ENGINEERING ESTIMATE FOR PROPOSED CONSTRUCTION

OF

TRANSITIONAL BUS TERMINAL

AT

BOGAMBARA

Package No. SCDP/WB/WK/KD/27


MINISTRY OF MEGAPOLIS AND WESTERN DEVELOPMENT

STRATEGIC CITIES DEVELOPMENT PROJECT

PROPOSED CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA

CONTRACT NO. SCDP/WB/WK/KD/27

GRAND SUMMARY
BILL NO DESCRIPTION AMOUNT (LKR)

Bill No. 1 PRELIMINARIES 10,199,400.00

Bill No. 2 TRANSITIONAL BUS STAND 107,067,165.00

Bill No. 3 RPTA OFFICE BUILDING - UPPER FLOOR 12,663,511.00

Bill No. 4 IMPROVEMENTS TO THE ROAD 7,565,400.00

Bill No. 5 PROVISIONAL SUMS 19,119,600.00

Bill No. 6 DAY WORKS 2,188,750.00

SUB TOTAL 158,803,826.00

ALLOW 10% PHYSICAL CONTENGENCIES 15,880,382.60

ALLOW 5% PRICE CONTENGENCIES 7,940,191.30


BID PRICE (EXCLUDING VAT) CARRIED FORWARD TO LETTER OF 182,624,399.90
BID
ADD VAT 15% 27,393,659.99

TOTAL AMOUNT 210,018,059.89


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA BILL NO. 1

BILL NO. 1

PRELIMINARIES
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA BILL NO. 1

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

1.1 Allow for submission of performance bond as


specified in Contract Data and as per
specimen form provided (Actual cost for
submission of performance guarantee shall be
reimbursed to the Contractor. Payment for
provisional sum item shall be made for actual
bill, submitted by the contractor.)

LS 84,000.00 84,000.00
-
1.2 Provisional sum for insurance of work , plant &
machinery, materials, third party and workmen's
compensation (Payment for provisional sum
item shall be made for actual bill, submitted by
the contractor.)
LS 504,000.00 504,000.00
-
1.3 Allow for submission of advance payment
guarantee as specified in Contract Data and as
per specimen form provided (Actual cost for
submission of advance payment guarantee shall
be reimbursed to the Contractor subject to
submission of documentary evidence).

LS 333,000.00 333,000.00

1.4 Mobilization of Contractor's facilities and


plant/Equipment and maintain throughout the
contract period including fencing around the site.

LS 6,609,600.00 6,609,600.00
-
1.5 De-Mobilization of Contractor's facilities and
Plant/Equipment on completion of works as per
approval of Engineer
LS 240,000.00 240,000.00

1.6 Provide, furnish and removal at the end of the


contract, Engineer's office (as per the Appendix
01) with sanitar, electricity, water supply

LS 753,600.00 753,600.00
-
1.7 Maintain above 1.6 item facilities throughout the
contract.
Months 6.00 18,000.00 108,000.00

-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA BILL NO. 1

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


1.8 Provide & maintain project sign boards of size
3000 x 2400mm made of 32 gauge zinc coated
sheet, 3/4" x 3/4", 2mm box bar frame, support
with 2" dia. GI pipes, 3/4" x 3/4" 2mm box bar
supporter, writing in Sinhala, Tamil, English.
Rate to include for posts & concrete base etc.
(Sketch drawing for frame work is attached for
Appendix - 02)

Item 84,000.00 84,000.00


-
1.9 Removal of all rubbish and debris, clearing up the
site and leaving building clean internally and
externally at the completion of the project
work.
Item 72,000.00 72,000.00
-
1.10 Traffic Management, safety and control and
provision of traffic control personals in required
numbers at entrance and exit to site for vehicle
entry and exit as directed by the Engineer and
according to the EMP
Months 6.00 91,200.00 547,200.00

1.11 Allow for encironmental and social mitigation


measures according to the EMP and SIMP
Months 6.00 36,000.00 216,000.00

1.12 Allow for prepare and submission of soft and


hard copy of construction programme using MS
Project or similar software for approval of the
Enginner
Item 12,000.00 12,000.00

1.13 Provide for setting out of works, provision of shop


drawings, erection of notice board and maintaing
weather chars, Man power utilization schedule
and progress of works.
636,000.00 636,000.00

-
TOTAL OF BILL NO. 1 CARRIED TO GRAND Rs 10,199,400.00
SUMMARY
MINISTRY OF MEGAPOLIS AND WESTERN DEVELOPMENT

STRATEGIC CITIES DEVELOPMENT PROJECT

PROPOSED CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA

CONTRACT NO. SCDP/WB/WK/KD/27

SUMMARY - BILL NO. 2


BILL NO DESCRIPTION AMOUNT (LKR)

Bill No. 2.1 EXCAVATION AND EARTHWORK 4,530,920.00

Bill No. 2.2 CONCRETE WORK 13,799,280.00

Bill No. 2.3 MASONRY WORK 1,171,200.00

Bill No. 2.4 WATER PROOFING 693,540.00

Bill No. 2.5 STRUCTURAL METAL WORK 31,925,520.00

Bill No. 2.6 METAL WORK 5,100,996.00

Bill No. 2.7 ROOF COVERING / ROOF PLUMBING 8,405,400.00

Bill No. 2.8 PLUMBING / SANITARY INSTALLATION 7,725,036.00

Bill No. 2.9 MECHANICAL INSTALLATION 4,301,453.00

Bill No. 2.10 ELECTRICAL INSTALLATION 13,160,584.00

Bill No. 2.11 FLOOR / WALL / CEILING FINISHES 3,722,340.00

Bill No. 2.12 PAINTING 705,696.00

Bill No. 2.13 EXTERNAL DRAINAGE SYSTEM 352,800.00

Bill No. 2.14 EXTERNAL WORKS 11,472,400.00

TOTAL OF BILL NO. 2 CARRIED TO GRAND SUMMARY 107,067,165.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

BILL NO. 2

TRANSITIONAL BUS STAND


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

2.1 EXCAVATION AND EARTH WORK

Tenderers are advised to refer to relevant


preamble notes, drawings and specifications
before pricing each work section.

Before starting any operation at site, the


relevant authority shall be informed and obtain
prior approval.

Note:

All excavations are measured net. No allowance


is made for working space.

Rate for Shoring & dewatering included for


excavation.

Rock blasting if necessary for the excavation,


shall be paid separately.

2.1.1 Clearing the site including removal of roots,


growth of every description cutting down top soil
and existing foundations if any , all up to an
average depth of 150mm extended up to 3m
beyond the outer wall of the proposed building
including trees & stumps girth < 500 mm and
carrying away the waste materials from the site
where directed by the Engineer.

sq.m 2,080.00 116.00 241,280.00

2.1.2 Excavating trenches for wall foundation / Strip


footings commencing from formed ground level
width > 300 mm, depth not exceeding 1.5 m in
any type of soil (Except Rock requiring blasting).
Rate to include handling, backfilling , compaction
& transporting any excess from the site as
directed by the Engineer.

cu.m 40.00 1,620.00 64,800.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.1.3 Excavating foundation for column pits
commencing from formed ground level width >
300 mm, depth not exceeding 1.5 m in any type
of soil (Except Rock requiring blasting). Rate to
include handling, backfilling , compaction &
transporting any excess from the site as directed
by the Engineer.

cu.m 330.00 1,620.00 534,600.00

2.1.4 Excavation over site to reduce level (depth 1.0m)


in any material (except rock requiring blasting)
including depositing and levelling as directed by
the Engineer up to a distance not exceeding 10
Km from the site)
cu.m 4,620.00 762.00 3,520,440.00

Filling & Compaction

Note:-
Approved earth shall mean filling materials that
comply to the following :
( a ) The earth shall be free of vegetation, roots,
boulders, easily decomposable materials,
chemicals, industrial waste, plastic etc.
( b ) The maximum size of particle shall not
exceed 75mm.
( c ) The earth shall be well graded and the silt
and clay (fines) content shall not be lmore than
25%
( d ) The Standard proctor density shall be
greater than 1.70g/cm3

2.1.5 Approved hard earth supply & filling under


floors with approved quality soil watered
rammed and wet consolidated in 150 mm
thick layers to insure the compaction final
proctor density should be 95% .Rate to
include handling and transporting of approved
quality material as directed by the Engineer.

cu.m 35.00 2,880.00 100,800.00

Anti-termite Treatment
Note:
Termite treatment should be applied to all new
construction. Contractor shall submit and get
approval from Engineer for method statement
before commence the works.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Allow for anti termite treatment for barrier and
colony elimination at preconstruction stage. The
service provider should hold a valid license for
termite treatment issued from register
Department of Agriculture. Rate to include for a
complete treatment with

1. Treatment before placing the foundation


2. Treatment after placing floor concrete.
3. Treatment along the periphery of the building.

The services provider should give minimum 10


years warranty against termite treatment. The
service provider should submit the list of
Termiticide intended to use for Engineer's
approval. The following minimum requirements
to be maintained.

1. Application rate 5l/m2


2. Termiticide Concentration : 12.5ml/L
3. Termite pump pressure rate : 250 psi

2.1.6 Application of anti termite treatment (Biflex or


equivalent) under the ground floor slab including
1.2m beyond the outer wall in accordance with
the manufacture's specifications and to the
approval of Engineer

sq.m 250.00 276.00 69,000.00

TOTAL OF EXCAVATION AND EARTHWORK Rs. 4,530,920.00


CARRIED TO SUMMARY

2.2 CONCRETE WORKS

INSITU - CONCRETE

Note :-
Mass concrete Grade 15 (25 mm agg.) - including
supply, placing, compacting and curing.

Constituent material shall comply to following;


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


(i) River sand shall satisfy with the grading
criteria prescribed in Table 4.2 in the ICTAD
Publication SCA/4/I. & the clay content shall not
be more than 4%.

Reinforced concrete Grade 25 (20 mm agg.) -


Volume Batched, including supply, placing,
compacting and curing.

Constituent material shall comply to following;

(i) Cement of strength class 42.5N and shall


comply with SLS 107 (Ordinary Portland
Cement), that has been stored under proper
conditions and has manufactured within 90 days
at the time of concreting.

(ii) Clean river sand without impurities and clay


particles of grain distribution falling within the
prescribed grading limit in BS 882:1992.

(iii) Clean portable water

Contractor shall made available following


equipment at site before starting to concrete.

(i) Cube moulds -6Nos

(ii) Mixer and Vibrator (in working condition)

Payment for concreting shall be made upon


submission of following.

(a) Concrete cube crushing strength test results;


28 day results shall be available to make full
payment.

READY MIX CONCRETE

Requirement for Readymix concrete

Readymix Concrete - Contractor shall submit and


get approval from The Engineer for method
statement before commence the works.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


1. Minimum cement content shall be 300 kg/m3

2. Nominal maximum size of aggregate shall be


20mm.
3. Slump shall be 120mm ± 25mm - Maximum
temperature 300C
4. Maximum free water / cement ratio to be 0.5

5. Coarse and Fine aggregate used shall confirm


to BS 882 latest version
6. Concrete grade shall be as specified.
7. Concrete mix design shall be approved by the
Engineer or Engineer's nominated Senior
Technical officer.

8. The Ready mix supplier's plant should have


been calibrated in the recent past.
9. Testing
Collection of samples for testing shall be at the
point of placing. One sample per 5m3, one
sample shall mean 3 test cubes

Readymix Concrete - Confirming to SLS 1144-


1997, Rate shall include for transport 20km from
batching plant.

UP TO DPC LEVEL

Mass concrete Grade 15 (25 mm agg.)

2.2.1 Screed in column bases & strip foundation cu.m 15.00 17,040.00 255,600.00

Reinforced Concrete Grade 25

2.2.2 Beds and slabs on ground 150mm thick with


reinforcement R06@150mm c/c, b/w. (Readymix
Concrete)
cu.m 185.00 22,392.00 4,142,520.00

2.2.3 In column bases (Readymix Concrete) cu.m 100.00 18,504.00 1,850,400.00

2.2.4 In Isolated columns shaft. (Readymix Concrete)


cu.m 11.00 18,600.00 204,600.00

2.2.5 In Plinth beams / Tie beams (Readymix Concrete)


cu.m 62.00 18,600.00 1,153,200.00

ABOVE STRUCTURAL FLOOR LEVEL

GROUND FLOOR TO ROOF LEVEL

Reinforced Concrete Grade 25


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

2.2.6 In Slabs including sunshades.(Readymix Concrete)


cu.m 7.00 19,200.00 134,400.00

2.2.7 In Isolated columns shaft. (Readymix Concrete)


cu.m 5.00 19,200.00 96,000.00

2.2.8 In Attached beams. (Readymix Concrete) cu.m 2.00 19,200.00 38,400.00

2.2.9 In lintels 100x150mm size, 2Y10 with form works


Lm 90.00 540.00 48,600.00

2.2.10 In window sill 100x150mm size, 2Y10 with form


works
Lm 30.00 540.00 16,200.00

FORM WORK

Note :-
The rates given for items herein are applicable
for 15 mm thick plywood sheets.

Formwork - Contractor shall submit and get


approval from Engineer for method statement
with drawings before commence the works.

UP TO DPC (SF) LEVEL

2.2.11 Side of column bases sq.m 245.00 1,440.00 352,800.00

2.2.12 Side of Isolated column shaft sq.m 120.00 1,440.00 172,800.00

2.2.13 Side of plinth beam / Tie beam sq.m 420.00 1,440.00 604,800.00

ABOVE STRUCTURAL FLOOR LEVEL

GROUND FLOOR TO FIRST FLOOR LEVEL


Form work

2.2.14 Slab thickness < 150mm..including sunshade sq.m 55.00 1,680.00 92,400.00

2.2.15 Side of Isolated column shaft sq.m 90.00 1,500.00 135,000.00

2.2.16 Side/soffit of attached beam. sq.m 26.00 1,680.00 43,680.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.2.17 Side of Slab L.m 35.00 1,500.00 52,500.00

REINFORCEMENTS IN INSITU CONCRETE

Rate to include for supplying, cleaning, cutting ,


bending, fabricating, binding wires, distance
blocks, ordinary spacers, wastage, laps, placing
and provision of all necessary temporary fixing
and supports. No allowances in made for rolling
margin.

Mild steel bar reinforcement to BS 4449 and


strength (FY=250 N/mm²) including bends,
hooks, tying wire, distance blocks and ordinary
spacers.

High yield tor steel bar reinforcement to BS 4449


and strength (FY=460 N/mm²) including bends,
hooks, tying wire, distance blocks and ordinary
spacers.

UP TO DPC (SF) LEVEL

Mild Steel

Diameter<10mm

2.2.18 In Isolated columns shaft. kg 710.00 192.00 136,320.00

2.2.19 In plinth beam / Tie beams kg 2,500.00 192.00 480,000.00

Tor Steel

10 mm < Diameter<16mm

2.2.20 In column base kg 5,200.00 198.00 1,029,600.00

2.2.21 In column shaft kg 1,250.00 198.00 247,500.00

2.2.22 In plinth beam / Tie Beams kg 7,300.00 198.00 1,445,400.00

16 mm < Diameter< 25mm

2.2.23 In column base kg 2,350.00 198.00 465,300.00

2.2.24 In column shaft kg 800.00 198.00 158,400.00

ABOVE STRUCTURAL FLOOR LEVEL

GROUND FLOOR TO ROOF LEVEL


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

Mild Steel

Diameter<10mm

2.2.25 In isolated columns shaft. kg 150.00 198.00 29,700.00

2.2.26 In attached beam . kg 50.00 198.00 9,900.00

Tor Steel

Diameter<10mm

2.2.27 In Suspended slab. kg 450.00 198.00 89,100.00

10 mm < Diameter<16mm

2.2.28 In column shaft. kg 710.00 198.00 140,580.00

2.2.29 In attached beam . kg 210.00 198.00 41,580.00

MISSELANIOUS

2.2.30 Ramp and drain 3 " thick ,4'-6" wide 9"x 12 drain
in cement concrete 1:2:4 (3/4") finish smooth
with cement & sand 1:3 (1/2") (Laid on 1000g
DPM) around the building
L.m 20.00 6,600.00 132,000.00

TOTAL OF CONCRETE WORK CARRIED TO Rs. 13,799,280.00


SUMMARY

2.3 MASONRY WORK

STONE WORK

UP TO DPC LEVEL

Random rubble stone work in cement and sand


(1:5)

2.3.1 In foundations. cu.m 35.00 11,400.00 399,000.00

ABOVE STRUCTURAL FLOOR LEVEL

GROUND FLOOR TO ROOF LEVEL

BLOCK WORK
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Hollow blocks shall be made of cement and sand
to the proportion of 1:10, confirming to SLS 855
standard.

Mortar mix for block work shall be 1:5 Vertical


solid walls

2.3.2 150 mm thick walls sq.m 390.00 1,980.00 772,200.00

TOTAL OF MASONRY WORK CARRIED TO Rs. 1,171,200.00


SUMMARY

2.4 WATER PROOFING

Note :-
The water proofing material shall conform to
relevant British, Euro or ASTM specifications

(a) A written certificate stating that all material


and workmanship are in conformity with the
specifications and the manufacture's
requirements.

(b) The contractor shall jointly with


manufacture/supplier of the waterproofing
materials shall furnish a warranty to the
Employer valid for a period of 10 years after
handing over of the work against dampness
and/or moisture penetration through treated
surfaces due to defective materials and/or
workmanship.

Contractor shall submit and get approval from


Engineer for method statement before
commence the works.

