obtained from DNV,
Veritasveien 1, N-1322 Høvik, Norway; Tel +47 67 57 99 00, Fax +47 67 57 99 11.

© Det Norske Veritas. All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means, including
photocopying and recording, without the prior written consent of Det Norske Veritas.

Computer Typesetting (FM+SGML) by Det Norske Veritas.


Printed in Norway.

If any person suffers loss or damage which is proved to have been caused by any negligent act or omission of Det Norske Veritas, then Det Norske Veritas shall pay compensation to such person
for his proved direct loss or damage. However, the compensation shall not exceed an amount equal to ten times the fee charged for the service in question, provided that the maximum compen-
sation shall never exceed USD 2 million.
In this provision "Det Norske Veritas" shall mean the Foundation Det Norske Veritas as well as all its subsidiaries, directors, officers, employees, agents and any other acting on behalf of Det
Norske Veritas.
Offshore Service Specification DNV-OSS-300, April 2004
Introduction – Page 3

INTRODUCTION
This Service Specification was approved by the Director of
Technology in April 2004.
Publication of this Service Specification will make the Service
Specification DNV-OSS-303 obsolete.
— This general document gives the common framework and
an overview of processes in risk based verification.
— It introduces a levelled description of verification involve-
ment during all phases of an asset’s life.
— The document facilitates a categorisation into risk levels
High, Medium and Low, assisting in an evaluation of the
risk level.
— The document assists in planning the verification through
the making of a Verification Plan.
— Providing an international standard allowing a transparent
and predictable verification scope, as well as defining ter-
minology for verification involvement.

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Contents – Page 5

CONTENTS

Sec. 1 General.................................................................. 7 E 300 Acceptance criteria ......................................................... 13

A. General.................................................................................... 7 F. Simplified Verification Planning..........................................15


A 100 Introduction....................................................................... 7 F 100 General............................................................................ 15
A 200 Objectives ......................................................................... 7
A 300 Scope of application.......................................................... 7 G. Detailed Verification Planning .............................................15
A 400 Structure of DNV Offshore Service Specifications G 100 General............................................................................ 15
related to verification ........................................................ 7
A 500 Structure of this document................................................ 7 H. Risk Based Verification and National Regulations ..............15
A 600 Structure of related DNV documents ............................... 7 H 100 General............................................................................ 15
B. Definitions and Abbreviations................................................ 8 App. A Benefits of DNV Risk Based Verification......... 16
B 100 General.............................................................................. 8
B 200 Definitions ........................................................................ 8 A. General..................................................................................16
B 300 Abbreviations ................................................................. 8 A 100 Background information................................................. 16
C. References .............................................................................. 9 A 200 Verification trends .......................................................... 16
C 100 General............................................................................. 9 A 300 Benefits of DNV Risk Based Verification...................... 16
A 400 Other DNV services related to Risk Based Verification 17
Sec. 2 Principles of Risk Based Verification ............... 10
App. B Verification and Certification Documents ....... 18
A. General.................................................................................. 10
A 100 Objectives ....................................................................... 10 A. Verification Documents........................................................18
A 100 Purpose of Verification Documents................................ 18
B. General Verification Principles ............................................ 10 A 200 Validity of Verification Documents ............................... 18
B 100 Purpose of Verification................................................... 10 A 300 Verification Documents Provided ................................. 18
B 200 Verification as a Complementary Activity ..................... 10
B 300 Verification Based on Risk ............................................. 10 B. Certification documents........................................................19
B 400 Verification Management ............................................... 10 B 100 General............................................................................ 19
B 200 Validity of Certification documents ............................... 19
C. Risk Based Verification Concept ......................................... 10
C 100 Elements of the service .................................................. 10 App. C Example List of Typical High Risk Elements .. 20
C 200 Asset Planned.................................................................. 11
C 300 Asset Specification ......................................................... 11 A. High Risk Elements ..............................................................20
C 400 Risk Assessment ............................................................. 11 A 100 Offshore installations...................................................... 20
C 500 Definition of Verification Involvement .......................... 11
C 600 Verification Plan ............................................................. 11 App. D Detailed Performance Requirements and
C 700 Verification Execution.................................................... 12
C 800 Asset Completed ............................................................. 12 Verification
Activity Descriptions........................................... 22
D. Risk-Differentiated Levels of Verification........................... 12
D 100 Levels of verification ...................................................... 12 A. Performance Requirements...................................................22
A 100 Setting performance requirements.................................. 22
E. Defining a Verification Plan................................................. 13
E 100 Risk based verification planning .................................... 13 B. Verification Activities ..........................................................22
E 200 Selection of Level of Verification .................................. 13 B 100 Developing Verification Activity Lists .......................... 22

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 6 – Contents

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Sec.1 – Page 7

SECTION 1
GENERAL

A. General overall philosophy and services. The object-specific docu-


ments describe the principles and give detailed information re-
A 100 Introduction garding the potential scope of work for the verification of each
object.
101 This DNV Offshore Service Specification (DNV-OSS)
gives an overview of DNV Verification Services. 403 An object-specific DNV-OSS provides a basis for the
development of scope of work for verification activities. Sec-
A 200 Objectives tion 2 gives the service overview and principles for scope of
201 The main objectives of this document are to: work descriptions. Detailed examples of scope of work tables
are found in appendices to the object specific documents.
— describe DNV’s Risk Based Verification services 404 Some of the object-specific documents also give re-
— provide a common communication platform for describ- quirements to achieve and maintain a DNV Certificate of Con-
ing the extent of verification activities, i.e. how to define formity (Ref. Appendix B).
a verification scope
— give guidance to owners and other parties for selecting the A 500 Structure of this document
level of involvement of the verifier 501 This document contains two sections and four appendi-
— provide an opportunity to establish efficient, cost effec- ces:
tive, predictable and transparent verification plans.
Section 1 gives the scope of the document, definitions and ref-
A 300 Scope of application erences.
301 This specification applies to verification during the as- Section 2 explains the philosophy and principles of Risk Based
set owner’s control of the process leading up to the completion Verification. It explains the risk-differentiated levels of in-
of a physical asset, and further during the lifetime of the asset volvement, the elements in the RBV chain and the different
until abandonment. methodologies within risk assessment to develop a Verifica-
tion Plan.
302 This specification is primarily aimed at oil and gas re-
lated facilities and installations located onshore or offshore. Appendix A gives the benefits of a targeted and planned veri-
The principles may also be applied to general industrial devel- fication.
opments.
Appendix B gives an overview of the main verification and cer-
303 This specification may be adopted for full field develop- tification documents issued by DNV, including the DNV Cer-
ment, particular phases of an asset realisation process or for tificate of Conformity and the DNV Statement of Compliance.
particular elements. The owner may chose to utilise DNV’s re-
sources for all or selected parts of the scope. Appendix C is an example list of typical high risk elements for
the main types offshore installations
304 DNV’s Risk Based Verification services may be carried
out on assets specified in: Appendix D gives information on how to develop detailed per-
formance requirements and verification activities.
— DNV’s Offshore Standards,
A 600 Structure of related DNV documents
— International or national standards, or
— Owner’s specification 601 The DNV document systems consist of a three-level hi-
erarchy with these main features:
A 400 Structure of DNV Offshore Service Specifications
related to verification — Principles and procedures related to DNV’s services are
separate from technical requirements and are presented in
401 The DNV Offshore Service Specifications related to DNV Offshore Service Specifications. The documents
verification are organised according to the pyramidal princi- described in Figure 1 belong here.
ples in Figure 1.
— Technical requirements are issued as self-contained DNV
Offshore Standards.
General — Associated product documents are issued as DNV Recom-
DNV- service mended Practices.
OSS-300 overview
602 The hierarchy is designed with these objectives:

