SUMMARY

EVALUATION OF PRODUCTIVITY EXCAVATOR AND TRANSPORT


TOOLS IN COAL MINING ACTIVITIES IN PIT YUDISTIRA AT PT. PUTRA
MUBA COAL, DISTRICT SUNGAI LILIN, MUSI BANYUASIN REGENCY,
PROVINCE OF SOUTH SUMATERA
Scientific paper in the form of Skripsi, October 2018

M Andriyansya, Supervised by Ir. A. Taufik Arief, M.S and Bochori, ST, MT

Evaluasi Produktivitas Alat Gali-Muat dan Alat Angkut pada Kegiatan


Penambangan Batubara di Pit Yudistira di PT. Putra Muba Coal., Kecamatan
Sungai Lilin, Kabupaten Musi Banyuasin, Provinsi Sumatera Selatan

xiv + 45 pages, 11 Pictures, 8 Table, 7 Attachments

SUMMARY

PT. Putra Muba Coal is one of the coal mining companies located in Mekar Jadi Village,
District Sungai Lilin, Musi Banyuasin Regency, South Sumatra Province. Coal mining is
done by stripping the overburden first. The work system between the Digging-loading tool
and the conveyance at PT. Putra Muba Coal has a coal production target of 180,000 tons/
month at the Pit Yudistira. The mechanical equipment consists of 2 Digging-loading units
namely CAT 340D2 L Excavator with a capacity of 1,755 m3 and CAT 375L Excavator
with a capacity of 1,355 m3 combined with 21 Hino FM 260 JD dump trucks with a
capacity of 25.5 m3. The working series of this tool works on 1 working front of extracting
and transporting coal. The excavation and loading patterns applied are Top Loading
patterns with Single Back Up. Real production produced by the working combination is
160.083 tons / month,
Effective work time will be evaluated to achieve monthly production goals. The effective
working time in the company's plan has not been achieved where the working time of the
excavator and conveyance is (71%) and in actual fact there is a difference in loading
equipment (70%) for transport equipment (60%) so it is still possible to increased effective
work time is done by reducing or suppressing the time of obstacles that can be avoided.
The time that can be avoided is emphasized again so that work efficiency increases. Match
Factor calculations whose values are obtained from the productivity of the excavator and
conveyor and the effective working time obtained by the value of the work combination is
obtained by a value of 0.95 - 0.87 (MF <1), which means the digging tool waits for the
conveyance. Improvement of the working time of the transport equipment by reducing the
work time that can be avoided is obtained by producing 180,454 which means the
production target is reached.

Keyword : Coal, Producivity, Digging-loading and Hauling, Production, Match


Factor Pit Yudistira
Cititation : 12 (1968-2003)