Pond test shall be carried out after the


application, for a depth of 300mm for the period
of 24 hrs.

UP TO DPC LEVEL

DAMP PROOFING

2.4.1 Width > 300mm Damp proof course horizontal


comprising of two coats of hot tar blinded with
river sand on and including 20mm thick cement
and sand (1:3) screed on rubble foundation.

sq.m 60.00 2,880.00 172,800.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

2.4.2 DPM, width >300mm horizontal ,gauge 1000


polythene membrane with 150mm side and end
laps.(measured net no allowances made for laps).

sq.m 1,210.00 144.00 174,240.00

GROUND FLOOR TO ROOF LEVEL

DAMP PROOFING

2.4.3 Water proofing internal walls of toilet ( 300


mm high in toilet walls and 1500 mm in bath
room walls ) with approved quality liquid
type water proofing chemical. including cleaning
and protect the water proofing area with 20 mm
thick average thick. 1:3 cement and sand plaster
to walls and floor with forming required
shapes with fiber glass net for edges and to
manufacture specification. The contractor is
required to submit the details of
manufacture's specification with 10 years
guarantee for the Engineers approval.

sq.m 45.00 3,300.00 148,500.00

2.4.4 Water proofing of Toilet Roof slab with


application of crystalline type water proofing
system according to manufacturer's
specifications. The water proofing area to be
protected with 20 mm average thick 1:3 cement
and sand plaster to manufacture specification.
The contractor is required to submit the
details of manufacture's specification with 10
years guarantee for the Engineers approval.

sq.m 60.00 3,300.00 198,000.00

TOTAL OF WATER PROOFING CARRIED TO Rs. 693,540.00


SUMMARY

2.5 STRUCTURAL METAL WORK

Note:
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Rate shall include for all fabrication work,
including cutting, drilling, bolting, riveting,
welding, grinding delivering, unloading, hoisting,
erecting and fixing.

Rate shall include for all plates, cleats, reverts,


nuts and bolts, washers etc

All the truss rates shall include necessary


75x75x6mm size 150 mm long angle iron cleat at
1200 mm intervals to support to purlings.

GROUND FLOOR TO ROOF LEVEL.

TERMINAL AREA ROOF

2.5.1 Type SC1 - Supply, fabricating, hoisting and


positioning steel clumns with 610x225x125
kg/m size "I" section as per detail drawing, Rate
shall include for fillet welding, 660x300x25mm
thick base / shoe plate, 16mm dia. rag bolts and
two coats of anti corrosive paint.

Kg 22,250.00 348.00 7,743,000.00

2.5.2 Type SC2 - Supply, fabricating, hoisting and


positioning steel clumns with 250x125x25 kg/m
size "I" section as per detail drawing, Rate shall
include for fillet welding, 290x225x20mm thick
base / shoe plate, 16mm dia. rag bolts and two
coats of anti corrosive paint.

Kg 1,550.00 348.00 539,400.00

2.5.3 Type RF1 - Supply, fabricating, hoisting and


positioning steel roof with 457X191X67 kg/m
size "I" section Main Beam as per detail drawing,
Rate shall include for fillet welding, with
939x191x20mm thick end plate, 20mm dia. nut &
bolts and two coats of anti corrosive paint.

Kg 37,020.00 348.00 12,882,960.00

2.5.4 Type RF2 - Supply, fabricating, hoisting and


positioning steel roof with 250X125X25 kg/m
size "I" section Main Beam as per detail drawing,
Rate shall include for fillet welding,
190x75x16mm thick end plate, 20mm dia. nut &
bolts and two coats of anti corrosive paint.

Kg 3,050.00 348.00 1,061,400.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.5.5 Type RF3 - Supply, fabricating, hoisting and
positioning steel roof with 150x75x14 kg/m size
"I" section Main Beam as per detail drawing, Rate
shall include for fillet welding, 190x75x16mm
thick end plate, 20mm dia. nut & bolts and two
coats of anti corrosive paint.

Kg 525.00 348.00 182,700.00

2.5.6 Type RTB1 - Supply, fabricating, hoisting and


positioning steel Tie Beam with 150x75x14 kg/m
size "I" section as per detail drawing, Rate shall
include for fillet welding and two coats of anti
corrosive paint.
Kg 3,620.00 348.00 1,259,760.00

2.5.7 Supply, fabricating, hoisting and positioning, steel


roof with 457x191x67 kg/m size "I" section
Haunch as per detail drawing, Rate shall include
for fillet welding and two coats of anti corrosive
paint as per detail drawing.

Kg 2,320.00 354.00 821,280.00

2.5.8 Type WB - Supply, fabricating, hoisting and


positioning steel roof with 65mm dia. 4.5mm
thick circular hollow sections (CHS) Wind Bracings
as per detail drawing, Rate shall include for fillet
welding and two coats of anti corrosive paint.

L.m 300.00 2,520.00 756,000.00

2.5.9 150X65x20 mm, 2.3 mm thick G.I purlin laid on


steel truss at 1200 mm c/c fixing with 6 mm M.S
bolts and nuts and 12 mm dia tie/sag rods.
Including one coat of etch primer and two coats
of anti corrosive paint.
L.m 2,860.00 2,040.00 5,834,400.00

WATER TANK

2.5.10 Type SC2 - Supply, fabricating, hoisting and


positioning steel clumns with 250x125x25 kg/m
size "I" section as per detail drawing, Rate shall
include for fillet welding, 290x225x20mm thick
base / shoe plate, 16mm dia. rag bolts and two
coats of anti corrosive paint.

Kg 610.00 372.00 226,920.00

2.5.11 Type RTB1 - Supply, fabricating, hoisting and


positioning steel Tie Beam with 150x75x14 kg/m
size "I" section as per detail drawing, Rate shall
include for fillet welding, 190x75x16mm end
plates, 20mm dia. Nut & bolts and two coats of
anti corrosive paint.

Kg 795.00 348.00 276,660.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

2.5.12 Supply, fabricating, and fixing of 4mm thick


checker plates on TB1 deck as per detail drawing,
including riverts, other necessary fittings and two
coat of anti corrosive paint.
Sqm 16.00 8,520.00 136,320.00

STEEL LADDER & GUARD RAIL TO WATER TANK

2.5.13 Supply, fabricating & fixing of steel ladder for


water tank including 2 No, DN 25mm, 3.2mm
medium duty vertical GI bars (width 300mm) &
DN 25mm, 3.2mm thick medium duty horizontal
bars at 300mm c/c and all necessary specials as
per the detail drawing with two coats of anti
corrosive paint & two coats of enamel paint.

Lm 10.00 3,960.00 39,600.00

2.5.14 supply, fabricate and fixing of GI pipe guard rail


(1.0m high) on checker plate deck comprising DN
32mm, 3.2mm thick uprights at 450mm c/c, DN
50mm, 3.2mm thick top rail and DN 25mm
middle rail. Uprights fixed to checker plate deck
with 100 x 100 x 3mm thick base plate with 8mm
dia. GI nuts and bolts and two coats of
anticorrosive paint & two coats of enamel paint.
complete as per detail drawing.

L.m 16.00 10,320.00 165,120.00

TOTAL OF STRUCTURAL METAL WORKCARRIED RS 31,925,520.00


TO SUMMARY.

2.6 METAL WORK

All doors and windows shall be fixed complete to


working order as shown in drawings.

All the works involve with aluminum should


be carried out according to the detail
drawings and specifications. Rate shall include
for all fabrications works, delivery , unloading,
hoisting , all accessories and fixing in position.
and all Iron mongary fittings and locking
devices , 5 mm thick clear float glass. All
aluminum doors and widows frames sashes
1.2-1.6 mm thick & including necessary
gasket, sealant, glass wool etc.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

Rate shall include for all necessary fixing,


fittings, iron mongery, and locking devices of
approved quality as per specification schedule.

All Aluminium shall be natural anodizing


original sections (Anodizing coat shall be
standard aluminium alloy anodic oxidation
coating and thickness 10 - 15 Microns) approved
by the Engineer/Architect.

All windows are casement windows using 5 mm


float glass, rubber beadings strip with silicon
gum.

Aluminium alloy should confirm to- BS


1474:1972 Surface treatment shall confirm to BS
1615 and BS 3987

The over-all profile dimensions used for main


members of each component shall be as
follows.

Doors - 100mm x 1.6mm thick


Windows - Casement - 70 mm x 1.2 mm thick

Windows - Sliding -70mm x 1.5 mm thick


Fan Light - 60mm x 1.2mm thick
Partition - 76mm x 1.2mm thick

Shop drawings should be submitted and got


approval from the Engineer prior to fabrication.

ABOVE STRUCTURAL FLOOR LEVEL

GROUND FLOOR TO ROOF LEVEL.

DOORS

2.6.1 Type D1 - Supply, fabricating & fixing of


Aluminum framed single sash panelled door . as
per the detail drawing.
sq.m 3.50 15,684.00 54,894.00

2.6.2 Type D2 - Supply, fabricating & fixing of


Aluminum framed single sash panelled door . as
per the detail drawing.
sq.m 10.00 15,684.00 156,840.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.6.3 Type D3 - Supply, fabricating & fixing of
Aluminum framed single sash panelled door . as
per the detail drawing.
sq.m 2.50 15,684.00 39,210.00

2.6.4 Type RD - Size 3800x2100 mm, supply & fixing


0.47mm or more Zinc Alum Roller shutter door,
Rate shall include drums which rotates on an axle
compact cylinder mounted in wall/beam. Rate
shall include for aluminium slats to the thickness
of 1.2mm, centre bar, pulleys, side plate with the
racers, locks, square tubes, U channels complete
with manufactures details.

sq.m 16.00 10,800.00 172,800.00

2.6.5 Type WP - Size 3400x2100 mm, supply,


fabricating & fixing of Aluminium Framed Glazed
Wall Panel in 3 Parts with middle part double
sashed & 2 way openable doors and either sides
fixed panells. As per detail drawing.

sq.m 7.50 19,440.00 145,800.00

2.6.6 Type DW - Size 1900x2750 mm, supply,


fabricating & fixing of Aluminium Framed 3 Parts
wall panel with one side part panelled & fixed,
other two parts glazed & hinged to fold & fixed.
As per detail drawing.
sq.m 52.50 14,280.00 749,700.00

WINDOWS

2.6.7 Type F1- Aluminium framed Glazed fan light with


fixed glass panel. As per the detail drawing.
sq.m 11.00 11,952.00 131,472.00

PARTITION - KIOSKS

2.6.8 Type P1 - Supplying & Fixing Aluminium glazed


partition consist of 76 mm Section. All Aluminium
sections should be in accordance with the
specification given in preamble for Alluminium
work. Top partition to fix with 5 mm thick clear
glass and bottom part to fix with composite
cladding panel. all as per details drawings.

sq.m 116.00 10,980.00 1,273,680.00

ALUMINIUM LOUVER PANEL


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Fixed louvers shall be of the weather proof type,
suitable for overcoming water carried- over by
wind. The Contractor shall provide a guarantee
in respect of the weatherproof properties of the
fixed louvers.

2.6.9 Supply, fabricating and fixing of Aluminium louver


panneled consisting of 152mm x 96mm size
louver panels fixed to aluminium framework at
100mm c/c, on TB1, all other necessary
accessories and detail drawings, approved by the
engineer.

sq.m 170.00 13,980.00 2,376,600.00

TOTAL OF METAL WORK CARRIED TO SUMMARY Rs. 5,100,996.00

2.7 ROOF COVERING AND ROOF PLUMBING

ROOF COVERING

ABOVE STRUCTURAL FLOOR LEVEL

GROUND FLOOR TO ROOF LEVEL.

2.7.1 Supply and fixing Zn/Al colour bonded roofing


sheet (Minimum total thickness of 0.47mm), laid
on existing purlings using self drilling screws with
joints to be properly connected with an adequate
side lap to ensure water tightness along the
entire length and complete as per detail
drawings.

sq.m 3,225.00 1,728.00 5,572,800.00

2.7.2 Supply and Fixing of (0.47mm ) Zn/Al Colour


Bounded standard ridge cap (500mm girth) using
fasteners as per details drawing.
l.m 75.00 1,080.00 81,000.00

2.7.3 Reflective thermal insulation foil 8mm thick made


up of two layers of aluminium foil laminated to
polyethylene air bubble sheet. With minimum
thermal resistance of 12.3 hrft2'F . Including
double side adhesive tape and air gap tapes and
Gauge 18, 75x75 mm GI mesh.

sq.m 3,225.00 672.00 2,167,200.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.7.4 Valance board - Supply and fixing Zn/Al Colour
bonded 0.47 mm thick 470 mm girth Valance
board with 12mm width (1/2") angle iron
frame.as per detail drawing
l.m 260.00 1,500.00 390,000.00

2.7.5 Bardge Flashing - Supply and fixing Zn/Al Colour


bonded 0.47 mm thick 470 mm girth Bardge
Flashing with 12mm width (1/2") angle iron
frame.as per detail drawing
l.m 120.00 1,620.00 194,400.00

TOTAL OF ROOF COVERING AND ROOF Rs. 8,405,400.00


PLUMBING CARRIED TO SUMMARY

2.8 PLUMBING/SANITARY INSTALLATION

Note:-
The tenderer shall requested to refer the
Preamble notes, General notes, Drawings,
Specifications, Condition of contract, Special
condition of contract and other relevant
document prior to pricing of the following
items. The tenderer shall provide all dimensions,
and technical information, of all builders work to
the Engineer/Consultant in accordance with the
programme of work.

The tenderer shall submit the following


information on the items/equipment/fittings
quoted for together with the tender.

1. Make
2. Model no
3. Technical data
4. Country of manufacture

All equipment's shall be comply with relevant


British standards or SLS where relevant.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

All fittings to be completed with water supply


and disposal connections to working order.

Piping shall be measured to the net length along


the center line of the pipes over all bends,
junctions, tees and the similar pipe fittings and
shall be given in metre.

The size of PVC pipes are specified by the


external dimensions.

Before starting any operation at site, the


relevant authority shall be informed and get
prior approval.

Unless otherwise specified all sanitary fittings


shall be imported / local quality or approved by
the Engineer. Rates for fittings shall include for
all necessary accessories, traps and any
additional materials needed for fixing in position
to working order.

Rate shall include for necessary elbow, tee,


faucet socket, valve, socket, gate valve, reducing
socket excavation, compaction, back filing etc.
And cutting for chases & making goods

All P.V.C. pipes should confirm to S.L.S. 147. The


fittings should be of the same brand as pipes.

Rates for Plumbing shall include for:


(a) All laps, straight cutting and waste.
(b) All jointing and connected materials.
(c) Chasing in brickwork/ block work/ concrete
floor/ concrete columns and make good.
(d) Fixing pipes to brickwork / block work
(e) Solder rivets, screws, nails, clips, brackets, straps
etc.
(f) Testing installations on completion.
(g) Sterilization, of "Drinking water' pipes on
completion.

FIXTURES, APPLIANCES AND EQUIPMENT

Rates for sanitary fixtures shall include for:


(a) Installation complete with plugs.
(b) Grated waste outlets.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


( c ) Brackets and all fixings including jointing to
pipes.
(d) 10 Years Guarantee certificates of fittings should
be submitted to the Engineer with the bills. No
payments should be certified without bills.

(e) All the UPVC pipes to be certified products to SLS


147 & SLS 659
(f) The fittings are manufactured in conformity to
BS, JIS, A.S.T.M., A.S. or S.L.S. standards.
Approved Fittings with 1 year manufacturer's
warranty for taps

COLD WATER SYSTEM

Water Supply & Storage

2.8.1 Supply and Laying of underground Cold Water


Supply Main from road to the sump with 40mm,
uPVC type 1000 pipes as shown in the drawings.
Rate shall include for pipes, fittings, excavation
and refilling, pipe supporting and other necessary
items and consumables.

m 68.00 780.00 53,040.00


-
2.8.2 Provide a sum for construction of
cement/Conccrete chamber for the consumer
meter.
Item 1.00 5,400.00 5,400.00
-
2.8.3 Provide a sum for underground PVC water sump
(with concrete cylinder) having a capacity of
15,000 liters (10,000L portable water[separatly] &
5,000L Fire system[separatly]) with ball vlaves,
drain out, double seal C. I. heavy duty access
cover etc as indicated in the drawing.

Item 1.00 456,000.00 456,000.00


-
Supply Installation of Cold Water Delivery Pump
Set.
-
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.8.4 Supply and install of cold water delivery pump
system (Duty & Standby) in the location indicated
in the drawings. The pumps shall have a capacity
to deliver 1.2 lits/sec @ 15m head. Pump set shall
inlcude electrical pump control panel with all
necessary pump safety features, level sensors for
the overhead tank, pressure gauges & necessary
valves and as per manufactures specific. (One
duty one stand by). Offer shall include all
necessary protection including, but not limited to
dry run protection, overload and over current
protection. Also the control panel shall have the
facility run pumps both Automatic and manual
modes. Recommended brands are Grundfose,
KSB, DP, Calpeda or equivalent.

Item 1.00 276,000.00 276,000.00


-
2.8.5 Pump suction pipes including foot valve, Pressure
gauges, strainers, valves, all fixtures and fittings
required to complete pump installation for
efficient operation of the delivery pumps.

Item 1.00 42,600.00 42,600.00


-
2.8.6 Supply and installation of 32 mm uPVC, type
1000 delivery pipes laid on under ground or
chased in to walls from the water sump to
delivery pumps & delivery pumps to overhead
tank with necessary valves, accessories.

m 18.00 744.00 13,392.00


-

Supply & installation of Isolation Valves -


-
Supply Installation of Delivery Line's Isolating
valves fittings Rates shall include all necessary
pipe fittings, holding brackets & supporters &
other necessary accessories & consumables.