DNV-OSS-3nn — Offshore Service Specifications present the scope and ex-


Object specific tent of DNV’s services.
detailed — Offshore Standards are issued as neutral technical stand-
ards to enable their use by national authorities, as interna-
specifications
tional codes and as company or project specifications
without reference to DNV’s services.
— The Recommended Practices give DNV’s interpretation
of safe engineering practice for general use by industry.
Figure 1
Hierarchy of DNV’s offshore service specifications for verifica- Guidance note:
tion The latest revision of all DNV documents may be found in the
publications list on the DNV web site www.dnv.com.

402 The top level document DNV-OSS-300, describes the ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 8 – Sec.1

B. Definitions and Abbreviations or maintained. Can refer to a full field development, a topside
facility, a pipeline system, a compressor station etc. or a part of
B 100 General these. It is interchangeable with the term Asset.
101 The following definitions should be applied only in the 210 Owner: In the document used not just to describe the ac-
context of this document, and may not necessarily be appropri- tual owner, but also to used to reflect DNV’s contractual part-
ate for services outside the Risk Based Verification approach ner. In many projects the owner authorises the contractor to act
as described. on his behalf and it shall then mean the contractual partner.
B 200 Definitions 211 Performance requirement: A description of the essential
requirements to be met, maintained or provide on demand by
201 Asset: Loose term used to describe the item to be made an element. Appendix D may be used for guidance.
or maintained. Can refer to a full field development, a topside
facility, a pipeline system, a compressor station etc. or a part of 212 Risk: The qualitative or quantitative likelihood of an ac-
these. It is interchangeable with the term Object. cident or unplanned event occurring, considered in conjunc-
tion with the potential consequences of such a failure. In
202 Certificate of Conformity: A document signed by a qual- quantitative terms, risk is the quantified probability of a de-
ified party affirming that, at the time of assessment, the product fined failure mode times its quantified consequence.
or service met the stated requirements (BS 4778: Part 2).
Guidance note:
Guidance note: Risk is not only related to physical failure modes, but also to op-
For this OSS, a Certificate is a short document (often a single erational errors, human errors and so on. For some risks the func-
page) stating conformity with specified requirements. The results tional failures or physical failure modes contribute less than 20%
from associated verification shall be contained in a separate (sin- while more than 80% of the risk relates to other devices.
gle or multiple volume) report.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
213 Risk Reduction Measures: Those measures taken to re-
203 Certification: Used in this document to mean all the ac- duce the risks to the operation of the system and to the health
tivities associated with the process leading up to the Certifi- and safety of personnel associated with it or in its vicinity by:
cate.
Guidance note: — Reduction in the probability of failure.
In the DNV- OSS when Certification is used it designates the — Mitigation of the consequences of failure
overall scope of work or multiple activities for the issue of a Cer-
tificate, whilst Verification is also used for single activities asso- Guidance note:
ciated with the work. This in essence means that Certification is The usual order of preference of risk reduction measures is:
Verification for which the deliverable includes the issue of a Cer-
tificate. a) Inherent Safety.
Other (related) definitions are: b) Prevention.
BS 4778: Part 2: Certification: The authoritative act of docu- c) Detection.
menting compliance with requirements.
d) Control.
EN 45011: Certification of Conformity: Action by a third party,
demonstrating that adequate confidence is provided that a duly e) Mitigation.
identified product, process or service is in conformity with a spe- f) Emergency Response.
cific standard or other normative document.
ISO 8402: 1994: Verification: Confirmation by examination and ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
provision of objective evidence that specified requirements have
been fulfilled. 214 Safety Objectives: The safety goals for the construction,
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e--- operation and decommissioning of the asset including accept-
ance criteria for the level of risk acceptable to the Owner.
204 Element: Loose term which can mean anything from a 215 Statement of Compliance: A statement or report signed
drilling rig to a system or a component. the level of detail will by a qualified party affirming that, at the time of assessment,
depend on the situation. In a hierarchic structure elements are the defined asset phase, or collection of activities, met the re-
below asset. quirements stated by the Owner.
205 Hazard: A deviation (departure from the design and op- 216 Verification is confirmation by examination and provi-
erating intention) which could cause damage, injury or other sion of objective evidence that specified requirements have
form of loss (Chemical Industries Association HAZOP been fulfilled (ISO 8402: 1994).
Guide).
Guidance note:
206 HAZOP (HAZard and OPerability study): The applica- The examination shall be based on information, which can be
tion of a formal systematic critical examination to the process proved true, based on facts obtained through observation, meas-
and engineering intentions of new or existing facilities to as- urement, test or other means.
sess the hazard potential of mal-operation or mal-function of See also Certification.
individual items of equipment and their consequential effects
on the facility as a whole (Chemical Industries Association ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
HAZOP Guide).
207 HAZID, (HAZard IDentification): A technique for the B 300 Abbreviations
identification of all significant hazards associated with the par- 301
ticular activity under consideration. (ISO-17776)
208 Life cycle: Loose term which includes all phases of an DNV Det Norske Veritas
asset; concept studies, front end engineering design (FEED), OS Offshore Standard, used in the form DNV-OS
design, procurement, fabrication, hook-up, commissioning, OSS Offshore Service Specification, used in the form
operation/ production, maintenance, inspection and abandon- DNV-OSS
ment. QRA Quantitative Risk Analysis
209 Object: Loose term used to describe the item to be made RBV Risk Based Verification

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Sec.1 – Page 9

C. References 103 BS4778 Quality Vocabulary, Part 2 Quality concepts


and Related Definitions, 1991, British Standard Institute, Lon-
C 100 General don
101 A guide to Hazard and Operability studies, 1979, Chem- 104 EN 45011 General Criteria for Certification Bodies Op-
ical Industries Association Limited. London erating Product Certification, 1998, European Committee for
102 ISO 8402 Quality – Vocabulary, 1994, International Or- Standardization, Brussels
ganization for Standardization, Geneva 105 ISO 17776 Petroleum and natural gas industries – Off-
shore production installations - Guidelines on Tools and Tech-
niques for Hazard Identification and Risk Assessment, 2000,
International Organization for Standardization, Geneva.