-
-
2.8.7 50mm dia Nos. 2.00 3,000.00 6,000.00
-
2.8.8 40mm dia Nos. 5.00 2,880.00 14,400.00
-
2.8.9 32mm dia Non return Valve Nos. 3.00 2,280.00 6,840.00
-
Supply Installation of Over Head Tank -
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


-
2.8.10 Supply Installation of overhead water tank above
the Roof level with 5000L capacity. Rates shall
include drain, over flow with all necessary pipe
fittings, isolation valves, supporters & other
necessary accessories & consumables.

Item 1.00 90,000.00 90,000.00


-
Supply, Laying and Installation of Cold Water
Distribution Lines
-
-
Supply, laying ,Installation of Cold Water
horizontlly distribution pipe line with pipe &
required fittings, laid on riser/wall, under
ground, buried in concrete floor,hang on
concreate above the ceiling . Rates shall include
mounting brackets, required pipe fittings & other
necessary accassaries. with chipping of walls,
concreting, excavation & back filling & ect.

-
-
2.8.11 40mm diameter (uPVC type 1000) with
accessories
m 45.00 780.00 35,100.00
-
2.8.12 32mm diameter (uPVC type 1000) with
accessories
m 95.00 744.00 70,680.00
-
2.8.13 25mm diameter (uPVC type 1000) with
accessories
m 35.00 672.00 23,520.00
-
2.8.14 20mm diameter (uPVC type 1000) with
accessories
m 33.00 588.00 19,404.00
-
Supply Installation of Delivery Line's Isolating
valves/Non return valves fittings Rates shall
include all necessary pipe fittings, holding
brackets & supporters & other necessary
accessories & consumables.Manufactured in
Japan, UK or equivalent.

-
-
2.8.15 32mm diameter Nos. 2.00 2,400.00 4,800.00
-
2.8.16 25mm diameter Nos. 3.00 4,200.00 12,600.00
-
2.8.17 20mm diameter No. 1.00 3,840.00 3,840.00
-
SUPPLY OF SANITARY FITTINGS AND
ACCESSORIES
-
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Supply of Sanitary Fittings and Accessories -
-
Supply of sanitary fittings with all necessary
sanitary fittings such as angle valves, flexible
connections with all necessary fixing
accessories. .
-
-
2.8.18 Water Closets(WCs) with angle valves, flexible
connections, all necessary fixing accessories.
Nos. 7.00 26,400.00 184,800.00
-
2.8.19 Wash Basin with angle valve, flexible connection,
rubber plug and chromium plated chain, waste
bottle trap and all necessary fixing accessories
(Pedestal)
Nos. 19.00 17,400.00 330,600.00
-
2.8.20 Toilet paper holder with accessories. Nos. 7.00 1,440.00 10,080.00
-
2.8.21 Bidet spray with angle valve and all necessary
fixing accessories.
Nos. 7.00 1,800.00 12,600.00
-
2.8.22 Robe hooks, fixed to doors of water closets with
chromium plated brass screws.
Nos. 7.00 720.00 5,040.00
-
2.8.23 Soap dish fixed to wall with fiber plugs and
chromium plated brass screws.
Nos. 19.00 1,200.00 22,800.00
-
2.8.24 PVC floor gullies with water trap and stainless
steel grating.
Nos. 13.00 2,760.00 35,880.00
-
2.8.25 Garden tap with all necessary fixing accessories.
No. 1.00 840.00 840.00
-
2.8.26 Supply and fixing of 5mm thick 450x600mm size
Mirror double coated with pencil edge back
stretcher fix to wall with rawl plugs.
Nos. 7.00 3,000.00 21,000.00

2.8.27 Supplying and fixing stainless steel grab bar


(600mm long) for wash basin (Disable Toilet )
Nos. 2.00 3,000.00 6,000.00

2.8.28 Supplying and fixing foldable hand grab bar for


water closet ( Disable Toilet.)
Nos. 2.00 3,600.00 7,200.00

Installation of Sanitary Fittings and Accessories.


-
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Installation of all Sanitary fittings with all
necessary sanitary fittings such as angle valves,
flexible connections & all required bathroom
accessories .
-
-
2.8.29 Installation of Water Closets(WCs) with angle
valves, flexible connections, all necessary fixing
accessories.
Nos. 7.00 26,400.00 184,800.00
-
2.8.30 Installation of Wash Basin with angle valve,
flexible connection, rubber plug and chromium
plated chain, waste bottle trap and all necessary
fixing accessories (Pedestal)

Nos. 19.00 17,400.00 330,600.00


-
2.8.31 Installation of Toilet paper holder with
accessories.
Nos. 7.00 1,440.00 10,080.00
-
2.8.32 Installation of Bidet spray with angle valve and all
necessary fixing accessories.
Nos. 7.00 1,800.00 12,600.00
-
2.8.33 Installation of Robe hooks, fixed to doors of water
closets with chromium plated brass screws.
Nos. 7.00 720.00 5,040.00
-
2.8.34 Installation of Soap dish fixed to wall with fiber
plugs and chromium plated brass screws.
Nos. 19.00 1,200.00 22,800.00
-
2.8.35 Installation of PVC floor gullies with water trap
and stainless steel grating.
Nos. 13.00 2,760.00 35,880.00
-
2.8.36 Installation of Garden tap with all necessary
fixing accessories.
No. 1.00 840.00 840.00
-
2.8.37 Fixing only 5mm thick 450x600mm size Mirror
double coated with pencil edge back stretcher fix
to wall with rawl plugs.
Nos. 7.00 3,000.00 21,000.00

2.8.38 Fixing only stainless steel grab bar (600mm long)


for wash basin (Disable Toilet )
Nos. 2.00 3,000.00 6,000.00

2.8.39 Fixing only foldable hand grab bar for water


closet ( Disable Toilet.)
Nos. 2.00 3,600.00 7,200.00

WASTE WATER SYSTEM -


-
Supply and Installation of Underground Waste
Water Pipe Lines
-
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Supply and Installation of Waste Water Pipe Lines,
laid underground, required connections of waste
water line to manholes up to soakage pit. Rates
shall include pipes & required fittings, excavation
and back filling, levelling pads, brackets & other
necessary accassaries.

-
-
2.8.40 110mm diameter (uPVC type 600) m 90.00 2,640.00 237,600.00
-
2.8.41 63mm diameter (uPVC type 600) m 25.00 1,440.00 36,000.00
-
2.8.42 50mm diameter (uPVC type 600) m 8.00 900.00 7,200.00
-
2.8.43 40mm diameter (uPVC type 600) m 12.00 720.00 8,640.00
-
Supply Installation of Manholes, Screen
chambers
-
-
2.8.44 Construction and connection of Waste Water
manhole having 450x450mm dimensions
internally as per drawings with invert depth not
exceeding 900mm including excavation and back
filling, 100 mm thick RCC grade 30 foundation
including necessary reinforcement forming
channels and benching, 100mm thick grade 25
concrete walls, sealed D. I. manhole covers with
lifting arrangement. Inlet and outlet connections
to complete the manhole.

Nos. 16.00 27,600.00 441,600.00


-
2.8.45 Construction and connection of Waste Water
trapped manhole having 450x450mm dimensions
internally as per drawings with invert depth not
exceeding 900mm including excavation and back
filling, 100 mm thick RCC grade 30 foundation
including necessary reinforcement forming
channels and benching, 100mm thick grade 25
concrete walls, sealed D. I. manhole covers with
lifting arrangement. Inlet and outlet connections
to complete the manhole.

Nos. 2.00 27,600.00 55,200.00


-
SEWER DISPOSAL SYSTEM -
-
Supply Installation of Underground Sewer Pipe
Lines
-
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Supply and installation of Sewer Pipe Line's laid
underground, required connection of Sewer lines
to manholes and interconnect to manhole up to
septic tank. Rates shall include pipes & required
fittings, excavation and back filling, levelling pads,
brackets & other necessary accassaries.

-
-
2.8.46 110mm diameter (uPVC type 600) m 31.00 2,640.00 81,840.00
-
2.8.47 63mm diameter (uPVC type 600) m 5.00 1,440.00 7,200.00
-
Supply Installation of Manholes, Screen
chambers,
-
-
2.8.48 Construction and connection of Sewer manhole
having 600x600mm internal dimensions as per
drawings with invert depth not exceeding 900mm
including excavation and back filling, 100 mm
thick RCC grade 30 foundation including
necessary reinforcement forming channels and
benching, 100mm thick grade 25 concrete walls,
Double sealed D.C. manhole covers with lifting
arrangement. Inlet and outlet connections to
complete the manhole.

Nos. 3.00 45,600.00 136,800.00


-
2.8.49 Construction and connection of Sewer
interceptor manhole having 600x600mm internal
dimensions as per drawings with invert depth not
exceeding 900mm including excavation and back
filling, 100 mm thick RCC grade 30 foundation
including necessary reinforcement forming
channels and benching, 100mm thick grade 25
concrete walls, Double sealed D.C. manhole
covers with lifting arrangement. Inlet and outlet
connections to complete the manhole.

No. 1.00 45,600.00 45,600.00


-
STORM WATER DISPOSAL SYSTEM -
-
Supply and installation of Vertical Storm Water
Drain Pipe Line
-
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Supply and installation of Zn/Al down pipes in
Outside walls/column with necessary connecting
fittings with joints, brackets, supports, and all
other required accessories., Rates shall include
chipping of walls & concrete etc if requires.

-
-
2.8.50 4 x 4 inch (main roof) m 92.00 1,080.00 99,360.00
-
2.8.51 4 x 2 inch (lower roof) m 75.00 960.00 72,000.00
-
2.8.52 110mm dia uPVC type 600 down pipes m 165.00 1,980.00 326,700.00
-
Supply Installation of Underground Storm water
Pipe Lines
-
-
Supply and installation of storm water Pipe Line's
laid underground, required connection of storm
water pipe interconnect to drain line. Rates shall
include pipes & required fittings, excavation and
back filling, levelling pads, brackets & other
necessary accassaries.

-
-
2.8.53 110mm dia uPVC type 600 down pipes m 75.00 2,640.00 198,000.00
-
2.8.54 160mm dia uPVC type 600 down pipes m 50.00 2,640.00 132,000.00
-

Construction of concrete storm water drain -


2.8.55 Construction of concrete drain 300mm width
x 450mm(Avg) depth internal and varies up to
750mm. Consists of necessary excavation in
hard earth, 100mm thick concrete base and walls
in Grade 20 concrete, fair finish internal surface
without cover slab. Drain reinforced with tor
steel 10mm @ 150mm c/c both ways &
neccessary form works. all as per detail drawing.

m 250.00 11,040.00 2,760,000.00


-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.8.56 Cover slabs preparing and placing with grade 25
concrete (20mm agg.) 650x400x150mm size, light
duty, reinforcement Y16@100mm c/c in shorter
span and Y10@150mm c/c in long span including
formwork.

Nos. 400.00 1,620.00 648,000.00


-
TESTING, COMMISSIONING & HANDING OVER
ALL PLUMBING SYSTEM
-
-
2.8.57 Preparation of shop drawings, as built drawings
& Handing over document
Item 1.00 12,000.00 12,000.00
-
2.8.58 Testing and commissioning of total plumbing
services
Item 1.00 12,000.00 12,000.00

TOTAL OF PLUMBING / SANITARY INSTALLATION Rs. 7,725,036.00


CARRIED TO SUMMARY.

2.9 MECHANICAL INSTALLATION

FIRE ALARM AND DETECTION SYSTEM


INSTALLATION

INFRASTRUCTURE

Scope of work includes the Supply, installation,


testing and commissioning of Fire Alarm and
Detection system for this Project.

Note

Fire Alarm Control panel and all other items


mentioned in this BOQ shall comply with the
specifications issued for this project.
Note

Fire Alarm and Detection system shall complete


with Main Fire Alarm Control Panel, Repeater
Panels, ensors, Sounders, Manual Call Points,
Relay and control modules for interfacing with
other systems.
Note

The Scope of work includes laying of cables


including conduits, making opening, chasing
wall/concrete for installing the Fire Detection
and Alarm System and made good in appropriate
manner.
Note

Fire Alarm Control Panel (FACP)


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


The main FACP Central Console shall contain a
microprocessor based Central Processing Unit
(CPU). The CPU shall communicate with and
control the following types of equipment used to
make up the system: intelligent addressable
smoke and thermal (heat) detectors, addressable
modules, control circuits, and notification
appliance circuits, local and remote operator
terminals, printers, annunciators, and other
system controlled devices. (All Equipments are
complying with BMS system , on/off and other)

2.9.1 Supply, installation, testing and commissioning of


micro processor controlled Analog Addressable
Fire Alarm Control Panel (FACP) single loop to
NFPA 72 standards and complying to
specifications. FACP shall be UL or LPCB approved
type with Battery power supply & Charger unit,
Provision to be made for future expansion
,including graphical display, and to network
interface with FAC Panels.

Nos. 1.00 1,266,545.00 1,266,545.00

Addressable Monitor Modules

Supply, installation, testing and commissioning


of intelligent addressible Monitor Modules with
mimimum IP30 casing having required number
of inputs for monitored quering of potential free
contacts with in-built short circuit isolator to
monitor the functiopn of following
euipment/items in areas related of this project;
Agency Listings: UL Approved or LPCB Approved

2.9.2 Ground floor Nos. 3.00 16,953.00 50,859.00

Addressable Control/Relay Modules

The addressable Control/relay output module


shall monitor the circuit healthyness.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Supply, installation, testing and commissioning
of inteligent addressable control modules with
minimum IP 30 casing containing a potential-free
DPDT contact with a fail-safe and in-built short
circuit isolator to to control the following
equipment/items in areas related of this project;
Agency Listings: UL Approved or LPCB Approved

2.9.3 Ground floor Nos. 3.00 19,748.00 59,244.00

Isolator Module

2.9.4 Supply, installation, testing and commissioning of


intelligent addressable isolator module to
automatically isolate wire-to-wire short circuits
on an SLC Class A or Class B branch. The isolator
module shall limit the number of modules or
detectors that may be rendered inoperative by a
short circuit fault on the SLC loop segment or
branch. At least one isolator module shall be
provided for each floor or protected zone of the
building. Agency Listings: UL Approved or LPCB
Approved

No 1.00 23,705.00 23,705.00

2.9.5 Supply and wiring of 1.5sqmm twin twisted Fire


resistant cables required for the SLC –loops to
connect to the fire command center and cables
required to connect repeater panels to the FACP

m 185.00 868.00 160,580.00

2.9.6 Supply and installation of approved type


Termination box to connect the riser and floor
wiring
Nos 1.00 939.00 939.00

2.9.7 Testing, Commissioning & Programming of the


Fire Detction & Alarm system
Item 1.00 45,900.00 45,900.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.9.8 Staff Training, providing all original manuals
including maintenance and spare parts sections,
providing 3 sets of shop drawings, certified as
built drawing (Hard format) and one set of
drawings in the soft format, Handing Over and
providing one year free servicing of the Fire
Alarm and Detection System.

Item 1.00 76,500.00 76,500.00

Supply, installation, testing and commissioning


of UL or LPCB approved Analog Addressable
Heat Detectors with the base complete with dual
LEDs and with integrated short circuit isolator
and all other required accessories.

2.9.9 Ground floor Nos 10.00 8,650.00 86,500.00

Supply, installation, testing and commissioning


of UL or LPCB approved, Analog Addressable
Photoelectric type Smoke Detector with the base
complete with dual LEDs and with integrated
short circuit isolator and all other required
accessories.

2.9.10 Ground floor Nos 3.00 8,915.00 26,745.00

Supply, installation, testing and commissioning


of UL or LPCB approved addressable manual call
point which is used for manually trigger a fire
alarm with inbuilt short circuit isolator and all
other required accessories.

2.9.11 Ground floor Nos 3.00 31,590.00 94,770.00

Supply, installation and commissioning of


Illuminating LED Exit board with White Letters
on Green Background with 3hrs battery back up
and all other required accessories.

2.9.12 Ground Floor Nos 2.00 11,333.00 22,666.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Supply, installation, testing and commissioning
of UL or LPCB approved addressable multi tone
sounder strobe with minimum 4 different tone
variants and integrated short circuit isolator all
other required accessories.

2.9.13 Ground Floor Nos 11.00 22,166.00 243,826.00

2.9.14 Testing, Commissioning, Fire department


inspection, Staff Training, Handing Over and one
year free servicing. System will be tested for
proper functioning & each equipments and
Submitting of shop drawing (2 set, A2) and "as
built" (2 set, A2) drawings, technical
specifications and Fire department approval.