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 10 – Sec.2

SECTION 2
PRINCIPLES OF RISK BASED VERIFICATION

A. General oretical and practical knowledge and experience of the activity


being examined. An adequate verification of some activities
A 100 Objectives may require access to specialised technical knowledge.
101 The objectives of this section are to provide: 403 As well as demonstrating competence of individuals,
the verification organisation shall also be able to show compe-
— an introduction to the DNV Risk Based Verification Con- tence and experience in verification work for relevant assets.
cept and the elements of the Risk Based Verification
Chain
— an introduction to the principles of risk differentiated lev-
els of verification activities C. Risk Based Verification Concept
— guidelines on the selection of levels of verification.
C 100 Elements of the service
101 The risk based verification concept can be visualised to
involve the elements in Figure 1. It is a chain with iterative
B. General Verification Principles loops.
B 100 Purpose of Verification
101 Verification constitutes a systematic and independent Asset Planned
examination of the various lifecycle phases of an asset to de-
termine whether it is (or continues to be) in compliance with
some or all of the asset specifications. Asset Specification
102 Verification activities are expected to identify errors or including overall Owner acceptance criteria,
failures in the work associated with the asset and to contribute
to reducing the risks to the operation of the asset and to the performance requirements and verification
health and safety of personnel associated with it or in its vicin- objectives
ity or other unwanted situations.
B 200 Verification as a Complementary Activity Risk Assessment
201 Verification shall be complementary to routine design, including identification of hazards and
construction and operations activities and not a substitute for
them. Therefore, although verification will take into account ranking of hazards based on risk evaluation
the work, and the assurance of that work, carried out by the
owner and its contractors, it is inevitable that verification will
duplicate some work that has been carried out previously by
other parties involved in the asset or system. Definition of Verification Involvement
B 300 Verification Based on Risk including detailing of acceptance criteria and
301 Verification based on risk is founded on the premise that performance requirements
the risk of failure can be assessed in relation to a level that is
acceptable and that the verification process can be used to
manage that risk. The verification process is therefore a tool to Verification Plan
maintain the risk below the acceptance limit.
including list of verification activities
302 Verification based on risk aims to be developed and im-
plemented in such a way as to minimise additional work, and
cost, but to maximise its effectiveness. The development of a
risk based verification plan shall depend on a risk assessment
and the findings from the examination of quality management Verification Execution
systems, documents and production activities. including reporting of compliance or non-
B 400 Verification Management compliance
401 The philosophy and verification methods used shall be
described in a Verification Plan to ensure satisfactory comple-
tion of verification. Asset Completed
The philosophy and these methods should ensure that verifica-
tion: Figure 1
The DNV Risk Based Verification Chain
— has a consistent and constructive approach to the satisfac-
tory completion and operation of the asset
— is available world-wide wherever the owner or his contrac- 102 Asset is used collectively. It is an onshore or offshore in-
tors operate stallation or part thereof, a system or process, or a development
— uses up-to-date methods, tools and procedures phase such as feasibility, design, construction, commissioning,
— uses qualified and experienced personnel. operation and decommissioning.
402 All verification activities shall be carried out by compe- 103 The Asset Planned and Asset Decommissioned are the
tent personnel. Competence includes having the necessary the- boundaries of the Risk Based Verification process.

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Sec.2 – Page 11

104 Asset Specification, Risk Assessment and Definition of that risk. Similarly, if the risk was very small it would not be rea-
Verification Involvement are inputs into the Verification Plan, sonable to expect great expense or effort to be incurred in reduc-
while Verification Execution is the implementation of the Ver- ing it.
ification Plan. ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
The Risk Based Verification service comprises of one, some or
all of these main elements. 405 The systematic assessment of risks and the implementa-
tion of measures to reduce these, results in a relative ranking of
C 200 Asset Planned the risk level of the elements and /or sub-elements of the asset.
201 Asset Planned is the starting point for any project or 406 The ranking of the elements will differ depending on the
project phase and is the decision of the owner. It comprises a acceptance criteria; safety, environmental impact, economics,
general description of the project in the form of functionality, schedule, public relations, reputation or others. Different crite-
safety, capacity, economics etc. ria may be applied to factor the importance of these.
C 300 Asset Specification C 500 Definition of Verification Involvement
301 Asset Specification has been identified as a separate el- 501 Definition of verification involvement or level(s) in-
ement to focus on the need to address objectives, acceptance cludes defining the cut-off level under which no verification
criteria and performance requirements to the asset. activity shall be performed and to define the appropriate level
302 This element in the chain comprises: of involvement for the others.
502 Based on the relative risk level of the elements the ver-
— detailing of the description at the system level of the ification intensity should increase towards the highest risk ele-
project in the form of functionality, safety, capacity, eco- ments.
nomics etc.
— identification or definition of verification philosophy, Guidance note:
safety objectives etc., including selection of safety and/or Verification of risk reducing measures e.g. in the form of risk re-
business and/or environmental focus and goals ducing barriers, should be directed towards the risk reducing
— identification of codes and technical specifications (e.g. measures (barriers) which claims to have the highest risk reduc-
ing effects.
standard company material specifications) to be adopted
— definition of high level performance requirements for the ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
asset and identification of main elements and specific per-
formance requirements thereof. 503 In this process the overall acceptance criteria from the
Asset Specification should be cascaded down to more detailed
303 The detailing of elements and requirements will vary performance requirements for individual elements or groups of
from project to project. The timing for detailing will also vary elements.
and is affected by matters like contract type and philosophy,
owners involvement in the process, level of innovative ele- 504 The risk ranking is used in the selection of the appropri-
ments in the project, life time business philosophy etc. ate verification activity level and type to be described in the
verification plan.
C 400 Risk Assessment
C 600 Verification Plan
401 Risk Assessment is the identification of hazards, fre-
quencies of occurrence, consequences and risk drivers. The 601 The Verification Plan is the pivot element in the DNV
risk can be defined on a general level for the project, for differ- Risk Based Verification systematics.
ent phases of a project or for detailed elements of the asset. 602 The Verification Plan is the scope of work (SOW) for
402 The risk can be evaluated based on safety, environmen- verification. It should be revisited, re-evaluated and possibly
tal impact, economics, schedule, Public Relations, reputation revised as the project progresses and new information becomes
or other criteria set by the owner. available.
403 Risk Assessment can be based on engineering judge- 603 The more specific the Verification Plan, the more pre-
ment (pragmatic) or on analytical processes. In section E dif- dictable the verification activities will be.
ferent methods have been described to arrive at the conclusions
necessary to formulate a risk based verification plan. 604 The Verification Plan repeats the verification objective
and the criteria for selecting the highest risk elements and the
404 Once the risks have been identified their extent can be verification involvement, as given by the Owner. It includes
reduced to a level as low as reasonably practicable or as low as the findings from the risk assessment step, defines which asset
corporately required, by means of one or both of: specifications shall be verified, and also the level of involve-
ment by party and type of verification activity.
— reduction in the probability of failure
— mitigation of the consequences of failure. 605 The Verification Plan further consists of listing the el-
ements and their performance requirements together with the
Guidance note: type and depth of scrutiny to which each shall be subjected.
Reasonable Practicability 606 The verification involvement level can be described us-
The term “as low as reasonably practicable (ALARP)” has come ing the tables in Sect.2 of the relevant object specific DNV-
into use through the United Kingdom’s “The Health and Safety OSS.
at Work etc. Act 1974”. Reasonable Practicability is not defined
in the Act but has acquired meaning by interpretations in the 607 Detailed scope of work tables listing all the sub-ele-
courts. ments of an asset, can either be developed from the tables in
Sec. 2 of the relevant object specific DNV-OSS or they can be
It has been interpreted to mean that the degree of risk from any based on the example tables included in the appendices.
particular activity can be balanced against the cost, time and trou-
ble of the measures to be taken to reduce the risk. 608 For information typical high risk elements with respect
It follows, therefore, that the greater the risk the more reasonable to safety of personnel, often termed Safety Critical Elements,
it would be to incur substantial cost, time and effort in reducing are presented in Appendix C.