Item 1.00 96,900.00 96,900.00

FIRE PROTECTION SYSTEM INSTALLATION

FIRE PUMP

2.9.15 Supply, installation, testing and commissioning of


Fire pump; such as Duty and Standby pump
complete with Heavy duty GI Pipe, Pressure
Gauge, Non return valves, Isolation valves,
pressure vessel with necessary accessories.
Duty & Stand by pump - 60 l/min @ 3 bar
electrical Driven

Item 1.00 912,972.00 912,972.00


-
PIPES -
-
2.9.16 Supply and installation of 50 mm Heavy Duty GI
pipes inclusive of all fittings, accessories, pipe
supports, paint etc.
m 62.00 5,733.00 355,446.00
-
2.9.17 Supply and installation of Underground 50 mm
Heavy Duty GI pipes inclusive of all fittings,
accessories, pipe supports, paint etc.

m 55.00 6,610.00 363,550.00


-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.9.18 Supply and installation of 25 mm Heavy Duty GI
pipes inclusive of all fittings, accessories, pipe
supports, paint etc.
m 12.00 2,622.00 31,464.00
-
2.9.19 Supply and installation of 50mm Puddle flanges
inclusive of all 50mm Heavy Duty GI pipes,
accessories, pipe supports, paint etc.
Item 2.00 5,672.00 11,344.00
-
FIRE HOSE REEL -
-
2.9.20 Supply & Installation of 19 mm x 30m swing arm
type Fire Fighting Hose Reel complete with
Drum, 25mm dia: non fire hose, jet / spray
shutoff nozzle & control ball valve and all
necessary accessories.
Nos 5.00 41,106.00 205,530.00
-
FIRE EXTINGUISHERS -
-
2.9.21 Supplying & Installation of ( 6Kg ) Dry Powder Fire
Extinguishers (fully charged and controllable
type) complete with metal mounting brackets and
Horn.
Nos 6.00 8,568.00 51,408.00
-
2.9.22 Supplying & Installation of ( 3Kg -CO2) Carbon
Dioxide Fire Extinguishers (fully charged and
controllable type) complete with metal mounting
brackets and Horn.
Nos 6.00 7,294.00 43,764.00
-
2.9.23 Supplying & Installation of 9 Lt water (H2O) Fire
Extinguishers (fully charged and controllable
type) complete with with metal mounting
brackets and Horn.
Nos 3.00 6,432.00 19,296.00
-
2.9.24 Testing, Commissioning, Fire department
inspection, Staff Training, Handing Over and one
year free servicing of the Fire Hydrant.
System will be tested for proper functioning &
each equipments and Submitting of shop
drawing (2 set, A2) and "as built" (2 set, A2)
drawings, technical specifications and Fire
department approval.

Item 1.00 51,000.00 51,000.00

TOTAL OF MECHANICAL INSTALLATION CARRIED Rs. 4,301,453.00


TO SUMMARY.

2.10 ELECTRICAL INSTALLATIONS

Note:-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


The Tenderers are requested to refer the General
notes, Drawings and study the taxes, safety
procedures, site conditions before the pricing.
The Tenderer shall provide all dimensions, and
technical information, of all builders work to the
Engineer/Consultant in accordance with the
programme of work.

Work shall be done in accordance with


specifications for electrical and mechanical
works - ICTAD Publication No. SCA/8 of
Aug.2000(2 nd Edition -Revised).

Rates in Bill of Quantities shall include all


necessary materials (Cables, conduits, PVC sunk
box, bulbs, switches etc.) and labour required to
complete the electrical installation to good
working order.

Except where specifically stated, all costs


associated with provision of all holes, openings,
chases, ducts and other builders' work required
for installation and make them good, shall be
included in the rates.

Where reference is made to certain


manufactures' products and items identified by
registered trade marks, has been done for the
sole purpose of defining and establishing
standards of quality and performance and not
with the intention of restricting the procurement
of material or fitting to a particular
manufacturer. However all equipment and
material should meet the BS or an equivalent
standard.

Testing and commissioning of the electrical


installation is to be carried out by the contractor
and inspection report submitted according to the
requirements of the power supply Authority.

Electrical Items (MCB,RCCB etc.) should be of


European/Japanese origin or to the BS or
equivalent and items without an accredited
agent in Sri Lanka shall not be accepted.
Guarantee cards should be provided from
accredited agent before installation.

All the quantities given here are approximated


values and Quantities may change with the
actual installation at the site.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


All types of fittings, materials, painting and
finishes shall be approved by the Engineer prior
to installation.

All panel boards and consumer units should


have wire numbering and a laminated circuit
diagram should be pasted on the inside surface
of the door.

Internal light wiring shall comply with the


drawings and shall be in 230/440 volt single core
PVC insulated copper cables

All switches and socket outlets shall be plated


type approved.
complying to SLS1000:1993 for switches & SLS
1998 : 1991 for socket outlets .

All Fluorescent fittings shall be zinc coated steel


sheet finished with powder coated to 0.45mm
thickness complete with electronic choke starter
and the tube.

All ceiling fans with guarantee card issued by the


authorized dealer.(Minimum warranty 1 year)

The whole installation shall be carried out


according to CEB/IEE wiring regulations.
Point wiring only with and including switches
(Rate includes wiring from MCB through switch
to lamp point and includes the switch, switch
box, lamp holder wire and conduit)

Point wiring only with and including Socket (Rate


includes wiring from MCB to the Socket, socket
box, and conduit)

No ceiling fan should be installed at a height of


less than 2.7m from floor level

ELECTRICAL PANEL BOARDS

Supply and installation of electrical panel board


three(3) phase, neutral and earth complete with
powder coated sheet steel enclosure, hinged and
lockable door as per specification and drawings

Note

Electrical Panel shall include MCCB, Isolator,


MCBs, RCDs, Surge protectors, automatic change
over switch, busbars, terminals and all required
accessories.
Note

Quantity and current rating of equipments to be


installed in Panel boards shall be as given in the
drawings.
Note
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

2.10.1 Automatic Transfer Switch(ATS) Nos 1.00 255,933.00 255,933.00


-
2.10.2 Main distribution board( MSB) Nos 1.00 228,570.00 228,570.00
-
2.10.3 Distribution board Grocery Shop(DB -GS) Nos 1.00 27,922.00 27,922.00
-
2.10.4 Distribution board Cafeteria(DB - CF) Nos 1.00 27,888.00 27,888.00
-
2.10.5 Distribution board Kiosks(DB KS) Nos 1.00 27,922.00 27,922.00
-
-
FEEDER CABLES -

Supply and installation of 600/1000V feeder


cables in cable tray/conduit, XLPE insulated or
PVC insulated, PVC sheathed, copper conductor
cable with three core/single core & earth cable.

Note
Rate to include for supply and installation of
cable terminations at both ends and necessary
glands
Note

2.10.6 Power cable from the CEB Meter board to ATS:


4X1C-6sqmm Cu/PVC/PVC cable
m 8.00 1,185.00 9,480.00

2.10.7 Power cable from the Genetator to ATS: 4X1C-


6sqmm Cu/PVC/PVC cable
m 5.00 1,185.00 5,925.00

2.10.8 Power cable from ATS to MDB:4C-6sqmm


Cu/PVC/SWA/PVC cable
m 48.00 2,536.00 121,728.00

2.10.9 Power cable from MDB to DB GS; 2C,6 sqmm


Cu/PVC/PVC cable+ 1C-6qmm Cu/PVC/ Earth
m 68.00 1,058.00 71,944.00

2.10.10 Power cable from MDB to DB-CF:2C-6sqmm


Cu/PVC/PVC cable+ 1C-6sqmm Cu/PVC/ Earth
m 92.00 1,058.00 97,336.00

2.10.11 Power cable from MDB to DB -KS:2C-6 sqmm


Cu/PVC/PVC cable+ 1C-6 sqmm Cu/PVC/ Earth
m 8.00 1,058.00 8,464.00

2.10.12 Power cable from MDB to ISO - WP(Water


pump):4C-2.5 sqmm Cu/PVC/PVC cable+ 1C-2.5
sqmm Cu/PVC/ Earth
m 38.00 708.00 26,904.00

2.10.13 Main Earth cable;1C-6 sqmm Cu/PVC/ Earth m 35.00 309.00 10,815.00
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


FINAL SUB CIRCUIT POINT WIRING -

Supply all materials and provide final sub circuit


point wiring for the following outlets with
conduit, 10A switches and connectors Including
other materials required to make complete
installation as specified and as shown in the
electrical drawings.

Note -

2.10.14 Wiring of high bay light point using 2x1Cx1.5


Sqmm Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu
earth cable in GI conduits and controlled by a 10A
Switch.
Nos 35.00 13,133.00 459,655.00

2.10.15 Wiring of flood light point using 2x1Cx1.5 Sqmm


Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu earth
cable in GI conduits and controlled by a 10A
Switch.
Nos 12.00 14,842.00 178,104.00

2.10.16 Wiring of out door post lamp point using 2Cx 4


Sqmm Cu/PVC/SWA/PVC and 1Cx4 sqmm PVC/Cu
earth cable in GI conduits/under ground path as
per the detail given.

Nos 9.00 59,926.00 539,334.00

2.10.17 Wiring of light point using 2x1Cx1Sqmm


Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu earth
cable in PVC conduits and controlled by a 10A
Switch.
Nos 55.00 2,806.00 154,330.00

2.10.18 Wiring of Ceiling Fan point using 2x1Cx1Sqmm


Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu earth
cable in PVC conduits and controlled by a 10A
Switch.
Nos 4.00 2,806.00 11,224.00

2.10.19 3Ph, 16A Industrial socket outlet wired using 4C,


2.5Sqmm Cu/PVC/PVC and 1Cx2.5Sqmm Cu/PVC
Earth in GI conduits /casing c/w all fixing
accessories.
Nos 2.00 18,870.00 37,740.00

2.10.20 13A raw power switched socket outlet wired


using 2Cx 2.5 Sqmm Cu/PVC/PVC and
1Cx2.5Sqmm Cu/PVC Earth in radial circuit with
GI conduits /casing c/w all fixing accessories.

Nos 58.00 22,542.00 1,307,436.00


-

SUPPLY OF LIGHTING FIXTURES -


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

Supply of the following lighting fixtures with all


accessories as per the specifications and as
annexed scheduled of lighting fixtures for all
areas. lamp fitting and accessories should be
reputed makes as given in the schedule.

Note -

2.10.21 LED 100W High bay light Nos 35.00 24,124.00 844,340.00

2.10.22 LED 210W Flood light Nos 3.00 21,370.00 64,110.00

2.10.23 LED 100W Flood light Nos 10.00 8,956.00 89,560.00

2.10.24 LED 70W Flood light Nos 2.00 6,274.00 12,548.00

2.10.25 LED 18 W recessed down light Nos 22.00 1,174.00 25,828.00

2.10.26 LED 18W soffit ounted down light Nos 19.00 1,317.00 25,023.00

2.10.27 LED 9W Pendent Light Nos 21.00 6,825.00 143,325.00

2.10.28 LED 160W Cobra head type post mounted light


Nos 10.00 51,664.00 516,640.00

2.10.29 LED 30W Spot light Nos 10.00 8,212.00 82,120.00

2.10.30 1200mm dia Celing fan Nos 3.00 10,558.00 31,674.00


-
INSTALLATION OF LIGHTING FIXTURES -

Installation of the following lighting fixtures with


required junction box, terminations, connectors
and all required accessories as per the
manufacturer's recommendations. (Fixing
method has to be approved method by the
lighting supplier/manufacturer)

Note -

2.10.31 LED 100W High bay light Nos 35.00 2,550.00 89,250.00

2.10.32 LED 200W Flood light Nos 3.00 1,530.00 4,590.00

2.10.33 LED 100W Flood light Nos 10.00 1,530.00 15,300.00

2.10.34 LED 60W Flood light Nos 2.00 1,530.00 3,060.00

2.10.35 LED 18 W recessed down light Nos 22.00 664.00 14,608.00

2.10.36 LED 18W soffit mounted down light Nos 19.00 664.00 12,616.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.10.37 LED 9W Pendent Light Nos 21.00 664.00 13,944.00

2.10.38 LED 160W Cobra head type post mounted light


incuding minor material
Nos 10.00 1,530.00 15,300.00

2.10.39 LED 30W Spot light Nos 10.00 664.00 6,640.00

CCTV SYSTEM -

2.10.40 Wiring of CCTV camera points using RG 59 power


over Coaxial cable in PVC conduits from CCTV
rack to each camera complete with all conduit,
fixing accessories up to the camera terminal.

Nos 30.00 13,618.00 408,540.00

2.10.41 Supply and installation of 1/4‑inch HD Colour


Indoor and night vision fix CCTV camera with
640x480 TV lines resolution including with
necessary power supply arrangement as per the
specification.
Nos 30.00 9,609.00 288,270.00

2.10.42 Supply and Install 2kVA, 230V offline UPS unit


with EMI/RFI full time suppression noise filtering
facility and 2ms transfer time.

Item 1.00 21,216.00 21,216.00

2.10.43 Supply and install Combined Multiplexer system


for 32 cameras, Quad units, 32 channel Digital
Video Recorder (2TB) or as per specification and
rack including necessary software

Item 1.00 146,880.00 146,880.00

2.10.44 Supply and installation of 29'' LCD monitor


console with mouse and required other
accessories
Nos 2.00 35,496.00 70,992.00

2.10.45 UPS power for CCTV camera wired using RG 59


power over Coaxial cable with PVC conduits c/w
all conduit and fixing accessories

Nos 30.00 8,874.00 266,220.00

PUBLIC ADDRESS SYSTEM -

2.10.46 Supply & installation of 350W Power amplifier


with emergency power bank for minimum 10
miniute, mounting rack and all the other
necessory accessories
Nos 1.00 104,040.00 104,040.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.10.47 Supply & installation of PA Gooseneck
Microphone with all the other necessory
accessories
Nos 1.00 4,590.00 4,590.00

2.10.48 Wiring of loudspeaker point using Twin twisted


speaker wire 24/0.1mm dia. From the amplifier to
each loudspeaker point Including PVC conduits,
hanging brackets and aii the other accessories

Nos 16.00 8,874.00 141,984.00

2.10.49 Supply & installation of 15W high impedance PA


Horn Loudspeakers including transformer,
mounting brackets and all the other necessory
accessories
Nos 16.00 7,602.00 121,632.00

SUPPLY & INSTALLATION OF LAMP FITTINGS -

2.10.50 Supply & installation of GI lamp pole 9m height


Nos 8.00 127,500.00 1,020,000.00

2.10.51 Supply & installation of telephone socket outlet in


the Control room and builder's work to provide a
SLT TP connection
Nos 7.00 7,702.00 53,914.00

2.10.52 TV point Wiring & installation Charges( including


cables,Hardware and Labour).
Item 2.00 8,752.00 17,504.00

2.10.53 Supply and installation of wall fan, Nos 10.00 13,770.00 137,700.00

2.10.54 Supply and installation of exhaust fan Nos 4.00 24,582.00 98,328.00

2.10.55 Supply & installation of 1200mm dia Celing fan.


Nos 3.00 10,558.00 31,674.00

2.10.56 Supply and installation of a Surge Protection


Device: Type 1+2 (Class B+C) , Imax : 50 kA )
32A,4P HRC fuse, metal enclosure & all the oter
accessories.
Item 1.00 23,970.00 23,970.00

2.10.57 Installation of Earth electrode as per the


specification given
Nos 1.00 25,500.00 25,500.00

2.10.58 Supply & installation of 72'' LED multi-fuction


vedio screen with all the necesory accessories
incuding hardware, software, cabing & other
necessory interfaces.
Item 2.00 739,500.00 1,479,000.00

STANDBY POWER SUPPLY


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.10.59 Supply & installation of 25 KVA prime rated,
supper silent, sound proof canopy type Diesel
Power Generator with all the other accessories
including builders work.
Item 1.00 2,652,000.00 2,652,000.00

CEB POWER SUPPLY

2.10.60 Builder's work to provide the CEB power supply.


Item 1.00 228,000.00 228,000.00

PUBLIC SERVICE TELEPHONE CONNETION

2.10.61 Builder's work to provide the SLT TP connection


Item 1.00 72,000.00 72,000.00

CERTIFICATION OF WIRING

2.10.62 Preparation of sample submission, shop


drawings, as-built drawings, operation and
maintenance manuals and Testing &
Commissioning of the each systems.
Item 1.00 76,500.00 76,500.00

2.10.63 Final testing of entire electrical installation and


submit charted engineer's certificate from CEB
Colombo city registered Chartered Engineer.

Item 1.00 51,000.00 51,000.00

-
TOTAL ELECTRICAL WORKS CARRIED TO Rs 13,160,584.00
SUMMARY

2.11 FLOOR/WALL/CEILING FINISHES

Note:-

For the full description of materials and


workmanship refer "Specification of works"
"Preambles" and "Drawings"

Plastering
The rate for plastering items includes the cost of
"Febmix"as a workability enhancer.
For coarse textured plaster ( identified as "semi-
rough") all the sand should pass through 4.0mm
sieve.

Floor / Wall Tiles


Floor Tiles should comply to SLS 1181:2013
"specification for ceramic tiles" and shall comply
to relevant abrasion resistant class.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Copy of the tile purchase bill should be produced
at the time of payment.
Wall Tiles should be Lanka Wall Tile or approved
equivalent.
Floor Tiles Shall be Homogenous, porcelain floor
tiles of industrial grade floor tile range
manufactured by Rocell or approved equivalent.

ABOVE STRUCTURAL FLOOR LEVEL

GROUND FLOOR TO FIRST FLOOR LEVEL.