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 12 – Sec.2

C 700 Verification Execution Guidance note:


701 Verification Execution is document review, independent An element can be everything from a drilling rig to an important
analyses, inspection, monitoring, site visits, process audits, component or system, depending on the detailing level of the risk
assessment being carried out.
technical audits, testing, etc. according to the Verification
Plan. ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
702 Information arising from execution should be used to
identify continuous improvements to the Verification Plan.
E.g. evidence of good systematic control may be used to re- Increasing

Probability of Failure
High
duce the verification activities. Risk
HIGH
703 The purpose of verification activities is to confirm com-
pliance or identify non-compliance with the asset specifica-
tion. MEDIUM

C 800 Asset Completed

Low
LOW
801 Asset Completed is the end point of any lifecycle phase
or phases, which complies with the relevant planned asset and Low High
the asset specification. Consequence of Failure
Figure 2
Levels of verification
D. Risk-Differentiated Levels of Verification
D 100 Levels of verification
A
101 The level of verification activity should be differentiat- B
ed according to the risk to the asset or element or phases there-
C
Elements

of. If the risk to the asset is higher, the level of verification


involvement is higher. Conversely, if the risk to the asset is D
lower, the level of verification activities can be reduced, with- E
out any reduction in their effectiveness. F
102 It is emphasised that the activity level describes the G
depth of the verification involvement. It follows, therefore, H
that an increase in the level of involvement above that consid- I
ered necessary, based on an evaluation of the risks, involves
minimal extra risk reduction for increased cost. This practice is
unlikely to be cost-effective.
Axis of increasing risk
103 Verification of assets or elements thereof are typically and depth of scrutiny
categorised into Low, Medium and High. Figure 3
Low is the level of verification applied where the risks to the Increasing verification scrutiny as a function of increasing risk
asset are lower than average. For example, it has benign con- level for each element
tents, it is located in congenial environmental conditions, or
the contractors are well experienced in the design and con-
struction of similar assets. This level may also be appropriate 105 It is the prerogative of the owner of the asset system to
when the Owner (or other parties) performs a large degree of choose the level of verification. The selection should be docu-
verification and/or quality assurance work. mented.
Medium is the customary level of verification activity and is 106 Different levels of verification can be chosen for differ-
applied to the majority of assets. ent lifecycle phases of the asset, or even within the same phase
if necessary. For example, asset design may be innovative and
High is the level of verification applied where the risks to the considered high risk whereas the installation method is well
asset is higher than average. For example, it has highly corro- known and considered low risk. The converse might be true al-
sive contents, it is in adverse environmental conditions, it is so.
technically innovative or the contractors are not well experi-
enced in the design and construction of similar assets. This lev- 107 The level of verification can be reduced or increased
el may also be appropriate when the Owner chooses to have a during a phase if the originally chosen level is considered too
small technical involvement or performs little own verifica- rigorous or too lenient, as new information on the risks to the
tion. asset becomes available. Care should be taken to ensure that
short term gains do not influence the reduction of verification,
Guidance note: which could lead to a long term detriment.
The terms Basic, Regular and Special are sometimes used to de-
scribe the level of involvement. If these are used in connection 108 Verification should be planned in close co-operation
with DNV Risk Based Verification, then Basic shall mean Low, with the Owner and each of the contractors, to provide a scope
Regular shall mean Medium and Special shall mean High. of work that is adjusted to the schedule of each lifecycle ele-
ment, i.e. to make the verification activities, surveillance and
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
hold points, an integrated activity and not a delaying activity.
104 Illustrations of the levels of involvement are given in Guidance note:
Figures 2 and 3. Figure 2 illustrates the levels as a function of Many Contractors have adequate quality control systems and
probability and consequence of failure. Figure 3 illustrates quality control departments, with competent personnel to per-
how increasing depth of scrutiny is assigned to elements with form, for example, inspection at plants and specialist engineers
increasing risk levels. competent to review and verify the performance of plants.

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Sec.2 – Page 13

In that case, all verification work need not be done by DNV per- ing the Verification Plan the appropriate analytical tools can be
sonnel. Where applicable, the various inspections may be carried utilised.
out by competent persons other than DNV personnel.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
In that situation a substantial part of DNV’s verification activities
may be encompassed by:
E 200 Selection of Level of Verification
- reviewing the competence of the Contractor’s personnel,
- auditing their working methods and their performance of that 201 Suitable selection factors include:
work, and
- reviewing the documents produced by them. — overall asset specification
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
— assessment of the risks associated with the asset and the
measures taken to reduce these risks
109 Verification should direct greatest effort at those ele- — degree of technical innovation in the asset system
ments of the asset or system whose failure or reduced perform- — experience of the contractors in carrying out similar work
ance will have the most significant impact on safety or the — quality management systems of the Owner and their con-
other defined project risks. These elements are termed high tractors.
risk elements or sometimes Critical Elements.
202 To facilitate the selection of the level of verification a
110 The degree of confidence placed in verification reports set of trigger questions based on the above list of selection fac-
depends on the degree of confidence in the verification activi- tors, has been prepared and is included in the object specific
ties carried out. Therefore, the verification plan must be trans- DNV-OSS.
parent and give clear details of the level of verification for both
elements and phases. 203 To further assist in the selection of general level of ver-
ification Table E1 can give some guidance.
204 The level of verification is selected for each individual
element and should reflect the risk level as well as the type of
E. Defining a Verification Plan performance requirements.
E 100 Risk based verification planning Guidance note:
101 The selection of the level of verification shall depend on To achieve a consistent verification involvement relative to risk
level a practical and visual approach can be to plot the elements
the risk level of each element having an impact on the manage- and relative risk levels as in Figure 3. Decide on the maximum
ment of hazards and associated risk levels of the asset. level of involvement (L, M or H) and draw the line to the left of
102 The effort spent to select the overall level of verification which no verification shall be made. The area enveloping the el-
and the detailing and differentiation between different ele- ements to be verified can then be split in to areas with uniform
verification involvement.
ments will vary from project to project. It is a business decision
on how to balance the effort of up-front planning with that of ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
some additional effort during verification execution.
103 The tools used to arrive at a Verification Plan range E 300 Acceptance criteria
from engineering judgement risk assessment to analytical risk 301 Defined acceptance criteria are essential to confirm
assessments. The former generally reflects less effort in the up- compliance and identify non-compliance.
front planning stage while the latter directs more efforts into
the particulars of a specific project. 302 The format and detailing may differ. Assets, elements or
lifecycle phases for which technical standards or company
104 The span in the method is illustrated in Figure 4. Most specifications exist, may have relatively short and simple ac-
projects will utilise a combination of tools. ceptance criteria. For assets, elements or lifecycle phases not
Guidance note: readily covered by prescriptive standards, greater effort is di-
Typically, for a tender phase it may be useful to utilise engineer- rected into the particulars of the specific project and this often
ing judgement to make an initial Verification Plan. When updat- results in more detailed performance requirements.

Table E1 Levels of verification and guidance on typical involvement at system level


Level Typical System Characteristics Description of typical verification involvement
Low — Proven designs with relatively harmless content and/or in- — Review of General Principles and production systems dur-
stalled in benign environmental conditions. ing design and construction.
— State of the art design, manufacturing and installation by — Review of principal design documents, construction pro-
experienced contractors. cedures and qualification reports.
— Low consequences of failure from a commercial, safety or — Site attendance only during system testing.
environmental point of view. — Less comprehensive involvement than level Medium.
— Relaxed to normal completion schedule.
Medium — Asset in moderate or well controlled environmental condi- — Review of General Principles and production systems dur-
tions. ing design and construction.
— Plants with a moderate degree of novelty — Detailed review of principal and other selected design
— Medium consequences of failure from a commercial, safe- document with support of simplified independent analy-
ty or environmental point of view. ses.
— Ordinary completion schedule. — Full time attendance during (procedure) qualification and
review of the resulting reports.
— Audit based or intermittent presence at site.
High — Innovative designs. — Review of General Principles and production systems dur-
— Extreme environmental conditions. ing design and construction.
— Plants with a high degree of novelty or large leaps in tech- — Detailed review of most design document with support of
nology. simplified and advanced independent analyses.
— Contractors with limited experience or exceptionally tight — Full time attendance during (procedure) qualification and
completion schedule. review of the resulting reports.
— Very high consequences of failure from a commercial, — Full time presence at site for most activities.
safety or environmental point of view. — More comprehensive involvement than level Medium.

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 14 – Sec.2

Asset
Specification

Simplified verification Detailed verification


Combined
planning, based on verification planning, based on
Engineering judgement planning Analytical risk assessment:

Risk assessment HAZID for the asset. This may be done


based on trigger stepwise with increasing detailing on the
questions. more complex components/processes.

Conclude on The predefined tables may be useful


overall references
Risk Identify
Assessment verification elements for
involvement; verification
H, M or L Frequency of occurrence Consequence
and prepare
verification
plan based
on any Analytical assessment of risk and
Prepare combination identification of relative risk levels.
Verification of the The relative risk may be grouped into
Plan based on simplified Low, Medium or High
predefined and detained
tables. verification
planning.
Include Define acceptance criteria or performance
Definition of requirements in more detail
Verification adjustments to
Level tailor for the
particular asset. Prepare Verification Plan based on the
assessed risks, risk drivers and acceptance
Confirm criteria as defined above.
acceptance The type and depth of verification is
criteria to be described using the same terminology as used
sufficient. in the predefined tables.

Verification
Plan

Figure 4
Verificaton planning

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Sec.2 – Page 15

F. Simplified Verification Planning 103 A description on how to carry out HAZID, HAZOPD
and QRA in general is not given in this DNV-OSS. The meth-
F 100 General odology is described in numerous books and publications on
101 Simplified verification planning is mainly based on en- the subject.
gineering judgment and reflects DNV's in-house experience as 104 Particularly for projects or project elements were there
well as the industry experience as reflected in a number of are limited or inadequate prescriptive technical standards or if
technical standards. Both have been used to make up the object the performance requirements are of a nature that make avail-
specific DNV-OSS’s. able prescriptive standards inadequate, it is advisable to invest
102 The steps in the simplified verification planning are as more time and effort in the planning stages.
follows: 105 With limited prescriptive standards the need and also the
effort required to define the acceptance criteria for individual
— Use trigger questions to assess the overall risk level of the or groups of elements will normally increase. Appendix D ad-
project (or manageable elements thereof). dresses how to formulate detailed performance requirements
— Evaluate the risk against the relevant owner or project ac- and also how these and the risk elements are developed into
ceptance criteria (often this can be directly tied to the own- verification activity lists, which are finally included in the Ver-
er core values or a sub-set of these) and decide whether the ification Plan
general verification involvement shall be Low, Medium or
High.
— Use the detailed scope of work tables in the object DNV-
OSS to make a first draft of a Verification Plan H. Risk Based Verification and National
— Generate the project specific Verification Plan by include
a project specific engineering judgment to adjust the table Regulations
to suit the project
— Perform the verification execution according to the Verifi- H 100 General
cation Plan, making revision to the plan if and when nec- 101 Many national authorities have specific requirements to
essary. the verification activities. These can be in the form of mini-
mum requirements to documentation of risk and risk reducing
103 Care shall be taken not to use this process without suf- measures, which documents shall be presented to the authori-
ficient attention to its built-in simplifications. Particularly the ties, mandatory use of standards etc. The authorities may also
use of example tables in the appendices can never replace the have requirements to roles and responsibility, independence of
need for project specific assessments. They can, however, be verifier, content and form of verification activities, terminolo-
very useful starting and reference points. gy etc.
102 The particulars of the relevant national requirements
shall be observed when planning and performing Risk Based
G. Detailed Verification Planning Verification.
Guidance note:
G 100 General The Offshore Installations (Safety Case) Regulations in UK can
101 The analytical verification planning is based on the use be an example of particular National Authority requirements.
of (quantitative) risk methods to establish project specific The risk based verification approach fits very well with these reg-
identification of the relative risk level of the project elements. ulations, but one needs to ensure that the correct documents and
terminology are used and understood e.g. Major Accidents Haz-
102 Depending on the project size and type the risk assess- ards, Safety-Critical Elements, Performance Standards etc.
ment will often include an initial qualitative risk assessment
screening prior to a full quantitative risk analysis, QRA. ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 16 – App.A