FLOOR FINISHES

2.11.1 Preparing concrete floor area with power trowel


finished as per the Engineers instructions.
sq.m 2,210.00 1,080.00 2,386,800.00

2.11.2 300 x 300 mm size coloured non-skid pattern,


homogenoius ceramic floor tiling joint and point
in cement to match, on and including 19mm thick
cement and sand (1:3) screed bed in toilet floor
area. (joints filled with polymer grout) [Prime
Cost per Sq.ft. - Rs.166.52]

sq.m 40.00 3,720.00 148,800.00

WALL AND CEILING FINISHING

WALL TILE
Approved type 300x600mm glazed ceramic wall
tiling joint and point in coloured cement on and
including 12 mm thick cement and sand (1:3)
screed backing on walls up to 1500 mm high
from floor level in toilet area .( joints filled with
polymer grout ) [Prime Cost per Sq.ft. -
Rs.171.64]

2.11.3 Internal wall for toilet. sq.m 95.00 3,840.00 364,800.00

PLASTERED/RENDERED

16 mm thick cement and sand (1:5) plaster


finished smooth with skim coat (internally)

Width < 300 mm


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

2.11.4 On blocks / Concrete surfaces. l.m 125.00 276.00 34,500.00

Width > 300mm

2.11.5 On blocks / Concrete surfaces. sq.m 490.00 780.00 382,200.00

16 mm thick plastering to R.C.C beam, slab soffit


in cement and sand 1:3 including floating with
Skim coat,

Ceiling width < 300mm

2.11.6 To soffit of slab. sq.m 55.00 840.00 46,200.00

2.11.7 To side and soffit of beam. sq.m 26.00 840.00 21,840.00

16 mm thick cement and sand (1:5) plaster


finished semi-rough (externally)

Width < 300mm

2.11.8 On blocks / Concrete surfaces. l.m 80.00 240.00 19,200.00

2.11.9 Forming drip for sunshade edge cement & sand 1:


3 finished semi rough.
l.m 35.00 240.00 8,400.00

Width > 300mm

2.11.10 On blocks / Concrete surfaces. sq.m 290.00 720.00 208,800.00

Plinth Plaster

2.11.11 20mm thick plinth plaster in cement, sand 1:3


and finish smooth with cement slurry floating.
sq.m 120.00 840.00 100,800.00

TOTAL OF FLOOR / WALL / CEILING FINISHINGS Rs 3,722,340.00


CARRIED TO SUMMARY.

2.12 PAINTING

PLASTER WORK

ABOVE STRUCTURAL FLOOR LEVEL


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


GROUND FLOOR TO FIRST FLOOR LEVEL.

2.12.1 Apply one coat of appoxi paint to plinth wall after


preparing surface.
sq.m 120.00 720.00 86,400.00

Prepare and apply one coats of approved wall


filler and two coats of emulsion paints to new
walls.(internally)

Plastered work general surfaces, plain surfaces.

Girth > 300mm


2.12.2 On walls/concrete surface sq.m 500.00 672.00 336,000.00

Prepare and apply one coat alkali resistant


primer and two coats of emulsion paint.

2.12.3 To soffit of slab. sq.m 55.00 696.00 38,280.00

2.12.4 To side and soffit of beam. sq.m 26.00 696.00 18,096.00

Prepare and apply one coat of primer and two


coats of weather shield emulsion paint
(externally)

Plastered work general surfaces, plain surfaces.

Girth > 300mm


2.12.5 On walls/concrete surface sq.m 305.00 744.00 226,920.00

TOTAL OF PAINTING CARRIED TO SUMMARY Rs 705,696.00

2.13 EXTERNAL DRAINAGE SYSTEM

2.13.1 63mm dia. PVC vent pipe type 600 with all
specials.
L.m 5.00 960.00 4,800.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.13.2 Construction of 1800mm diameter internal fully
built type soakage pit , built up 225mm thick
briCk work in 1:8 cement ,sand mortar invert
depth from ground level 3.0m, on 225mm x
150mm ring beam 1:2:4(20mm) concrete mix,
including 1:3 cement and sand plaster finished
smooth with neat gray cement (0.9m invert depth
only) & 100mm high 1:2:4(20mm ) concrete ring
pad above . ground level, complete with 75mm
thick RCC cover slab with lifting handle. All as per
detail drawing

Nos 2.00 84,000.00 168,000.00

2.13.3 Construction of 100 person Brick Septic tank,


internal size 4125x1050x1950mm,in ordinary soil
including necessary excavation, 225mm thick
brick walls, 75mm thick 1:3:6 (25mm) screed
concrete, 150mm thick Grade 20 concrete base
with Y10@225mm c/c, b/w and 75mm thick
Grade 20 concrete cover slab with Y10mm@
150mm c/c, b/w and all complete as per detail
Drawing.

Nos 1.00 180,000.00 180,000.00

TOTAL OF EXTERNAL DRAINAGE SYSTEM Rs 352,800.00


CARRIED TO SUMMARY

2.14 EXTERNAL WORKS

NOTE :-
Paving blocks should confirming to S.L.S 1425 :
Part I & II and subject to the approval of the
quality & colour including transport and laying.

2.14.1 Supply & paving 80mm thick Non-Rectangular


(Approx. size 200mm x 100mm ) natural colour
precast interlocking paving blocks of 40 N/mm2
compressive strength , on 50mm thick compacted
Quarry dust laid on top of a levelled and well
compacted earth sub base for the garden and car
park areas. Rate shall include for removal of
unsuitable soil, compact the existing ground using
vibrating roller complete with filling and
compacting suitable soil to necessary levels.

sq.m 900.00 3,060.00 2,754,000.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.14.2 Supply, fabricating and fixing of Gauge 10,
50x50mm size, 1500mm high PVC coated mesh
binding with PVC coated wires fixed to 40mm
diameter 4.0mm thick heavy duty GI pipe
columns @ 2400mm c/c with 225x225mm size
concrete column base and 25mm diameter,
3.2mm thick medium duty GI horizontal bars in
top & bottom including approved painting color &
quality.

Lm 20.00 7,560.00 151,200.00

2.14.3 Supply & laying pre cast concrete Curb size


125mm x 255mm x 915mm of 25 N/mm2
compressive strength laid with 1:3 cement mortar
concrete bed and backing of a well compacted
existing earth sub base.
Lm 310.00 1,620.00 502,200.00

2.14.4 Supply and placing(laying) buffalo grass turfs of


size not less than 200mm x 200mm x 75mm and
laid closed butted to one another while ensuring
lateral joints between turfs being staggered,
where necessary turfs shall be pegged to the soil
to prevent movement or slippage. Rate shall
include for 25mm thick coir bed. Thereafter,
turfing shall be compacted, levelled and
maintained for a period of there(3) months by
watering, weeding and trimming, until roots are
firmly rooted in to the ground.

Sqm 250.00 660.00 165,000.00

TERMINAL AREA FLOOR

Rate shall include for Blinding materials ( sand &


6.3mm aggregate) transport up to 3 km,
transport cost of bitumen & Asphalt up to 10 Km
and pilling.

2.14.5 Dense graded aggregate base 100mm thick


(Aggregate base course - ABC) Supplying, Pilling,
spreading, watering & compacting graded 37.5
mm aggregate to from a dense aggregate base
including 03 km transport of aggregates
(Compacted Volume)

Cum 250.00 2,940.00 735,000.00

2.14.6 Supplying and Application of Prime Coat on


prepared base using emulsion with CSS1 at the
rate of 1.0 lit/m2 including cleaning of road
surface
Sqm 2,500.00 276.00 690,000.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 2

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


2.14.7 Supply, laying and compacting 50mm thick
Asphalt Concrete Surfacing Material binder
bitumen @ 4.7% Mix 60/70 with 19mm
aggregates.
MT 260.00 15,600.00 4,056,000.00

PUBLIC ADDRESSING SYSTEM


REFLECTIVE DIRECTION BOARDS

2.14.8 Direction Boards (W-900mm, H-750mm)


including internal lighting system with reflective
printed letters hanging on roof /fixed to
columns / Walls with 25x25mm size, 2mm thick
angle irons. Rate shall include for electrical
supply, Aluminium framework for light boards
and steel work painting with two coats of
anticorossive paint. all as per the detail drawings
and manufacturer specifications.

Nos 25.00 59,000.00 1,475,000.00

TIME TABLE DISPLAY BOARDS.


2.14.9 Time Table Display Boards (W-750mm, H-
1800mm) fixed to 150mm diameter, 5mm thick,
GI column with concrete base including internal
lighting system with reflective printed letters.
Rate shall include for electrical supply, Aluminium
framework for light boards and steel work
painting with one coat of etch primer and two
coats of anticorossive paint. all as per the detail
drawings and manufacturer specifications.

Nos 10.00 94,400.00 944,000.00

TOTAL OF EXTERNAL WORK CARRIED TO Rs 11,472,400.00


SUMMARY
MINISTRY OF MEGAPOLIS AND WESTERN DEVELOPMENT

STRATEGIC CITIES DEVELOPMENT PROJECT

PROPOSED CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA

CONTRACT NO. SCDP/WB/WK/KD/27

SUMMARY - BILL NO. 3


BILL NO DESCRIPTION AMOUNT (LKR)

Bill No. 3.1 CONCRETE WORK 1,449,828.00

Bill No. 3.2 MASONRY WORK 851,400.00

Bill No. 3.3 WATER PROOFING 247,500.00

Bill No. 3.4 STRUCTURAL METAL WORK 1,604,820.00

Bill No. 3.5 METAL WORK 1,358,160.00

Bill No. 3.6 ROOF COVERING / ROOF PLUMBING 1,194,840.00

Bill No. 3.7 PLUMBING / SANITARY INSTALLATION 906,444.00

Bill No. 3.8 MECHANICAL INSTALLATIONS 144,887.00

Bill No. 3.9 ELECTRICAL INSTALLATION 1,336,772.00

Bill No. 3.10 FLOOR / WALL / CEILING FINISHES 2,804,580.00

Bill No. 3.11 PAINTING 680,280.00

Bill No. 3.12 MISCELLENIOUS WORKS 84,000.00

TOTAL OF BILL NO. 2 CARRIED TO GRAND SUMMARY 12,663,511.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

BILL NO. 3

RPTA OFFICE BUILDING - UPPER FLOOR


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

3.1 CONCRETE WORKS

INSITU - CONCRETE

Note :-
Mass concrete Grade 15 (25 mm agg.) - including
supply, placing, compacting and curing.

Constituent material shall comply to following;

(i) River sand shall satisfy with the grading


criteria prescribed in Table 4.2 in the ICTAD
Publication SCA/4/I. & the clay content shall not
be more than 4%.

Reinforced concrete Grade 25 (20 mm agg.) -


Volume Batched, including supply, placing,
compacting and curing.

Constituent material shall comply to following;

(i) Cement of strength class 42.5N and shall


comply with SLS 107 (Ordinary Portland
Cement), that has been stored under proper
conditions and has manufactured within 90 days
at the time of concreting.

(ii) Clean river sand without impurities and clay


particles of grain distribution falling within the
prescribed grading limit in BS 882:1992.

(iii) Clean portable water

Contractor shall made available following


equipment at site before starting to concrete.

(i) Cube moulds -6Nos

(ii) Mixer and Vibrator (in working condition)


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Payment for concreting shall be made upon
submission of following.

(a) Concrete cube crushing strength test results;


28 day results shall be available to make full
payment.

READY MIX CONCRETE

Requirement for Readymix concrete

Readymix Concrete - Contractor shall submit and


get approval from The Engineer for method
statement before commence the works.

1. Minimum cement content shall be 300 kg/m3

2. Nominal maximum size of aggregate shall be


20mm.
3. Slump shall be 120mm ± 25mm - Maximum
temperature 300C
4. Maximum free water / cement ratio to be 0.5

5. Coarse and Fine aggregate used shall confirm


to BS 882 latest version
6. Concrete grade shall be as specified.
7. Concrete mix design shall be approved by the
Engineer or Engineer's nominated Senior
Technical officer.

8. The Ready mix supplier's plant should have


been calibrated in the recent past.
9. Testing
Collection of samples for testing shall be at the
point of placing. One sample per 5m3, one
sample shall mean 3 test cubes

Readymix Concrete - Confirming to SLS 1144-


1997, Rate shall include for transport 20km from
batching plant.

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL

Reinforced Concrete Grade 25

3.1.1 In Slabs including - Water Tank Slab (Readymix


Concrete)
cu.m 3.00 19,200.00 57,600.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.1.2 In Isolated columns shaft. (Readymix Concrete)
cu.m 7.00 19,200.00 134,400.00

3.1.3 In Attached beams. (Readymix Concrete) cu.m 1.50 19,200.00 28,800.00

3.1.4 In Roof tie beams. (Readymix Concrete) cu.m 3.50 19,200.00 67,200.00

3.1.5 In lintels 100x150mm size, 2Y10 with form works


Lm 55.00 540.00 29,700.00

3.1.6 In window sill 100x150mm size, 2Y10 with form


works
Lm 40.00 540.00 21,600.00

FORM WORK

Note :-
The rates given for items herein are applicable
for 15 mm thick plywood sheets.

Formwork - Contractor shall submit and get


approval from Engineer for method statement
with drawings before commence the works.

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL

Form work

3.1.7 Slab thickness < 150mm. (Water Tank Slab) sq.m 25.00 1,680.00 42,000.00

3.1.8 Side of Isolated column shaft sq.m 125.00 1,500.00 187,500.00

3.1.9 Side/soffit of attached beam. sq.m 19.00 1,680.00 31,920.00

3.1.10 Side/soffit of roof tie beam. sq.m 112.00 1,680.00 188,160.00

3.1.11 Side of Slab L.m 22.00 1,500.00 33,000.00

REINFORCEMENTS IN INSITU CONCRETE

Rate to include for supplying, cleaning, cutting ,


bending, fabricating, binding wires, distance
blocks, ordinary spacers, wastage, laps, placing
and provision of all necessary temporary fixing
and supports. No allowances in made for rolling
margin.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Mild steel bar reinforcement to BS 4449 and
strength (FY=250 N/mm²) including bends,
hooks, tying wire, distance blocks and ordinary
spacers.

High yield tor steel bar reinforcement to BS 4449


and strength (FY=460 N/mm²) including bends,
hooks, tying wire, distance blocks and ordinary
spacers.

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL

Mild Steel

Diameter<10mm

3.1.12 In isolated columns shaft. kg 170.00 192.00 32,640.00

3.1.13 In attached beam & roof tie beam . kg 120.00 192.00 23,040.00

Tor Steel

Diameter<10mm

3.1.14 In Suspended slab. kg 255.00 198.00 50,490.00

10 mm < Diameter<16mm

3.1.15 In column shaft. kg 1,061.00 198.00 210,078.00

3.1.16 In attached beam . kg 210.00 198.00 41,580.00

3.1.17 In roof tie beam . kg 1,020.00 198.00 201,960.00

MISSELANIOUS

3.1.18 Grade 15 (25mm agg.) 150mm thick mass


concrete to the toilet floor areas.
Cum 4.00 17,040.00 68,160.00

TOTAL OF CONCRETE WORK CARRIED TO Rs. 1,449,828.00


SUMMARY

3.2 MASONRY WORK

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

BLOCK WORK

Hollow blocks shall be made of cement and sand


to the proportion of 1:10, confirming to SLS 855
standard.

Mortar mix for block work shall be 1:5 Vertical


solid walls

3.2.1 150 mm thick walls sq.m 430.00 1,980.00 851,400.00

TOTAL OF MASONRY WORK CARRIED TO Rs. 851,400.00


SUMMARY

3.3 WATER PROOFING

Note :-
The water proofing material shall conform to
relevant British, Euro or ASTM specifications

(a) A written certificate stating that all material


and workmanship are in conformity with the
specifications and the manufacture's
requirements.

(b) The contractor shall jointly with


manufacture/supplier of the waterproofing
materials shall furnish a warranty to the
Employer valid for a period of 10 years after
handing over of the work against dampness
and/or moisture penetration through treated
surfaces due to defective materials and/or
workmanship.

Contractor shall submit and get approval from


Engineer for method statement before
commence the works.

Pond test shall be carried out after the


application, for a depth of 300mm for the period
of 24 hrs.

FIRST FLOOR TO ROOF LEVEL

DAMP PROOFING
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.3.1 Water proofing internal walls of toilet ( 300
mm high in toilet walls and 1500 mm in bath
room walls ) with approved quality liquid
type water proofing chemical. including cleaning
and protect the water proofing area with 20 mm
thick average thick. 1:3 cement and sand plaster
to walls and floor with forming required
shapes with fiber glass net for edges and to
manufacture specification. The contractor is
required to submit the details of
manufacture's specification with 10 years
guarantee for the Engineers approval.

sq.m 50.00 3,300.00 165,000.00

3.3.2 Water proofing of Toilet Roof slab with


application of crystalline type water proofing
system (Xypex or equivalent) according to
manufacturer's specifications. The water proofing
area to be protected with 20 mm average thick
1:3 cement and sand plaster to manufacture
specification. The contractor is required to
submit the details of manufacture's
specification with 10 years guarantee for the
Engineers approval.

sq.m 25.00 3,300.00 82,500.00

TOTAL OF WATER PROOFING CARRIED TO Rs. 247,500.00


SUMMARY

3.4 STRUCTURAL METAL WORK

Note:
Rate shall include for all fabrication work,
including cutting, drilling, bolting, riveting,
welding, grinding delivering, unloading, hoisting,
erecting and fixing.

Rate shall include for all plates, cleats, reverts,


nuts and bolts, washers etc

All the truss rates shall include necessary


75x75x6mm size 150 mm long angle iron cleat at
1200 mm intervals to support to purlings.

FIRST FLOOR TO ROOF LEVEL


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.4.1 Supply, fixing, hoisting and positioning steel
universal beam to roof with 250x125x25 kg/m
size H iron principal rafter as per detail drawing,
including fillet welding, 20mm thick base / shoe
plate, 20mm dia. rag bolts and two coat of anti
corrosive paint, as per detail drawing.