APPENDIX A
BENEFITS OF DNV RISK BASED VERIFICATION

A. General phases can often be determined by what is addressed in inter-


national technical standards and from general experience. For
A 100 Background information these projects the ability to communicate the correct or desired
101 This appendix gives background information on verifi- level of verification may be the most time consuming exercise.
cation and the possible benefits thereof. 211 At the other end of the scale are the projects that have
greater uncertainty, and often appears to be high risk, but
which need to be systematically addressed to be able to identi-
A 200 Verification trends fy the hazards, the probability and consequences of occurrence
and the risk levels of the elements. For these projects the cor-
201 Verification has historically been carried out with a va- rect identification and ranking of the risk of the elements is es-
riety of scope and depth of involvement. The depth of involve- sential for the project optimisation process and planning of the
ment, or level of verification, has not always been very verification activities. However, it is also for these necessary
transparent. to be able to communicate the level of verification and link it
202 There are national authorities requiring verification or to the associated risk.
even certification of offshore or onshore installations (assets) 212 For almost all projects, interface activities are important
and have appointed specific organisations qualified for this and many have experienced that inadequate interface manage-
work. ment can be very costly and time consuming.
203 Some of these national authorities may have detailed re-
quirements to the verification or certification activity, while A 300 Benefits of DNV Risk Based Verification
others leave the definition of the necessary work up to the ap- 301 Business today is characterised by the need to balance
pointed organisation. Other national authorities require specif- cost and benefits through a better understanding and mastering
ic documents to be verified and approved by them, some hold of the assets and their associated risks. Risk Based Verification
the owner responsible for the verification activities, others aims at balancing the efforts to control the operational and
again may not have any specific requirements. technological risks and for an optimum control of risks and un-
204 The trend is that authorities remove themselves from the certainties from the concept stage to decommissioning or
prescriptive regimes and convert to functional requirements abandonment of any asset. It may provide cost and time sav-
and safety and risk approaches. It is therefore believed that ings compared with prescriptive verification or certification by
there will be a stronger demand for measurable objectives to be focusing on risk and by prioritising verification efforts.
presented by the owners. The objectives are linked, as a mini- 302 The use of a more elaborate analytical method to plan
mum, to the expectations from the authorities on safety to the the verification may give substantial cost benefits during the
work force, the public and the environment. Economics may verification execution. Particularly for projects characterised
be an additional minimum requirement from the owner and his by the following:
partners.
— a high degree of complexity
205 As a means to fulfilling these expectations business to- — significant elements of new or unproven technology
day is often characterised by a defined desire to systematically — proven elements being introduced to new operating condi-
balance expected costs and benefits. The aim is an optimum tions or applications
control of the uncertainties (or risks) related to the objectives. — participants having limited experience in a type of asset or
206 Even where national authorities do not require verifica- development
tion of installations (assets), verification (or certification) is a — challenging development programmes.
convenient tool for the owner to get an independent evaluation
of the contractor(s) work or to show financiers, partners, insur- 303 DNV aims through Risk Based Verification, to instil
ers and the public that the asset complies with relevant safety confidence in our customers. Through independent and com-
levels and other requirements in the asset specification. petent scrutiny the intent is to confirm that the asset is de-
signed, constructed and/or operated so that:
207 It is good business practice to subject important work to
a third-party check as this reduces the possibility of errors re- — it is fit for its intended purpose,
maining undetected. Third-party verification will ensure that — its level of integrity is as high as reasonably practicable
the verifier has an independent view and perspective when per- — the associated risk to health, life, property and environ-
forming this activity. Furthermore, it will avoid the situation ment is as low as reasonably practicable.
where errors could be overlooked by engineers or others be-
cause of their closeness to the work with the asset. 304 Such confidence arising from Risk Based Verification is
208 Systematic risk based assessment methods are more of- not necessarily limited to DNV’s traditional customers – it can
ten used to identify the risk associated with the elements. be extended to contractors or other project participants, own-
Based on this identified risk, focus is put on the relevant ac- ers, financiers, partners, insurers etc. that an asset complies
ceptance criteria pertaining to integrity, functionality, surviva- with a relevant basis, even in areas where formal references
bility, availability, reliability, maintainability, and may be missing or are under development.
environmental impact of an asset throughout its lifecycle. 305 The advantages for DNV’s customers in applying a Risk
209 The result of the systematic identification of risk can be Based Verification approach may include:
utilised in the design and construction by the Contractor and by — reduced probability of undesirable events
the Owner or a 3rd party to optimise the verification activities — improved availability and reliability
through a well defined and transparent verification plan. — cost and time savings through avoiding undue attention to
210 Not all projects nor all high risk elements have great de- areas and activities that are low contributors to risk
grees of novelty or innovation requiring a large degree of so- — contributing to optimised expenditure (CAPEX, OPEX
phistication when predicting risk. The high risk elements or and RISKEX) in high risk areas

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
App.A – Page 17

— early involvement in projects to ensure correct decisions


and minimal rework
— a demonstrable and auditable case for safety or other own- Input
er or project core values
— active support to, and demonstration of achievement of,
these core values
— confirmation, and increased visibility, of the above to Management
(project) partners and other stakeholders and to Regulato-

Verification Planning
ry Bodies.

Risk Management
306 For a new asset development Risk Based Verification

Verification
services should seek to reduce any uncertainty in the design as
Design
early as possible, and if any weaknesses are revealed allow for
effective management of necessary changes, ref. Figure 2 “Ef-
Construction
fects of Early Involvement”. DNV’s verification experience
reinforces the important message of early involvement and the
Operation
need for in-depth knowledge of the activities required to obtain
optimal resource allocation for the verification process. A
proactive approach is required and places particular emphasis
on roles and responsibilities. Management

Optimum output
Figure 2
Increase

Ability to Cost of The asset realisation process


Influence Change

310 The optimisation can be regarded as the process to


shrink the total volume of the circle in Figure 2 and to find the
Concept Commissioning
ideal balance between Contractor and 3rd party volumes within
that circle.
Time
311 Alternatively, the volume of the ball can be used to indi-
cate the cost of the process. The correct balance between the
Figure 1 two sides may reduce the total volume of the whole process
Effect of early involvement and at the same time achieve the optimum asset. By optimum
asset we mean one that through its lifecycle is suitable for the
operation and has the correct balance between the quality, cost,
307 The above processes should consider all phases of the environmental impact, safety, schedule and any other elements
asset lifecycle. For example during the offshore commission- defined by Owner.
ing phase of a new asset there may be temporary items of A 400 Other DNV services related to Risk Based Verifi-
equipment provided which should be identified as high risk el- cation
ements (e.g. temporary fire/gas detection).
401 Any of the areas of Risk Based Verification involvement
308 DNV believes that a strong focus on the development of can be integrated with other DNV services, potentially with
the Verification Plan will support a common interpretation of enhanced effectiveness, such as:
verification philosophies and requirements (which may differ — Project Risk Management
from one project to another), and this should facilitate a more — assisting with development of project HSE philosophy
cost effective verification execution and provide for greater — conducting, or participating in, Hazid
potential value to be obtained from the overall verification — risk studies or assessments (e.g. QRA)
process. — reviewing the customer’s formal safety assessment (safety
case) to confirm the adequacy and robustness of the proc-
309 Database applications (for example DNV’s Verifier ess
software) can be implemented to assist with development and — providing a suitable computer application to manage veri-
execution of Verification Plans, including the capability to fication requirements and findings
record the status of all verification activities, and provide re- — managing other legislative compliance requirements on
behalf of the customer or asset owner
ports on their status. Such database applications can assist co- — developing or reviewing Reliability Centred Maintenance
ordination by making the status available to all involved in ver- (RCM) and Risk Based Inspection (RBI) philosophies and
ification, including the customer, simultaneously. procedures.

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 18 – App.B

APPENDIX B
VERIFICATION AND CERTIFICATION DOCUMENTS

A. Verification Documents
A 100 Purpose of Verification Documents Statement of Compliance
101 Verification documents are issued by DNV. The pur- with accompanying
pose of these documents is to provide documentation that ob- verification report
jective evidence has been presented to confirm compliance
with the requirements and to document the work performed by
DNV.
Guidance note:
Examples of document forms are found in the objects specific Verification Report
DNV-OSS.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---

102 Intermediate verification documents act as a form of


progress reporting showing satisfactory completion of com- Intermediate documents
plete life cycle verification activities for various issues, items
or phases of the asset.
Figure 1
103 The verification documents follow the hierarchy shown Document hierarchy for verification
below and in Figure 1:
— Statement of Compliance A 200 Validity of Verification Documents
— Verification Report
— Intermediate documents 201 Verification documents are, in principle, documents
confirming that an examination has been carried out, and are
— Audit reports valid only at the time of issue.
— Verification Comments
A 300 Verification Documents Provided
— Visit reports
301 The types of documents issued by DNV relative to the
104 A description of each of these is given in the respective different stages of the verification process are illustrated by
object specific DNV-OSS. Table B1.

Table B1 Asset VERIFICATION – Documents provided by DNV


Reference Standard DNV Offshore Standard or other agreed technical standard
for verification
Design Construction Operation
Manufacturing of

Manufacturing of

Operation, Main-
Equipment and
Detail Design

Components

tenance and
Completion
Assemblies
Conceptual

Installation
Design

Project

Project Phases Repair

Types of Verification
Documents Provided Statement of Compliance for individual phase or natural part thereof

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
App.B – Page 19

B. Certification documents
Certificate of Conformity
B 100 General
with accompanying
101 DNV Certification is a special form of verification verification report
where the total scope is defined by DNV. Reference is given to
the section on definitions. For statutory certification the scope
should in principle be defined by the regulating body.
102 The certification documents consist of the verification
documents described above with an overlying Certificate of Statement of Compliance
Conformity. Hence, the hierarchy of documents are as illus- with accompanying
trated in Figure 2. In relation to the project phases, reference is
given to Table B1. verification report
B 200 Validity of Certification documents
201 In general the same validity, i.e. the time of issue, ap-
plies as for verification documents.
Verification Report
202 However, for Certificates of Conformity, a specified pe-
riod of validity and maintenance conditions for ensuring this
validity may be given in the certificate.

Intermediate documents

Figure 2
Document hierarchy for certification

Table B1 Asset CERTIFICATION – Documents Provided by DNV


Reference Standard DNV Offshore Standard
for certification
Design Construction Operation
Manufacturing of

formity (retention) Maintenance and


Manufacturing of
Equipment and
Detail Design

Components

Completion
Assemblies
Conceptual

Installation

Operation,
Project
Design

Repair
Project Phases

Certificate of Con-
Certificate of
Conformity

Types of Statement of Compliance for individual phase or natural part


Certification thereof
Documents Provided

Pre - Maintenance of
Certification phase Certification Certification Certification

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 20 – App.C

APPENDIX C
EXAMPLE LIST OF TYPICAL HIGH RISK ELEMENTS

A. High Risk Elements ments (ref e.g. UK Safety Case regime). This list is intended as
a tool to help to ensure that key systems identified as high(est)
A 100 Offshore installations risk are not omitted. However, the list can never be guaranteed
101 The following table presents typical high risk elements to be exhaustive and shall never be used without due consider-
with respect to safety of personnel for the main types of off- ations.
shore installation. These are often called safety critical ele-

FPSO/FPU
FLOTEL
MODU

FOI
TYPICAL HIGH RISK ELEMENTS

STRUCTURE
Jackets and Piles - - - X
Gravity Based Structure - - - X
Jack-up Legs and associated Jacking and Locking Systems X X - -
Hull (including Watertight Closures) X X X -
Drilling Derrick X - - X
Firewater Caisson and Supports - - - X
Topsides Primary Structure including Bridge and Flare Tower X X X X
Helideck X X X X
Lifting (cranes) and Hoisting (drilling equipment) X X X X
Crane Pedestal X X X X
Foundations X X X X
Blast Protection including Blast Venting Provisions X - X X
Dropped Object Protection incl. Subsea Protective Structures X X X X
Turret - - X -
DRILLING
Mud Systems X - - X
Blowout Preventer System X - - X
Choke and Kill (including Emergency Blowdown) X - - X
Cement System X - - X
Marine Riser System X - - X
Well Control Instrumentation X - - X
Diverter system X - - X
POWER
Emergency Power X X X X
Battery Systems X X X X
Protection of Electrical Equipment X X X X
IGNITION PREVENTION
Electrical Earthing Continuity X X X X
Electrical Equipment in Hazardous Areas X X X X
Protection of Hot Surfaces X X X X
Natural Ventilation X X X X
FIRE AND GAS
Gas (Flammable and Toxic) Detection System X X X X
Fire Detection System X X X X
Deluge X X X X
Sprinklers X X X X
Fire Pumps X X X X
Firewater Ring Main X X X X
Foam System X X X X
Gaseous Systems (e.g. Halon, CO2) X X X X
Passive Fire Protection (including Doors, Walls and Penetrations) X X X X
Ventilation Systems X X X X
EMERGENCY RESPONSE AND EVACUATION
Temporary Refuge X X X X