Kg 2,375.00 348.00 826,500.00

3.4.2 Supply & fixing 75x45x15 mm, 2.3 mm thick G.I


purlin laid on steel truss 1200 mm c/c fixing with
6 mm M.S bolts and nuts and 10 mm dia tie rods.
including one coat of etch primer and one coat of
anti corrosive paint. As per detail drawing.

Kg 1,450.00 372.00 539,400.00

STEEL LADDER & GUARD RAIL TO WATER TANK

3.4.3 Supply, fabricating & fixing of steel ladder for


water tank including 2 No, DN 25mm, 3.2mm
medium duty vertical GI bars (width 300mm) &
DN 25mm, 3.2mm thick medium duty horizontal
bars at 300mm c/c and all necessary specials as
per the detail drawing with two coats of anti
corrosive paint & two coats of enamel paint.

Lm 3.00 3,960.00 11,880.00

3.4.4 supply, fabricate and fixing of GI pipe guard rail


(1.0m high) on checker plate deck comprising DN
32mm, 3.2mm thick uprights at 450mm c/c, DN
50mm, 3.2mm thick top rail and DN 25mm
middle rail. Uprights fixed to checker plate deck
with 100 x 100 x 3mm thick base plate with 8mm
dia. GI nuts and bolts and two coats of
anticorrosive paint & two coats of enamel paint.
complete as per detail drawing.

L.m 22.00 10,320.00 227,040.00

TOTAL OF STRUCTURAL METAL WORKCARRIED RS 1,604,820.00


TO SUMMARY.

3.5 METAL WORK

All doors and windows shall be fixed complete to


working order as shown in drawings.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


All the works involve with aluminum should
be carried out according to the detail
drawings and specifications. Rate shall include
for all fabrications works, delivery , unloading,
hoisting , all accessories and fixing in position.
and all Iron mongary fittings and locking
devices , 5 mm thick clear float glass. All
aluminum doors and widows frames sashes
1.2-1.6 mm thick & including necessary
gasket, sealant, glass wool etc.

Rate shall include for all necessary fixing,


fittings, iron mongery, and locking devices of
approved quality as per specification schedule.

All Aluminium shall be natural anodizing


original sections (Anodizing coat shall be
standard aluminium alloy anodic oxidation
coating and thickness 10 - 15 Microns) approved
by the Engineer/Architect.

All windows are casement windows using 5 mm


float glass, rubber beadings strip with silicon
gum.

Aluminium alloy should confirm to- BS


1474:1972 Surface treatment shall confirm to BS
1615 and BS 3987

The over-all profile dimensions used for main


members of each component shall be as
follows.

Doors - 100mm x 1.6mm thick


Windows - Casement - 70 mm x 1.2 mm thick

Windows - Sliding -70mm x 1.5 mm thick


Fan Light - 60mm x 1.2mm thick
Partition - 76mm x 1.2mm thick

Shop drawings should be submitted and got


approval from the Engineer prior to fabrication.

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL

DOORS
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

3.5.1 Type D - Supply, fabricating & fixing Aluminium


framed double sashed fully openable glazed
Paneled Door with louver pannel on top. As per
detail drawing.
sq.m 18.00 16,680.00 300,240.00

3.5.2 Type D1 - Supply, fabricating & fixing Aluminium


framed double sashed fully openable glazed
Paneled Door with louver pannel on top. As per
detail drawing.
sq.m 6.00 16,680.00 100,080.00

3.5.3 Type D2 - Supply, fabricating & fixing Aluminium


framed double sashed fully openable glazed
Paneled Door with louver pannel on top. As per
detail drawing.
sq.m 7.00 16,680.00 116,760.00

WINDOWS

3.5.4 Type W - Supply, fabricating & fixing Aluminium


framed paneled openable glazed window with
louver panels at top. As per detail drawing.

sq.m 11.00 12,360.00 135,960.00

3.5.5 Type W1 - Supply, fabricating & fixing Aluminium


framed paneled openable glazed window with
louver panels at top. As per detail drawing.

sq.m 9.00 12,360.00 111,240.00

3.5.6 Type W2 - Supply, fabricating & fixing Aluminium


framed paneled openable glazed window with
louver panels at top. As per detail drawing.

sq.m 20.00 12,360.00 247,200.00

3.5.7 Type W3 - Supply, fabricating & fixing Aluminium


framed paneled openable glazed window with
louver panels at top. As per detail drawing.

sq.m 7.00 12,360.00 86,520.00

3.5.8 Type FL1 - Supply, fabricating & fixing Aluminium


framed glazed fanlight. As per detail drawing.
sq.m 6.00 12,360.00 74,160.00
HAND RAIL

All stainless steel tubes shall be heavy quality,


1.5 mm thick. Grade 304

Test certificates shall be submitted for samples


collected from the site and approved by the
Engineer.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

3.5.9 Supply, fabricating & fixing Stainless steel hand


rail for the stair case. with 50mm dia.
(Horizontally) Heavy quality Stainless Steel tube
rail and 20 mm dia horizontal bracing @ 750mm
c/c and necessary fixing and fitting. As per detail
drawing.

L.m 10.00 10,680.00 106,800.00

3.5.10 Supply, fabricating and fixing stainless steel pipe


hand rail at staircase comprising 32mm dia.
uprights at 300mm c/c, 50mm dia. top rail and
25mm dia. middle rail. Uprights fixed to steps
with 100 x 100 x 8mm thick S.S. base plate with
8mm dia. S.S. nuts and bolts complete as per
working order. As per detail drawing.

L.m 6.00 13,200.00 79,200.00

TOTAL OF METAL WORK CARRIED TO SUMMARY Rs. 1,358,160.00

3.6 ROOF COVERING AND ROOF PLUMBING

ROOF COVERING

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL

3.6.1 Supply and fixing Zn/Al colour bonded roofing


sheet (Minimum total thickness of 0.47mm), laid
on existing purlings using self drilling screws with
joints to be properly connected with an adequate
side lap to ensure water tightness along the
entire length and complete as per detail
drawings.

sq.m 300.00 1,728.00 518,400.00

3.6.2 Supply and Fixing of (0.47mm ) Zn/Al Colour


Bounded standard ridge cap (500mm girth) using
fasteners as per details drawing.
l.m 30.00 1,080.00 32,400.00

3.6.3 Reflective thermal insulation foil 8mm thick made


up of two layers of aluminium foil laminated to
polyethylene air bubble sheet. With minimum
thermal resistance of 12.3 hrft2'F . Including
double side adhesive tape and air gap tapes and
Gauge 18, 75x75 mm GI mesh.

sq.m 300.00 672.00 201,600.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.6.4 Down pipe- Supply and fixing Zn/Al Colour
bonded 0.47 mm thick 470 mm girth down pipe
consist of external bracket @ 450mm c/c , reverts
etc. As per detail drawing.
l.m 220.00 1,080.00 237,600.00

3.6.5 Eaves gutter- Supply and fixing Zn/Al Colour


bonded 0.47 mm thick 470 mm girth Gutter
consist of internal bracket @ 450mm c/c , reverts
etc. As per detail drawing.
l.m 60.00 1,320.00 79,200.00

3.6.6 Valance board - Supply and fixing Zn/Al Colour


bonded 0.47 mm thick 470 mm girth Valance
board with 12mm width (1/2") angle iron
frame.as per detail drawing
l.m 60.00 1,500.00 90,000.00

3.6.7 Bardge Flashing - Supply and fixing Zn/Al Colour


bonded 0.47 mm thick 470 mm girth Bardge
Flashing with 12mm width (1/2") angle iron
frame.as per detail drawing
l.m 22.00 1,620.00 35,640.00

TOTAL OF ROOF COVERING AND ROOF Rs. 1,194,840.00


PLUMBING CARRIED TO SUMMARY

3.7 PLUMBING / SANITARY INSTALLATION

Note:-
The tenderer shall requested to refer the
Preamble notes, General notes, Drawings,
Specifications, Condition of contract, Special
condition of contract and other relevant
document prior to pricing of the following
items. The tenderer shall provide all dimensions,
and technical information, of all builders work to
the Engineer/Consultant in accordance with the
programme of work.

The tenderer shall submit the following


information on the items/equipment/fittings
quoted for together with the tender.

1. Make
2. Model no
3. Technical data
4. Country of manufacture

All equipment's shall be comply with relevant


British standards or SLS where relevant.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

All fittings to be completed with water supply


and disposal connections to working order.

Piping shall be measured to the net length along


the center line of the pipes over all bends,
junctions, tees and the similar pipe fittings and
shall be given in metre.

The size of PVC pipes are specified by the


external dimensions.

Before starting any operation at site, the


relevant authority shall be informed and get
prior approval.

Unless otherwise specified all sanitary fittings


shall be imported / local quality or approved by
the Engineer. Rates for fittings shall include for
all necessary accessories, traps and any
additional materials needed for fixing in position
to working order.

Rate shall include for necessary elbow, tee,


faucet socket, valve, socket, gate valve, reducing
socket excavation, compaction, back filing etc.
And cutting for chases & making goods

All P.V.C. pipes should confirm to S.L.S. 147. The


fittings should be of the same brand as pipes.

Rates for Plumbing shall include for:


(a) All laps, straight cutting and waste.
(b) All jointing and connected materials.
(c) Chasing in brickwork/ block work/ concrete
floor/ concrete columns and make good.
(d) Fixing pipes to brickwork / block work
(e) Solder rivets, screws, nails, clips, brackets, straps
etc.
(f) Testing installations on completion.
(g) Sterilization, of "Drinking water' pipes on
completion.

FIXTURES, APPLIANCES AND EQUIPMENT

Rates for sanitary fixtures shall include for:


(a) Installation complete with plugs.
(b) Grated waste outlets.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


( c ) Brackets and all fixings including jointing to
pipes.
(d) 10 Years Guarantee certificates of fittings should
be submitted to the Engineer with the bills. No
payments should be certified without bills.

(e) All the UPVC pipes to be certified products to SLS


147 & SLS 659
(f) The fittings are manufactured in conformity to
BS, JIS, A.S.T.M., A.S. or S.L.S. standards.
Approved Fittings with 1 year manufacturer's
warranty for taps

COLD WATER SYSTEM

Water Supply & Storage

3.7.1 Supply and Laying of underground Cold Water


Supply Main from road to the overhead tnak with
32mm, uPVC type 1000 pipes as shown in the
drawings. Rate shall include for pipes, fittings,
excavation and refilling, pipe supporting and
other necessary items and consumables.

m 45.00 720.00 32,400.00


-
3.7.2 Provide a sum for construction of
cement/Conccrete chamber for the consumer
meter
Item 1.00 5,400.00 5,400.00
-
Supply Installation of Over Head Tank -
-
3.7.3 Supply Installation of PVC overhead water tank
above the Roof Slab with 5000L capacity. Rates
shall include drain, over flow with all necessary
pipe fittings, isolation valves, supporters & other
necessary accessories & consumables.

Item 1.00 90,000.00 90,000.00


-
Supply, Laying and Installation of Cold Water
Distribution Lines
-
-
Supply, laying ,Installation of Cold Water
horizontlly distribution pipe line with pipe &
required fittings, laid on riser/wall, under
ground, buried in concrete floor,hang on
concreate above the ceiling. Rates shall include
mounting brackets, required pipe fittings & other
necessary accassaries. with chipping of walls,
concreting, excavation & back filling & ect.

-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


-
Upper floor -
-
3.7.4 32mm diameter (uPVC type 1000) with
accessories
m 15.00 744.00 11,160.00
-
3.7.5 25mm diameter (uPVC type 1000) with
accessories
m 25.00 672.00 16,800.00
-
3.7.6 20mm diameter (uPVC type 1000) with
accessories
m 8.00 588.00 4,704.00
-
3.7.7 63mm diameter (uPVC type 1000) with
accessories
m 5.00 1,632.00 8,160.00
-
Supply Installation of Delivery Line's Isolating
valves/Non return valves fittings Rates shall
include all necessary pipe fittings, holding
brackets & supporters & other necessary
accessories & consumables.Manufactured in
Japan, UK or equivalent.

-
-
3.7.8 50mm diameter No. 1.00 7,200.00 7,200.00
-
3.7.9 40mm diameter Nos. 5.00 6,120.00 30,600.00
-
3.7.10 32mm diameter Nos. 3.00 4,560.00 13,680.00
-
3.7.11 25mm diameter Nos. 2.00 4,200.00 8,400.00
-
SUPPLY OF SANITARY FITTINGS AN ACCESSORIES
-
-
Supply of Sanitary Fittings and Accessories. . -
-
Supply of sanitary fittings with all necessary
sanitary fittings such as angle valves, flexible
connections with all necessary fixing
accessories. .
-
-
3.7.12 Water Closets(WCs) with angle valves, flexible
connections, all necessary fixing accessories.
Nos. 4.00 26,400.00 105,600.00
-
3.7.13 Vanity Wash Basin with angle valve, flexible
connection, rubber plug and chromium plated
chain, waste bottle trap and all necessary fixing
accessories
Nos. 5.00 17,400.00 87,000.00
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.7.14 Toilet paper holder with accessories. Nos. 4.00 1,440.00 5,760.00
-
3.7.15 Bidet spray with angle valve and all necessary
fixing accessories.
Nos. 4.00 1,800.00 7,200.00
-
3.7.16 Robe hooks, fixed to doors of water closets with
chromium plated brass screws.
Nos. 4.00 720.00 2,880.00
-
3.7.17 Soap dish fixed to wall with fiber plugs and
chromium plated brass screws.
Nos. 5.00 1,200.00 6,000.00
-
3.7.18 PVC floor gullies with water trap and stainless
steel grating.
Nos. 7.00 2,760.00 19,320.00
-
Installation of Sanitary Fittings and Accessories.
-
-
3.7.19 Installation of all Sanitary fittings with all
necessary sanitary fittings such as angle valves,
flexible connections & all required bathroom
accessories .
-
-
3.7.20 Installation of Water Closets(WCs) with angle
valves, flexible connections, all necessary fixing
accessories.
Nos. 4.00 26,400.00 105,600.00
-
3.7.21 Installation of Vanity Wash Basin with angle
valve, flexible connection, rubber plug and
chromium plated chain, waste bottle trap and all
necessary fixing accessories
Nos. 5.00 17,400.00 87,000.00
-
3.7.22 Installation of Toilet paper holder with
accessories.
Nos. 4.00 1,440.00 5,760.00
-
3.7.23 Installation of Bidet spray with angle valve and all
necessary fixing accessories.
Nos. 4.00 1,800.00 7,200.00
-
3.7.24 Installation of Robe hooks, fixed to doors of water
closets with chromium plated brass screws.
Nos. 4.00 720.00 2,880.00
-
3.7.25 Installation of Soap dish fixed to wall with fiber
plugs and chromium plated brass screws.
Nos. 5.00 1,200.00 6,000.00
-
3.7.26 Installation of PVC floor gullies with water trap
and stainless steel grating.
Nos. 7.00 2,760.00 19,320.00
-
WASTE WATER SYSTEM -
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Supply and Installation of Vertical & Horizontal
Waste Water Pipe Lines
-
-
Supply and Installation of Waste Water Pipe Lines,
laid underground, required connections of waste
water line to manholes up to soakage pit. Rates
shall include pipes & required fittings, excavation
and back filling, levelling pads, brackets & other
necessary accassaries.

-
-
3.7.27 63mm diameter (uPVC type 600) m 68.00 1,440.00 97,920.00
-
3.7.28 50mm diameter (uPVC type 600) m 9.00 900.00 8,100.00
-
3.7.29 40mm diameter (uPVC type 600) m 6.00 720.00 4,320.00

SEWER DISPOSAL SYSTEM -


-
Supply Installation of Vertical & Horizontal
Sewer Pipe Lines
-
-
Supply and installation of Sewer Pipe Line's laid
underground, required connection of Sewer lines
to manholes and interconnect to manhole up to
septic tank. Rates shall include pipes & required
fittings, excavation and back filling, levelling pads,
brackets & other necessary accassaries.

-
-
3.7.30 110mm diameter (uPVC type 600) m 19.00 2,640.00 50,160.00
-
3.7.31 63mm diameter (uPVC type 600) m 18.00 1,440.00 25,920.00
-
TESTING, COMMISSIONING & HANDING OVER
ALL PLUMBING SYSTEM
-
-
3.7.32 Preparation of shop drawings & Handing over
document
Item 1.00 12,000.00 12,000.00
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.7.33 Testing and commissioning of total plumbing
services
Item 1.00 12,000.00 12,000.00

TOTAL OF PLUMBING / SANITARY INSTALLATION Rs. 906,444.00


CARRIED TO SUMMARY

3.8 MECHANICAL INSTALLATION

FIRE PROTECTION SYSTEM INSTALLATION


FIRE EXTINGUISHERS

3.8.1 Supplying & Installation of ( 6Kg ) Dry Powder Fire


Extinguishers (fully charged and controllable
type) complete with metal mounting brackets and
Horn.
Nos 2.00 8,568.00 17,136.00
-
3.8.2 Supplying & Installation of ( 3Kg -CO2) Carbon
Dioxide Fire Extinguishers (fully charged and
controllable type) complete with metal mounting
brackets and Horn.
Nos 2.00 7,294.00 14,588.00
-
3.8.3 Supplying & Installation of 9 Lt water (H2O) Fire
Extinguishers (fully charged and controllable
type) complete with with metal mounting
brackets and Horn.
Nos 2.00 6,432.00 12,864.00
-
FIRE ALARM AND DETECTION SYSTEM
INSTALLATION
-
3.8.4 Supply, installation and commissioning of
Illuminating LED Exit board with White Letters on
Green Background with 3hrs battery back up and
all other required accessories.

Nos 3.00 11,333.00 33,999.00


-
FIRE PROTECTION SYSTEM INSTALLATION -
3.8.5 Testing, Commissioning, Fire department
inspection, Staff Training, Handing Over and one
year free servicing of the Fire Hydrant.
System will be tested for proper functioning &
each equipments and Submitting of shop
drawing (2 set, A2) and "as built" (2 set, A2)
drawings, technical specifications and Fire
department approval.

Item 1.00 51,000.00 51,000.00


-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.8.6 Any other item required to operate the Fire
Protection system effectively and efficiently or
required as per the prudent engineering
practices, but not included in this BOQ.(please
specify clearly. Incase, if the bidder fails to
include such items which are not included in this
BOQ but required to operate the system, prices of
such items are considered as included in this
offer.)

Item 1.00 15,300.00 15,300.00


-
TOTAL OF MECHANICAL INSTALLATION CARRIED Rs. 144,887.00
TO SUMMARY
-
3.9 ELECTRICAL INSTALLATION -

GENERAL

The Tenderers are requested to refer the General


notes, Drawings and study the taxes, safety
procedures, site conditions before the pricing.
The Tenderer shall provide all dimensions, and
technical information, of all builders work to the
Engineer/Consultant in accordance with the
programme of work.

PREAMBLE NOTES

The Contractor is to refer to ICTAD publication No


SCA/8 (Specifications for Electrical and
Mechanical Works associated with Buildings and
Civil Engineering).

Not with standing Preamble Notes of the


Standard Method of Measurement of Building
Works, the Contractor shall refer to the
specification and Drawings for full particulars and
descriptions of workmanship and shall include for
the full intent and meaning there of in the prices
of the item

Preamble notes , measurement and prices


clauses from all other relevant trades within this
section of Tender Document shall apply equally to
this trade where required

Prices are deemed to include for the following


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Prices for the panels boards deemed to include
for finished enclosures, bus bars , panels locks ,
legend
plates , danger boards , DB's , ACB's , MCCB's,
MCB's and the required fixing materials like coach
screws , nuts & bolts and foundations etc.

Prices of Distribution boards deemed to include


for finished enclosures, MCB's, ELCB's, Neutral
links dummy plates if any and the required
chipping, fixing of DB in walls etc.

Prices of Cable running in the cable trays deemed


to include for cable clamps, tags and cable
ferrules

Prices for Under Ground Cable deemed to include


for excavation, protection of cable, refilling with
excavated earth, consolidation / compaction etc.

Prices for Cable termination deemed to include


for double compression glands, accessories for
crimping / soldering, earth tags and earth
connection lugs etc.

Prices for Cable termination deemed to include


all required structural steel members, welding,
screws, nuts & bolts required for fixing etc
including one coat of primer and two coats of
paint.

Prices deemed to include for screws, nails, bolts,


nuts, nipples, standard cable fixing or supporting
clips, saddles brackets, straps, rivets, plugs and
similar items and all incidental accessories.

Prices for Earth pits deemed to include for


excavation, backfilling, compaction, cable covers,
warning tapes, GI pipes, charcoal, salt and other
required materials etc.

Prices deemed to include for interviewing and


connections between components and control
gear within the board.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Prices deemed to include for cutting and jointing
cable for carriers at fittings together with cutting
or forming openings in cable carriers for conduits,
entries from equipment and control gear and
similar items; cradles,
pin racks for support.

Prices for conduits deemed to include for


standard junction boxes and fittings and fixing
conduits to or
through all building surfaces.

Prices deemed to include for all cable supports


and fixings; providing draw wires, draw cables
and similar
items for drawing or hoisting cables.

Prices deemed to include for all items listed for


conduits, cables and conduit sleeves; all cable
joints and skinning ends and connecting cables to
switches, outlets, accessories, light fittings and
similar items.

Prices are also deemed to include the following :

Any additional costs in complying with the


programme such as staging and/or phasing,
access limitations working in or adjacent
occupied areas and providing uninterpted service
for the areas where hotel in operating,
maintenance of existing services as set out in the
Contract Documents;

Co-ordination of works between contractor and


subcontractors and/or Principal

Strict control to minimize the effects of noise,


vibration, dust, mud, smoke, fumes, interruption
or hindrance of access and other nuisance which
could adversely affect the public areas of
adjacent buildings;

Rectification and making good to services


disturbed during construction; and chased walls
plaster

All chasings in walls, beams, column, slabs


wherever required
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

Providing all samples of materials and finishes as


required by the Specification.

Complying with the relevant Acts, By-laws and


regulations.

Carrying out tests as required

Testing all installations as required and specified.

Submit notices, obtaining permits and


completion certificates, paying fees and charges
in connection with
the relevant installations.

Obtaining and submitting all guarantees and


warranties as specified.

Quality Assurance and control as specified.

Providing plans, diagrams, manuals and similar


items as required for the relevant installations.

Coordinating penetrations in connection with the


installations.

Maintaining operation of the existing buildings


during the Contract.

Penetrations and chases required through new


existing walls, ceilings and floors for electrical
services cable and fittings including additional
support framing members where required.

Providing holes and trimmings, suspension and


trimming support for the installation of
luminaries and speakers in ceilings.

Provision of rigid framework in stud walls for the


fixing of cable support channels, distribution
boards,control panels and similar equipment.

Lifting the panels to required floors with


necessary plant and machinery.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Cable trays shall be measured net in running
meters.

Cables shall be measured net as shown on the


GFC / As built drawings without any additional
leverage for
loose cables. The unit rate shall include all
necessary loose cables required for the works in
bends / curves
/ circles and end terminations etc.

Wiring shall be measured net as shown on the


GFC / As built drawings without any additional
leverage for
loose cables. The unit rate shall include all
necessary loose wiring required for the works in
switch boards / junctions / bends / curves /
circles and end terminations etc

Hume pipes shall be measured net as shown on


the GFC / As built drawings. The unit rate shall
include all necessary earthwork excavation, laying
of pipes, backfilling and consolidations etc.

Al / PVC sunk box to be deep type

All socket outlets to be switched and shuttered


type

All socket outlets to be SLS approved 13A socket


outlets to BS 1363

All underground cables to be armored type.

All outdoor underground cables used for lamp


point wiring shall be 3 core unless otherwise
specified.

ELECTRICAL PANEL BOARDS

Supply and installation of electrical panel board


three(3) phase, neutral and earth complete with
powder coated steel sheet enclosure, hinged and
lockable door as per specification and drawings
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Electrical Panel shall include MCCB, Isolator,
MCBs, RCDs, Surge protectors, automatic change
over switch, busbars, terminals and all required
accessories.

Quantity and current rating of equipments to be


installed in Panel boards shall be as given in the
drawings.

3.9.1 Main distribution board DB-UF wall mount type.


No. 1.00 70,788.00 70,788.00
-
-
-
-
-
FEEDER CABLES -
-
Supply and installation of 600/1000V feeder
cables in cable tray/conduit, XLPE insulated or
PVC insulated, PVC sheathed, copper conductor
cable with three core/single core & earth cable.

-
Rate to include for supply and installation of cable
terminations at both ends and necessary glands
-
-
3.9.2 Power cable from Existing panel to DB-UF:
4C-6sqmm Cu/PVC/PVC cable + 1C-6sqmm
Cu/PVC/PVC
m 32.00 1,335.00 42,720.00
-
WIRRING OF LAMP & S/O AND FAN POINT -
FINAL SUB CIRCUIT POINT WIRING -
-
Supply all materials and provide final sub circuit
point wiring for the following outlets with PVC
conduit, 10A switches and connectors Including
other materials required to make complete
installation as specified and as shown in the
electrical drawings.

-
-
3.9.3 Wiring of light fitting using 2x1Cx1.5Sqmm
Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu earth
cable in PVC conduits and controlled by a 10A
Switch.
Nos. 50.00 2,933.00 146,650.00
-
3.9.4 Wiring of emergency lamp using 2x1Cx1.5Sqmm
Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu earth
cable in PVC conduits.
Nos. 4.00 2,933.00 11,732.00
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.9.5 Wiring of exist lamp point using 2x1Cx1.5Sqmm
Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu earth
cable in PVC conduits.
Nos. 3.00 2,933.00 8,799.00
-
3.9.6 Wiring of Fan point using 2x1Cx1.5Sqmm
Cu/PVC/PVC and 1Cx2.5 sqmm PVC/Cu earth
cable in PVC conduits and controlled by a 10A
Switch.
Nos. 6.00 2,933.00 17,598.00
-
3.9.7 13A switched socket outlet wired using
2x1Cx2.5Sqmm Cu/PVC/PVC and 1Cx2.5Sqmm
Cu/PVC Earth in radial circuit with PVC conduits
c/w all conduit and fixing accessories.

Nos. 40.00 4,678.00 187,120.00


-
3.9.8 Wiring for Exhust-fan using 2x1Cx1.5Sqmm
Cu/PVC/PVC and 1Cx2.5Sqmm Cu/PVC Earth in
PVC conduits c/w all conduit and fixing
accessories.
Nos. 2.00 2,933.00 5,866.00
-
3.9.9 Wiring of 2-way light points using
2x1Cx1.5Sqmm Cu/PVC/PVC cable and 1Cx2.5
sqmm PVC/Cu earth cable.
Nos. 3.00 3,010.00 9,030.00
-
SUPPLY OF LIGHTING FIXTURES -
-
Supply of the following lighting fixtures with all
accessories as per the specifications and as
annexed scheduled of lighting fixtures for all
areas. lamp fitting and accessories should be
reputed makes as given in the schedule.

-
-
3.9.10 18W LED down light Nos. 50.00 1,317.00 65,850.00
-
3.9.11 15W LED wall bracket light No. 1.00 5,447.00 5,447.00
-
3.9.12 Emergency lamp fittings with 2 x 10W, completed
with sealed lead acid battery for 2Hrs back up
time & wall mounted type.Model:SAMCOM ETL-
210 or equivalent
Nos. 3.00 7,242.00 21,726.00
-
3.9.13 Ceiling fan 1200mm dia. (KDK or equivalent) with
electronic speed regulator & accessories.
Nos. 6.00 10,558.00 63,348.00
-
-
INSTALLATION OF LIGHTING FIXTURES -
-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Install of the following lighting fixtures with
required junction box, terminations, connectors
and all required accessories as per the
manufacturer's recommendations. (Fixing
method has to be approved by the lighting
supplier/manufacturer)

-
-
3.9.14 18W LED down light Nos. 50.00 664.00 33,200.00
-
3.9.15 15W LED wall bracket light No. 1.00 664.00 664.00
-
3.9.16 Emergency lamp fittings with 2 x 10W, completed
with sealed lead acid battery for 2Hrs back up
time & wall mounted type.Model:SAMCOM ETL-
210 or equivalent
Nos. 3.00 868.00 2,604.00
-
3.9.17 Ceiling fan 1200mm dia. (KDK or equivalent) with
electronic speed regulator & accessories.
Nos. 6.00 664.00 3,984.00
-
TELEPHONE SYSTEM -
-
SUPPLY & INSTALLATION OF TELEPHONE SYSTEM
-
-
3.9.18 Supplying, installing, connecting and testing of 50
pair Main Distribution Frame(MDF-UF) including
krone type modules, steel cabinet , labeling,
connectors and all necessary accessories and
ancillary works and materials required for
complete installation and operation as specified
and as indicated on the drawings.

No. 1.00 10,710.00 10,710.00


-
3.9.19 Supply and installation of surge protection system
for all incoming telephone lines(Plug in to the
Krone modules)
Item 1.00 4,590.00 4,590.00
-
3.9.20 Earthing of MDFby installing of 1C- 6 sqmm
Cu/PVC (Earth) cable & standard copper earth
electrode including all accessories / joints etc. as
per B.S. code of practice for earthing to achieve
an earth resistance of less than 1 Ohm.

Item 1.00 22,440.00 22,440.00


-
3.9.21 Supply and installation of jelly filled 15 pair 0.5
mm Cu underground telephone cable from
service providers termination point to MDF

m 25.00 705.00 17,625.00


-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.9.22 Wiring of Telephone outlets using 2 pair 0.5mm
Telephone cable in PVC conduits from MDF/PABX
to each outlet complete with all conduit, fixing
accessories and termination and including of RJ11
outlet plate .

Nos. 8.00 7,038.00 56,304.00


-
3.9.23 Supply & installation of Analogue Telephone
instruments
Nos. 7.00 2,754.00 19,278.00
-
-
-
-
-
-
-
-
EARTHING SYSTEM -
-
3.9.24 Earthing of main electrical panel by installing of
1C- 16 sqmm Cu/PVC (Earth) cable & standard
copper electrode including all accessories / joints
etc. as per BSEN62305 & to achieve an earth
Resistance less than 5 Ohms

item 1.00 33,048.00 33,048.00


-
LIGHTNING PROTECTION SYSTEM -
-
3.9.25 25 mm x 3 mm copper tape fixed to wall (Down
Conductor) with brass clips and screws at every
500 mm.
m 38.00 2,204.00 83,752.00
-
3.9.26 25 mm x 3 mm copper tape fixed to roof
Conductor with clips and brackets at every 750
mm.
m 18.00 2,204.00 39,672.00
-
3.9.27 Early Streamer Emission Type Lightning
Protection System with minimum covarage
radius of 25m in Protection Level -1 and Air
Terminal -1,supported on to a 02 m GI Pipe
mounted on the roof top of the Building.
nr 1.00 148,716.00 148,716.00
-
3.9.28 Test clamp fixed at height of 1200 mm. nr 1.00 4,407.00 4,407.00
-
3.9.29 Earthing of the system by installing of 600 mm X
600 mm X 5mm copper plate including all
accessories / joints etc. as per BSEN62305 & to
achieve an earth Resistance less than 5 Ohms

nr 1.00 71,604.00 71,604.00


-
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


FINAL DOCUMENT -
-
3.9.30 Testing the installation by a Chartered Electrical
engineer registered with the CEB and obtaining a
Test Certificate.
Item 1.00 51,000.00 51,000.00
-
3.9.31 Preparation of Shop Drawings, as-built drawings,
operation and Maintainers manuals.
Item 1.00 76,500.00 76,500.00
-
TOTAL OF ELECTRICAL INSTALLATION CARRIED TO Rs 1,336,772.00
SUMMARY.

3.10 FLOOR/WALL/CEILING FINISHES

Note:-

For the full description of materials and


workmanship refer "Specification of works"
"Preambles" and "Drawings"

Plastering
The rate for plastering items includes the cost of
"Febmix"as a workability enhancer.
For coarse textured plaster ( identified as "semi-
rough") all the sand should pass through 4.0mm
sieve.

Floor / Wall Tiles


Floor Tiles should comply to SLS 1181:2013
"specification for ceramic tiles" and shall comply
to relevant abrasion resistant class.

Copy of the tile purchase bill should be produced


at the time of payment.
Wall Tiles should be Lanka Wall Tile or approved
equivalent.
Floor Tiles Shall be Homogenous, porcelain floor
tiles of industrial grade floor tile range
manufactured by Rocell or approved equivalent.

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL

FLOOR FINISHES
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.10.1 400 x 400 / 600x600 mm size coloured non-skid
pattern, homogenoius ceramic floor tiling, joint
and point in cement to match, on and including
19mm thick cement and sand (1:3) screed bed in
Upper floor area. (joints filled with polymer
grout) [Prime Cost per Sqft - Rs.200.00]

sq.m 190.00 4,320.00 820,800.00

3.10.2 300 x 600 mm size coloured non-skid pattern,


homogenoius ceramic floor tiling, joint and point
in cement to match, on and including 19mm thick
cement and sand (1:3) screed bed in ground floor
staircase. (joints filled with polymer grout and
1/2" aluminium edge strips) [Prime Cost per Sqft -
Rs.171.64]

sq.m 70.00 4,200.00 294,000.00

3.10.3 100mm high Tile skirting l.m 120.00 432.00 51,840.00

3.10.4 300 x 300 mm size coloured non-skid pattern,


homogenoius ceramic floor tiling joint and point
in cement to match, on and including 19mm thick
cement and sand (1:3) screed bed in toilet floor
area. (joints filled with polymer grout) [Prime
Cost per Sq.ft. - Rs.166.52]

sq.m 25.00 3,720.00 93,000.00

WALL AND CEILING FINISHING

WALL TILE
Approved type 300x600mm glazed ceramic wall
tiling joint and point in coloured cement on and
including 12 mm thick cement and sand (1:3)
screed backing on walls up to 1500 mm high
from floor level in toilet area .( joints filled with
polymer grout ) [Prime Cost per Sq.ft. -
Rs.171.64]

3.10.5 Internal wall for toilet. sq.m 45.00 3,840.00 172,800.00

PLASTERED/RENDERED

16 mm thick cement and sand (1:5) plaster


finished smooth with skim coat (internally)

Width < 300 mm

3.10.6 On blocks / Concrete surfaces. l.m 250.00 240.00 60,000.00

Width > 300mm


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

3.10.7 On blocks / Concrete surfaces. sq.m 650.00 720.00 468,000.00

16 mm thick plastering to R.C.C beam, slab soffit


in cement and sand 1:3 including floating with
Skim coat,

Ceiling width < 300mm

3.10.8 To soffit of slab. sq.m 25.00 840.00 21,000.00

3.10.9 To side and soffit of beam. sq.m 65.00 840.00 54,600.00

16 mm thick cement and sand (1:5) plaster


finished semi-rough (externally)

Width < 300mm

3.10.10 On blocks / Concrete surfaces. l.m 190.00 240.00 45,600.00

3.10.11 Forming drip for sunshade edge cement & sand 1:


3 finished semi rough.
l.m 22.00 240.00 5,280.00

Width > 300mm

3.10.12 On blocks / Concrete surfaces. sq.m 210.00 720.00 151,200.00

INTERNAL CEILING

3.10.13 Supply and fabricating of 600 x 600 mm size,


3.2mm thick cement fiber (Superflex or
equivalent) sheet flat ceiling (Asbestos free) with
aluminium frame consisting of "T" bars, main
bars, "L" bars & steel hangers for the internal
area. As per the manufacturing specification and
given instruction.

sq.m 203.00 1,620.00 328,860.00

EXTERNAL CEILING

3.10.14 Eave ceiling, Supply and fixing of 4mm thick


cladding sheet ceiling with framework consisting
of 1" x 1" heavy quality angle iron and 1 1/2"
aluminium box bar, wire clips, wall clips and other
necessary fittings. All as per the manufacturing
specification and given instruction.

sq.m 90.00 2,640.00 237,600.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

TOTAL OF FLOOR / WALL / CEILING FINISHINGS Rs 2,804,580.00


CARRIED TO SUMMARY.