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
App.C – Page 21

Escape Routes X X X X
Helideck Systems (Markings, Nets, Obstacle Marking/Lighting etc.) X X X X
Escape (battery-backed) Lighting X X X X
Internal Communications (e.g. Public Address,/General Alarm, Manual Alarm Call Points, Tel- X X X X
ephones)
External Communications (including Marine and Aviation) X X X X
TEMPSC X X X X
PPE (incl. Lifejackets, Survival/Immersion Suits, Helideck Crash Equip.) X X X X
ESCAPE SYSTEMS
Descent to Sea Systems (Personal Descent Devices, Knotted Ropes, Nets) X X X X
Ladders to Sea X X X X
Life rafts X X X X
Standby Vessel and associated Fast Rescue Craft X X X X
HYDROCARBON CONTAINMENT
Hydrocarbon Piping and Equipment (including Valves and Instrumentation) - - X X
Emergency Shutdown System including Software, Process Shutdown, High Integrity Protection X X X X
Systems, Overpressure Protection Systems etc.
Relief and Blowdown System X X X X
High Speed Machinery Trips X - X X
Local Atmospheric Vents X - X X
Drains (Open and Closed Hazardous) X X X X
Risers and Riser Emergency Shutdown Valves - - X X
Pipelines - - X X
Pipeline Subsea Isolation Valves - - X X
MARINE
Mooring (including Move-off) X X X -
Navaids (including Lights, Foghorns, Marine/Weather Monitoring Systems) X X X X
Radar Early Warning System X X X X
Ballast and Bilge (Stability) X X X -
Inert Gas System - - X -
Dynamic Positioning System X X X -
Thrusters X X X -
TEMPORARY EQUIPMENT
Bridge Connections to Support Vessels X X X X
Gas Cylinders and Attachments X X X X
Power Generators X X X X
Temporary Public Address/General Alarm Systems X X X X
Well Test Equipment X - - X
Radioactive Source Store X - X X
Explosives Store X - - X
SAFETY MANAGEMENT SYSTEM X X X X

DET NORSKE VERITAS


Offshore Service Specification DNV-OSS-300, April 2004
Page 22 – App.D

APPENDIX D
DETAILED PERFORMANCE REQUIREMENTS AND VERIFICATION
ACTIVITY DESCRIPTIONS

A. Performance Requirements ure on demand for each safety function (complete loop),
consistent with the concept of Safety Integrity Level (SIL) as de-
A 100 Setting performance requirements scribed in IEC 61508.
101 Performance requirements should describe the essential ---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
requirements that a high risk element must meet, maintain, or
provide on demand. Ideally it is a statement, which can be ex-
pressed in qualitative or quantitative terms, of the performance B. Verification Activities
required of a system, item of equipment or procedure and
which is used as the basis for managing a risk and any events B 100 Developing Verification Activity Lists
requiring emergency response, through the lifecycle of the as- 101 The objective of an activity is to confirm that the per-
set. formance requirements are achieved. The verification activity
102 The most suitable performance requirement should ide- list constitutes the main pert of the Verification Plan and cor-
ally satisfy all of the following conditions: responds to the example tables included as Appendix to the ob-
ject specific DNV-OSS.
— it requires measurement of the performance/capability of
a parameter of the component/system 102 The list should give details of what needs to be done, by
— the measured parameter provides evidence of the ability of whom and when. For each performance requirement there
the component/system to prevent, or limit the effect of, an should be at least one examination activity. The activity list
unplanned event should include:
— acceptance criteria/range are defined for the parameter in — what is to be done – a description of the examination ac-
question tivity to be performed to verify that the criteria specified in
— the parameter can be monitored/measured. each performance requirement is met
Guidance note:
— type of examination activity to be performed, e.g. inspec-
tion, witness, review, monitoring
DNV’s experience is that performance requirements should be at — extent of involvement in activity, where applicable (e.g.
a level that sets an objective for the element in question, they
should not describe how that objective is to be achieved, or how percentage of sample)
it is to be demonstrated (verified), this is part of the verification — how often it is to be repeated (if at all, e.g. for initial suit-
plan. ability only)
— unique identifier for each activity, for control and report-
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e--- ing purposes (ideally aligned to high risk element and per-
formance requirement identifier)
103 As a minimum the following characteristics should be — a clear reference to a specific performance requirement
considered in generating performance requirements: and high risk element for each activity
— note of specific documents or processes (e.g. planned
— functionality – what the element must achieve maintenance activities, rolling inspection programmes)
— reliability – how often it will be required to operate satis- which will be used as a basis for verification or for refer-
factorily ence as part of the examination activity.
— availability – how often it will be required to operate on
demand 103 The activity list should state which examinations shall
— survivability – the conditions under which it will be re- only be performed prior to the high risk element being put into
quired to operate, e.g. if exposed to fire, blast, vibration, service (examination for “initial suitability”). No further activ-
ship impact, dropped objects, adverse weather etc. ities of this type will be performed during operation, unless
modifications are made to the element. Other examination ac-
104 The consequence of a performance requirement not be- tivities (examination for continued suitability), especially dur-
ing met (demonstrated) should also be considered. If the con- ing the operational phase, should be repeated at intervals
sequences are such that an unplanned event cannot result, or a specified to ensure that the high risk element to which it refers
significant reduction in the effectiveness to prevent, detect, maintains its suitability and adequacy.
control, mitigate, or monitor a major unplanned event cannot
result, then the performance requirement should not be consid- 104 The following may contribute to the specification of in-
ered as necessary. terval or frequency of examination:
105 In the same way that parts of an asset may be considered — requirements of recognised codes and standards,
as high risk for certain periods of its lifecycle it is possible for — risk assessments
performance requirements to be applicable during specific — assumptions and conclusions of risk and/or reliability
phases of an asset’s lifecycle only. At all times that a part of an studies on relevant systems
asset is high risk, there must be at least one performance re- — extent of installation maintenance routines and inspection
quirement. plans
Guidance note: — interval between the asset operator’s assurance activities,
— manufacturer’s recommendations for the equipment
Quantitative performance requirements for reliability or availa-
bility of an element are essential for high risk elements contain- — findings of previous examination activities (including
ing instrument-based protective systems. Where such those for related high risk elements or performance re-
performance requirements are specified, it is recommended that quirements).
the precise requirements are fully defined (i.e. not just “reliability
to be ....”), that there is a clear means of verifying the require- 105 The activity list may often (but optionally) be contained
ment, and that verification can provide positive demonstration of in a database application in order to facilitate the dynamic
the element’s suitability. DNV’s preferred style of such perform- process of modifications and updates, and also provides for a
ance requirements is to specify the maximum probability of fail- powerful management and reporting tool.

DET NORSKE VERITAS

Potrebbero piacerti anche