3.11 PAINTING

PLASTER WORK

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL

Prepare and apply one coats of approved wall


filler and two coats of emulsion paints to new
walls.(internally)

Plastered work general surfaces, plain surfaces.

Girth > 300mm


3.11.1 On walls/concrete surface sq.m 670.00 672.00 450,240.00

Prepare and apply one coat alkali resistant


primer and two coats of emulsion paint.

3.11.2 To soffit of slab. sq.m 25.00 696.00 17,400.00

3.11.3 To side and soffit of beam. sq.m 65.00 696.00 45,240.00

Prepare and apply one coat of primer and two


coats of weather shield emulsion paint
(externally)

Plastered work general surfaces, plain surfaces.

Girth > 300mm


3.11.4 On walls/concrete surface sq.m 225.00 744.00 167,400.00

TOTAL OF PAINTING CARRIED TO SUMMARY Rs 680,280.00

3.12 MISCELLENIOUS WORKS

ABOVE STRUCTURAL FLOOR LEVEL

FIRST FLOOR TO ROOF LEVEL


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 3

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


3.12.1 Demolition and removing the existing additional
slab on top of staircase area and waste remove
from the site as directed by the Engineer.

Item - Allow 30,000.00

3.12.2 Cleaning and removing the existing slab top waste


materials and remove from the site as directed by
the Engineer. Rate shall include for cleaning, wire
brushing and all other preparatory works to the
existing slab top)

Item - Allow 54,000.00

TOTAL OF MISCELLENIOUS WORKS CARRIED TO Rs 84,000.00


SUMMARY
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 5

BILL NO. 5

PROVISIONAL SUMS
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 5

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

5.0 PROVISIONAL SUMS

5.1 Allow sum for Demolition existing buildings


shown in the drawings including walls, roof,
concrete items, foundation if any and debris PS - 500,000.00 500,000.00
carted away from the site.

5.2 Allow sum for Providing all operations pertaining


to the planting and maintenance of trees, shrubs,
ground cover. The Work shall also include all
operations pertaining to removing and replacing PS - 500,000.00 500,000.00
trees and protecting existing trees in place.

5.3 Allow sum for Providing the passenger seating


facilities in waiting areas with 50mm diameter
3.2mm thick GI pipe framework horizontal bars
and vertical columns fixed to concrete floor
including 300mm wide class II timber deck and PS - 900,000.00 900,000.00
back rest, all inclussive of painting, all as per the
engineers approval.

5.4 Allow sum for Initial Mangement of Re-routing


and Re-location of the busses. PS - 10,000,000.00 10,000,000.00

5.5 Attendance fee for Item No. 5.4 (10%) Item 1.00 8% 800,000.00

5.6 Allow sum for Initial Mangement for


commissioning of the new terminal area all PS - 5,000,000.00 5,000,000.00
activities.

5.7 Attendance fee for Item No. 5.6 (10%) Item 1.00 8% 400,000.00

5.8 Provisional sum for payment for water supply


connection to N.W.S. & D.B. PS - 120,000.00 120,000.00

5.9 Attendance fee for Item No. 5.8 (10%) Item 1.00 8% 9,600.00

5.10 Provisional sum for payment to be made to C.E.B/


LECO for three phase connection and complete
with incoming cable and all other accessories. PS - 300,000.00 300,000.00

5.11 Attendance fee for Item No. 5.10 (10%) Item 1.00 8% 24,000.00

5.12 Provisional sum for payment for Telephone


connection to SLT. PS - 200,000.00 200,000.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 5

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

5.13 Attendance fee for Item No. 5.12 (10%) Item 1.00 8% 16,000.00

5.14 Allow sum for supplying specimens and samples


of materials and carrying out tests (Additional
tests ordered by the Engineer). PS - 150,000.00 150,000.00

-
5.15 Allow sum for providing road marking and bus
lane marking as directed by the Engineer. PS - 200,000.00 200,000.00

TOTAL OF BILL NO. 4 CARRIED TO GRAND Rs 19,119,600.00


SUMMARY
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 4

BILL NO. 4

IMPROVEMENTS TO THE ROADS


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 4

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


4.1 GENERAL

4.1.1 Provision and Maintenance of arrangement for


traffic during construction.
Mon 2.00 216,000.00 432,000.00

4.2 SITE CLEARING

4.2.1 Removal of Structure and Obstructions along the


road side as per the Engineers instructions.
Item - Allow 96,000.00

4.3 RECONSTRUCTION OF EXISTING PAVEMENTS

4.3.1 Dense graded aggregate base (Approx. 100mm


thick) (Aggregate base course - ABC) Supplying,
Pilling, spreading, watering & compacting graded
37.5 mm aggregate to from a dense aggregate
base including 03 km transport of aggregates.
(Compacted Volume)

Cum 120.00 2,940.00 352,800.00

4.3.2 Scarify and remove existing bitumen layer as


directed by the Engineer.
Sqm 1,200.00 216.00 259,200.00

4.3.3 Supplying and Application of Prime Coat on


prepared base using emulsion with CSS1 at the
rate of 1.0 lit/m2 including cleaning of road
surface.
Sqm 1,200.00 204.00 244,800.00

4.3.4 Bituminous tack coat (Cationic Emulsion grade


CRS1) at the rate od 0.3 liter per Sq.m.
Sqm 1,200.00 108.00 129,600.00

4.3.5 Supply, laying and compacting (Approx. 50mm


thick) Asphalt Concrete Surfacing Material binder
bitumen @ 4.7% Mix 60/70 with 19mm
aggregates.
MT 150.00 15,600.00 2,340,000.00

4.4 REPAIRS TO EXISTING DRAINS

4.4.1 Supply, mixing and placing of Grade 25(20mm


agg.) concrete for 200mm thick drain cover slabs
(Heavy Duty) as per detail drawings and as
directed by the Engineer.
Cum 90.00 19,200.00 1,728,000.00

4.4.2 Supply and placing 15mm thick playwood sheet


formworks for cover slabs as directed by the
Engineer.
Sqm 300.00 1,440.00 432,000.00
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 4

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

4.4.3 Supply and placing tor steel reinforcements (BS


4449 and strength FY=460 N/mm²) as directed by
the Engineer.
Kg 6,500.00 198.00 1,287,000.00

4.5 ROAD FURNITURE & MARKING


Item to mark Center line, Edge line & Pedestrian
crossing using reflectorized thermoplasticc
material with glass beads, to 3mm thickness.

4.5.1 Thermoplastic material (white) Sq.m. 110.00 2,400.00 264,000.00

TOTAL OF BILL NO. 4 CARRIED TO GRAND Rs. 7,565,400.00


SUMMARY
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 6

BILL NO. 6

DAY WORKS
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 6

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

6.0 DAY WORKS

The Contractor is required to include the


following provisional quantities of labor,
materials and plant to be executed as Dayworks
for the purpose of ascertaining the cost of works
where work cannot otherwise be properly Note
measured and valued.

The total value of this section as priced by the


Tenderer will be deemed Provisional under the Note
terms of this Contract.

The Day work sheets shall be numbered and


fully describe the instructions to which they
refer and shall be summarized and submitted to
the Engineer for verification, not later than the
end of the week following that in which the
work has been executed or earlier if the
Engineer so directs. The Contractor shall arrange
for signed copies of the day work sheets to be
returned to him by the Engineer. A signed copy
of the day work sheet should then be fully Note
priced out and sent to the Engineer within 14
calendar days of the work being executed.

Except in cases of prior agreement, any decision


with regard to payment on a Day work basis for
any variation will be made by the Engineer Note

Rates

All day work rates shall be all inclusive rates


including any working out side normal working Note
hours (overtime)

Overheads & Profit

All labour, materials and plant day work rates


shall be deemed to include for necessary Note
overheads and profits applicable.
CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 6

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

6.1 LABOUR RATES

The Contractor shall quote the rate he requires


for his labourers and craftsmen in the following
schedule and extend the rate by the hours
stated. The rates quoted shall be included for Note
overheads and profit.

6.1.1 Labour- Un skilled Hrs 250.00 228.00 57,000.00

6.1.2 Labour- Semi skilled Hrs 100.00 270.00 27,000.00

6.1.3 Labour -skilled (A) Hrs 100.00 345.00 34,500.00

6.1.4 Labour -skilled (B) Hrs 100.00 312.00 31,200.00

6.1.5 Labour ganger -supervisor Hrs 25.00 240.00 6,000.00

6.1.6 Bar bender Hrs 50.00 345.00 17,250.00

6.1.7 Mason Hrs 100.00 345.00 34,500.00

6.1.8 Carpenter/Joiner Hrs 100.00 345.00 34,500.00

6.1.9 Plumber/Pipe fitter Hrs 50.00 345.00 17,250.00

6.1.10 Plasterer/Tile fixer Hrs 50.00 345.00 17,250.00

6.1.11 Painter Hrs 100.00 312.00 31,200.00

6.1.12 Transport Driver Hrs 50.00 228.00 11,400.00

6.1.13 Crane Driver Hrs 50.00 348.00 17,400.00

6.1.14 Plant Operator Hrs 50.00 345.00 17,250.00

6.1.15 Electrician Hrs 50.00 348.00 17,400.00

6.1.16 Fitter Ductwork Hrs 50.00 345.00 17,250.00

6.1.17 Aluminium fabricator Hrs 50.00 348.00 17,400.00

TOTAL BOQ 6.1 405,750.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 6

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

6.2 MATERIAL

The Contractor shall quote the rate he requires


for material delivered to the site in the following
schedule. The rates quoted shall be included for Note
overheads and profit.

6.2.1 Aggregate base, dense graded (37.5 mm) Cum 30.00 2,220.00 66,600.00

6.2.2 Aggregate, 12 mm Cum 10.00 2,880.00 28,800.00

6.2.3 Aggregate, 20 mm Cum 10.00 2,880.00 28,800.00

6.2.4 Aggregate, 25 mm Cum 10.00 2,880.00 28,800.00

6.2.5 Aggregate, 37.5 mm Cum 10.00 2,880.00 28,800.00

6.2.6 Asphalt concrete, hot mix (wearing course) Mt 5.00 15,000.00 75,000.00

6.2.7 Bitumen emulsions, ( CRS 1) Ltr 15.00 96.00 1,440.00

6.2.8 Bitumen prime coat, Emulsion CSS1 Ltr 50.00 1,080.00 54,000.00

6.2.9 Cement, ordinary Portland - 50Kg Bags Nos 25.00 1,080.00 27,000.00

6.2.10 Exterior emulsion paint Ltr 10.00 1,080.00 10,800.00

6.2.11 Interior emulsion paint Ltr 10.00 840.00 8,400.00

6.2.12 Enamel paint Ltr 10.00 840.00 8,400.00

6.2.13 Standard Bricks Nos 1,000.00 17.00 17,000.00

6.2.14 150mm thick Blocks Nos 100.00 95.00 9,500.00

6.2.15 Ply wood 12mm thick-8'x4' marine Nos 15.00 3,360.00 50,400.00

6.2.16 Ply wood 16mm thick-8'x4' marine Nos 15.00 4,080.00 61,200.00

6.2.17 Slaked lime (40 kg) Bag 5.00 960.00 4,800.00

6.2.18 DPC bitumen Ltr 5.00 72.00 360.00

6.2.19 1000 gauge polythene kg 100.00 168.00 16,800.00

6.2.20 Concrete, Grade C 15 Cum 5.00 17,040.00 85,200.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 6

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

6.2.21 Concrete, Grade C 20 Cum 5.00 18,120.00 90,600.00

6.2.22 Concrete, Grade C 25 Cum 5.00 19,200.00 96,000.00

6.2.23 Reinforcement, high-yield steel, Grade 460/425


kg 150.00 174.00 26,100.00

6.2.24 Reinforcement, mild steel, Grade 250 kg 50.00 168.00 8,400.00

6.2.25 Rubble, 150 - 225 mm Cum 40.00 2,640.00 105,600.00

6.2.26 River Sand Cum 25.00 5,760.00 144,000.00

6.2.27 Precast concrete slabs, 450x450x50mm Nos 15.00 1,080.00 16,200.00

6.2.28 Precast concrete standard Kerb, 250x125x900mm


m 15.00 1,140.00 17,100.00

6.2.29 Grade 40 concrete paving block (220x110x80mm)


Nos 50.00 54.00 2,700.00

6.2.30 Precast concrete Guard stone , 300x300x450mm


Nos 10.00 4,800.00 48,000.00

6.2.31 Reflective, thermoplastic road paint kg 25.00 4,200.00 105,000.00

6.2.32 Auto diesel Ltr 10.00 120.00 1,200.00

6.2.33 Petrol Ltr 10.00 156.00 1,560.00

6.2.34 Kerosene Oil Ltr 25.00 240.00 6,000.00

TOTAL BOQ 6.2 1,280,560.00

6.3 PLANT & EQUIPMENT


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 6

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)


Attendant labour on mechanical plant and
labour erecting and dismantling other plant will
be paid for as "labour". Where plant is employed
on Daywork the Contractor shall be reimbursed
for the use of mechanically operated plant and
transport for the time engaged in daywork at the
rates contained in the Plant Schedule. These
rates include for Contractor establishment
charges. Mechanical Plant not included in the
Schedule will be paid for at rate analogous to the Note
Schedule. The rates quoted are all inclusive and
shall be included for overheads and profit.

Standing and breakdown time will be deemed to


be included in the rates. Note

Plant that is working inefficiently due to


mechanical defector deficiency shall be paid at
rates pro-rata to the rated capacity of the plant. Note

Labour involved in servicing and maintenance of


plant shall be deemed to be included in the rates Note
for plant.

6.3.1 Lorry, 3 tones Hrs 10.00 720.00 7,200.00

6.3.2 Lorry, 10 tones Hrs 10.00 1,020.00 10,200.00

6.3.3 Tipper truck, 5 tones Hrs 10.00 1,380.00 13,800.00

6.3.4 Tipper truck, 10 tones Hrs 10.00 1,560.00 15,600.00

6.3.5 Bowser, water, 6,000 liters with Spray Bar Hrs 5.00 720.00 3,600.00

6.3.6 Bitumen distributor, 750 liters Hrs 5.00 840.00 4,200.00

6.3.7 Emulsion Sprayer self prop.(4000 liters) Hrs 5.00 720.00 3,600.00

6.3.8 Farm Tractor & Broom Hrs 5.00 600.00 3,000.00

6.3.9 Farm Tractor with emulsion browser Hrs 5.00 600.00 3,000.00

6.3.10 Backhoe loader (JCB) Hrs 15.00 2,880.00 43,200.00

6.3.11 Backhoe Loader, 4WD Hrs 20.00 2,880.00 57,600.00

6.3.12 Motor grader, 120 to140HP Hrs 20.00 240.00 4,800.00


CONSTRUCTION OF TRANSITIONAL BUS TERMINAL AT BOGAMBARA. BILL NO. 6

ITEM DESCRIPTION UNIT QTY RATE (Rs.) AMOUNT (Rs.)

6.3.13 Steel-wheeled roller, static, 8 to 10 tones Hrs 15.00 5,400.00 81,000.00

6.3.14 Pneumatic-tired roller, 8 to 10 tones Hrs 15.00 4,800.00 72,000.00

6.3.15 Vibrating Roller (1/2-1 Ton) Hrs 15.00 600.00 9,000.00

6.3.16 Vibrating Roller Smooth (10 Ton) Hrs 15.00 4,800.00 72,000.00

6.3.17 Tandem roller, 6 to 7 tones, Vibrating Hrs 10.00 3,600.00 36,000.00

6.3.18 Plate compactor, vibratory, 90 kg Hrs 10.00 450.00 4,500.00

6.3.19 Vibrating Rammer, 60kg Hrs 10.00 444.00 4,440.00

6.3.20 Water pump with hoses, 100mm outlet Hrs 15.00 360.00 5,400.00

6.3.21 Concrete mixer with weigh batcher 14/10 Hrs 25.00 420.00 10,500.00

6.3.22 Generator, 50KVA Hrs 15.00 720.00 10,800.00

6.3.23 Welding plant Engine driven: with Welder Hrs 15.00 960.00 14,400.00

6.3.24 Poker Vibrator Hrs 15.00 360.00 5,400.00

6.3.25 Road marker hand cart gas heater Hrs 15.00 480.00 7,200.00

TOTAL OF BILL NO. 5 CARRIED TO GRAND Rs 502,440.00


SUMMARY